|
Home
BEMR
Contents
U.S.
Map
The Gasbuggy site and the Gnome-Coach site are administered by the Nevada
Operations Office. A more thorough description of the environmental activities
managed by the Nevada Operations Office can be found in the Nevada
Offsite Program narrative.
LOCALITY MAP GASBUGGY
LOCALITY MAP GNOME-COACH
Estimated Site Total
| (Thousands of Current Year Dollars)
|
| |
|
|
|
| Environmental Restoration
|
86 |
1,155
|
2,391
|
5,468
|
4,394
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation |
105
|
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
330 |
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2030
|
| Environmental Restoration
|
2,474 |
281
|
83 |
44
|
12 |
8
|
|
14,511
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The Gnome-Coach and Gasbuggy sites were part of the Plowshare program, which
was a series of nuclear and conventional tests conducted by the Atomic Energy
Commission to explore peacetime uses of nuclear explosives. The Project Gnome
test was conducted in bedded salt approximately 31 miles southeast of Carlsbad,
New Mexico in December 1961. The purpose of the test was to determine the
effects and products of a nuclear explosion in a salt medium. Because the test
vented radioactivity into the atmosphere, Project Coach, another experiment
scheduled for this location, was canceled.
The Gasbuggy Site, located approximately 88 kilometers (55 miles) east of
Farmington, New Mexico, was the location of a single subsurface nuclear test in
December 1967. The purpose of the test was to determine whether or not nuclear
explosions would stimulate release of natural gas not recoverable by
conventional methods. This test was the first joint government-industry gas
stimulation experiment.
The Gasbuggy site includes radioactive contamination of the deep bedrock around
the shot cavity, contamination of the bedrock from the injection of tritiated
water, possible surface contamination from the gas flaring and decontamination
activities, and near-surface hazardous waste contamination from the closed mud
pits. Ground water is the most likely transport medium for the deep
contamination; however, because of the depth of the contamination (in excess of
1,290 meters [4,240 feet]) exposure to humans from this material is unlikely.
There has been no confirmation regarding the existence of surface contamination
from the gas flaring and decontamination operations or the abandoned drill-back
mud pit.
Contamination at the Gnome-Coach site consists of radioactive contamination of
the deep bedrock around the shot cavity and the emplacement drift, the location
for the disposal of contaminated soil. Contamination is also present in a
shallower aquifer from a tracer test that was conducted shortly after the test.
Ground water is the most likely transport medium for the deep contamination;
however, because the shot cavity is in dry salt, exposure to humans from this
material is unlikely. The Department is conducting modeling and field
investigations to determine if this is a concern. Surface contamination of this
site occurred when the shot vented shortly after the detonation.
FUTURE USE
Preliminary hydrologic studies and ground-water characterization at these sites
is in progress; therefore, a definitive future-use plan is not complete.
However, this report assumes the surface of the sites will be cleaned to a
level that permits a mix of Open Space and Recreational use. The future-use
designation for subsurface of the sites will remain Controlled Access. The
Department of Energy will maintain control of the subsurface and retain all
mineral rights; any disturbance of the subsurface (for example, well drilling,
mining, excavation) will require Department approval. The final future use will
be negotiated with the State of New Mexico. The Department will maintain both
sites under a mix of Industrial, Open Space, and Controlled Access use until
remedial action is complete.
ENVIRONMENTAL RESTORATION
Surface contamination at the Gasbuggy site is the result of fallout from the
gas flaring and equipment decontamination operations. Surface contamination at
the Gnome-Coach site is the result of an unplanned vent at the time of the
Gnome test. These areas were reportedly cleaned up during site cleanup and
decommissioning in the 1968 to 1969 time frame, but the Department has not
confirmed this. The drill-back mud pit at the Gasbuggy site has the potential
to be contaminated with low-level waste; however, this assumption has not been
confirmed.
The cleanup strategy at both sites will include characterizing ground-water
flow and area of contamination, assessing risk, and modeling contaminant
movement away from the shot cavities. The focus will be on tritium, since it is
the most mobile of the potential radiological contaminants. Attenuation
characteristics provide for little migration of other radionuclides. Tritium
results will indicate whether other radionuclides should be included in the
source evaluation. Maximum use will be made of existing data, including
monitoring data collected from the Long-Term Hydrologic Monitoring program well
networks.
