|
Home
BEMR
Contents
U.S.
Map
The Nevada Test Site is located approximately 104 kilometers (65 miles)
northwest of Las Vegas, Nevada in a sparsely populated region about the size of
the State of Rhode Island. The Tonopah Test Range is approximately 240
kilometers (150 miles) northwest of Las Vegas. The site encompasses 3,510
kilometers (1,350 square miles) of desert and mountainous terrain, and is
surrounded on three sides by the Nellis Air Force Range, which provides a
substantial buffer between the site and public lands.
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
| |
|
|
|
| Nuclear Material and Facility Stabilization
|
|
|
|
|
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| Environmental Restoration
|
48,649
|
62,591
|
57,028
|
58,690
|
60,370
|
|
| Waste Management
|
32,887
|
26,735
|
23,261
|
20,734
|
21,146
|
|
| Total |
81,536
|
89,326
|
80,289
|
79,425
|
81,516
|
|
| 1996 Appropriation
|
65,944 |
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
76,292
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
|
| Nuclear Material and Facility Stabilization
|
|
37,660
|
47,100 |
43,448
|
11,825
|
|
|
|
| Environmental Restoration
|
54,104 |
52,727
|
59,341
|
60,194
|
61,183 |
62,332
|
62,527 |
|
| Waste Management
|
23,706
|
15,977 |
14,397
|
13,397 |
13,197
|
5,902
|
5,902
|
|
| Total |
77,810
|
106,364
|
120,838
|
117,039 |
86,205
|
68,234 |
68,429
|
|
| |
|
| Nuclear Material and Facility Stabilization
|
|
|
|
|
|
|
|
|
| Environmental Restoration
|
22,292 |
3,854
|
4,138
|
4,467
|
|
|
|
|
| Waste Management
|
5,902
|
5,902
|
5,902
|
5,902
|
5,902
|
5,902
|
5,902
|
|
| Total |
28,194
|
9,756
|
10,040
|
10,369 |
5,902
|
5,902
|
5,902
|
|
| |
2075
|
2080
|
2085
|
2090
|
2095
|
2100
|
| Nuclear Material and Facility Stabilization
|
|
|
|
|
|
|
|
700,166
|
| Environmental Restoration
|
|
|
|
|
|
|
|
2,235,796
|
| Waste Management
|
7,902
|
|
|
|
|
|
|
708,472
|
| Total |
7,902
|
|
|
|
|
|
|
3,644,434
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
For over 40 years, the primary mission of the Department of Energy, Nevada
Operations Office was to conduct field testing of nuclear explosives in
connection with the research and development of nuclear weapons. This testing
was conducted primarily at the Nevada Test Site, which was established in 1950,
when President Truman authorized a continental weapons testing area at the Las
Vegas Bombing and Gunnery Range.
In addition to weapons testing, the Nevada Test Site has also hosted secondary
missions: neutron and gamma-ray interaction studies; open air reactor, nuclear
engine, and nuclear furnace tests; hazardous materials spill response testing;
and a variety of other experiments involving radioactive and nonradioactive
materials conducted by the Department of Defense.
The Department of Energy, Albuquerque Operations Office and the Department of
Defense have historically used the Tonopah Test Range, northwest of the Nevada
Test Site, for research and development of ordnance delivery systems,
electronic combat training missions, and other activities. For cost and project
management efficiency, the Department of Energy has consolidated the management
of all Department of Energy environmental restoration activities for the site
under the purview of the Department of Energy, Nevada Operations Office. This
Baseline Environmental Management Report treats the two sites as one.
SITE MAP #1
Environmental restoration activities at the site, which began in 1989, focus on
characterizing and remediating sites and facilities contaminated as the result
of the historic nuclear testing activities. Contaminants include surface and
subsurface radionuclides; organic compounds; chromium and other metals;
petroleum; and residues from plastics, epoxy, and drilling muds used during
test hole drilling and instrumentation. Most of the materials were released as
an unavoidable consequence of testing activities. Most of the waste generated
was from post-test sampling and construction and/or maintenance operations
associated with testing. Disposal of this waste occurred in landfills,
underground injection, sumps, and leachfields, as well as offsite disposal.
Some residual materials remain in inactive storage tanks. In addition,
approximately 1,200 hectares (3,000 acres) of surface and shallow subsurface
soils are contaminated as the result of safety shots and plutonium-dispersion
tests conducted on the Nevada Test Site and portions of the Tonopah Test Range
and Nellis Air Force Range. When atmospheric and shallow cratering tests are
included, this number increases to 10,900 hectares (27,000 acres). Areas
highlighted in the above map are discussed in the Environmental Restoration
program section.
SITE MAP #2
The Department of Energy, Nevada Operations Office operates a variety of waste
facilities at the Nevada Test Site. Low-level radioactive waste originating
both from the Nevada Test Site and from other U.S. Department of Energy
installations is disposed of onsite. The site also stores the current inventory
of transuranic mixed waste from Lawrence Livermore National Laboratory, pending
shipment to the Waste Isolation Pilot Plant in Carlsbad, New Mexico. Limited
mixed waste disposal for offsite generators will be available on the Nevada
Test Site pending completion of the Site-Wide Environmental Impact Statement in
FY 1996 and approval from the State of Nevada of the Site Treatment Plan. An
expanded mixed waste disposal facility will be constructed when the State of
Nevada issues the Resource Conservation and Recovery Act permit application.
The site remains an active facility for other Department of Energy programs
(the Office of Environmental Management constitutes only 10 percent of the
current Department of Energy budget for the Nevada Site Operations Office).
This estimate assumes the site will remain an active facility for other
Department of Energy activities, and landlord responsibility for the site will
remain with the Department of Energy.
REGULATORY ISSUE
FEDERAL FACILITY AGREEMENT AND CONSENT ORDER
The previous Baseline Environmental Management Report reflected the
Comprehensive Environmental Response, Compensation, and Liability Act as the
central legal driver for cleanup activities. Completion of negotiations with
the State of Nevada has resulted in a Federal Facility Agreement and Consent
Order that governs Department of Energy environmental management activities in
Nevada under the state's Resource Conservation and Recovery Act authority and
its hazardous waste and water pollution control laws.
On November 22, 1995, in a letter to the Nevada Operations Office that
contained review comments on the FY 1996 Department of Energy/Nevada submittal
to the Baseline Environmental Management Report, the state identified key
issues regarding information contained within the submittal. These issues are
addressed in highlighted portions of this report in "Regulatory Issues" sidebar
discussions to assist the reader in understanding the state's position
regarding Environmental Management activities within the state.
|
Because the Nevada Test Site, Tonopah Test Range, and Nellis Air Force Range
are under institutional control, risk to workers and the public is considered
minimal. However, the site conducts risk assessments and interim removal
actions where necessary to ensure the safety of workers and the public.
REGULATORY ISSUE
DISPOSAL OF WASTE GENERATED OFFSITE
"Nevada Test Site land withdrawal orders restrict the use of the site to atomic
testing activities. State officials in Nevada have long contended that the U.S.
Department of Energy must seek both congressional and State approval to use the
site for new activities, such as the disposal of radioactive waste from offsite
generators." (Letter from the State of Nevada to Carl Gertz, Acting Assistant
Manager for Environmental Restoration and Waste Management Division, November
22, 1995).
|
FUTURE USE
This Baseline Environmental Management Report assumes the Nevada Test Site will
remain under Department of Energy institutional control and maintain its
current mix of Industrial, Open Space, and Controlled Access uses. A Site-Wide
Environmental Impact Statement is in progress and a formal land-use plan will
be developed based on the results of that effort. The Department will also
conduct risk assessments, as appropriate, to determine future land uses.
Several public briefings have been held to obtain public input, which has
provided valuable feedback to the Environmental Impact Statement and the
land-use planning process. As the Department completes these activities and
makes final decisions, annual updates of the Baseline Environmental Management
Report will reflect the accumulated data.
In conjunction with the Nevada Test Site-Wide Environmental Impact Statement,
the Nevada Operations Office is developing a Resource Management Plan for the
Nevada Test Site to take advantage of the extensive data collection and public
participation activities associated with the National Environmental Policy Act.
The Department is developing the Resource Management Plan to improve land-use
and resource management planning at the Nevada Test Site. This plan will use
the data in the Technical Site Information document as a starting point, and
will ultimately gather other ongoing management and planning activities under
the comprehensive plan. It will identify the criteria for evaluating the
compatibility of activities with human health and safety, ongoing missions,
existing infrastructures, cultural and natural resources, public values, and
other resource issues and constraints.
REGULATORY ISSUE
FUTURE USE
"State officials contend that any final strategy to address surface soil
contamination at the Nevada Test Site must be developed in the context of
future land uses that embrace the concept of how clean is clean for what use.
