|
Home
BEMR
Contents
U.S.
Map
INTRODUCTION TO URANIUM MILL TAILINGS
REMEDIAL ACTION PROGRAM OFFICE
24 Surface and Ground-Water Sites in 10 States
Twenty-four designated Uranium Mill Tailings Remedial Action (UMTRA) sites are
located in 10 states, including Arizona (two sites), Colorado (nine sites),
Idaho (one site), New Mexico (two sites), North Dakota (two sites), Oregon (one
site), Pennsylvania (one site), Texas (one site), Utah (three sites), and
Wyoming (two sites). The UMTRA Surface Project is managed out of the
Albuquerque Operations Office located in New Mexico. The UMTRA Ground-Water
Compliance Project is managed out of the Grand Junction Projects Office.
Uranium Mill Tailings Remedial Action (UMTRA) Program
FACILITY MISSION
The United States Congress passed the Uranium Mill Tailings Radiation Control
Act in 1978 in response to public concern regarding potential health hazards of
long-term exposure to radiation from uranium mill tailings. The Act authorized
the Department of Energy to stabilize, dispose of, and control uranium mill
tailings and other contaminated material at 24 uranium mill processing sites
and approximately 5,200 associated vicinity properties.
During the 1950s and 60s, private firms processed most uranium ore mined in the
United States for the Atomic Energy Commission, a predecessor of the Department
of Energy. The processing plants were shut down, and the tailings piles from
mill operations were abandoned. These sites presented a potential long-term
health hazard because they contained low-level radioactive and other hazardous
substances that migrated to surrounding soil, ground water, and surface water.
Furthermore, the piles often emitted radon gas. The tailings and other
contaminated material were also used as fill dirt or incorporated into various
construction materials at thousands of offsite locations.
The goals of the UMTRA Program are to: (1) address immediate risk concerns and
prevent further increases in relative risk at all sites; (2) complete surface
remedial action work at all 24 mill tailings sites and related vicinity
properties by FY 1998; and (3) complete ground-water activities in compliance
with Environment Protection Agency standards no later than FY 2014.
The Uranium Mill Tailings Radiation Control Act directed the Environmental
Protection Agency to promulgate cleanup standards (40 Code of Federal
Regulations 192) and assigned the Nuclear Regulatory Commission to oversee the
cleanup and license the completed disposal cells. The responsibilities of the
states and Tribes include (1) acting as an interface between the Department and
the local community; (2) participating in public meetings; (3) acquiring real
estate, where necessary; (4) interfacing with the Department on the
environmental assessment; (5) reviewing remedial action plans; (6) concurring
on supplemental standards; and (7) concurring that remedial action is complete.
The Act also required the states to pay 10 percent of the remedial action and
site acquisition costs.
The UMTRA program does not have any current or anticipated need for nuclear
material and facility stabilization activities. The scope of environmental
restoration includes all costs for waste management, program management, and
landlord activities attributable to the Department of Energy.
FUTURE USE
Eleven of the 24 sites will employ a stabilize-in-place or stabilize-on-site
disposal option. Portions of the sites not used by the disposal cell and its
buffer area may be available for other uses but will likely maintain some form
of land-use restriction. The Federal Government will maintain the portion of
the site that contains the disposal cell under the Long-Term Surveillance and
Maintenance program. Administration and costs associated with the Long-Term
Surveillance and Maintenance program are provided for by the Grand Junction
Projects Office. They are accounted for in the summary for that site in the
Colorado section of this report.
Contamination at the 13 remaining sites will be excavated and disposed of
offsite at remote disposal locations typically owned by the Department of
Energy. These locations will also enter the Long-Term Surveillance and
Maintenance program. Although these sites may be released without radiological
restriction, the Department could enforce ground-water restrictions for many
years. In most cases, the title to the portion of the site that does require
institutional control by the Department will be transferred to the state or
Tribe or remain with the original owners.
In all cases, the Nuclear Regulatory Commission will review and approve the
ground-water remedial action plan strategy for the site, before any decisions
regarding its future use are made. The affected states and Tribes will actively
participate in this decision.
| PRODUCTIVITY IMPROVEMENTS AND COST EFFECTIVENESS
The National Performance Review, instituted by Vice President Gore, presented
the Hammer Award to the UMTRA program in October 1995 for the success of its
Cost Productivity/Reduction Improvement Program. Since FY 1988, the UMTRA
program has saved over $65 million through 1,300 contributions made by project
participants.
|
ENVIRONMENTAL RESTORATION
The UMTRA program consists of two distinct projects, the Surface Project and
the Ground-Water Compliance Project, which are directed by the Albuquerque
Office and the Grand Junction Projects Office respectively. For clarity, this
site summary has consolidated both projects. Costs for these activities have
been apportioned to applicable sites. Under the provisions of the Uranium Mill
Tailings Radiation Control Act, the Department pays 100 percent of the cost of
the assessment activities and 90 percent of the remedial action activities for
both surface and ground-water projects. The affected states pay the remaining
10 percent of the remedial action costs, with the exception of those sites
located on Indian Tribal lands, where the Department pays 100 percent of the
costs.
