|
Home
BEMR
Contents
U.S.
Map
The Wayne site is located at 868 Black Oak Ridge Road in Wayne
Township in a highly developed area of Passaic County, New Jersey. This area is
approximately 58 kilometers (36 miles) northwest of New York City.
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
| |
|
|
|
| Environmental Restoration
|
5,900
|
5,895
|
7,556
|
8,417
|
8,315
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
6,095
|
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
6,080
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2020
|
2025
|
2030
|
| Environmental Restoration
|
6,767
|
7,423
|
5,533
|
58
|
|
|
|
98,904
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
From 1948 to 1971, Rare Earths, Inc., and W.R. Grace and Company extracted
naturally occurring radioactive thorium and rare earth elements from monazite
sand ore for use in commercial products. During that period of time,
contaminants from plant operations migrated offsite, primarily via Sheffield
Brook.
SITE MAP
In 1974 W.R. Grace and Company partially decontaminated the site. The
company razed some buildings and buried the resulting rubble and processing
equipment on the property. W.R. Grace decontaminated the remaining buildings,
and covered the onsite disposal areas with clean fill.
The Department of Energy acquired the site in 1984 under a Congressional
mandate. The Department currently maintains and monitors an onsite office
building and a 29,500-cubic meter (38,000cubic yard) storage pile, which
is the result of cleanups of nearby properties during 19851987. The
storage pile will be excavated and removed from the site for permanent disposal
at a licensed, out-of-state facility beginning in late 1995. In addition to the
pile, the former factory site contains up to 53,500 cubic meters
(70,000 cubic yards) of contaminated soil, ore tailings, and process
sludges. This subsurface material will be characterized concurrently with pile
removal to help select the best remedial alternative for the ultimate site
cleanup.
FUTURE USE
After the property has been fully remediated, the Department of Energy will
release it for land use in accordance with the Record of Decision. The cost
estimate assumes that the land will be designated for Industrial/Commercial
use.
ENVIRONMENTAL RESTORATION
In 1984, Congress assigned responsibility for cleanup of the Wayne site to the
Department of Energy. The site was added to the Environmental Protection Agency
National Priorities List during the same year. Since then, the Department of
Energy has managed it under FUSRAP. The key regulator is Environmental
Protection Agency Region II, with additional oversight from the New Jersey
Department of Environmental Protection and the local health department.
Documentation for the remaining actions to be taken for the site include the
proposed plan and the Record of Decision. An Engineering Evaluation/Cost
Analysis documents removal actions used to expedite portions of the cleanup
process, such as pile cleanup.
Environmental restoration activities at the site have been designed to identify
and evaluate contaminated areas through surveying and sampling, to devise
cleanup strategies, and to carry out cleanups as needed. From 1985 to 1987, the
Department of Energy cleaned up 18 vicinity properties in Wayne that had
become contaminated through past W.R. Grace operations. The soil storage
pile at the site is a result of these cleanups. During 1992 and 1993, another
eight vicinity properties were cleaned up in the Town of Pequannock at a rail
spur where thorium-containing sands were offloaded during the years when
W.R. Grace was an operating facility. The Department shipped soil from
these cleanups out of state for permanent disposal.
In April 1991, the Department of Energy and the Environmental Protection Agency
entered into a Federal Facilities Agreement that sets the procedural framework
and schedule for the cleanup and helps foster cooperation between the two
agencies. The agreement is designed to ensure thoroughness and legal compliance
during all phases of planning and implementation of the cleanup.
Future cleanup activities will address both the storage pile and subpile
materials. Although the storage pile is being completely excavated and shipped
for out-of-state, permanent disposal, the Department is still considering
treatment for subpile materials. It is evaluating treatment technologies that
may significantly reduce waste volume. Volume reduction through soil treatment
would result in substantial cost savings in the areas of transportation and
disposal. However, the local community historically has expressed strong
opposition to treatment of any kind and has pressed for complete removal of
subpile materials that are above guidelines, as is planned for the storage
pile.