Department officials in Nevada are establishing an approach to embrace this
concept by developing a site-wide Resource Management Plan as part of the
Nevada Test Site-Wide Environmental Impact Statement" (Letter from the State of
Nevada to Carl Gertz, Acting Assistant Manager for Environmental Restoration
and Waste Management Division, November 22, 1995).
|
NUCLEAR MATERIAL AND FACILITY STABILIZATION
The facility stabilization and maintenance activities commenced at the Nevada
Test Site in 1995. However, these activities are currently performed by the
Environmental Restoration program. All of the 289 Nevada Test Site facilities
identified on the Surplus Facilities Inventory Assessment listing are potential
candidates for stabilization and maintenance activities pending future
decisions on the missions of the Nevada Test Site. Some of these facilities are
buildings and equipment previously used in support of nuclear tests such as
explosive magazines, fallout shelters, railroad boxcars, etc. The resulting
waste will be managed by the Waste Management program for disposition and is
accounted for in their cost estimate. Completion of stabilization and
maintenance activities is anticipated by 2012.
Nuclear Material and Facility Stabilization Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
|
FY 1996-2000
|
2025
|
2030
|
| Nuclear Material and Facility Stabilization
|
|
37,660
|
47,100 |
43,448
|
11,825
|
|
|
700,166
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
ENVIRONMENTAL RESTORATION
Within the Nevada Test Site and the Tonopah Test Range approximately 2,400
potential corrective action sites require some level of investigation and
possible remediation. Approximately 930 of these sites are related to the
underground testing of nuclear weapons; more than 100 resulted from
above-ground testing. The remaining sites include waste disposal facilities,
leach fields, landfills, storage tanks, injection wells, inactive and abandoned
buildings, and associated equipment contaminated by prior operations, spill
areas, and hundreds of other small sites where unregulated disposal or storage
of waste materials occurred during more than 40 years of operations. The
Department has divided the assessment and remediation of these sites into three
categories: Industrial Sites, which include all sites used in support of
testing operations; Soils Sites, which include all surface and shallow
subsurface soil contamination resulting primarily from historic safety shots;
and Underground Test Areas, which are sites that were impacted by previous
underground testing activities. Activities within the Industrial Sites focus on
physical investigation and remediation of the individual sites. Activities
within Soils Sites focus on defining appropriate cleanup levels (standards do
not exist at this time) and remediating surface soils where risk potentially
exists to workers and the public. Activities within Underground Test Areas
focus on determining the potential boundaries of contamination and the
requirements to monitor the identified boundaries. See the Site Maps for the
location of Environmental Restoration program activities at the Nevada Test
Site and Tonopah Test Range.
Major Environmental Restoration Activity Milestones
| Industrial Sites
|
|
Assessment
|
2015
|
|
Remedial Action
|
2035
|
|
Decommissioning
|
2025
|
|
Soil Sites
|
|
Assessment
|
2025
|
|
Remedial Action
|
2030
|
|
Underground Test Areas
|
|
Assessment
|
1996
|
|
Remedial Action
|
2002
|
|
Site-Wide
|
|
Long-Term Monitoring
|
2050
|
The Department of Energy Albuquerque Operations Office initiated environmental
restoration activities at the Tonopah Test Range in the late 1980s. In 1987,
the Department conducted a preliminary assessment that was evaluated by
Environmental Protection Agency-Region IX in 1988. The Environmental Protection
Agency declared the facility to be in a No Further Action Planned status with
respect to the Comprehensive Environmental Response, Compensation and Liability
Act activities. Corrective actions would, however, continue to be completed
according to the requirements of the Resource Conservation and Recovery Act. In
1993, for logistical reasons, the Albuquerque Operations Office agreed to turn
over environmental restoration responsibilities for this site to the Nevada
Operations Office. Since 1993, the Nevada Operations Office has conducted a
comprehensive inventory of potential release sites and has identified
approximately 40 sites that will require site characterization activities.
Tonopah Test Range is now managed under the Industrial Sites grouping of the
Nevada site.
The following figure describes the process used by the Nevada Office to clean
up a site. The process, which applies to all areas at the Nevada Test Site,
groups all of the sites into Corrective Action Sites and then groups these into
Corrective Action Units to facilitate administration. After a Corrective Action
Unit has been organized, the process to be used to remediate it is identified.
After the office takes several steps mandated by environmental regulations, a
closure report is submitted to the State of Nevada certifying the site has been
closed properly and actions are complete.
The corrective action strategy portion of the Federal Facility Agreement and
Consent Order establishes the methodology by which all other site
investigations and corrective actions will take place. In general, the strategy
calls for sites to be grouped using various combinations of similarity of site
Aowner", functional category, location, and length of time required for
corrective action. The groupings enable economies of scale from commonality of
work, including approach and logistics during assessment and remediation.
Consideration is given to minimizing long-term monitoring when choosing a
remediation approach. Sites will use the Streamlined Approach for Environmental
Restoration, often referred to as SAFER, when it is applicable and acceptable
to the State of Nevada. Sites will consider the probable remediation method
when performing and coordinating assessments. To facilitate the estimating
process, this report has made two assumptions. The first is that activated
metals are considered a source and are estimated in the categories of
rubble/debris and low-level radioactive waste. The second assumption is radon
is not considered to be a significant source because it is controlled by
ventilation in impacted tunnels and exists at near-background levels for
surface-based activities.
Technical Approach to Remediation
Activities
To determine the expected costs and waste volumes for the potential release
sites not yet characterized, parametric modeling and bounding conditions were
used to fill in data gaps. For example, the waste volumes assumed to be
generated at some facilities were calculated by multiplying the square footage
of the facility by contamination factors developed using characterization
information to date. Estimates generated for this document do not include
active sites and sites not yet transitioned to the Environmental Management
program. Such sites include, but are not limited to nuclear shots in the
Pacific (including Bikini Atoll), the Liquefied Gaseous Fuels Test Facility,
and contaminated sites remaining under Department of Defense funding.
Waste disposal for onsite environmental restoration activities takes place
primarily at the Area 3 and Area 5 Radioactive Waste Management Sites on the
Nevada Test Site. All costs for treatment, storage, transportation, and
disposal of waste generated by environmental restoration activities at the
Nevada Test Site are included within the estimated costs for assessment,
remedial action, and decommissioning activities. Bulk low-level waste is
disposed of as containerized bulk waste at the Area 3 site. All other low-level
waste is disposed of at Area 5. Mixed waste is also disposed of in Area 5,
while mixed waste subject to land disposal restrictions is placed on the
Transuranic Waste Pad in Area 5 to await treatment. Hazardous waste is shipped
offsite to approved commercial disposal facilities. Disposal costs for the Area
3 and Area 5 disposal facilities are $446 per cubic meter ($341 per cubic yard)
for FY 1996, $623 per cubic meter ($475 per cubic yard) for FY 1997 through FY
2021, and then $2,402 per cubic meter ($1,833 per cubic yard) through the
outyears.
Industrial Sites
The Nevada Test Site Source Groupings include the assessment and remediation of
"like-waste units", e.g., tunnel muck piles, tunnel ponds, sumps and injection
wells, inactive tanks, leach fields, contaminated waste sites, atmospheric test
debris, and miscellaneous other sites. The subject waste units are the result
(or byproduct) of past testing and support activities at the Nevada Test Site.
The Tonopah Test Range Source Groupings include the assessment and remediation
of contaminated sites on the Tonopah Test Range, such as landfills, storage
tanks, bomblet pits, and construction debris areas. Contamination at the
subject sites is the result of testing ordnance delivery systems employing
mock-ups of nuclear weapons and tests with conventional explosives.
Contaminants include chemicals, lead, explosives, unexploded ordnance items,
and radioactive and mixed waste.
The Environmental Restoration Sites Inventory involves conducting an inventory
of all known release sites (approximately 2,400) and validates information
through photographic monitoring and field verification, including surveys using
global positioning system techniques. New sites are identified through
reviewing archived literature and photographs, visiting sites, and maintaining
an established data base to compile all the information on each site. Existing
and newly identified sites are assigned to the Industrial Sites, Soil Sites, or
Underground Test Areas if remedial action is required. The inventory fulfills
the Nevada Test Site Resource Conservation and Recovery Act Part B applicable
requirements to list solid waste management units. Over 266 closure reports
have been delivered to the state for sites identified in the inventory.
Specific Resource Conservation and Recovery Act Closures provide for closure of
eight industrial sites named in the Resource Conservation and Recovery Act Part
B Permit Application. These waste units were generally used more recently than
Source Groupings Waste Units. Three of the units have been closed: U-3fi
Injection Well, Area 23 Landfill trenches, Area 27 Explosive Ordnance Disposal
Facility. The remaining five facilities include the Area 6 Decontamination
Facility, Area 6 Steam Cleaning Effluent Ponds, Area 23 Building 650 Leach
Field, Area 2 Bit Cutter Shop Injection Well, and U-2bu Subsidence Crater.
Activities in support of these Resource Conservation and Recovery Act closures
include developing and implementing characterization plans, analyzing data,
analyzing risk, preparing characterization reports, developing closure
strategies, and preparing and implementing Resource Conservation and Recovery
Act Closure Plans.
