|
Home
BEMR
Contents
U.S.
Map
The former Shiprock site is located on a 93-hectare (230-acre) tract on Navajo
Nation land, south of the San Juan River and adjacent to the town of Shiprock.
Two piles of tailings covered approximately 29 hectares (72 acres). The former
raffinate pond area and a few buildings were located to the west of the piles.
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
| |
|
|
|
| Environmental Restoration
|
1,213
|
695
|
903
|
1,594
|
1,436
|
Grey shaded area reflects annual cost estimates for the
first five years of the site BEMR Base Case (as of October 1995) and includes
3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
1,979
|
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
1,872
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
1,095
|
283
|
136
|
|
|
|
|
7,569
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The mission of the Shiprock mill site was to provide uranium for the United
States Government. The source of contamination was the residual tailings that
remained after the milling process extracted the uranium. Various companies
operated the uranium mill at the Shiprock site from 1954 until 1968. Before and
during the milling operations, the site was leased from the Navajo Nation. When
the Foote Mineral Company's lease expired in 1973, full control of the site
reverted to the Navajo Nation.
SITE MAP
The Environmental Management program is responsible for cleaning up surface-
and ground-water contamination at the UMTRA sites. The Uranium Mill Tailings
Radiation Control Act designated the residual radioactive material found at
this site for cleanup and stabilization. The Act directed the Environmental
Protection Agency to promulgate standards (Code of Federal Regulations Title
40, Part 192) and directed the Department of Energy to perform the cleanup. It
also assigned the Nuclear Regulatory Commission to oversee and certify the
cleanup, and license the completed disposal cell. The affected Tribes will
participate in decisionmaking.
FUTURE USE
The Shiprock former processing site is located on Navajo Nation land. However,
the long-term surveillance of the disposal cell will remain the responsibility
of the Department of Energy through a Custodial Access Agreement between the
Navajo Nation and the Federal Government. Provisions of the Custodial Access
Agreement will allow the Department to have permanent access to the site and
will likely include restrictions, as necessary, to protect the public health
and safety. The provisions will include control of public access and posting of
appropriate warning signs.
ENVIRONMENTAL RESTORATION
Surface remediation has been completed and the source of contamination has been
stabilized. However, residual milling related contaminated ground water
remains.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2015
|
2020
|
2025
|
2030
|
| UMTRA Ground water
|
|
|
|
|
|
|
|
|
| Assessment
|
230
|
50
|
25
|
|
|
|
|
1,525
|
| Remedial Action
|
47
|
|
|
|
|
|
|
233
|
| Direct Program Management/Support
|
818
|
233
|
111
|
|
|
|
|
5,811
|
| Total |
1,095
|
283
|
136
|
|
|
|
|
7,569
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Surface Project
Remedial action was completed in November 1986 at the Shiprock former
processing site. It involved consolidating approximately 2.1 million cubic
meters (2.8 million cubic yards) of residual radioactive material and placing
it in a controlled, engineered disposal cell to preclude further release of
contaminants into the environment, including the ground water. Fifteen vicinity
properties were remediated concurrently with site remediation activities. The
Nuclear Regulatory Commission certified the site in May 1991, and this report
assumes that the Commission will license the disposal cell in October 1996.
Major Surface Project Milestones
| Nuclear Regulatory Commission Issues General License
|
1997
|
| Transfer to Grand Junction Projects Office's Long-Term
Surveillance and Maintenance Program
|
1997
|
The Shiprock Remedial Action Plan outlined the contaminant distribution and
necessary remediation. The Remedial Action Plan, which requires Nuclear
Regulatory Commission concurrence, was published in June 1985. The UMTRA
Surface Project will conduct surveillance and maintenance of the disposal cell
after completion of remedial action and prior to its transfer to the Grand
Junction Projects Office's Long-Term Surveillance and Maintenance program in FY
1997.
Ground-Water Compliance Project
The Department is developing a Programmatic Environmental Impact Statement
pertaining to all 24 UMTRA sites. For a discussion of the statement, see the
UMTRA program narrative in the New Mexico section of this report. Site-specific
National Environmental Policy Act documentation will be developed to propose an
appropriate ground-water compliance strategy and reasonable alternatives for
the Shiprock site once the Programmatic Environmental Impact Statement is
completed.
This cost estimate assumes that the ground-water compliance strategy will be
natural flushing with a passive flow-through barrier. Because of the existence
of ambient contamination in the background ground water, additional
site-specific information will be collected to fill data gaps and to determine
the applicability of the supplemental standards strategy. For all types of
ground-water compliance strategies, once the Nuclear Regulatory Commission
determines that the site is in compliance with Subpart B of the Environmental
Protection Agency Standards and the site is certified, no additional long-term
surveillance or monitoring will be conducted.
The total volume of contaminated ground water is estimated to be 984 million
liters (260 million gallons), and the contaminant plume extends offsite. The
ground-water contaminants of potential concern are antimony, arsenic, cadmium,
magnesium, manganese, nitrate, selenium, sodium, strontium, sulfate, and
uranium.
Major Ground-Water Compliance Project Milestones
| Site Observational Work Plan
|
1998
|
|
Publish Environmental Assessment/Finding of No Significant Impact
|
1999
|
|
Publish Remedial Action Plan
|
2001
|
|
Licensing
|
2002
|
During the ground-water project, the Department must explore two hydrologic
regimes in detail: flood plain and terrace. The flood plain regime has known
contaminant levels. Additional information is necessary to predict ground-water
movement more accurately. The origin of the water in the terrace system has not
yet been established. Drilling further from the former milling site will
determine whether the area is recharged or the water in the terrace is
predominantly from the milling operation.
At present, there are eight monitor wells on the terrace, 34 monitor wells on
the north and south flood plains, and 20 surface-water locations that are
currently monitored or have been sampled in the past. Monitoring wells located
in the terrace alluvium have not provided adequate information to define the
real extent of the contamination to the east, south, or west of the former mill
site. All samples collected from terrace monitoring wells during 1994 show
evidence of contamination by former milling activities. Ground-water samples
collected from background monitoring wells indicate that sulfate concentrations
in background ground water are relatively high, but uranium concentrations are
low.
Direct Program Management/Support
Program management supports management efforts for the National Environmental
Policy Act process, site characterization and licensing, public
information/participation, applicable state and federal regulator costs,
quality assurance audits, program and management support for the technical
assistance contractor, special studies, document control, technical assistance
contractor site and technical management, cost and schedule controls, planning
and preparation of the federal budget, and the Environmental Management
Progress Tracking System.
FUNDING ESTIMATE
The following table presents estimated funding information for the Shiprock
site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
1,095
|
283
|
136
|
|
|
|
|
7,569
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|
 |