The Edgemont, South Dakota site is the only UMTRA site that has no remaining
Surface and/or Ground-water Project scope or open legal issues. There is no
additional Department of Energy liability at this site. The mill was
constructed in 1956 to extract uranium from uranium ore and was operated by a
subsidiary of Susquehanna-Western, Inc. Vanadium processing capability was
added in 1960. All processing was complete by 1974, and the owners stabilized
the tailings and other contamination onsite prior to the enactment of the
Uranium Mill Tailings Radiation Control Act. Although the Edgemont site was not
designated as one of the 24 UMTRA sites, a 1983 amendment to the Act required
the Department to address the 135 vicinity properties associated with the
Edgemont site. Material was removed from the vicinity properties and stabilized
at the Edgemont site's Nuclear Regulatory Commission-licenced disposal cell.
The current licensee is expected to turn the site over to the Grand Junction
Projects Office's Long-Term Surveillance and Maintenance program in 1996.
The State of North Dakota has requested that the Department remove the
Bellfield and Bowman sites from designation under the Uranium Mill Tailings
Radiation Control Act. All activities have been suspended pending their removal
from the designation list. However, estimated costs and site summaries are
provided for these sites to frame the potential scope of Department of Energy
activities in the event that these sites are not delisted.
| STAKEHOLDER INTERACTIONS
No Baseline Report public participation activities were conducted for the
Uranium Mill Tailings Remedial Action sites. However, most sites held meetings
with their stakeholders for the Programmatic Environmental Impact Statement,
which had many issues in common with the Baseline Report. If you would like
more information about the report or have questions about the results for these
sites, please contact:
|
| Surface Project
|
Public Participation
Gaeton Falance
(505) 845-5636
gfalance@umtra.ccmail
compuserve.com
|
Technical Liaison
Steven Hamp
(505) 845-5640
shamp@umtra.ccmail
compuserve.com
|
Public Affairs
Gaeton Falance
(505) 845-5636
gfalance@umtra.ccmail
compuserve.com
|
| Ground-Water Compliance Project
|
Public Participation
Audry Berry
(970) 248-7727
audrey.berry@gjpomail.doegjpo.com
|
Technical Liaison
Chris Pennal
(970) 248-6011
cpennal@gjpomail.doegjpo.com
|
|
UMTRA Surface Project
Surface remedial action consists of stabilizing the tailings onsite or, in some
cases, relocating the tailings to more remote locations. The tailings are
covered with soil and rock to prevent radon release, control erosion or
biointrusion, and to minimize infiltration of rain and snow that could leach
contaminants through the pile into the ground water. Surface remedial action at
the 24 sites includes the costs for applicable vicinity properties and remote
disposal locations.
For the surface project at each site a Remedial Action Plan will be generated
that will (1) present the series of activities that are proposed by the
Department to accomplish long-term stabilization and control of the radioactive
materials at the inactive processing site; (2) provide a characterization of
the present conditions of the sites; (3) document the concurrence by the state
or Tribe and the Nuclear Regulatory Commission in the remedial action plan; and
(4) consolidate available engineering, radiological, geotechnical,
hydrological, and other information pertinent to the remedial action.