The Resource Conservation and Recovery Act Permit governs all work at the
Industrial Sites for the next two to three years, except decommissioning, which
is currently governed by Department of Energy Orders. All work is governed by
requirements of the Federal Facility Agreement and Consent Order, which
establishes the methodology by which all site investigation and corrective
actions will take place.
ASSESSMENT
Because of the extensive number of sites, most of the Industrial Sites have not
been fully characterized to date. However, initial assessment activities
indicate contamination problems include surface and subsurface soils that have
been impacted by releases from leach fields, sumps, disposal wells, leaking
tanks, and other sources of waste. Contaminants may include petroleum
hydrocarbons, hazardous waste, low-level radioactive materials, and mixed
waste. In general, this report assumes most of the soil contamination related
to the units in question is confined to the vadose zone at the Nevada Test
Site. However, it is possible that Industrial sites at the Tonopah Test Range
have impacted ground water.
Completed activities include work plans for abandoned septic tanks and leach
fields, including sampling; completed characterization of the U-3fi Injection
Well, the Area 27 Explosive Ordinance Disposal Facility, the Area 6 Bit cutter
shop Injection Well, the Tonopah Test Range 5 Points Landfill, the Jr. Hot
Cell, and the EPA Farm. The Department completed field verification on 864
sites, surveyed 670 sites, and identified 134 new sites. Outyears beyond FY
2001 are still being prioritized in site baselining activities. This estimate
assumes assessment activities will continue through 2015.
REMEDIAL ACTION
Because characterization at Industrial Sites is not complete, definitive
remedial action approaches are not available. However, conventional unexploded
ordnance will be detonated in place. Any explosive residue will be detonated on
range, rendering nonhazardous debris, recyclable debris, or nonhazardous solid
waste.
INTERIM REMOVAL AND COMPLETED REMEDIAL
ACTIONS TO DATE
Area 23 Hazardous Waste Trenches
Area 27 Explosive Ordnance Disposal Facility
U-3fi Injection Well
Tonopah Test Range Bomblet Pit
Tonopah Test Range 5 Points Landfill Ordnance Removal
Tonopah Test Range Roller Coaster Sewage Lagoons Ordnance Removal
Tonopah Test Range Area 9 Landfill Ordnance Removal
Tonopah Test Range Area 9 Construction Debris Area Ordnance Removal
Tonopah Test Range Antelope Lake Road Site Ordnance Removal
Closure or removal of 55 Underground Storage Tanks
Completion of 71 Environmental Restoration Inventory Sites
Submission of 266 Closure Reports to the State
|
Outyear activities beyond FY 2001 are still being prioritized in site
baselining activities. This estimate assumes remedial action activities will
continue through FY 2035. As discussed in the introduction to the Environmental
Restoration section, low-level waste and low-level mixed waste will be disposed
onsite and hazardous waste will be shipped offsite. Pollution control
activities include well established waste minimization programs. During waste
generating operations, the waste is segregated to the extent possible to avoid
contaminating clean material and to avoid mixing different contaminants. The
Department estimates the waste volumes generated at the Industrial Sites during
assessment and remedial action will consist of the following:
Industrial Sites Waste Type and Volume
| Low-Level Mixed
|
Liquid
Soil
|
230
50
|
| Low-Level
|
Debris
Liquid
Soil
|
600
10
2,000
|
| Hazardous
|
Ground water
Liquid
Soil
|
270
420
75,980
|
| Sanitary
|
Debris
|
350
|
DECOMMISSIONING
Industrial sites include facilities no longer needed and contaminated by
Department of Energy mission-related activities. Decommissioning activities
include the decontamination and decommissioning of these surplus facilities.
Decommissioning activities are governed by the terms of the Federal Facility
Agreement and Consent Order with the state. Surveillance and monitoring of the
identified facilities is ongoing, and initial decommissioning activities were
conducted at the sites in 1974 and 1983.
This report assumes the eight surplus facilities already transferred from
Defense Programs to Environmental Management will undergo decommissioning. All
of the facilities except two were used for nuclear rocket, nuclear engine,
nuclear furnace, and associated tests; one was used for radiological research
on intake of radionuclides through the food chain, and the other evaluated the
response of missile parts to radiation flux. The facilities include E-MAD,
RMAD, Pluto, Super Kukla, Test Cell A, Test Cell C, EPA Farm, and Jr. Hot
Cell. This estimate assumes no additional facilities will transition to
Environmental Restoration, and that all eight facilities will be demolished.
Characterization of the identified decontamination and decommissioning
facilities includes periodic surveillance and maintenance before
decommissioning takes place. Characterization activities include documenting
building deterioration, planning characterization, collecting and analyzing
samples, managing and evaluating data, assessing risks and doses, and preparing
assessment reports. The Facility Assessment Report documents and discusses the
nature and extent of contamination present in each facility, release criteria
calculations and the risk/dose assessment, and findings. Design for each of the
facilities specifies the construction and demolition activities necessary to
remediate facilities.
Contamination in the facilities is generally limited to portions of buildings
specifically used for "hot" work on radioactively impacted machinery,
equipment, or experiments. Most of the contamination appears to be
radioactivity, although other constituents of concern will be investigated.
Some facilities also have asbestos- containing materials in their construction,
and at least one facility is known to have poly-chlorinated biphenyl
contaminated hydraulic oil. A site-specific work plan is prepared for each
characterization effort, and applicable permits are obtained. National
Environmental Policy Act determination is made and endangered species
clearances obtained. Surveys to comply with the Historic Preservation Act of
1966 are also completed.
Characterization field activities completed to date include Jr. Hot Cell and
the EPA Farm. Remediation of Jr. Hot Cell is complete. It included demolition
of the facility and waste disposal at the Area 5 Radioactive Waste Management
Site. Remediation of the EPA Farm is scheduled for FY 1997 and this report
assumes the facility will be demolished. Final determination of the appropriate
decommissioning approach for the rest of the facilities awaits completion of
scheduled assessment activities; most of the facilities will not begin
assessment prior to FY 2000.
This estimate assumes that debris generated by decommissioning will consist of
approximately 6,200 cubic meters (8,122 cubic yards) of sanitary waste, and 240
cubic meters (314 cubic yards) of low-level waste.
Soils Sites
The Soils Sites comprise several activities related to the investigation of and
necessary corrective remedial actions for contaminated surface and shallow
subsurface soils on the Nevada Test Site, Tonopah Test Range, and Nellis Air
Force Range. Contamination is the result of historic U.S. Department of Energy,
Nevada Operations Office above-ground and near surface nuclear detonations,
safety shot tests, rocket engine development, and hydro nuclear testing.
Contaminants of concern include americium, plutonium, depleted uranium, and
other types of transuranic waste; radionuclides; and fission products. In
addition, metals, particularly lead, are of concern at some sites. Long-term
soils remediation strategies have not been finalized with the State and other
stakeholders.
The Department conducted safety shots at several locations on the Nellis Air
Force Range and Tonopah Test Range (Double Tracks; Clean Slates 1, 2, and 3;
and Area 13); at Plutonium Valley in Area 11 of the Nevada Test Site; and the
GMX site in Area 5 of the Nevada Test Site. The safety tests did not result in
significant nuclear yield, but did disperse contaminants in excess of 40
picocuries per gram, in surficial soils over more than 1,200 hectares (3,000
acres). When 82 atmospheric and near surface tests are included, the acreage
contaminated in excess of 40 Pico curies per gram increases to approximately
10,800 hectares (27,000 acres). Most of the increased area is on the Nevada
Test Site.
Soils Sites include nine cratering events from underground tests. The events
used nuclear devices to excavate large volumes of earth. Contamination from
these tests includes subsurface impacts, less than 300 meters (984 feet) deep
and impacts to surface soils as the result of material expelled during testing.
The nine events include Sedan, Schooner, Ess, Buggy, Cabriolet, Palanquin,
Johnnie Boy, Danny Boy, and Uncle.
Hydronuclear tests involve classified data. Therefore, this report cannot
address the details of these tests. Most of the tests impacted shallow surface
soils to depths of less than 30 meters (98 feet). No surface soil impacts have
been identified at this time.
REGULATORY ISSUE
CLEANUP LEVELS
"The current cleanup strategy calls for reducing contaminated soils by
excavation and disposal in existing subsidence craters. This strategy proposes
to increase radionuclide concentration action levels from 40 picocuries per
gram to a Anegotiated" 200 picocuries per gram. The State has only concurred
that this higher level is acceptable as interim action level. The U.S.
Department of Energy, Nevada Operations Office is proposing to establish
>Land Withdraw Zone(s)' to provide containment of these contaminants at
these levels, which would be preemptive of the future decisions in the Resource
Management Planning process." (Letter from the State of Nevada to Carl Gertz,
Acting Assistant Manager for Environmental Restoration and Waste Management
Division, November 22, 1995).
