|
Home
BEMR
Contents
U.S.
Map
The Savannah River Site is located in west-central South Carolina and is
bordered on the southwest by the Savannah River. The closest major population
centers are Aiken, South Carolina, and Augusta, Georgia. The Savannah River
Site comprises approximately 806 square kilometers (310 square miles); its
production facilities occupy less than ten percent of the total area.
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
| |
|
|
|
| Nuclear Material and Facility Stabilization
|
603,464
|
514,905
|
606,490
|
641,418
|
660,300
|
Grey shaded area reflects annual cost estimates
for the first five years of the site BEMR Base Case (as of October 1995) and
includes 3% annual inflation, see Readers' Guide.
|
| Environmental Restoration
|
152,780
|
127,180
|
170,086
|
172,462
|
192,539
|
|
| Waste Management
|
592,971
|
576,774
|
627,154
|
643,451
|
697,510
|
|
| Directly Appropriated Landlord
|
40,204
|
12,347
|
10,210
|
14,509
|
14,158
|
|
| Total |
1,389,419
|
1,231,205
|
1,413,940
|
1,471,840
|
1,564,508
|
|
| 1996 Appropriation
|
1,259,161 |
|
|
These levels reflect the current estimates for compliance with
applicable statutes and agreements (as of March 1996), see Readers' Guide.
|
| 1997 Congressional Request
|
|
1,152,346
|
|
|
| (Five-Year Averages, Thousands of Constant 1996 Dollars)
|
| |
|
| Nuclear Material and Facility Stabilization
|
569,741 |
380,341
|
286,106 |
114,596
|
88,334 |
49,080
|
87,903 |
|
| Environmental Restoration
|
153,095 |
260,955
|
274,847 |
494,356
|
518,682 |
391,474
|
236,826 |
|
| Waste Management
|
590,535
|
649,625
|
632,159
|
693,027
|
754,067
|
762,459
|
671,534
|
|
| Directly Appropriated Landlord
|
17,534 |
14,841
|
15,189 |
15,730
|
15,648 |
15,907
|
15,652 |
|
| Total |
1,330,905
|
1,305,762 |
1,208,301
|
1,317,708 |
1,376,731
|
1,218,920 |
1,011,915
|
|
| |
2055
|
2060
|
2065
|
| Nuclear Material and Facility Stabilization
|
36,614 |
|
|
|
|
|
|
8,063,567
|
| Environmental Restoration
|
142,628 |
47,681
|
16,863 |
|
|
|
|
12,687,036
|
| Waste Management
|
425,790
|
259,182
|
6,623
|
62
|
|
|
|
27,225,313
|
| Directly Appropriated Landlord
|
15,990 |
16,012
|
16,137 |
|
|
|
|
793,203
|
| Total |
621,022
|
322,875 |
39,623
|
62
|
|
|
|
48,769,120
|
| * Total Life Cycle is the sum of the annual costs in constant FY
1996 dollars.
|
Nuclear Material and Facility Stabilization Section
Environmental Restoration Section
Waste Management Section
Landlord Section
FACILITY MISSION
The Atomic Energy Commission established the Savannah River Site in 1950 to
produce special radioactive isotopes for national security purposes. The
primary purpose of this mission was the production of strategic isotopes (for
example, plutonium-239 and tritium) used in the development and production of
nuclear weapons for national defense. The Savannah River Site also produced
other special isotopes (for example, californium-252, plutonium-238, and
americium-241) to support research in nuclear medicine, space exploration, and
commercial applications. To produce these isotopes, the Department of Energy
fabricated selected materials into metal targets and irradiated them in the
Savannah River Site nuclear reactors. The targets were transferred to the
chemical separations facilities and dissolved in acid, and the desired isotopes
were chemically separated and converted into a solid form, either an oxide
powder or a metal. The oxide or metal was fabricated into a usable form at the
Savannah River Site or other Department of Energy sites. In addition, the
Savannah River Site chemically reprocessed spent nuclear fuel to recover
uranium-235.
After the Cold War, the mission of the Savannah River Site changed as emphasis
shifted from nuclear material production to environmental management. Despite
this shift, the Savannah River Site remains a major defense installation
capable of processing and purifying tritium and plutonium; however, the fuel
and target manufacturing facilities, along with the five production reactors,
are not in operation at this time. With the exception of these facilities, the
processing facilities have been inventoried and are waiting for the resumption
of operations to stabilize nuclear materials that are considered programmatic
or at-risk.
The Environmental Management program was initiated at the Savannah River Site
in 1989 to address the closure of old burial grounds and seepage basins. During
that same year, reactor operations were halted to address safety and
environmental upgrades to selected reactor facilities. The chemical processing
facilities continued operation into 1992, when chemical processing and recovery
activities were halted to address potential safety concerns. These concerns
were addressed; however, before operations resumed, the end of the Cold War
reduced the need for additional defense materials. Current operation of the
chemical processing facilities is limited to the recycling of tritium, which
continues today under the Office of Defense Programs, and to materials
containing plutonium-238, which are used to support exploratory space missions.
During January 1995, the Nuclear Material and Facility Stabilization program
was designated as the landlord, placing the Savannah River Site under
Environmental Management program control, except for the tritium mission.
SITE MAP
Current activities under the Environmental Management program are conducted
under three major programs at the Savannah River Site: Nuclear Material and
Facility Stabilization, Environmental Restoration, and Waste Management.
The stabilization/deactivation of nuclear materials and deactivation of
facilities is accomplished under the Nuclear Material and Facility
Stabilization program. When these activities are complete, the facilities are
transferred to the Environmental Restoration program for decontamination and
decommissioning. Environmental Restoration is also responsible for the cleanup
of soils and ground water contaminated as a result of operations at the site.
Waste generated by both of these programs is treated, stored, and disposed of
under the Waste Management program.
The primary drivers for these programs are the Federal Facility Agreement and
the Federal Facility Compliance Act Consent Order. These agreements define
legal actions and milestones for the Savannah River Site. The key issue that is
emerging from these agreements is the projected budget shortfall and its effect
on programmatic and technical decisions, including decisions on Environmental
Impact Statements pertaining to the management of spent nuclear fuels and
plutonium-239 disposition.
FUTURE USE
The Savannah River Site began work on a Future Use Project in early 1994, and a
report on the Future Use Project was issued in January 1996. The purpose of
this project is to determine the stakeholder-preferred future-use options for
Savannah River Site land and facilities. Stakeholders include: interested
citizens, former landowners, hunters, employees, civic organizations, local
government officials, representatives from local communities (for example,
Citizens for Environmental Justice), the Savannah River Site Citizens' Advisory
Board, Citizens for Nuclear Technology Awareness, and the Savannah River
Regional Diversification Initiative.