UMTRA Surface Project Activities
| Ambrosia Lake, New Mexico
|
1995 |
1996
|
1997 |
1997
|
| Belfield, North Dakota1, 2
|
1997 |
1998
|
NA |
NA
|
| Bowman, North Dakota1
|
1997 |
1998
|
1998 |
1998
|
| Canonsburg, Pennsylvania 2, 3
|
1987 |
1995
|
1996 |
1994
|
| Durango, Colorado 2
|
1991 |
1996
|
1996 |
1996
|
| Falls City, Texas
|
1994 |
1996
|
1997 |
1997
|
| Grand Junction, Colorado2
|
1994 |
1999
|
1999 |
2000
|
| Green River, Utah
|
1990 |
1992
|
1996 |
1996
|
| Gunnison, Colorado 2
|
1996 |
1997
|
1997 |
1998
|
| Lakeview, Oregon 2
|
1990 |
1994
|
1995 |
1995
|
| Lowman, Idaho |
1992
|
1994
|
1994
|
1995
|
| Maybell, Colorado
|
1997 |
1998
|
1998 |
1998
|
| Mexican Hat, Utah
|
1995 |
1996
|
1996 |
1997
|
| Monument Valley, Arizona 2
|
1994 |
1996
|
NA |
NA
|
| Naturita, Colorado 2
|
1997 |
1998
|
1998 |
1998
|
| Rifle, Colorado (2 sites) 2
|
1996 |
1998
|
1998 |
1998
|
| Riverton, Wyoming 2
|
1990 |
1995
|
NA |
NA
|
| Salt Lake City, Utah
|
1989 |
1997
|
1998 |
1998
|
| Shiprock, New Mexico
|
1987 |
1991
|
1996 |
1997
|
| Slick Rock, Colorado (2 sites) 2
|
1996 |
1998
|
1998 |
1998
|
| Spook, Wyoming |
1989
|
1992
|
1993
|
1994
|
| Tuba City, Arizona
|
1990 |
1996
|
1997 |
1996
|
1 The State of North Dakota has requested that the
Department remove these sites from designation under the Uranium Mill Tailings
Radiation Control Act. All activities have been suspended pending their removal
from the designation list.
2 Indicates remote disposal cell.
3 This date represents the licensing date for the processing site. Remote
disposal cell was licensed in 1994.
|
The Long-Term Surveillance Plan, which describes how the disposal site will be
managed, will be written concurrently with the each site's disposal cell
Completion Report and final Audit Report. These two documents will be included
as part of the Department's site Certification Report, which explains that the
processing site has been cleaned up according to the provisions of the Remedial
Action Plan. The site Certification Report and the Long-Term Surveillance Plan
will be submitted to the Nuclear Regulatory Commission for concurrence as the
first step towards licensing the disposal cell. Between the time that the
remedial action is completed and the licensed site's surveillance activities
are transferred to the Long-Term Surveillance and Maintenance Program, annual
site inspections and custodial maintenance will be conducted under the UMTRA
Surface Project's Pre-licensing Custodial Care activities. The prime objective
will be to maintain cell integrity. Long-term surveillance of the disposal site
will ensure that the cell continues to function as designed and that it
continues to meet the licensing conditions. Also included will be general
custodial maintenance, such as grass mowing and sign repair, and annual reports
describing all site activities and findings, which will be provided to the
Nuclear Regulatory Commission, applicable state governments, and other affected
parties.Future assessment efforts for the UMTRA Surface Project will center
around investigating new vicinity properties (particularly the Grand Junction
site) and the certification and licensing of all completed site remedial
actions and disposal cells. Remediation will consist of completing the six
sites started prior to FY 1995, starting the cleanup of the last five
processing sites in FY 1995 and FY 1996, and completing cleanup of all sites by
the end of FY 1998. Activities in FY 1999 will consist of finalization of site
and vicinity property completion reports. Surface remedial action activities
have been completed at 16 of the 24 sites, including: Ambrosia Lake,
Canonsburg, Durango, Falls City, Grand Junction, Green River, Gunnison, Mexican
Hat, Lakeview, Lowman, Monument Valley, Riverton, Shiprock, Salt Lake City,
Spook, and Tuba City. The disposal cell at Grand Junction remains open to
accept additional vicinity property material.Of the eight surface remedial
action sites remaining, six are currently under way. As noted earlier, the
State of North Dakota recently requested that the remaining two sites, Belfield
and Bowman, be removed (delisted) from designation under the Uranium Mill
Tailings Radiation Control Act.