Although risk to the public resulting from the materials at the Wayne site is
minimal, several environmental monitoring and pollution control measures are in
place to help protect the safety and health of the public and the environment.
The waste material in the storage pile is encased in a synthetic material that
is sealed at the edges to control radon and thoron emissions and to prevent
migration of the enclosed material. All leachate is collected, tested, and
removed for treatment (if necessary) and disposal. A separate ground-water
seepage collection system collects uncontaminated ground water and channels it
to the storm drain system. Pollution control during excavation includes wetting
soils to prevent dust from becoming airborne. Air monitoring during excavation
further ensures that no contamination is leaving the site.
Major Environmental Restoration Activity Milestones
| Assessment (Record of Decision)
|
1996
|
|
Remedial Action
|
2015
|
ASSESSMENT
During 1980, the New Jersey Department of Environmental Protection conducted a
radiological survey of the area. The survey identified elevated radiation
levels at the plant site and in areas west of the plant. Additional
radiological surveys conducted from 1981 to 1983 further delineated the
contaminated areas. The studies included an aerial radiological survey
conducted over a 142-square kilometer (55square mile) area; "driveby"
surveys, in which a van outfitted with instrumentation was driven through the
community being studied; and walkover surveys of individual properties. These
studies identified radioactive contamination at four offsite areas: Wayne
Township Park; a school bus maintenance facility; the Sheffield Brook area,
including 15 properties along the brook, ditch, and drainage pipe; and the
Pompton Plains Railroad Spur.
An environmental surveillance program has been in place since 1984. The
Department monitors air, ground water, and soil and periodically samples them
to detect any above-background contamination from the site. An annual report
compiles and interprets the previous year's monitoring and sampling data.
During activities such as pile removal or residential excavations, the
Department conducts additional monitoring to ensure that no contaminants are
spread as a result of the work.
The Remedial Investigation Report for the site was published in October 1993,
and a Feasibility Study is being completed in preparation for the
decisionmaking process for remedial action. A baseline risk assessment,
published in January 1994, addresses risk to the public based on current and
future use scenarios. Concurrent with pile removal, the Department will perform
characterization of subpile material to define further the nature and extent of
contamination in burial pits.
REMEDIAL ACTION
The Department has cleaned up all offsite properties that were once
contaminated. During 19851987, the Department undertook a series of
cleanup actions for contaminated properties along Sheffield Brook, in Wayne
Township Park, and at the school bus maintenance facility adjacent to the plant
site. Approximately 29,500 cubic meters (38,500 cubic yards) of
contaminated materials were removed from the properties and transported back to
the site for storage. These properties were formally certified for use with no
radiological restrictions and released from FUSRAP in 1990. In 1993, the
Department cleaned up seven additional residential properties and the Pompton
Plains Railroad Spur.
Removal of the soil storage pile will begin during the fall of 1995. Complete
removal will take from three to five years depending on annual funding. As
the pile is removed, the Department will perform characterization of the
subpile soils to determine the nature and extent of contamination in underlying
burial pits.
The scenario used for the Baseline Environmental Management Report cost
estimate assumes phased excavation and treatment of contaminated soils, with
disposal at an existing outofstate commercial disposal facility. The
cost estimate also includes decontamination of the building at the interim
storage site. The estimate assumes that trucks will transport the waste to a
rail siding for loading into rail cars, which will transport the material to an
existing out-of-state commercial disposal facility. The cost estimate assumes a
total site waste volume of 83,500 cubic meters (109,000 cubic yards).
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2020
|
2025
|
2030
|
| FUSRAP - Wayne Site
|
|
|
|
|
|
|
|
|
| Assessment
|
200
|
|
|
|
|
|
|
1,000
|
| Remedial Action
|
6,567
|
7,423
|
5,533
|
58
|
|
|
|
97,904
|
| Total |
6,767
|
7,423
|
5,533
|
58
|
|
|
|
98,904
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FUNDING ESTIMATE
The following table presents estimated funding information for the Wayne site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2020
|
2025
|
2030
|
| Environmental Restoration
|
6,767
|
7,423
|
5,533
|
58
|
|
|
|
98,904
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|
 |