FUTURE USE MAP
Despite the diverse spectrum of interested parties, several common themes and
recommendations emerged from the future-use planning process. The most common
recommendations are that (1) the Savannah River Site boundaries should remain
unchanged, and the land should remain under the ownership of the Federal
Government; (2) residential use of site land should be prohibited; (3) if the
Department of Energy or the Federal Government should ever decide to sell any
of the Savannah River Site land, former landowners or their descendants (as of
1950-1952) should have first option to repurchase their former land; (4) some
of the land should continue to be available for industrial uses; (5) industrial
and environmental research and technology development and transfer should be
expanded; (6) natural resource management should be pursued with biodiversity
being the primary goal; (7) recreational uses should be increased as
appropriate; (8) all land should be available for multiple uses (for example,
ecological research, natural resource management, research and technology
demonstration, and recreation); and (9) future-use planning should consider the
full range of worker, public, and environmental risks, benefits, and cost.
These recommendation are consistent with the Department's support for
legislation to formally designate the Savannah River Site as a National
Environmental Research Park.
Land-use assumptions used in the development of this report are consistent with
the Future Use Project and input from the Savannah River Site Citizens'
Advisory Board. The Savannah River Site life-cycle cost estimate assumes that
the Federal Government will continue to own the Savannah River Site, and
Savannah River Site will provide land for the Department's defense activities
with adequate isolation from population centers. The central industrial area
will be used by the Official of Defense Programs for continued activities and
by the Environmental Management program for maintaining and monitoring the
buried and stored waste remaining at the Savannah River Site. The central
industrial area includes low-level radioactive waste disposal areas that will
be restricted as long as necessary to ensure protection of human health and the
environment. The goal for restoration is to remediate all land and ground water
located near the perimeter of the Savannah River Site to permit multiple,
concurrent uses.
The Department of Energy will consider the stakeholder-preferred options
throughout future planning and decision making activities as it weighs mission
needs, technological capabilities, legal requirements, and funding. The assumed
future-use profile for the site is portrayed in the map above.
NUCLEAR MATERIAL AND FACILITY STABILIZATION
The Nuclear Material and Facility Stabilization program is responsible for the
development and implementation of nuclear material management activities on the
Savannah River Site. This includes stabilization of production materials and
deactivation and decommissioning of associated facilities prior to release to
the Environmental Restoration program for ultimate decommissioning.
NUCLEAR MATERIAL AND FACILITY STABILIZATION
MAP
The facilities in the Nuclear Material and Facility Stabilization program
comprise more than 1,000 buildings; 35 additional buildings are currently
dedicated to the tritium program; and approximately 300 additional buildings
are in the Environmental Restoration and Waste Management programs. This
analysis is based on the Surplus Facility Inventory and Assessment data base.
Projects at these facilities are grouped into scheduling transfer units. These
groupings are based on geographical and functional criteria. Facilities in each
scheduling transfer unit are to be stabilized, deactivated, and placed in a
two-year surveillance and maintenance process before being transitioned to the
Environmental Restoration program.
Current plans and estimates are Federal Facility Agreement-driven, with
schedules that assume requirement-level funding and timely decisions on the
Environmental Impact Statement for management of spent nuclear fuels and
nuclear materials. Uncontaminated facilities are assumed to go directly to the
Environmental Restoration program for decommissioning. Characterization and
packaging costs associated with waste from each scheduling transfer unit are
included in the estimates for the Nuclear Material and Facility Stabilization
program. Costs for treatment, storage and disposal of this waste are included
in Waste Management program costs. Once transferred, facility costs are assumed
to be the responsibility of the Environmental Restoration program. All reactors
and canyons will be deactivated prior to transfer to the Environmental
Restoration program for decontamination and decommissioning.
Costs for the Nuclear Material and Facility Stabilization program are reported
by scheduling transfer unit. They do not include new mission programs or
facilities, and they assume the program will not remediate tritium-contaminated
ground water. Costs associated with these facilities are summarized in the
tables at the end of this section.
The cessation of processing operations resulted in a large inventory of
unrecovered nuclear materials in various stages of the production and recovery
cycle. These materials include acidic solutions containing dissolved target or
fuel materials; recovered isotopes stored in stainless steel tanks; product
forms of isotopes (oxide powders and metals) packaged in storage containers
(for example, cans and drums); residue forms containing varying amounts of
isotopes packaged in cans; and unirradiated and irradiated metal fuel, targets,
control rods, and other reactor core components (stored both dry and in
water-filled basins).
The Defense Nuclear Facilities Safety Board 94-1 recommendation to use the
separations facilities to concentrate, purify, and stabilize surplus nuclear
materials would reduce the risk posed by interim management and is the subject
of several studies and National Environmental Policy Act evaluations (for
example, the F Canyon Plutonium Solutions Environmental Impact Statement
and the Interim Management of Nuclear Materials Environmental Impact
Statement). The facilities in the Nuclear Material and Facility Stabilization
program include chemical processing facilities, reactor and reactor materials
facilities, and landlord facilities. These three categories are subdivided into
scheduling transfer units based on geographic proximity, function, responsible
organization, and size. This was done to ensure that (1) physical areas could
be turned over to the Environmental Restoration program in their entirety, (2)
similar processes could be employed for required tasks, and (3) responsibility
for planning and execution could be assigned.
Chemical processing facilities are located within the F and H Areas. The
primary mission of the facilities was to separate special nuclear materials
from spent reactor fuels and irradiated targets. Chemical separation and
purification of these materials is accomplished in facilities known as canyons,
which are supported by ancillary facilities that provide further chemical
conversion, cold chemical feeds, or general facility services. Chemical
Processing Facility projects are represented by the following scheduling
transfer units: (1) F Canyon and supporting facilities; (2) 235-F Area
metallurgical facilities; (3) 247-F Naval fuels fabrication facilities; and (4)
H Canyon and supporting facilities.
The completion of the Savannah River Site Stabilization program for the
identified at-risk materials is expected by FY 2002, with the consolidation of
special nuclear materials in the proposed new Actinide Packaging and Storage
Facility. Currently, there is no authorized future mission for the chemical
processing facilities after the stabilization of the at-risk materials.
Alternative uses for these facilities are being evaluated; options include the
future disposition of fissile materials and the support of the continuing
defense programs.
The reactor and reactor materials facilities at Savannah River Site are located
in C, K, L, P, and R Areas. The materials fabrication facilities are located in
M Area, and the heavy water facilities are located in D Area. All of the
reactor areas are similar in physical size and layout. The past mission of the
reactor areas was to produce material for the Department of Defense nuclear
weapons program. Currently, the five production reactors are nonoperable, and
future operations are not planned. The present reactor deactivation programs
will be completed in approximately 18 years.
D Area facilities were designed to produce heavy water for use in the
production reactors. The area originally contained three sets of heavy water
extraction towers with the necessary support facilities. The area was
operational until 1982. As of September 1995, two sets of extraction towers and
most support facilities have been removed. Surveillance and maintenance
requirements are minimal. The existing site inventories of contaminated heavy
water are currently being processed in the heavy water rework and purification
facilities for future onsite storage. These facilities are scheduled to close
and become surplus by FY 2001.