Nuclear Rocket Engine tests encompass a number of sites in Area 25 where
surface soils were contaminated with a wide range of radionuclides released
during the tests. Buildings associated with these activities are included under
the Industrial Sites activities.
|
This report assumes the immediate effort will include interim actions to clean
up the Double Tracks and Clean Slates 1, 2, and 3 sites. These remedial actions
will be in accord with the Federal Facility Agreement and Consent Order.
Currently, no cleanup standards exist for these sites; this report assumes a
final cleanup level will be negotiated near the 200 Pico curries per gram
level. For the long term, this report assumes all areas on the Nevada Test Site
will remain under institutional control and will provide for an economically
feasible containment of contaminants. It further assumes the cleanup of soils
sites, when warranted, will consist of excavation and transportation to bulk
disposal in an appropriate subsidence crater located onsite. This is a critical
assumption, since bulk disposal should reduce costs by at least an order of
magnitude. The cleanup will comply with State of Nevada and National Emissions
Standards for Hazardous Air Pollutants regulations, with particular attention
paid to minimizing fugitive dust emissions during excavation of contaminated
soil.
ASSESSMENT
Most sites within the Soils Sites have sufficient background data available
regarding the sources of contamination, but some of the data is classified and
few of the sites have been characterized because of funding constraints. All
assessment activities concentrate on determining the type and extent of
contamination. Most radiological assessment activities will involve in situ
measurements using a wide array of approaches. Some discrete sampling is
required to determine the extent of such contamination by wet chemical
analysis. Once cleanup levels are established, based on future land use and
related risks, cleanup scenarios will be evaluated and documentation will be
prepared for negotiating cleanup procedures, if required.
In the past, assessment activities have concentrated on determining the extent
of plutonium-contaminated soils and preliminary testing of soil removal
technologies. Sites at which plutonium contaminated soil might be excavated
have conducted soil stabilization revegetation experiments and an existing
Nevada Test Site facility was retrofitted into a Treatability Test Facility at
which five bench-scale soil volume reduction tests were conducted.
Current assessment activities include completing the characterization effort in
support of an Interim Corrective Action Plan for the Double Tracks site on the
Nellis Air Force Range. Assessment efforts over the next few years will
concentrate on Clean Slates 1, 2, and 3 sites on the Tonopah Test Range.
Outyear activities beyond FY 2001 are still being prioritized in site
baselining activities. This estimate assumes that assessment activities will
continue through FY 2025.
REMEDIAL ACTION
Surface soil remedies will include in situ identification and removal of hot
spot materials located in small selected areas. Larger areas will require the
use of mechanical excavation to remove the contaminated materials. Mechanical
excavation may use size separators or other physical processes to reduce waste
volumes. Subsurface remedies will range from soil excavation to containment
strategies. Remedial actions will be based on applicable regulatory standards
or proposed cleanup levels, if no standards apply. Proposed levels will be
based on pertinent factors, including but not limited to assessment of risk,
current and projected land use, resource management, and technical and cost
feasibility. Where sufficient information is available, the Department will use
the Streamlined Approach for the Environmental Restoration process. Interim
removal actions will be performed when risk exists to workers and the public.
The first site scheduled for remediation is the Double Tracks site. It is
scheduled for an interim removal action in FY 1996. Outyear activities beyond
FY 2001 are still being prioritized in site baselining activities. This
estimate assumes remediation will be completed by FY 2030.
The large areas and volumes of contaminated soils potentially result in high
disposal costs; therefore, bulk disposal in subsidence craters has been assumed
for cost estimates for this report. This report also assumes approximately 1.1
million cubic meters (1.4 million cubic yards) of low-level waste will be
generated by remediation of the Soils Sites and disposed of in subsidence
craters. The Department is continually evaluating new technologies to find a
more cost-effective way to clean up the sites. The search for technologies has
thus far focused on volume reduction and cost-effectiveness.
Underground Test Areas
The Nevada Test Site has been the location for approximately 930 underground
nuclear tests conducted between 1951 and 1992. These locations test areas have
been bounded into six geographic areas that have distinct contaminant source,
geologic, and hydrologic characteristics. The six areas include Frenchman Flat,
Western Pahute Mesa, Yucca Flat, Central Pahute Mesa, Ranier Mesa/Shoshone
Mountain, and Climax Mine.
Frenchman Flat consists of ten sites located in the northern portion of Area 5
and the southern part of Area 11. These test events were conducted in both
vertical emplacement holes and mine shafts located in deep alluvium. The deeper
geology is not well known.
Western Pahute Mesa consists of 18 sites along the western edge of Area 20.
These events were all conducted in vertical emplacement holes. This area is
separated from Central Pahute Mesa by the Boxcar Fault and is distinguished by
the relative abundance of tritium. Transport of contaminants on and from
Western Pahute Mesa involves ground-water flow in both welded and vitric tuffs,
both in the rock matrix and in the fracture system.
Yucca Flat consists of 717 sites located in Areas 1, 2, 3, 4, 6, 7, 8, 9, and
10. Events at these sites were conducted in vertical emplacement holes.
Contaminant transport in Yucca Flat may involve alluvium, both welded and
vitric tuffs, and carbonate rock.
Central Pahute Mesa consists of 64 sites in Areas 19 and 20 on Pahute Mesa.
Events at these sites were all conducted in vertical emplacement holes. While
distinguished from Western Pahute Mesa only by the presence of the Boxcar
Fault, this Corrective Action Unit also contains a relative abundance of
tritium. In addition, transport of contaminants and/or from Central Pahute Mesa
involve ground-water flow in volcanic rocks and flow in both the rock matrix
and the fracture system.
Rainier Mesa/Shoshone Mountain consists of 60 sites where events were all
conducted in tunnels. Contaminants from this Corrective Action Unit flow in
volcanic rock and fractured media. Climax Mine consists of three sites where
events were all conducted in tunnels. Contaminants from the climax Mine
Corrective Action Unit flow through fractured granite rock.
The Department is investigating the effects of the underground testing on the
ground water and surrounding media in these areas. Investigations are using
data collection and analysis to determine whether contaminants have moved
appreciable distances from the nuclear explosion locations. Because all of the
sites are under institutional control, the Department considers risk to public
health and the environment from the testing activities to be minor at this
time. The ambient or background radiological conditions around the site are
normal. However, assessment activities will include risk assessment to quantify
risk to human health and the environment.
Field activities include the use of new and existing wells for monitoring and
testing to help develop transport models. The Department will install some new
wells near shot cavities to collect data about the near-field environment. The
Department expects to encounter tritium during drilling; therefore, a liquid
waste treatment system will be used. Attenuation characteristics provide for
little migration of radionuclides other than tritium. Other radionuclides will
be included in the source evaluation if tritium migration indicates the need.
There are many uncertainties regarding remedial action of the Underground Test
Area. This report assumes that for the foreseeable future the Department will
concentrate on the modeling and ground-water monitoring activities to limit the
extent of contamination. These actions will be in accord with the Federal
Facility Agreement and Consent Order. For the long term, because no known
cost-effective technologies exist to extract contamination, or neutralize and
stabilize the shot cavities, this report assumes that the sites will be
characterized and the ground-water resource withdrawn from future-use
considerations. Estimates within this report reflect the necessary modeling and
ground-water monitoring to limit the contamination to satisfy the State of
Nevada Division of Environmental Protection. The estimates do not include
remedial actions or Natural Resource Damage Assessments that might be necessary
if contamination exceeds the boundaries agreed upon for closure.
REGULATORY ISSUE
UNDERGROUND TEST SITES
"It is an undisputed fact that the underground nuclear testing program
contaminated the ground water beneath the Nevada Test Site because
approximately one-third of the underground nuclear tests were conducted at or
within the ground water. The water beneath the Nevada Test Site is under State
of Nevada jurisdiction and accordingly is regulated by the state. State
officials believe that, at the present time, it is unreasonable to assume that
limited monitoring of the Underground Test Areas will be sufficient to document
that there is containment and control over the contaminant plumes. It is also
presumptive to conclude, without knowledge or control over the future regional
stresses and withdrawals from these groundwater resources, that there will be
definitive monitoring results to support a 30-year target date for Underground
Test Area closure activities"
"While modeling will be utilized to define the extent of ground-water
contamination, it must be able to verify the validity of the models through the
acquisition of actual hydrological information. After the model's
predictability has been verified, it may then be used to understand the
existing complex hydrological regime and to determine the extent of
radionuclide contamination and rate of movement of nuclides of concern in the
ground water. Such a determination can only be achieved through the
installation of a number of deep characterization wells, which may subsequently
be able to function as monitoring wells or part of any remedial actions."
(Letter from the State of Nevada to Carl Gertz, Acting Assistant Manager for
Environmental Restoration and Waste Management Division, November 22, 1995.)
|
The estimate assumes these areas will be closed in place, assuming there is no
threat to the environment or natural barrier failure, and monitoring will
continue for 30 years.