UMTRA Ground-Water Compliance Project
Former uranium processing activities at most of the 24 inactive mill sites
resulted in contamination of ground water beneath, and in some cases,
downgradient of the sites. This contaminated ground water often has elevated
levels of contaminants such as uranium or nitrates.The UMTRA Ground-Water
Compliance Project is currently in the planning stages and includes completing
a baseline risk assessment for six sites and preparing site observational work
plans for nine sites. In addition, ground-water monitoring activities will be
conducted to ensure public safety. The project was established to achieve
compliance with Environmental Protection Agency standards. A Programmatic
Environmental Impact Statement will be used as a decision making framework for
determining the project-wide ground-water compliance strategy. The UMTRA
Ground-Water Project Programmatic Environmental Impact Statement analyzes the
potential impacts of four alternatives for conducting the Ground- Water
Project, including the proposed action. These alternatives do not address
site-specific ground-water compliance strategies because the Programmatic
Environmental Impact Statement is a planning document only. It assesses the
potential programmatic impacts of conducting the Ground-Water Project, provides
a method for determining the site-specific ground water compliance strategies,
and provides data and information that can be used to prepare site-specific
environmental impacts analyses more efficiently. These proposed compliance
strategies reflect the variety of ground-water conditions anticipated at the
UMTRA sites and include No Further Action, No Action with Additional
Characterization and/or Supplemental Standards or Alternate Concentration
Limits, passive remediation (natural flushing), and engineered remedial
actions. The draft Programmatic Environmental Impact Statement was published in
the spring of 1995. In conjunction with that activity, the UMTRA Program is
preparing site-specific baseline risk assessments. These assessments evaluate
risks to human health and the environment by collecting field data and
performing calculations and simulations. With one exception, the baseline risk
assessments were complete in FY 1995. The last baseline risk assessment is
scheduled for completion in FY 1996.
UMTRA Ground-Water Compliance Project Activities
| Ambrosia Lake, New Mexico
|
1999 |
No Further Action
|
2000 |
| Belfield, North Dakota1
|
2004 |
No Further Action
|
2005 |
| Bowman, North Dakota1
|
2004 |
No Further Action
|
2005 |
| Canonsburg, Pennsylvania
|
2000 |
Characterization & Supplemental Standards
|
2001 |
| Durango, Colorado
|
2005 |
Natural Flushing
|
2011 |
| Falls City, Texas
|
2000 |
Characterization &Supplemental Standards
|
2001 |
| Grand Junction, Colorado
|
2004 |
Natural Flushing
|
2011 |
| Green River, Utah
|
2003 |
Characterization & Supplemental Standards
|
2004 |
| Gunnison, Colorado
|
2004 |
Natural Flushing
|
2010 |
| Lakeview, Oregon
|
2002
|
Characterization & Supplemental Standards
|
2002 |
| Lowman, Idaho |
N/A
|
No Further Action
|
2002 |
| Maybell, Colorado
|
2002 |
Characterization & Supplemental Standards
|
2002 |
| Mexican Hat |
1999
|
Characterization & Supplemental Standards
|
2002 |
| Monument Valley, Arizona
|
2003 |
Active
|
2015 |
| Naturita, Colorado
|
2007 |
Natural Flushing
|
2013 |
| Rifle, Colorado (2 sites)
|
2004 |
Natural Flushing
|
2010 |
| Riverton, Wyoming
|
2002 |
Natural Flushing
|
2009 |
| Salt Lake City, Utah
|
2005 |
Characterization &Supplemental Standards
|
2005 |
| Shiprock, New Mexico
|
2001 |
Natural Flushing with passive flow-through barrier
|
2002 |
| Slick Rock, Colorado (2 sites)
|
2007 |
Natural Flushing
|
2013 |
| Spook, Wyoming |
1998
|
Supplemental Standards
|
1999 |
| Tuba City, Arizona
|
2002 |
Active
|
2013 |
| 1 The State of North Dakota has requested that the
Department remove these sites from designation under the Uranium Mill Tailings
Radiation Control Act. All activities have been suspended pending their removal
from the designation list.
|
Site observational work plans for applicable sites began in FY 1994 and will
continue through FY 2004 per the project schedule. These plans will define the
technical scope, objectives, and strategies for the anticipated ground-water
compliance activities at the site from characterization through engineering
design and remediation. Site-specific environmental assessments, adhering to
the framework defined in the Programmatic Environmental Impact Statement, will
describe each site's compliance strategy. Because they follow the completion of
the site observational work plans, preparation of environmental assessments
will be initiated in FY 1996 and continue, according to the project schedule,
through FY 2005.
The site-specific Remedial Action Plans will describe regulatory compliance
strategies for the sites where active remediation strategies are proposed. The
Remedial Action Plans will provide the information for States and Tribes to
participate and the Nuclear Regulatory Commission to concur upon the selection
of the compliance strategy. Remedial Action Plans will be initiated just prior
to finalization of environmental assessments and publishing of the Findings of
No Significant Impacts in the Federal Register. They are scheduled to begin in
FY 1997 and continue through FY 2007.
Although no decisions can be made prior to release of the Programmatic
Environmental Impact Statement, budget preparation requires that site-specific
scenarios be addressed as described above. This estimate assumes that two sites
will require active compliance strategies. The active remedial action at these
sites will require certification by the Nuclear Regulatory Commission that they
are complete. This report assumes that active remediation will begin in FY 2002
and will be complete by FY 2014.