M Area facilities were designed for machine fabrication of special fuel
assemblies that contained targets used in the production of special nuclear
materials. These facilities were also used as safe storage for the assemblies
prior to use in the reactor areas. Recently, these facilities were used to
stabilize existing stockpiles by consolidating (melting) fabricated assemblies
into ingots, which have since been stored in another facility until the Oak
Ridge Reservation can receive them. The area is now being decontaminated, and
the facilities are being made available for commercial business operations. All
stabilization activities will be completed by FY 2002.
The reactor and reactor material facilities comprise seven scheduling transfer
units. For the purposes of this report, two scheduling transfer units are
discussed in detail: (1) P Area - P reactor and supporting facilities and (2) M
Area - alloy fabrication facilities. Costs for the remaining reactors and
reactor material facilities appear in the "additional scheduling transfer
units" presented later in this section.
The landlord facilities comprise administrative offices, laboratories,
maintenance and other service facilities, utilities, and related
infrastructure. These facilities are co-located with the operating facilities
to provide direct mission support or are centrally located as site-wide needs
dictate. These facilities range in size from two-square meter (25-square foot)
test stations to 20,000-square meter (250,000-square foot) laboratory
facilities. There are 15 different landlord facility scheduling transfer units.
The landlord facility project addressed in this report, A Area site services
facilities, is the largest grouping at the Savannah River Site. The following
table presents the milestones for transferring major facilities from the
Nuclear Material and Facility Stabilization program to the Environmental
Restoration program.
Major Nuclear Material and Facility Stabilization Activity Milestones
| Chemical Processing
|
| Building 247-F
|
2005
|
|
Metallurgical Building 235-F
|
2010
|
|
F Canyon
|
2013
|
|
H Canyon
|
2013
|
|
Reactor/Reactor Materials
|
|
R Area
|
1999
|
|
M Area
|
2001
|
|
D Area
|
2002
|
|
C Area
|
2003
|
|
P Area
|
2004
|
|
K Area
|
2007
|
|
L Area
|
2014
|
|
Landlord Facilities
|
|
M Area
|
2001
|
|
D Area
|
2002
|
|
R Area
|
2002
|
|
S Area
|
2002
|
|
T Area
|
2004
|
|
P Area
|
2004
|
|
C Area
|
2009
|
|
K Area
|
2011
|
|
B Area
|
2011
|
|
A Area
|
2014
|
|
F Area
|
2015
|
|
N Area
|
2015
|
|
H Area
|
2018
|
|
L Area
|
2018
|
|
G Area
|
2019
|
F Canyon and Supporting Facilities
The 221-F Canyon Building contains the plutonium uranium extraction (solvent)
process. The processing facility, referred to as the Canyon Building, began
operating in 1954. The primary mission of the facility was the recovery of
plutonium and uranium from irradiated depleted and natural uranium reactor
targets, spent reactor fuels containing large fractions of plutonium, and
plutonium metal returned from weapons production and support sites. The Canyon
Building is supported by several major ancillary facilities. The outside
facilities (211-F) provide cold chemical feed makeup and storage of bulk
chemicals, along with limited facility support services. The Depleted Uranium
Processing Facility (221-FA Line) converts depleted uranium solution to oxide
and packages it for onsite storage. The Canyon Building and supporting
facilities are now in a standby mode.
The FB Line Facility is a hardened structure located in the F Area Canyon
Facility. The FB Line was placed into service around 1960 to produce
high-purity plutonium metal from the dilute plutonium-239 solution produced in
F Canyon. FB Line vaults currently store special nuclear materials, some of
which require further stabilization to meet Department of Energy storage
standards.
PRE-STABILIZATION SURVEILLANCE AND MAINTENANCE
The F Canyon and supporting facilities have been maintained in a state of
standby since early 1992. Improvements to the overall facilities (for example,
structures, process equipment, procedures, and safety documentation) have led
the Department of Energy to authorize startup of F Area facilities for the
stabilization of at-risk nuclear materials, as identified in Environmental
Impact Statement studies. Startup is continuing for implementation of the
preferred options identified in the Savannah River Site Interim Management of
Nuclear Materials Environmental Impact Statement, and work is complete for
stabilization startup. No further activities associated with pre-stabilization
are required for F Area facilities.
A new Actinide Packaging and Storage Facility (a $137 million, 1997 line-item
project) will be added to the F Area facilities. Completion of this facility is
scheduled for FY 2001. The purpose of this facility is to provide the necessary
capabilities for high-firing plutonium oxide and to package all plutonium to
current Department standards for interim storage. In addition, the facility
will provide sufficient vault storage capacity to consolidate nuclear material
storage. This consolidation will allow the systematic shutdown of vaults in
older Savannah River Site facilities.
STABILIZATION
Currently, the F Area chemical processing facilities are not declared surplus
and are staffed to provide necessary support for facility restart and the
eventual stabilization of nuclear materials that have been identified as
at-risk by the Defense Nuclear Facilities Safety Board 94-1 recommendations.
Several preferred options were identified for the stabilization of nuclear
materials that would use the F Canyon and supporting facilities according to
the Interim Management of Nuclear Materials Environmental Impact Statement
process. These preferred options include stabilization and repackaging of
existing high-grade plutonium vault inventories (metal and oxide), conversion
of plutonium solutions to stable vault material, stabilization and packaging of
plutonium residues, dissolution of at-risk targets and fuels, conversion of
special nuclear materials, conversion of programmatic nuclear material
solutions to solid form for storage and eventual shipment, and stabilization of
highly enriched uranium in the Savannah River Site inventory. A schedule for
the stabilization of nuclear materials outlines a program that envisions
completion of material stabilization by FY 2001. Waste forecasts for this phase
are estimated at 12,000 cubic meters (15,700 cubic yards); more than 90 percent
of the waste is low-level waste. Liquid waste streams are transferred to the F
Area tank farm and will be eventually processed through the Defense Waste
Processing Facility.
POST-STABILIZATION SURVEILLANCE AND MAINTENANCE
The purpose of the F Canyon post-stabilization surveillance and maintenance
program (which has an anticipated time frame of FY 2002 to FY 2004) is to
maintain the viability of the chemical processing facilities during a period of
evaluation. If declared excess, the facilities will undergo removal of all
remaining residual hazardous materials. The process systems and process cells
will be thoroughly flushed, and process lines will be drained. These activities
will not jeopardize future restart of these facilities. Building systems and
components will be evaluated, and an engineering analysis will be completed to
determine which critical systems must be maintained to ensure structural
integrity of the building and minimize the impact to health and safety of the
public and workers. Facility deactivation plans still must be completed. This
three-year program is estimated to cost about $250 million. Waste associated
with process system flushes will be transferred to the F Area tank farm and
will eventually be processed through the Defense Waste Processing Facility. The
waste estimate for this phase is 4,500 cubic meters (5,900 cubic yards), and
over 90 percent of the waste is low-level waste. Although the chemical
processing facilities have no authorized mission after the stabilization of all
at-risk nuclear materials, alternative uses for these facilities are currently
being evaluated.