ASSESSMENT
This report assumes that Underground Test Area assessment activities will be
complete in FY 1996. Most of the extensive data for the Underground Test Areas
is classified; therefore, the assessment activities to date have focused
primarily on data collection and analysis to determine the potential for
contamination of deep aquifers. Installation, testing, and monitoring of wells
has been an essential element of the assessment tasks to determine if migration
of contaminants has occurred. These activities have addressed the portion of
the saturated zone where ground water could be effected, the vadose zone
between sources, and the water table.
Assessment activities to date have also included developing a data base to
analyze existing and newly acquired data; data management and analysis,
including flow and transport modeling; and preliminary risk assessment
activities. Thirteen characterization wells have been installed, and 11
existing wells have been modified for characterization.
Present efforts include the completion of regional ground-water flow and solute
transport modeling. Future work involves the quantification of risk to human
health and the environment based on the ground-water flow and solute transport
models, and the completion of the Phase I Report to document the assessment
activities.
REMEDIAL ACTION
No cost-effective technologies exist for restoring these sites. Remediation
activities that will begin in FY 1996 are limited to developing specific
ground-water flow and solute transport modeling for the six areas previously
identified. Based on this effort, the Department will establish a regulatory
compliance zone. Field activities in each area will provide data collection in
the near field environment, including installation of monitoring wells in
locations specified by modeling results. The effort will include near-field
ground-water flow and solute transport modeling; risk assessment;
stakeholder/regulatory concerns; and a monitoring network design.
The Department is currently conducting monitoring activities to assess the
extent of contamination and to support modeling efforts to establish protective
boundaries around the six areas. A five-year monitoring program will determine
if data is consistent with predictions. If monitoring results are satisfactory
to the State, the Department will prepare a closure report for approval by the
Nevada Division of Environmental Protection. The Department will conduct
post-closure monitoring for 30 years. Monitoring will be consistent with the
compliance requirements.
Waste generated during remediation activities will take the form of the
low-level liquid effluent drilling mud and drill cuttings. The largest volume
of waste to be generated is liquid effluent (approximately 7,600 cubic meters
[9,956 cubic yards] ). Pollution control activities involving liquid effluents
rely on evaporation to reduce waste volume. After evaporation, the low-level
waste residual will include 1,150 cubic meters (1,507 cubic yards) of
contaminated soils and 1,190 cubic meters (1,559 cubic yards) of contaminated
sludge. This report assumes low-level waste will be disposed of at the Area 5
Radioactive Waste Management Site.
Long-Term Surveillance and Monitoring
Post-closure monitoring activities consist of collecting periodic measurements
and/or samples from monitoring wells, and effluent streams, as stipulated in
each unit's Post-Closure Care Permit. Condition inspection and maintenance of
any remedial systems, such as caps or active systems is included in estimates
of scheduled activities. Sample analysis and preparation of a report for each
monitoring period is also included. The need for, and specifics of post-closure
monitoring is determined on a case-by-case basis. Monitoring typically lasts
for 30 years for complex Resource Conservation and Recovery Act sites, but the
State has approved shorter periods of time.
Estimates in this report differentiate between monitoring to establish the
contamination boundaries and monitoring to obtain closure and post-closure
monitoring. The cost for the former are included within the costs for
assessment and remedial action. The latter are provided for under the costs for
long-term surveillance and maintenance. This report assumes the post-closure
monitoring (long-term surveillance and maintenance) will continue through FY
2050.
Current post-closure surveillance and monitoring at the Industrial Sites
includes quarterly monitoring of the Area 23 Hazardous Waste Trenches and U-3fi
Injection Well. At this time, maintenance of these systems consists of an
inspection of the condition of the Area 23 closure cap for erosion or other
disturbances and monitoring and general integrity of the U-3fi Injection Well
unit. Post-closure monitoring of the Soils Sites and Underground Test Area will
begin when the site receives the Notice of Completion approval of the final
corrective actions.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
|
| Nevada Contaminated Soils
|
|
|
|
|
|
|
|
|
| Assessment
|
506
|
1,859
|
1,859
|
1,859
|
1,859
|
1,859
|
|
|
| Remedial Action
|
5,339
|
9,104
|
12,815
|
12,771 |
12,771
|
12,661
|
3,788
|
|
| Nevada Industrial Sites and Facilities
|
|
|
|
|
|
|
|
|
| Assessment
|
1,501
|
4,827
|
2,367
|
2,386
|
37
|
174
|
|
|
| Remedial Action
|
6,292
|
11,988 |
25,630
|
25,700 |
27,900
|
27,900
|
38,556
|
|
| Facility Decommissioning
|
756
|
1,023
|
1,003
|
914
|
1,063
|
926
|
110
|
|
| Nevada Underground Test Areas
|
|
|
|
|
|
|
|
|
| Assessment
|
560
|
|
|
|
|
|
|
|
| Remedial Action
|
26,739
|
10,001 |
|
|
|
|
|
|
| Long-Term Surveil. and Monitoring
|
164
|
611
|
1,576
|
1,620
|
1,620
|
1,730
|
1,660
|
|
| Direct Program Management/Support
|
12,247 |
13,315
|
14,091
|
14,944
|
15,933 |
17,082
|
18,413 |
|
| Total |
54,104
|
52,727
|
59,341
|
60,194 |
61,183
|
62,332 |
62,527
|
|
| |
2055
|
2060
|
2065
|
| Nevada Contaminated Soils
|
|
|
|
|
|
|
|
|
| Assessment
|
|
|
|
|
|
|
|
49,005
|
| Remedial Action
|
|
|
|
|
|
|
|
346,245
|
| Nevada Industrial Sites and Facilities
|
|
|
|
|
|
|
|
|
| Assessment
|
|
|
|
|
|
|
|
56,458
|
| Remedial Action
|
14,406
|
|
|
|
|
|
|
891,860
|
| Facility Decommissioning
|
110
|
110
|
110
|
110
|
|
|
|
31,174
|
| Nevada Underground Test Areas
|
|
|
|
|
|
|
|
|
| Assessment
|
|
|
|
|
|
|
|
2,800
|
| Remedial Action
|
|
|
|
|
|
|
|
183,699
|
| Long-Term Surveil. and Monitoring
|
1,660
|
1,660
|
1,660
|
1,660
|
|
|
|
78,105
|
| Direct Program Management/Support
|
6,116
|
2,084
|
2,368
|
2,697
|
|
|
|
596,450
|
| Total |
22,292
|
3,854
|
4,138
|
4,467
|
|
|
|
2,235,796
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Direct Program Management/Support
Activities conducted within this work scope provide management support of the
Department of Energy, Nevada Operations Office Environmental Management
activities that will characterize and remediate environmental conditions on the
Nevada Test Site, Tonopah Test Range, and Nellis Air Force Range; as well as
offsite locations in five states. The scope of this work also involves managing
the treatment, storage, and disposal facilities and operations under the
purview of the Department of Energy, Nevada Operations Office.
The Environmental Restoration Project Support activity provides for
administrative and technical project management support; project planning,
including Activity Data Sheet development; project control, including Project
Tracking System and Performance Measurement System reporting; programmatic
Quality Assurance and Self Assessment support; programmatic health and safety
support; training; development of programmatic National Environmental Policy
Act documentation; waste management coordination; compliance reporting; and
public participation support. An Activity Data Sheet entitled Project Support
captures these activities.
| COST SAVINGS
Cost savings for FY 1995 are being achieved through a series of productivity
initiatives. These initiatives include contracting initiatives; replacing
contractor Full-Time Equivalents with Federal Full-Time Equivalents; reducing
infrastructure costs; engaging in a single contractor for remediation;
streamlining documents; integrated field activities; and reducing analytical
cost and culture resource costs. The FY 1995 cost savings target of $4.3
million was not fully achieved because of a delay in a contract award.
Initiatives are being determined to achieve the FY 1996 target savings of $7.4
million.
|
Management of the Federal Facility Agreement with the State of Nevada and
oversight of Agreements-in-Principle and grants is covered under an Activity
Data Sheet entitled Agreements
.
This section does not include Program Direction within Environmental
Restoration. These activities provide overall management of the entire
Department of Energy, Nevada Operations Office Environmental Restoration
program. The direct costs of subproject activities capture subproject
management costs because those costs are directly attributable and are required
to accomplish field activities.
Agreements-in-Principle fund the States of Alaska, Mississippi, and Nevada to
provide oversight of the Department of Energy Environmental Restoration
activities. The Agreements-in-Principle describe the understandings and
commitments between the parties regarding the Department of Energy' s provision
of technical and financial support for state activities in environmental
oversight, monitoring, site access, and emergency response initiatives.
