|
Home
BEMR
Contents
U.S.
Map
WYOMING UMTRA SITES
The Riverton and Spook former processing sites are two of 24 uranium mill
processing sites designated by the Uranium Mill Tailings Radiation Control Act
for remediation by the Department of Energy. During the 1960s, private firms
processed most of the uranium ore mined in the United States for the Atomic
Energy Commission, a predecessor of the Department of Energy. Congress passed
the Act in 1978 in response to public concern regarding potential health
hazards from long-term exposure to uranium mill tailings. It authorized the
Department of Energy to stabilize, dispose of, and control uranium mill
tailings and other contaminated material at 24 uranium mill processing sites
and vicinity properties. For a general discussion of the UMTRA Program, see the
overview presented in the New Mexico section of this report.
The cost estimate model used for this report provides costs for each of the
UMTRA sites. All costs for waste management activities, program management, and
relevant landlord activities attributable to the Department are provided for
within the scope of the environmental restoration. There are no Uranium Mill
Tailings Radiation Control Act sites with either current or planned nuclear
material and facility stabilization activity needs. Funding for all sites is
100 percent nondefense.
RIVERTON, WYOMING (UMTRA SITE)
The Riverton mill site and tailings pile covered 88 hectares (218 acres) located
four kilometers (2.5 miles) southwest of the center of Riverton on the north
side of State Highway 789 in Fremont County, Wyoming. Before remedial action,
the tailings pile occupied about 29 hectares (72 acres) at an average depth of
1.2 meters (4 feet). The site is located within the boundaries of the Wind
River Indian Reservation, which is occupied by the Shoshone and Arapaho Tribes;
however, the parcel of land upon which it sits is privately owned.
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
| |
|
|
|
| Environmental Restoration
|
551
|
190
|
364
|
914
|
1,721
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
1,645 |
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
406
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
689
|
765
|
522
|
|
|
|
|
9,879
|
| Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The mission of the mill site was to provide uranium for the United States
Government. The source of contamination was the residual tailings that remained
after the milling process extracted the uranium. In 1958, Susquehanna-Western,
Inc., formerly known as Fremont Minerals, Inc., became the operational owner of
the site. Solution Engineering Corporation of Alice, Texas, later acquired the
mill and owned it until 1978 when Lome Drilling and Well Service, a Wyoming
corporation, purchased most of the site. Western Nuclear, Inc. owned part of
the mill area after Susquehanna-Western and operated a sulfuric acid plant at
the site. In 1985, Chemical Marketing Services purchased the sulfuric acid
plant, and this company operates it today. In 1987, the State of Wyoming
acquired the tailings pile and mill site from Lome Drilling and Well Service
and will participate in decisionmaking.
SITE MAP
The Environmental Management program is responsible for cleaning up surface-
and ground-water contamination at the UMTRA sites. The Uranium Mill Tailings
Radiation Control Act designated the residual radioactive material found at
this site for cleanup and stabilization. The Act directed the Environmental
Protection Agency to promulgate standards (Code of Federal Regulations, Title
40, Part 192) and the Department of Energy to perform the cleanup. It also
assigned the Nuclear Regulatory Commission to oversee and certify the cleanup,
and license the completed disposal cell.
FUTURE USE
The site will be released for use consistent with existing land-use controls.
Since the tailings were disposed of at an active Title II facility, the
Department of Energy does not need to acquire the former mill site land.
Ownership of the processing site will revert from the State of Wyoming to
Industrial/Commercial use following completion of the UMTRA Surface Project.
However, the Department of Energy must fulfill the requirements of the UMTRA
ground-water restoration program and will maintain control of the property
until all phases of the Riverton UMTRA Project are complete.
ENVIRONMENTAL RESTORATION
Surface remedial action has been completed and the source of contamination has
been stabilized. However, residual milling-related contaminated ground water
remains and will be addressed in the second phase of the UMTRA Project.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2015
|
2020
|
2025
|
2030
|
| UMTRA Ground water
|
|
|
|
|
|
|
|
|
| Assessment
|
143
|
38
|
59
|
|
|
|
|
1,200
|
| Remedial Action
|
5
|
145
|
23
|
|
|
|
|
866
|
| Direct Program Management/Support
|
541
|
582
|
440
|
|
|
|
|
7,813
|
| Total |
689
|
765
|
522
|
|
|
|
|
9,879
|
| Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Surface Project
Remedial action at the Susquehanna-Western uranium mill tailings site began in
May 1988 and was completed in September 1990. The Nuclear Regulatory Commission
certified the processing site in January 1995. The cleanup involved relocating
the tailings and contaminated materials from vicinity properties to the UMETCO
facility located within the Gas Hills Uranium Mining District approximately 72
kilometers (45 miles) east of Riverton. The Gas Hills Uranium Mining District
contains several active uranium mill sites licensed by the Nuclear Regulatory
Commission. The tailings were consolidated and stabilized with the existing
tailings at this Nuclear Regulatory Commission-licensed commercial disposal
facility. UMETCO is responsible for all long-term surveillance and monitoring
costs associated with the disposal cell.