DEACTIVATION
Because of their size, potential residual contamination, and complexity, the F
Canyon and associated facilities present a challenge for deactivation. To date,
only a very limited study of deactivation requirements has been undertaken. For
planning purposes, a significant reduction in costs is not expected until the
completion of deactivation activities. The estimated cost for this deactivation
phase, including surveillance and maintenance, is $450 million, based on
experience at the Hanford Site and best engineering judgment.
No major decontamination or dismantlement activities are expected to be
completed during the deactivation phase for the F Area chemical processing
facilities; therefore, no significant increase in the overall waste generation
is expected. Liquid waste associated with deactivation of the facilities will
be transferred to the F Area tank farm and processed through the Defense
Waste Processing Facility. Waste estimates for this phase forecast 5,000 cubic
meters (6,550 cubic yards) of waste; 90 percent of the waste is low-level
waste.
POST-DEACTIVATION SURVEILLANCE AND MAINTENANCE
Current plans are to maintain the facilities in post-deactivation, minimal
surveillance and maintenance status for two years prior to transfer to the
Environmental Restoration program in FY 2013. Estimated costs associated with
maintaining a minimal surveillance and maintenance program for the F Area
chemical processing facilities are estimated to average $13 million per year.
Waste estimates for the post-deactivation phase have not been fully developed;
however, it is anticipated that a significant reduction in waste is feasible,
and waste generation should not exceed 200 cubic meters (260 cubic yards) per
year. More than 95 percent of the waste is low-level waste.
235-F Area Metallurgical Facilities
Built in the early 1950s, the 235-F Building is a two-story, windowless,
reinforced concrete structure. The 235-F Facility has as its mission the
continued safe, secure storage of special nuclear materials until a new storage
and treatment facility can be funded and constructed to enable consolidation of
the special nuclear materials. Portions of the 235-F Facility were once used to
fabricate heat sources from plutonium-238 oxide powder for space mission
applications. These selected production areas of the 235-F Facility have been
shut down and do not support the existing facility mission. Upon transfer and
consolidation of nuclear material into a new vault, the remaining 235-F
Facility could be declared surplus.
PRE-STABILIZATION SURVEILLANCE AND MAINTENANCE
Pre-stabilization activities are considered complete for the highly
contaminated surplus sections of the 235-F Facility associated with the
plutonium-238 fabrication program.
STABILIZATION
Currently, $15 million to $17 million per year is required for surveillance and
maintenance of the contaminated process areas and for management of the stored
special nuclear materials. Interim storage of special nuclear materials at the
235-F vault is expected to be required through FY 2002 to support the secure
storage of nuclear materials. During this period, provisions will be made to
support additional shipment and receipt of special nuclear materials from the
vaults in order to stabilize and package all nuclear materials in a manner that
meets interim storage criteria. Current and future operation of the facility is
based on the Interim Management of Nuclear Materials Environmental Impact
Statement and subsequent decisions and responses to the Defense Nuclear
Facilities Safety Board 94-1 recommendations.
The inventory of nuclear material in this facility will be consolidated in the
proposed new Actinide Packaging and Storage Facility (expected by FY 2002) and
the future use of the 235-F vaults will be evaluated to determine whether or
not to declare the entire facility excess. The best engineering judgment
considers it undesirable to deactivate the shutdown of plutonium-238 production
areas while vault storage areas are in active use.
POST-STABILIZATION SURVEILLANCE AND MAINTENANCE
During the year following the de-inventory of the 235-F vaults, studies
regarding the viability of the 235-F Facility will be conducted. Surveillance
and maintenance will be conducted to ensure continued protection of the
environment and the safety of the workers and the public. Estimates forecast
costs for the one-year post-stabilization period at $12 million to maintain the
facility at an acceptable level of risk. Low-level waste volume has been
forecast to be 10 cubic meters (13.5 cubic yards) per year for this phase.
DEACTIVATION
A deactivation plan for the 235-F Facility has not been developed. The
Plutonium-238 processing lines will continue to comprise the largest portion of
the 235-F Facility surveillance and maintenance costs until a decontamination
and dismantling plan is implemented. Deactivation costs are expected to be $80
million for a four-year period. Accomplishments during deactivation are
expected to include limited decontamination, contamination fixation, improved
containment, possible limited dismantling or removal of highly contaminated
items to reduce the risk of nuclear material migration. Low-level waste is
forecast at 4 to 5 cubic meters (5 to 6.5 cubic yards) per year for
surveillance and maintenance of the facility; however, this estimate does not
include any waste volume assumptions for the decontamination or dismantling
segments of the deactivation work.
POST-DEACTIVATION SURVEILLANCE AND MAINTENANCE
A preliminary engineering study that was completed in FY 1993 estimated that
decontamination and partial dismantling of the plutonium-238 processing
facilities would cost in excess of $100 million. This effort would result in a
significant reduction in plutonium-238 contamination. A deactivation program of
this nature would reduce the facility risk with a corresponding reduction in
facility surveillance and maintenance costs. Post-deactivation surveillance and
maintenance costs are estimated to average three million dollars per year; and
low-level waste generation is forecast at three cubic meters (four cubic yards)
per year. The facilities are targeted to be conveyed in this condition to the
Environmental Restoration program during FY 2010.
247-F Naval Fuels Building and Supporting Facilities
The 247-F Facility is located within a deactivated security zone in F Area. The
247-F Building and nearby ancillary facilities were utilized for fabrication of
enriched uranium fuel for use in the production of naval reactor fuel elements,
until the operation was shut down in 1988. Currently, there is no identified
mission for the facility.
After the process was shut down, the 247-F Facility was de-inventoried of
enriched uranium and chemicals, and the process equipment was flushed and
isolated; however, portions of the building and equipment are contaminated with
corrosive residue, containing a measurable quantity of enriched uranium.
Characterization surveys found transferable contamination within the process
cabinets. Limited decontamination has been performed, and current conditions
are documented in monthly surveillance and maintenance contamination surveys of
the facility to ensure contamination in the cabinets has not migrated. The
247-F Building is currently in a shutdown mode. This facility is currently
surveyed and maintained to keep the safety and waste operation systems
functioning.
POST-STABILIZATION SURVEILLANCE AND MAINTENANCE
Safety documentation is being analyzed, and activities that would reduce
surveillance and maintenance of the facility are being evaluated. Early
investigations indicate that full-scale reduction to a passively maintained
facility is not possible until significant reductions in the residual
contamination of enriched uranium is accomplished. This would require
significant glovebox cleaning, material and equipment removal, and fixation of
residual contamination. Until this work is completed, the facility will require
periodic entry and inspection along with continued operation of key building
safety systems to ensure the safety of the environment, workers, and public.