Amendments to existing Agreements-in-Principle managed by other Department of
Energy offices will address activities in Colorado and New Mexico. Grants
provide educational and research opportunities for students and faculty at the
University of Nevada at Reno and the University of Nevada at Las Vegas, in
support of technical programs being conducted at the Nevada Test Site.
| PRODUCTIVITY
Because most sites are in the assessment characterization phase, it is
difficult to quantify estimates of productivity savings for the future. There
are areas of activities in which productivity savings can be realized based
upon previous experiences and assumptions of the future activities of the
project. In revising the estimate for savings, activities were examined for
possible efficiencies and reduction in work activities while achieving the
desired goals. These areas were identified and rough orders of magnitude
estimates were developed.
Areas in which savings could be realized include the learning curve. Multiple
closures in Corrective Action Units will yield remedies for future closures.
Increased use of management information systems will reduce support and
indirect costs. Cost/Risk/Benefit Analyses can be used to evaluate alternative
cleanup requirements. The Streamlined Approach for Environmental Restoration
method and the Supplier Quality Information Group will eliminate the expense of
an independent audit. In addition, negotiation with regulators concerning the
required level of cleanup and amount of monitoring needed will help define end
goals and provide opportunities to meet these goals at less cost.
|
| STAKEHOLDER INTERACTIONS
The Nevada Operations Office conducted public participation activities for the
Nevada Test Site and Tonapah. Activities consisted of announcement of
preliminary 1996 Nevada Operations Office data in Environmental
Restoration-Waste Management Update, a publication distributed to over 1,200
interested stakeholders, and a briefing to the Community Advisory Board for
Nevada Test Site Programs at the board's November 1995 meeting. Draft copies of
the Nevada Operations Office data and narrative submissions were made available
to the Board budget committee and others attending the meeting. The State of
Nevada provided comments, most of them of a philosophical nature, which were
incorporated as sidebar information in the 1996 report. If you would like more
information about the report or have questions about the results for these
sites, please contact:
|
Public Participation
Kevin Rohrer
(702) 2950197
rohrer@em.nv.doe.gov
|
Technical Liaison
Chuck Morgan
(702) 295-0938
morgan@em.nv.doe.gov
|
Public Affairs
Nancy Harkess
(702) 2954652
harkess@fsmo.nv.doe.gov
|
WASTE MANAGEMENT
Waste management operations include storing the current inventory of
transuranic mixed waste received previously from Lawrence Livermore National
Laboratory; developing construction projects to treat, store, and dispose of
waste generated by the Nevada Operations Office project; enforcing the
Radioactive Waste Acceptance Program waste generator review and audit process;
and identifying and storing Nevada Test Site-generated hazardous waste prior to
offsite disposal at appropriate commercial facilities. Waste Management manages
five types of waste at the Nevada Test Site: transuranic mixed waste, low-level
mixed waste, low-level waste, and hazardous waste. Sanitary waste is managed by
the site landlord, the Office of Defense Programs.
WASTE MANAGEMENT MAP
The Nevada Test Site is a major low-level waste disposal facility for other
Department of Energy and a few Department of Defense installations. Two
principal active waste management sites are located on the Nevada Test Site:
the Area 5 Radioactive Waste Management Site and the Area 3 Radioactive Waste
Management Site. The Area 5 Radioactive Waste Management Site is located
approximately 19 kilometers (12 miles) north of Mercury, Nevada. It consists of
296 hectares (732 acres). Less than 15 percent of the capacity is currently
used. The site is currently used for disposal of onsite- and offsite-generated
low-level waste and onsite-generated low-level mixed waste, as well as for
storage of transuranic waste. At the current rate of land use, the facility can
be expected to provide a total disposal capacity of 10,884 cubic meters (14,258
cubic yards) per year for more than 100 years. Some additional land may be
required to improve access for transport vehicles, but this is not expected to
impact operations for several years.
The Area 3 Radioactive Waste Management Site occupies an area of approximately
50 hectares (125 acres) and is situated about 38 kilometers (23 miles) north of
Mercury. Adjacent subsidence craters created from underground nuclear weapons
tests, which were conducted at depths well above the ground-water table, are
used as waste disposal cells. The subsidence craters have been modified for
shallow landfill disposal to accommodate waste disposal activities. The
remaining disposal capacity at the Area 3 Radioactive Waste Management Site is
1.8 million cubic meters (2.3 million cubic yards) and should provide
sufficient disposal capacity for more than 100 years.
Major Waste Management Activity Milestones
| Road 5-01 Construction
|
1997
|
|
U3AX/BL Closure
|
1998
|
|
Preparations to Ship TRU to Waste Isolation Pilot Plant
|
2000
|
|
Low-Level Waste Operations
|
2070
|
Transuranic Mixed Waste
Approximately 610 cubic meters (799 cubic yards) of transuranic mixed waste
received from Lawrence Livermore National Laboratory from 1974 to 1990 is
currently stored at the Nevada Test Site in the Transuranic Pad Cover Building.
Pursuant to an agreement reached with the State of Nevada in 1992, transuranic
mixed waste storage is limited to the current inventory. The Department plans
to initiate transportation of this waste to the Waste Isolation Pilot Plant in
FY 2000 once the waste is certified to meet Waste Isolation Pilot Plant waste
acceptance criteria. All costs for transportation and disposal of the waste are
included within the Waste Isolation Pilot Plant site summary located in the New
Mexico section. This estimate assumes no additional transuranic or transuranic
mixed
waste will be generated at, or transferred to, the Nevada Test Site.
The 1992 agreement with the State of Nevada was the result of the Finding of
Alleged Violation and Order of November 1, 1990, and the Finding of Alleged
Violation of June 24, 1991, related to the Transuranic Waste Storage Pad in
Area 5 of the Nevada Test Site.
Low-Level Mixed Waste
In 1987, the Department of Energy, Nevada Operations Office was granted interim
status under the Resource Conservation and Recovery Act to receive and dispose
of low-level mixed waste from the Rocky Flats Plant. This waste is disposed in
Pit 3 at the Area 5 Radioactive Waste Management Site. Because of the
promulgation of Environmental Protection Agency Land Disposal Restrictions,
disposal of low-level mixed waste from the Rocky Flats Plant ceased in May
1990. A revised Resource Conservation and Recovery Act Part B permit
application, which included sampling and analysis for Land Disposal Restriction
compliance, was submitted to the State of Nevada for review in July 1992.
During FY 1994, the Department of Energy, Nevada Operations Office continued to
revise the application in response to technical review comments by the Nevada
Division of Environmental Protection.
In accordance with the Federal Facility Compliance Act, the Department of
Energy, Nevada Operations Office and the Nevada Division of Environmental
Protection negotiated the Site Treatment Plan and its associated Compliance
Order for low-level mixed waste identified in the Mixed Waste Inventory Report.
On March 27, 1996, an agreement was achieved concerning enforceable treatment
schedules for these waste streams.
The Mutual Consent Agreement allows any low-level mixed waste generated by the
Department of Energy, Nevada Operations Office in the State of Nevada to be
stored on the unused portion of the existing Area 5 transuranic mixed waste
storage pad. The low-level mixed waste does not have to meet land disposal
restrictions prior to being accepted for storage on the Area 5 transuranic
mixed waste storage pad. For newly identified mixed waste not specified in the
Site Treatment Plan, the Department of Energy is required to develop treatment
and disposal alternatives within nine months of placing such waste on the
transuranic mixed waste storage pad. In anticipation of potential mixed waste
volumes generated from future operational, characterization, and remediation
activities conducted within the State of Nevada, the Department submitted a
Part B permit application in January 1995 for the construction of a Mixed Waste
Storage Facility.
GENERATION AND HANDLING
Currently, there are nine previously generated low-level mixed waste streams
located on the Nevada Test Site. They have a combined volume of approximately
290 cubic meters (340 cubic yards), and they are labeled as backlog waste. This
life-cycle report assumes that activities at the Nevada Test Site will generate
an additional 4,696 cubic meters (6,156 cubic yards) of low-level mixed waste.
TREATMENT
As required by the Federal Facility Compliance Act, the Site Treatment Plan
discusses low-level mixed waste at the Nevada Test Site and identifies
alternatives for treatment. The Proposed Site Treatment Plan, originally
scheduled for completion in February 1995, was delayed until March 1995 as
agreed upon by the National Governors' Association and the Department of
Energy. Final approval of the Site Treatment Plan by the State of Nevada was
originally expected to be received by October 6, 1995, via a Unilateral Order.
The State of Nevada extended final approval of the Site Treatment Plan
approximately six months beyond the October 6, 1995 deadline. Once completed,
schedules and activities identified in the Site Treatment Plan became
enforceable milestones. This report expects periodic negotiations with the
state on low-level mixed waste issues as long as mixed waste is listed in the
Site Treatment Plan or in the annual updates.
STORAGE
The low-level mixed waste previously generated at the Nevada Test Site is
currently being stored on the transuranic pad in accordance with a 1994 Mutual
Consent Agreement between the Department of Energy and the Nevada Division of
Environmental Protection developed in January 1994 and revised in June 1995.