Major Environmental Restoration Activity Milestones
| Gasbuggy
|
| Sample Gas Well Area
|
1997
|
|
Preliminary Site Characterization Report
|
1998
|
|
Risk Assessment Report
|
1998
|
|
Characterize Mud Pits
|
1998
|
|
Long-Term Surveillance and Monitoring
|
2025
|
|
Gnome-Coach
|
| Characterize Surface Contamination
|
1996
|
|
Preliminary Site Characterization Report
|
1998
|
|
Risk Assessment Report
|
1998
|
|
Characterize Ground Water (Tracer Study)
|
1999
|
|
Long-Term Surveillance and Monitoring
|
2025
|
ASSESSMENT
Assessment activities provide for continued data gathering and analysis of the
Gasbuggy and Gnome-Coach sites in New Mexico. This activity defines the
magnitude and extent of surficial contamination and risks associated with that
contamination through evaluation of existing information. These activities
include characterizing the physical setting and testing areas, defining the
occurrence of contamination, and identifying pathways to reach a potential
receptor. The risks to receptors will also be calculated using standard risk
assessment procedures. If risks exceed acceptable limits, the Department will
initiate remedial actions at the New Mexico test sites. Risk assessment
activities are not planned to begin until FY 1996.
Activities completed to date include the removal of production tubing at
Gasbuggy and completion of a casing integrity test. Ground water has been
characterized at Gasbuggy wells, and preliminary hydrologic studies at
Gnome-Coach have been completed.
REMEDIAL ACTION
This baseline estimate assumes subsurface waste in and around the shot cavities
will not be removed, and long-term monitoring will continue. The surface sites
and facilities will be remediated to appropriate levels and the waste treated
and disposed of offsite.
Surface contamination occurred at the Gasbuggy site as a result of the gas
flaring operation. No cleanup of soils around the flare stack was reported.
Surface soils at Gasbuggy around the flare stack will be removed. Site waste in
and around shot cavities will not be removed. This estimate assumes 2,926 cubic
meters (3,850 cubic yards) of hazardous waste will be shipped to an
appropriately permitted commercial facility for disposal. Remedial action at
the Gasbuggy site will begin in FY 1999 and is assumed to be complete in FY
2001.
Surface contamination at the Gnome-Coach site resulting from venting of the
shot at the time of the detonation may need to be removed. All of this
contamination was reportedly cleaned up. This estimate assumes no additional
surface cleanup will be required.
LONG-TERM SURVEILLANCE AND MONITORING
Monitoring of the sites began in 1992 as part of the Long-Term Hydrologic
Monitoring program. Monitoring consists of sampling selected ground-water and
surface-water collection locations around each site. Sampling requires
approximately one week per year per site plus the analysis of approximately 20
samples per site per year. Costs for this monitoring program are included in
the assessment and remediation costs. However, after remedial action is
complete, all costs are reflected under long-term surveillance and monitoring.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2030
|
| Nevada Offsite - Gasbuggy
|
|
|
|
|
|
|
|
|
| Assessment |
579
|
22 |
|
|
|
|
|
3,005 |
| Remedial Action |
220
|
|
|
|
|
|
|
1,100
|
| Nevada Offsite - Gnome-Coach
|
|
|
|
|
|
|
|
|
| Assessment |
1,125
|
45 |
|
|
|
|
|
5,848 |
| Remedial Action |
550
|
121 |
|
|
|
|
|
3,355 |
| Long-Term Surveil. and Monitoring
|
|
94 |
83 |
44
|
12 |
8
|
|
1,203
|
| Total |
2,474
|
281 |
83
|
44 |
12
|
8 |
|
14,511 |
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FUNDING ESTIMATE
The following table presents estimated funding information for the Gasbuggy and
Gnome-Coach sites.
Defense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2030
|
| Environmental Restoration
|
2,474 |
281
|
83 |
44
|
12 |
8
|
|
14,511
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
COMPARISON WITH PREVIOUS ESTIMATE
Environmental Management costs at the Gasbuggy and Gnome-Coach sites are
limited to Environmental Restoration program assessment, remediation, and
surveillance and monitoring costs. The 1996 life-cycle cost estimate is $14.5
million, a slight increase over the 1995 estimate of $12.6 million. This
increase reflects the application of a three percent annual escalation factor
and the adjustment of pre-FY 1996 costs to reflect actual costs through FY
1995.
|
 |