The costs associated with the two-year post-stabilization surveillance and
maintenance program, during FY 1996 and FY 1997, are estimated at $16 million.
Low-level waste volumes have been estimated at 200 cubic meters (260 cubic
yards) for this period.
DEACTIVATION
A conceptual study was completed that included the following scope:
decontaminate, dismantle, and remove limited equipment from the 247-F Core
Area. This study estimated the cost to be approximately $40 million to $45
million. There is currently no deactivation plan for 247-F Facility to achieve
a desired passive end-state. For planning purposes, costs are estimated at $45
million over a five-year period (FY 1998 to FY 2002) for routine surveillance
and maintenance, reduction in contamination, partial equipment removal, and the
lay-up of support systems, with associated reduction in surveillance and
maintenance costs to be achieved in the year 2003. Waste volumes for this phase
have been estimated at 300 cubic meters (400 cubic yards) of low-level waste.
POST-DEACTIVATION SURVEILLANCE AND MAINTENANCE
Post-deactivation surveillance and maintenance costs are estimated at less than
four million dollars per year, with waste generation forecast at less than 30
cubic meters (40 cubic yards) per year. It is expected that the facility will
transition to the Environmental Restoration program no later than FY 2005.
H-Canyon and Supporting Facilities
The canyon began operation in July 1955 as a Plutonium Uranium Extraction
Facility with a primary mission to recover enriched uranium from spent uranium
fuels. The canyon was modified in 1963 to recover neptunium as well as enriched
uranium. The Canyon Building is supported by three principal ancillary
facilities. The ancillary facilities comprise a number of processes and
services that provide bulk chemical storage, liquid waste disposal, the
recovery of plutonium-238, and vaults for storing nuclear materials. The canyon
and support facilities are currently maintained in inventoried standby.
The estimated costs and waste volume for H-Canyon assume that these facilities
will be used to stabilize the majority of the site's aluminum-clad fuels in
order to transform the highly enriched uranium into a nonweapons-usable form.
The canyon and supporting facilities have been maintained in a state of standby
since the early 1990s while the Department evaluates alternatives for the
stabilization of aluminum-clad highly enriched spent nuclear fuel remaining
from previous operations.
PRE-STABILIZATION SURVEILLANCE AND MAINTENANCE
The H Canyon and support facilities have been maintained in a state of
inventoried warm standby since the early 1990s pending a decision on the
options for stabilization. Start-up authorization is expected for
implementation of the preferred options resulting from the Savannah River Site
Interim Management of Nuclear Materials Environmental Impact Statement.
Pre-stabilization activities are essentially complete for existing H Area
facilities.
STABILIZATION
The Department expects that operations to stabilize the nuclear materials
identified as at-risk will begin in late 1997. The Interim Management of
Nuclear Materials Environmental Impact Statement identifies several options for
the stabilization of nuclear materials using the H Canyon and its associated
support facilities. These options include: (1) stabilization/blending/packaging
of plutonium-238 inventories, (2) conversion of plutonium solutions to stable
material, (3) dissolution of at-risk targets and fuels and conversion to stable
forms, (4) conversion of programmatic nuclear material solutions to a solid
form for storage and eventual shipment, and (5) dilution and stabilization of
highly enriched uranium currently held in the Savannah River Site inventory to
low enriched uranium. The cost for the stabilization of the nuclear materials,
including surveillance and maintenance, is forecast at $750 million.
Waste stream forecasts are 12,000 cubic meters (15,700 cubic yards); greater
than 80 percent of the waste is considered low-level waste, and the rest is
high-level waste. Liquid waste streams are transferred to the H Area tank farm
and will eventually be processed through the Defense Waste Processing Facility.
POST-STABILIZATION SURVEILLANCE AND MAINTENANCE
The primary purpose of the post-stabilization surveillance and maintenance
program (during FY 2002 to FY 2004) is to maintain the viability of the
chemical processing facilities until they are declared excess. When this
occurs, the facilities will undergo removal of all residual hazardous
materials, the process systems and process cells will be thoroughly flushed,
and the process lines will be drained. Building systems and components will be
evaluated, an engineering analysis will be completed to determine which
critical systems must be maintained to ensure structural integrity of the
building and to minimize the impact of any health and safety issues that may
affect the public or workers, and facility deactivation planning will begin.
This three-year program is estimated to cost approximately $210 million. Waste
associated with process system flushes will be transferred to the H Area tank
farm and will eventually be processed through the Defense Waste Processing
Facility. Low-level waste is estimated at 4,800 cubic meters (6,300 cubic
yards). There is currently no authorized mission for the H Area chemical
processing facilities following stabilization of the at-risk nuclear materials.
Alternative uses for these facilities in support of other stabilization and
nuclear material disposition programs are being evaluated.
DEACTIVATION
A limited investigation of deactivation requirements has been undertaken, but
no deactivation requirements have been defined. The best engineering judgment
in forecasting costs for this deactivation phase, including surveillance and
maintenance over the deactivation period (FY 2005 to FY 2010), is $350 million.
No major decontamination or dismantling activities are expected during the H
Area deactivation; therefore, no significant waste increase is forecast above
the waste volume generated during the post-stabilization period. Waste
associated with deactivating the facilities will be transferred to the H Area
tank farm and will be eventually processed through the Defense Waste Processing
Facility. Estimates for the period forecast waste at 5,800 cubic meters (7,600
cubic yards), almost all of which is low-level waste.
POST-DEACTIVATION SURVEILLANCE AND MAINTENANCE
The facilities are scheduled to begin a post-deactivation surveillance and
maintenance phase by FY 2011, and this report assumes transition to the
Environmental Restoration program will occur by FY 2013. Costs associated with
maintaining a minimal surveillance and maintenance program for the H Area
chemical processing facilities after deactivation are estimated at $11 million
per year. Waste estimates for post-deactivation activities have not been fully
developed; however, preliminary estimates suggest low-level waste volumes will
be less than 300 cubic meters (400 cubic yards) per year.
P Area Reactor and Supporting Facilities
P Reactor, similar to all of the reactors at the Savannah River Site, has two
functional areas, referred to as the exclusion area and the administrative
area. The reactor exclusion area contains production buildings and all
buildings and facilities necessary for operational support. The area outside
and surrounding the exclusion area contains the administrative support
facilities and the cooling water storage basins. The entire reactor area, both
exclusion and administrative areas, is enclosed by fencing to form an
operations/administrative compound. The past mission of the reactor was to
produce material for the Department of Defense Nuclear Weapons program. P Area
stabilization activities are complete. Activities included removing the fuel
from the reactor vessel.