The remaining sites would have passive (natural flushing) strategies imposed,
No Action with Additional Characterization, Supplemental Standards or Alternate
Concentration Limits, or No Further Action. For No Further Action or No Action
with Additional Characterization and/or sites where Supplemental Standards or
Alternate Concentration Limits can be applied, no monitoring will be conducted.
If natural flushing is selected as the compliance strategy, verification
monitoring will be conducted for a three-to-five year period, followed by
compliance monitoring under the LongTerm Surveillance and Maintenance
Program for up to 90 more years.
If an Active Remediation compliance strategy is selected, ground-water
monitoring will be conducted during the remedial action to ensure that active
remediation is working as predicted and to determine when compliance has been
achieved.
For all types of ground-water compliance strategies, once the Nuclear
Regulatory Commission determines that the site is in compliance with Subpart B
of the Environmental Protection Agency Standards, no additional long-term
surveillance or monitoring will be conducted for ground water.
DESCRIPTION OF PERSONNEL
Current staffing requirements presented in the table below represent the total
work force for the overall UMTRA program. The federal work force consists of a
manager and scientists. The contractor work force is a mix of professional
staff and labor, who plan and perform the remediation of the various sites.
Full-Time Equivalent Composition Table*
*The projections for Full-Time Equivalent employees are based on FY 1996
planning baselines (see Reader's Guide).
Site Management Structure
The UMTRA Ground-Water Project transferred from the Albuquerque Operations
Office to the Grand Junction Projects Office on October 1, 1995. The surface
project will continue to be supported by the technical assistance contract in
place with Jacobs Engineering Group, Inc., which is scheduled to expire in
1996. This report assumes that only the portion of the contract supporting the
surface project will be extended through completion of the surface project. The
ground water project will be supported by the new Grand Junction support
contract currently held by Rust Geotech beginning in April 1996. This contract
will expire June 30, 1996 and is in the process of being rebid as two support
services contracts, each with a three-year term and two one-year extensions.
| CONTRACTING OPPORTUNITIES
If you would like more information about performing work for the Department of
Energy's Environmental Management program at this site, please contact:
|
Major Procurements
William Meyers
Director
Contracts and Procurement Division
United States Department of Energy
Albuquerque Operations Office
P.O. Box 5400
Albuquerque, NM 87185- 5400
p: (505) 845-5777
f: (505) 845-4210
|
Small Business Procurements
Greg Gonzales
Contracts and Procurement Division
United States Department of Energy
Albuquerque Operations Office
P.O. Box 5400
Albuquerque, NM 87185-5400
p: (505) 845-6182
f: (505) 845-4210
|
COMPARISON WITH PREVIOUS ESTIMATE
The 1996 life-cycle cost for the UMTRA Program is $500 million, which, after
taking the 1995 expenditure into account, represents a three percent increase
over the 1995 estimate of $579 million.
FY 1995-1996 Program Cost Comparison
| Arizona
|
194,906
|
203,843
|
4
|
- Improved analysis of ground-water project planning levels
- Redistribution of program management support costs across all sites
|
| Colorado
|
181,820
|
216,643
|
16
|
- Increases in Grand Junction Vicinity Property remedial
action
- Increases in surface remedial action at Slick Rock, Maybell, and Naturita
sites
- Improved analysis of ground-water project planning levels
- Durango was not captured in 1995 estimate
- Redistribution of program management support costs across all sites
|
| Idaho
|
122
|
559
|
78
|
- Ground water long-term surveillance and monitoring
- Redistribution of program management support costs across all sites
|
| New Mexico
|
2,672
|
9,296
|
71
|
- Improved analysis of ground-water project planning levels
- Redistribution of program management support costs across all sites
|
| North Dakota
|
27,525
|
23,857
|
(15)
|
NA
|
| Oregon
|
4,081
|
6,564
|
38
|
- Improved analysis of ground-water project planning levels
- Redistribution of program management support costs across all sites
|
| Pennsylvania
|
5,374
|
2,821
|
(90)
|
- Improved analysis of ground-water project planning levels
- Redistribution of program management support costs across all sites
|
| Texas |
26,131
|
5,804 |
(350)
|
- Improved analysis of ground-water project planning levels
- Redistribution of program management support costs across all sites
|
| Utah |
7,064
|
19,400 |
64
|
- Improved analysis of ground-water project planning levels
- Redistribution of program management support costs across all sites
|
| Wyoming |
35,427
|
10,959 |
(223)
|
- Improved analysis of ground-water project planning levels
- Redistribution of program management support costs across all sites
|
|
 |