Nine Nevada Test Site backlogged low-level mixed waste streams are currently
stored on the transuranic pad having a combined volume of approximately 290
cubic meters (340 cubic yards). In accordance with this agreement, the
Department amended its Resource Conservation & Recovery Act Part B Permit
application in January 1995, to include construction of a low-level mixed waste
storage facility at the Area 5 Radioactive Waste Management Site.
The Cotter Concentrates, originally shipped to the Nevada Test Site in 1987
from the Mound Plant as strategic materials for storage, were formally declared
a waste in January 1995. Analytical and characterization data have shown the
Cotter Concentrates to be a low-level mixed waste stream. Further
characterization efforts resulted in dividing the waste into two populations.
Cotter Concentrate - Population A is stored northeast of the Area 5 Radioactive
Waste Management Site in the Strategic Materials Storage Yard. This waste
stream, which has a volume of approximately 260 cubic meters (341 cubic yards),
is stored in accordance with a management plan approved by the State of Nevada
in July 1995. Cotter Concentrate - Population B is stored on the transuranic
pad and consists of approximately 1.4 cubic meters (1.8 cubic yards).
DISPOSAL
The Nevada Test Site is one of the remaining 15 sites out of the original 49
sites the Department is evaluating for disposal of low-level mixed waste. The
ultimate identification of low-level mixed waste disposal activities at the
Nevada Test Site will follow state and federal regulations for siting and
permitting. It will also include public involvement in the decisionmaking
process and during preparation of the site-wide Environmental Impact Statement.
The State of Nevada has given the Department approval to dispose low-level
mixed waste in Pit 3 of the Area 5 Radioactive Waste Management Site if the
waste meets land disposal restrictions. The low-level mixed waste must also
meet the characteristics and packaging requirements for disposal under the
Nevada Department of Energy Waste Acceptance Criteria (NVO-325, Rev. 1). This
estimate assumes approximately 33,263 cubic meters (43,575 cubic yards) of
low-level mixed waste will ultimately be disposed at Pit 3. Approximately 4,696
cubic meters (6,152 cubic yards) of this total will be generated at the Nevada
Test Site. The remainder will originate from the Rocky Flats Site, which will
generate 28,199 cubic meters (36,940 cubic yards), and Lawrence Livermore
National Laboratory, which will generate 372 cubic meters (487 cubic yards).
Low-Level Waste
GENERATION AND HANDLING
Historically, approximately 50 percent of the 481,000 cubic meters (630,110
cubic yards) of low-level waste disposed of at the Nevada Test Site was
generated onsite. However, approximately 99 percent of waste received and
disposed of in the last five years was from offsite generators. Offsite
generated waste was accepted at the Nevada Test Site beginning in FY 1978. In
FY 1995, 24,353 cubic meters (31,902 cubic yards) of low-level waste was
disposed of at the Nevada Test Site. Of that volume, 62 cubic meters (81 cubic
yards) was generated at the Nevada Test Site. The Nevada Test Site is expected
to receive an average of 24,000 cubic meters (31,440 cubic yards) of low-level
waste per year for the next three years. In FY 1995, the Department limited the
total disposal volume at the Nevada Test Site to 26,043 cubic meters (34,116
cubic yards). This self-imposed limit is based on an interpretation of an Order
in a lawsuit brought against the Department of Energy by the State of Nevada.
Low-level waste treatment is not currently provided or assumed to be needed
during the life cycle of this estimate. Storage costs are avoided because
low-level waste is disposed of as soon as it is received.
REGULATORY ISSUE
LOW-LEVEL WASTE DISPOSAL
"The Order issued on January 12, 1995 by the U.S. District Court placed no
limits on the Department's ability to dispose of low-level waste at the NTS.
While the court dismissed claims by the State regarding shipment of low-level
waste from the DOE's Fernald site (based on a previous decision under CERCLA)
it upheld claims by the State concerning other low-level waste disposal
activities at the NTS. [Litigation under this lawsuit continues.]" (Letter from
the State of Nevada to Carl Gertz, Acting Assistant Manager for Environmental
Restoration and Waste Management Division, November 22, 1995).
|
DISPOSAL
The low-level waste disposal costs are contingent upon the amount of waste
shipped to the Nevada Test Site. The Department of Energy/Nevada Operations
Office Waste Management Division does not receive any Headquarters funding for
disposal costs of low-level waste at the Nevada Test Site. Instead, the Nevada
Operations Office relies on generator fees collected from the waste generators.
The Nevada Operations Office plans to maintain this generator fee structure in
the future.
The Nevada Test Site accepts and disposes of low-level waste at the Area 3 and
Area 5 Radioactive Waste Management Site from approved Department of Energy,
Department of Defense, and other designated facilities across the United
States. This estimate assumes that there will be a total of 19 approved
generators, and 16 are currently approved. Life-cycle estimate information for
13 of the generators is provided in the following table.
Nevada Offsite Waste Generators
| Energy Technology Engineering Center
|
2,540
|
1996
|
2001
|
| Fernald Environmental Management Project
|
57,330
|
1996
|
2005
|
| Inhalation Toxicology Research Institute
|
2,877
|
1996
|
2070
|
| Kansas City Plant
|
30
|
1996
|
2070
|
| Lawrence Livermore National Laboratory
|
4,429
|
1996
|
2070
|
| Mound Plant
|
1,390
|
1996
|
2012
|
| Oak Ridge K-25 Plant
|
26,434
|
1998
|
2002
|
| Oak Ridge National Laboratory
|
78,930
|
1996
|
2070
|
| Oak Ridge Y-12 Plant
|
244,506
|
1999
|
2070
|
| Pantex Plant
|
8,355
|
1996
|
2070
|
| Reactive Metals, Inc.
|
29,162
|
1996
|
2002
|
| Rocky Flats Environmental Technology Site
|
32,522
|
1996
|
2045
|
| Sandia National Laboratory - New Mexico
|
45,134
|
1996
|
2070
|
| TOTAL
|
544,715
|
|
|
At the current rate of land use, the facility can be expected to provide
disposal capacity of approximately 3 million cubic meters (4 million cubic
yards) in the next 100 years. The Nevada Operations Office conducts site
monitoring and characterization activities in support of the low-level waste
disposal operations at the Area 3 and 5 Radioactive Waste Management Sites.
The Performance Assessment for the Area 5 Radioactive Waste Management Site was
sent to the Department of Energy Performance Assessment Peer Review Panel for
approval. The Performance Assessment for the Area 3 Radioactive Waste
Management Site is scheduled for completion in March 1998. Performance
Assessments are required for low-level waste disposal sites under Department of
Energy Order 5820.2A.
The Waste Examination Facility is scheduled to be constructed in FY 1996 and
will provide a 140 square meter (1,500 square foot) facility to examine
low-level waste containers at the Area 5 Radioactive Waste Management Site. A
new primary access road, approximately 5 kilometers (3.1 miles) long, has been
designed and is scheduled for construction in FY 1997. The new road will meet
all transportation and safety standards. Design of an extensive 500-year flood
protection berm is currently proposed for FY 1998, with construction continuing
into FY 1999.
Hazardous Waste
Hazardous waste is accumulated at numerous satellite locations on the Nevada
Test Site and then transferred to the Area 5 Hazardous Waste Storage Unit.
Hazardous waste containers are checked for radioactive contamination by
hand-held instrument surveys and swipe sampling. Process knowledge and
radiological analyses are used to ensure none of the hazardous waste being
released for transport offsite contains radioactive constituents above
established limits. Although every operational entity at the Nevada Test Site
is a potential satellite generator of hazardous waste, the Department of
Defense is the primary generator. Sources include analytical laboratories,
paint shops, vehicle maintenance shops, and mining and construction operations.
Waste characterized as hazardous under the Land Disposal Restrictions must be
shipped offsite to a Resource Conservation and Recovery Act-permitted facility
within one year. The report expects a total of approximately 18,924 cubic
meters (24,790 cubic yards) will be shipped to commercial facilities during the
life cycle.
All waste shipments are made in accordance with applicable Department of
Energy, Department of Transportation, Environmental Protection Agency, state,
and local hazardous waste regulations. Generators of the waste pay the shipping
costs.