POST-STABILIZATION SURVEILLANCE AND MAINTENANCE
Post-stabilization surveillance and maintenance activities at these facilities
are forecast to be complete between FY 1996 and FY 2001. Most waste has been
shipped to proper treatment and disposal facilities. Currently, the major
stabilization and maintenance costs associated with the reactor facility relate
to moderator storage and fuel basin maintenance. The estimated cost for these
activities is $31 million; however, this work will result in a cost savings of
over ten million dollars when compared to continued surveillance and
maintenance. All waste generated is expected to be low-level waste and
generated at a rate of 341 cubic meters (450 cubic yards) annually.
DEACTIVATION
P Area deactivation activities are forecast for completion between FY 2002 and
FY 2004. This area includes the reactor and the ancillary facilities associated
with and located within the exclusion perimeter. The reactor and fuel basin
will require the most extensive deactivation.
The Department expects that deactivation of the reactor building will include
the following activities: (1) All fuel, targets, components, and scrap will be
removed from the disassembly basin; deuterium moderator (1,000 drums) will be
removed; all waste will be removed; and all lead not required for safe building
storage will be removed; however, bioshielding will remain. (2) All friable
asbestos will be stabilized in situ or removed; items presenting a significant
fire potential will be removed. (3) All water systems will be drained. (4) The
fire water dry standpipe will remain empty, and the service raw water source
will not be available. (5) Sump pumps will remain energized, and other systems
will be shut down. (6) One transformer room will remain energized to supply the
pumps and lighting when required. (7) Dampers will be positioned to allow air
circulation. (8) Permanent building and personnel monitoring equipment will be
removed or shut down. (9) All office furniture, equipment, tools, and supplies
will be removed. (10) All fuel and cadmium rods will be removed.
The Department expects that some activities will not be accomplished. These
include: (1) fuel basins will not be drained; however, components will be
removed from the reactor tank, (2) the reactor tank will not be sealed, (3) no
equipment will be removed for storage, (4) no provisions will be made to
preserve equipment or instruments, and (5) no established contamination areas
or equipment will be decontaminated. Therefore these activities are not
included in the cost estimate.
Several activities will be accomplished for long-term safe storage. Sump pumps
will remain operable and set for automatic operation, and the water will be
diverted for storage. Water level indication, sampling, and manually controlled
pump-out capabilities will be provided. The water level will be monitored
during periodic inspections. The Remote Monitoring and Control System will be
shut down. One exhaust fan will remain operable; however, it will be shut down.
Building lighting will be operable; however, it will be turned off except
during periodic inspections. One building transformer room will remain
energized. Some breakers will be closed to other transformer rooms, as
required, to provide power to equipment. All other breakers will be
de-energized. Roofs will be repaired as required to maintain structural
integrity and prevent rainwater intrusion. Maintenance of the safety envelope
around P Area will require seven to ten full-time employees, who will be
located on the premises. The estimated deactivation work schedule is three
years with the present resources available. The estimated cost is $15 million.
POST-DEACTIVATION SURVEILLANCE AND MAINTENANCE
P Area post-deactivation and surveillance and maintenance activities will
include regularly scheduled monitoring of basin pump operation and routine
facility maintenance to maintain roof integrity. No waste of significant volume
is expected to be generated during post-deactivation surveillance and
maintenance. Most of this waste should be in the form of personal protection
clothing and equipment, and all should be compactable low-level waste. The
estimated cost for post-deactivation activities is $1.5 million per year. These
activities are projected to last two to three years, after which the Department
expects that the Environmental Restoration program will initiate
decontamination and decommissioning activities.
M Area Alloy Fabrication Facilities
M Area facilities were designed for machine fabrication of special fuel
assemblies that contained targets used in the production of special nuclear
materials. As such, they are similar to those structures found in nonnuclear
metal fabrication and finishing operations. These facilities were also used as
safe storage for the assemblies prior to use in the reactor areas. Recently,
these facilities were used to stabilize existing stockpiles by consolidating
(melting) fabricated assemblies into billets. These billets have been stored in
another facility until the Oak Ridge Operations Office can receive them. The
area is being decontaminated, and the facilities are being made available for
commercial business operations. All stabilization activities will be completed
by FY 2000.
PRE-STABILIZATION SURVEILLANCE AND MAINTENANCE
The pre-stabilization activities, which primarily involved de-inventory of
large quantities of depleted uranium cores, excess enriched uranium, lithium
aluminum tubes, aluminum stock, and miscellaneous scrap, are scheduled for
completion in July 1996.
STABILIZATION
The stabilization phase is under way. Facility stabilization for M Area
production facilities (except the Liquid Effluent Treatment Facility, the 316-M
Chemical Storage Pad, and the laboratories) is forecast for completion by March
1996. Due to the required waste supernatant processing and sludge inventory,
the Liquid Effluent Treatment Facility is not forecast to complete
stabilization, tank cleaning, and closure activities until September 1998.
POST-STABILIZATION SURVEILLANCE AND MAINTENANCE
The post-stabilization surveillance and maintenance activities involve periodic
surveillance and inspection of the facilities by operations personnel, survey
of the facilities by radiological control operations personnel, and preventive
and corrective maintenance of necessary high-efficiency particulate air exhaust
systems, electrical substations, building lighting, fire protection systems,
and back-up diesel generators. Concurrent with these surveillance and
maintenance activities, deactivation work is being done. This approach will
result in a cost savings by reducing surveillance and maintenance costs in the
future.
DEACTIVATION
The facility deactivation phase requires limited isolation activities that will
be implemented after the Liquid Effluent Treatment Facility is stabilized.
Deactivation of M Area facilities is scheduled for FYs 1996 through 2000 and
will include deactivation and isolation of utilities, deactivation of
unnecessary security systems, and deactivation of nuclear incident monitors.
As each facility is phased out, its operating systems will be deactivated to
the extent practicable. The electrical systems will be tagged, and only
required lighting, alarms, and fire protection systems will remain active.
Other systems are to be blinded or locked out. Where possible, utilities will
be isolated at facility entrances and blanked or tagged out to leave the area
safe for the routine surveillance tours. Process and service drains will remain
open to the Liquid Effluent Treatment Facility. As facilities are cleared and
drains are checked, provisions will be made to provide direct outfall to the
storm sewer, and process sewer drains will be sealed, pending permit revisions.
The estimated cost for this phase is approximately $12 million.
POST-DEACTIVATION SURVEILLANCE AND MAINTENANCE
This phase will include establishing cost-effective surveillance and
maintenance while meeting environmental, safety, and health requirements. In
addition, it will include maintaining facilities in compliance with Department
Orders, standards, codes, and regulatory requirements.
A minimal level of activity will be continued to ensure that facilities are
maintained in a safe and environmentally sound manner. These activities include
routine waste handling, environmental effluent monitoring, emergency
preparedness, fire protection surveillance and maintenance, freeze protection,
security systems operation and maintenance, general plant housekeeping and
maintenance, radiological monitoring, compliance activities, occurrence
reporting, and audit and assessment closures. The estimated cost for this phase
is approximately $10 million.