After decontamination of the Susquehanna-Western mill tailings site, the
disturbed areas at the site were backfilled with uncontaminated soil to a level
compatible with the surrounding terrain, recontoured to promote surface
drainage, and revegetated.
The Riverton remedial action program included cleanup of all offsite properties
contaminated with tailings from the Riverton site. Contaminated materials from
vicinity properties were also transferred to the UMETCO facility.
Ground-Water Compliance Project
The Department is developing a Programmatic Environmental Impact Statement
pertaining to all 24 UMTRA sites. For a discussion of the Programmatic
Environmental Impact Statement, see the UMTRA program narrative in the New
Mexico section of this report. Site-specific National Environmental Policy Act
documentation will be developed to propose an appropriate ground-water
compliance strategy and reasonable alternatives for the Riverton site once the
Programmatic Environmental Impact Statement is completed.
This report assumes a ground-water compliance strategy of natural flushing,
based on data collected over the past decade and a site conceptual model. With
this approach, contamination concentrations are expected to be reduced
naturally to appropriate concentration limits within 100 years, as required by
Environmental Protection Agency standards. If an alternate compliance strategy
is selected, the Department will adjust the cost estimates accordingly. For all
types of ground-water compliance strategies, once the Nuclear Regulatory
Commission determines that the site is in compliance with Subpart B of the
Environmental Protection Agency Standards and the site is certified, no
additional long-term surveillance or monitoring will be conducted.
The total volume of contaminated ground water is estimated to be 870 million
liters (230 million gallons). The contaminant plume extends offsite. The
ground-water contaminants of potential concern are manganese, uranium, sulfate,
vanadium, and nickel.
The following milestone dates have been established for planning purposes.
Major Ground-Water Compliance Project Milestones
| Site Observational Work Plan
|
2000
|
|
Publish Environmental Assessment/Finding of No Significant Impact
|
2001
|
|
Publish Remedial Action Plan
|
2002
|
|
Compliance Strategy
|
2007
|
|
Licensing
|
2009
|
In January 1994, to obtain additional characterization information regarding
contaminant distribution in the surficial, semiconfined, and confined aquifers,
samples were collected from 15 monitoring wells that had been installed in
1993. Nine domestic wells located in the confined aquifer were sampled to
complete an assessment of potential impacts to domestic water sources located
near the site.
Other hydrologic data gathered during 1994 included ground-water and
surface-water elevations. To collect nearly continuous data on ground-water
levels, pressure transducers and data loggers were installed in nine monitoring
wells in 1994. Ground-water level measurements were also made in 14 other
wells. In addition, surface-water level measuring points were established near
the Little Wind River and at the wetland east of the site. These points will be
surveyed, and periodic readings will be made in the future.
Ground-water monitoring information obtained during 1994 confirmed the
previously established concepts regarding the extent of contamination in the
vicinity of the Riverton site. Environmental Protection Agency maximum
concentration limits were only exceeded in surficial aquifer samples from
beneath the southeastern edge of the former processing site and immediately
downgradient (southeast) of the site. Samples from domestic wells located near
the site confirmed that site-related contamination has not impacted the
confined aquifer. Consequently, continued use of the ground water from the
confined aquifer for domestic purposes is not expected to pose any risks to
human health.
During the first ten years of remediation, verification monitoring will be
performed to ensure that natural flushing is working according to predictions.
The data collected during this phase will be provided to the Nuclear Regulatory
Commission in a confirmation report. If the Nuclear Regulatory Commission
accepts this report, the site will be turned over to the Grand Junction
Projects Office's Long-Term Surveillance and Maintenance program. This program
will conduct "compliance monitoring" for up to 90 years. When maximum
concentration limits or background or alternate concentration limits have been
achieved, a certification report will be prepared to close out all Department
of Energy liability at this site.
Direct Program Management/Support
Program management supports management efforts for the National Environmental
Policy Act process, site characterization and licensing, public
information/participation, applicable state and federal regulator costs,
quality assurance audits, program and management support for the technical
assistance contractor, special studies, document control, technical assistance
contractor site and technical management, cost and schedule controls, planning
and preparation of the federal budget, and the Environmental Management
Progress Tracking System.
FUNDING ESTIMATE
The following table presents estimated funding information for the Riverton
site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
689
|
765
|
522
|
|
|
|
|
9,879
|
| Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|
 |