Landlord Facilities
The actions described here apply to the largest grouping of facilities within A
Area, which is the principal administrative and service area of Savannah River
Site. Current, previous and near-term continuing use of these facilities is
anticipated in order to house and support administrative offices, central
laboratories and their direct infrastructure service, and a number of
centralized maintenance and support functions (for example, machine shops) that
service organizations and areas across the Savannah River Site. Size and
functions of the 179 separate facilities within this scheduling transfer unit
range from a two-square meter (21-square foot) sewage test station to the
20,000-square meter (215,000-square foot) main laboratory building. The
complexity and diversity of facilities dictates that this scheduling transfer
unit will be further broken into smaller groupings for planning, management,
and execution.
Many of these facilities are currently classified as uncontaminated. Within
this group, a large number should be candidates for immediate decommissioning
without prior transfer to the Environmental Restoration program, and some of
the smaller facilities are expected to be retired and decommissioned in advance
of the identified transfer date by consolidating and, in some cases,
privatizing services. Contamination types and levels in this group of
facilities are related to the function of the facility. Power facilities are
likely to be contaminated by asbestos and, possibly, chemicals. Laboratory
facilities may have a spectrum of radiological contamination, chemical
contamination, and mixed waste.
PRE-DEACTIVATION/STABILIZATION SURVEILLANCE AND MAINTENANCE
Prior to deactivation, the facilities will be assessed in detail and classified
to confirm the extent and type of any contamination and to establish a
time-phased plan for stabilization. This assessment will also consider service
provided, organizations or missions affected by the service, feasibility for
early suspension or relocation of the supported service (for example,
administrative office), and the relative ease of decommissioning. This survey
will support the preparation of specific strategies for stabilization or
removal of the contaminants consistent with the integrated area deactivation
schedule and the schedule(s) for deactivation of supported facilities outside A
Area.
STABILIZATION
A Area stabilization activities consist primarily of the removal and
disposition of radionuclides, chemicals, and hazardous materials from
contaminated facilities. Some degree of system flushing or mechanical cleanout
will be required in the laboratory areas to reduce radioactive and chemical
deposits to acceptable levels. Stabilization schedules will have to be
integrated with deactivation schedules for the tank farms and other facilities
that may have to receive and treat these materials. In situ stabilization or
removal of asbestos-containing materials will be consistent with the regulatory
requirements and risk assessments in effect at that time.
POST-STABILIZATION SURVEILLANCE AND MAINTENANCE
Surveys will be conducted and evaluated to document that residual levels of
radionuclides, chemicals, and other contaminants are within tolerance
thresholds and are appropriately documented. This will provide a basis for
determining the technical and economic feasibility of salvaging and selling
furnishings, fixtures, instrumentation, and equipment from those facilities
that can be clearly determined to be within threshold limits for type and
degree of contamination.
DEACTIVATION
Fire detection and protection systems will be left in place and operable,
pending case-by-case decisions on reuse or decommissioning. Minimal lighting
for safe walk-about will be left operable. Process and domestic water supplies
will be isolated outside facilities. Inside drains will be opened. Sump pumps,
if installed, and the power supplies to those pumps will be left in place and
operable. Natural draft ventilation will be established. Records and documents
will be cataloged, boxed, stored or shredded, and recycled, as appropriate.
Office furnishings, computer systems, and telecommunications equipment will be
removed for reuse or excess. Salvageable instrumentation; equipment; fixtures;
piping; process systems; components; utility and heating, ventilation, and air
conditioning systems; instrumentation; and power cabling will be removed to the
extent warranted by salvage economics. Equipment for which salvage is either
technically or economically unfeasible will be left in place unless it poses a
fire hazard.
POST-DEACTIVATION SURVEILLANCE AND MAINTENANCE
Only a minimal degree of surveillance should be necessary for A Area
facilities. Laboratory facility systems not removed will be surveyed on a
yearly basis to confirm residual radioactivity levels, and the results will be
documented. Only a minimal amount of maintenance should be necessary and will
principally include roof inspections and repair.
Additional Scheduling Transfer Units
These facilities consist of the reactors/reactor materials facilities in R, D,
C, K, and L Areas and landlord facilities in Areas M, D, R, S, T, P, C, K, B,
F, N, H, L, which are not discussed in this report. Their scopes of work and
nature of activities are similar to those reactor and landlord facilities
previously discussed. Collectively, these costs represent 17 percent of the
Nuclear Material and Facility Stabilization program cost estimate. The reactor
facilities will be transferred to the Environmental Restoration program
beginning in FY 1999 (R Area Reactor). The last reactor to transfer will be L
Area Reactor in FY 2014. All landlord facilities will be transferred beginning
in FY 2001 through FY 2019.
Direct Program Management/Support
Program management involves the entire Nuclear Material and Facility
Stabilization program work scope and comprises activities directly related to
the cost-effective completion of program objectives. This includes planning,
scheduling, estimating, and baseline management and reporting, and it is
provided by program personnel. In all these areas, program management support
is required to oversee the management and operating contractor and to assess
performance on a regular basis through the established award fee process.
Direct support activities for ongoing stabilization and deactivation activities
in such areas as facility management and maintenance, environmental compliance
and reporting, safety and health, legal/permitting, financial management and
accounting, quality assurance, and personnel training are tailored to meet the
program and the Savannah River Site objectives and are provided from a
centralized source. Both program management and direct support services are
tracked and charged directly to the program. They are projected to average less
than 29 percent of the total program cost through FY 2001 with a projected
downward trend.
As discussed earlier in the narrative, the Office of Defense Programs ran the
majority of the Savannah River Site until FY 1995. Because they were the
largest program at the site, they paid for a large portion of site-wide
activities (e.g., providing utilities, maintaining grounds and roads) that
benefit all programs. As facilities are transferring from Defense Programs to
the Nuclear Material and Facility Stabilization program, the Nuclear Material
and Facility Stabilization program is also taking responsibility for a large
portion of the above mentioned support activities. These support costs are
reflected in the estimated costs for landlord activities, as well as Direct
Program Management/Support costs for the Nuclear Material and Facility
Stabilization program (the current landlord at the Savannah River Site).
Nuclear Material and Facility Stabilization Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996 Dollars)
|
| |
|
| F Area - Canyon and Supporting Facilities
|
|
|
|
|
|
|
|
|
| Stabilization
|
106,535
|
17,754
|
|
|
|
|
|
|
| Post-Stab. Surveil. and Maintenance
|
|
36,643
|
|
|
|
|
|
|
| Deactivation
|
|
12,072
|
51,841
|
|
|
|
|
|
| Post-Deact. Surveil. and Maintenance
|
|
|
|
3,693
|
|
|
|
|
| F Area - Building 235-F, Metallurgical Facilities
|
|
|
|
|
|
|
|
|
| Stabilization
|
11,436
|
4,460
|
|
|
|
|
|
|
| Post-Stab. Surveil. and Maintenance
|
|
1,761
|
|
|
|
|
|
|
| Deactivation
|
|
6,391
|
4,971
|
|
|
|
|
|
| Post-Deact. Surveil. and Maintenance
|
|
|
852
|
|
|
|
|
|
| F Area - Building 247-F and Supporting Facilities
|
|
|
|
|
|
|
|
|
| Post-Stab. Surveil. and Maintenance
|
2,158
|
|
|
|
|
|
|
|
| Deactivation
|
4,319
|
2,130
|
|
|
|
|
|
|
| Post-Deact. Surveil. and Maintenance
|
|
568
|
|
|
|
|
|
|
| H Area - Canyon and Supporting Facilities
|
|
|
|
|
|
|
|
|
| Stabilization
|
85,549
|
16,333
|
|
|
|
|
|
|
| Post-Stab. Surveil. and Maintenance
|
|
30,252
|
|
|
|
|
|
|
| Deactivation
|
|
9,232
|
40,478
|
|
|
|
|
|
| Post-Deact. Surveil. and Maintenance
|
|
|
|
3,125
|
|
|
|
|
| P Area - Reactor and Supporting Facilities
|
|
|
|
|
|
|
|
|
| Deactivation
|
1,882
|
|
|
|
|
|
|
|
| Post-Deact. Surveil. and Maintenance
|
436
|
|
|
|
|
|
|
|
| M Area - Alloy Fabrication Facilities
|
|
|
|
|
|
|
|
|
| Deactivation
|
1,630
|
|
|
|
|
|
|
|
| Post-Deact. Surveil. and Maintenance
|
431
|
|
|
|
|
|
|
|
| A Area - Site Services Facilities
|
|
|
|
|
|
|
|
|
| Pre-Stab. Surveil. and Maintenance
|
|
|
7,502
|
3,751
|
|
|
|
|
| Stabilization
|
|
|
|
6,480
|
|
|
|
|
| Post-Stab. Surveil. and Maintenance
|
|
|
|
750
|
|
|
|
|
| Deactivation
|
|
|
|
9,269
|
|
|
|
|
| Post-Deact. Surveil. and Maintenance
|
|
|
|
375
|
|
|
|
|
| Additional Scheduling Transfer Units
|
|
|
|
|
|
|
|
|
| Pre-Stab. Surveil. and Maintenance
|
240
|
1,283
|
6,874
|
1,129
|
|
|
|
|
| Stabilization
|
16,874
|
16,106
|
15,254
|
17,123
|
14,203
|
14,203
|
14,203
|
|
| Post-Stab. Surveil. and Maintenance
|
|
|
86
|
497
|
|
|
|
|
| Deactivation
|
59,552
|
27,909
|
14,111
|
5,941
|
|
|
|
|
| Post-Deact. Surveil. and Maintenance
|
724
|
853
|
281
|
652
|
49 |
|
|
|
| Direct Program Management/Support
|
277,975 |
196,593
|
143,857
|
61,812
|
74,082
|
34,877
|
73,700
|
|
| Total |
569,741
|
380,341
|
286,106
|
114,596 |
88,334
|
49,080
|
87,903
|
|
(Nuclear Material and Facility Stabilization Activities Cost Estimate table
continued on the following page.)
Nuclear Material and Facility Stabilization Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996 Dollars)
|
| |
2040
|
2045
|
2050
|
2055
|
2060
|
2065
|
| F Area - Canyon and Supporting Facilities
|
|
|
|
|
|
|
|
|
| Stabilization
|
|
|
|
|
|
|
|
621,443
|
| Post-Stab. Surveil. and Maintenance
|
|
|
|
|
|
|
|
183,217
|
| Deactivation
|
|
|
|
|
|
|
|
319,565
|
| Post-Deact. Surveil. and Maintenance
|
|
|
|
|
|
|
|
18,464
|
| F Area - Building 235-F, Metallurgical Facilities
|
|
|
|
|
|
|
|
|
| Stabilization
|
|
|
|
|
|
|
|
79,479
|
| Post-Stab. Surveil. and Maintenance
|
|
|
|
|
|
|
|
8,806
|
| Deactivation
|
|
|
|
|
|
|
|
56,811
|
| Post-Deact. Surveil. and Maintenance
|
|
|
|
|
|
|
|
4,260
|
| F Area - Building 247-F and Supporting Facilities
|
|
|
|
|
|
|
|
|
| Post-Stab. Surveil. and Maintenance
|
|
|
|
|
|
|
|
10,789
|
| Deactivation
|
|
|
|
|
|
|
|
32,249
|
| Post-Deact. Surveil. and Maintenance
|
|
|
|
|
|
|
|
2,841
|
| H Area - Canyon and Supporting Facilities
|
|
|
|
|
|
|
|
|
| Stabilization
|
|
|
|
|
|
|
|
509,409
|
| Post-Stab. Surveil. and Maintenance
|
|
|
|
|
|
|
|
151,259
|
| Deactivation
|
|
|
|
|
|
|
|
248,551
|
| Post-Deact. Surveil. and Maintenance
|
|
|
|
|
|
|
|
15,624
|
| P Area - Reactor and Supporting Facilities
|
|
|
|
|
|
|
|
|
| Deactivation
|
|
|
|
|
|
|
|
9,411
|
| Post-Deact. Surveil. and Maintenance
|
|
|
|
|
|
|
|
2,180
|
| M Area - Alloy Fabrication Facilities
|
|
|
|
|
|
|
|
|
| Deactivation
|
|
|
|
|
|
|
|
8,148
|
| Post-Deact. Surveil. and Maintenance
|
|
|
|
|
|
|
|
2,155
|
| A Area - Site Services Facilities
|
|
|
|
|
|
|
|
|
| Pre-Stab. Surveil. and Maintenance
|
|
|
|
|
|
|
|
56,262
|
| Stabilization
|
|
|
|
|
|
|
|
32,402
|
| Post-Stab. Surveil. and Maintenance
|
|
|
|
|
|
|
|
3,749
|
| Deactivation
|
|
|
|
|
|
|
|
46,344
|
| Post-Deact. Surveil. and Maintenance
|
|
|
|
|
|
|
|
1,875
|
| Additional Scheduling Transfer Units
|
|
|
|
|
|
|
|
|
| Pre-Stab. Surveil. and Maintenance
|
|
|
|
|
|
|
|
47,627
|
| Stabilization
|
14,203
|
|
|
|
|
|
|
610,848
|
| Post-Stab. Surveil. and Maintenance
|
|
|
|
|
|
|
|
2,911
|
| Deactivation
|
|
|
|
|
|
|
|
537,563
|
| Post-Deact. Surveil. and Maintenance
|
|
|
|
|
|
|
|
12,790
|
| Direct Program Management/Support
|
22,411
|
|
|
|
|
|
|
4,426,536
|
| Total |
36,614
|
|
|
|
|
|
|
8,063,567
|
| * Total Life Cycle is the sum of the annual costs in constant FY
1996 dollars.
|
Environmental Restoration Section
|
 |