Waste Management Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
|
| Transuranic Mixed Waste
|
|
|
|
|
|
|
|
|
| Storage and Handling |
200 |
200
|
|
|
|
|
|
|
| Low-Level Mixed Waste |
|
|
|
|
|
|
|
|
| Treatment |
2,742
|
1,402 |
1,402
|
1,402 |
1,402
|
1,402 |
1,402
|
|
| Disposal |
200
|
150 |
|
|
|
|
|
|
| Low-Level Waste |
|
|
|
|
|
|
|
|
| Disposal |
14,888
|
7,800 |
7,200
|
6,200 |
6,000
|
3,000 |
3,000
|
|
| Hazardous Waste |
|
|
|
|
|
|
|
|
| Treatment |
350
|
980 |
350
|
350 |
350
|
350 |
350
|
|
| Storage and Handling |
150 |
150
|
150 |
150
|
150 |
150
|
150 |
|
| Direct Program Management/Support
|
5,176 |
5,295
|
5,295 |
5,295
|
5,295 |
1,000
|
1,000 |
|
| Total |
23,706
|
15,977 |
14,397
|
13,397 |
13,197
|
5,902 |
5,902
|
|
| |
|
| Transuranic Mixed Waste
|
|
|
|
|
|
|
|
|
| Storage and Handling |
|
|
|
|
|
|
|
|
| Low-Level Mixed Waste |
|
|
|
|
|
|
|
|
| Treatment |
1,402
|
1,402 |
1,402
|
1,402 |
1,402
|
1,402 |
1,402
|
|
| Disposal |
|
|
|
|
|
|
|
|
| Low-Level Waste |
|
|
|
|
|
|
|
|
| Disposal |
3,000
|
3,000 |
3,000
|
3,000 |
3,000
|
3,000 |
3,000
|
|
| Hazardous Waste |
|
|
|
|
|
|
|
|
| Treatment |
350
|
350 |
350
|
350 |
350
|
350 |
350
|
|
| Storage and Handling |
150 |
150
|
150 |
150
|
150 |
150
|
150 |
|
| Direct Program Management/Support
|
1,000 |
1,000
|
1,000 |
1,000
|
1,000 |
1,000
|
1,000 |
|
| Total |
5,902
|
5,902 |
5,902
|
5,902 |
5,902
|
5,902 |
5,902
|
|
| |
2075
|
2080
|
2085
|
2090
|
2095
|
2100
|
| Transuranic Mixed Waste
|
|
|
|
|
|
|
|
|
| Storage and Handling |
|
|
|
|
|
|
|
2,000
|
| Low-Level Mixed Waste |
|
|
|
|
|
|
|
|
| Treatment |
1,402
|
|
|
|
|
|
|
111,852
|
| Disposal |
|
|
|
|
|
|
|
1,750
|
| Low-Level Waste |
|
|
|
|
|
|
|
|
| Disposal |
5,000
|
|
|
|
|
|
|
370,440
|
| Hazardous Waste |
|
|
|
|
|
|
|
|
| Treatment |
350
|
|
|
|
|
|
|
29,400
|
| Storage and Handling |
150 |
|
|
|
|
|
|
11,250
|
| Direct Program Management/Support
|
1,000 |
|
|
|
|
|
|
181,780
|
| Total |
7,902
|
|
|
|
|
|
|
708,472
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Direct Program Management/Support
Activities conducted within this work scope support the waste management
activities for treatment, storage, and disposal. Activities consist of project
planning, including Activity Data Sheet development; project control, including
Performance Measurement System and Progress Tracking System reporting;
administrative and technical support, including community relations and legal
services.
DESCRIPTION OF PERSONNEL
The following table reflects the mix of personnel involved in accomplishing the
Environmental Management mission of the sites managed by the Nevada Operations
Office. The Federal workforce consists mainly of managers, professionals,
engineers, and scientists. The contractor and sub-contractor mix is mostly
professionals and labor which plans and conducts the day-to-day activities at
the sites.
Full-Time Equivalents Composition Table*

* The Projections for Full-Time Equivalent employees are based on FY 1996
planning baselines (see Reader's Guide).
Site Management Structure
The management structure of Nevada is divided into four major suborganizations
( Assistant Manager for Operations; Assistant Manager for Environment, Safety
& Health; Assistant Manager for Environmental Management; and Assistant
Manager for Administration) and several matrix suborganizations (for example,
Office of Chief Counsel, Office of Chief Financial Officer, Office of External
Affairs, etc.). In turn, Nevada is supported by numerous contractors who
operate under contracts of a diverse nature (for example, management and
operating, architectural/engineering services, etc.), and type (for example,
cost plus award fee, cost plus fixed fee, etc.). Currently, the majority of the
contractor support to Nevada is provided by Bechtel Nevada, which took over
operations in January 1996.
| CONTRACTING OPPORTUNITIES
If you would like more information about performing work for the Department of
Energy's Environmental Management program at this site, please contact:
|
Major Procurements
Joanne M. Bradbury
Director
Contracts Division
United States Department of Energy
Nevada Operations Office
P.O. Box 98518
Las Vegas, NV 89193-8518
p: (702) 295-1040
f: (702) 295-5305
|
Small Business Procurements
Darby Dietrich
Contracts Division
United States Department of Energy
Nevada Operations Office
P.O. Box 98518
Las Vegas, NV 89193-8518
p: (702) 295-1560
f: (702) 295-5305
|
Future Full-Time Equivalent Needs
The consolidation of the previous management and operating contractors (that
is, three into one) into the Bechtel Nevada contract is expected to result in a
significant reduction in Full-Time Equivalents in the near term, and a gradual
reduction of Full-Time Equivalents in the long term, tailored to match the
accomplishment of the Nevada projects and programmatic activities.
FUNDING ESTIMATE
The following tables present estimated funding information for the Nevada Test
Site.
Defense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
|
| Nuclear Material and Facility Stabilization
|
|
36,067
|
45,108 |
41,610
|
11,325 |
|
|
|
| Environmental Restoration
|
54,104 |
52,727
|
59,341 |
60,194
|
61,183 |
62,332
|
62,527 |
|
| Waste Management |
23,706
|
15,977 |
14,397
|
13,397 |
13,197
|
5,902 |
5,902
|
|
| Total |
77,810
|
104,771 |
118,846
|
115,201 |
85,705
|
68,234 |
68,429
|
|
| |
|
| Nuclear Material and Facility Stabilization
|
|
|
|
|
|
|
|
|
| Environmental Restoration
|
22,292 |
3,854
|
4,138 |
4,467
|
|
|
|
|
| Waste Management |
5,902
|
5,902 |
5,902
|
5,902 |
5,902
|
5,902 |
5,902
|
|
| Total |
28,194
|
9,756 |
10,040
|
10,369 |
5,902
|
5,902 |
5,902
|
|
| |
2075
|
2080
|
2085
|
2090
|
2095 |
2100
|
| Nuclear Material and Facility Stabilization
|
|
|
|
|
|
|
|
670,549
|
| Environmental Restoration
|
|
|
|
|
|
|
|
2,235,796
|
| Waste Management |
7,902
|
|
|
|
|
|
|
708,472
|
| Total |
7,902
|
|
|
|
|
|
|
3,614,817
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
FY 1996-2000
|
2025
|
2030
|
| Nuclear Material and Facility Stabilization
|
|
1,593
|
1,992 |
1,838
|
500 |
|
|
29,617
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
COMPARISON WITH PREVIOUS ESTIMATE
The 1996 life-cycle cost estimate for the Environmental Management program at
the Nevada Test Site and Tonopah Test Range is $3.6 billion, about 8 percent
more than the 1995 estimate of $3.5 billion. Overall, the 1996 estimate is
comparable to the 1995 estimate. The pre-FY 1996 costs have been adjusted to
reflect actual costs through 1995 and an annual escalation factor of 3 percent
has been applied to the 1996 estimate. The 1996 estimate includes about $10
million in costs associated with Environmental Restoration program activities
at the Tonopah Test Range; these costs were reported under the Nevada Offsites
section of the 1995 report. Cost estimates associated with Environmental
Restoration program activities increased almost 50 percent in the FY 1996
estimate. Cost estimates for the Nuclear Materials and Facility Stabilization
program increased by about 80 percent, but this increase was offset by a 37
percent reduction in projected Waste Management program costs. The following
sections compare the 1995 and 1996 cost estimates for the Nuclear Material and
Facility Stabilization program, the Environmental Restoration program, and the
Waste Management program at the Nevada Test Site.
Comparison Table
|
Thousands of Dollars
|
|
| Nuclear Mat. & Fac. Stab.
|
386,413 |
-
|
700,166 |
313,753
|
81 |
| Environmental Restoration
|
1,557,449 |
31,784
|
2,235,796 |
710,131
|
47 |
| Waste Management |
1,142,309
|
21,098 |
708,472
|
412,739 |
37
|
| Landlord |
-
|
- |
-
|
- |
-
|
| Program Management 2
|
364,216 |
14,605
|
- |
-
|
-
|
| Site Total |
3,450,388
|
67,487 |
3,644,434
|
261,533 |
8
|
1 The FY 1995 life-cycle and annual costs are provided
to determine the corrected FY 1995 cost.
2 Program Management was reported in an independent cost table last year, but
is reported as a line item in the relevant program (Nuclear Material and
Facility Stabilization, Environmental Restoration, and Waste Management)
activity cost estimate tables for the FY 1996 Baseline Report.
|
Nuclear Material and Facility Stabilization
The 1996 life-cycle cost estimate for the Nuclear Material and Facility
Stabilization program is $700 million, an increase of about $314 million from
the 1995 estimate. Although parametric modeling was again used in developing
the 1996 estimate, the estimate assumes an increase in the scope of program
activities.
Environmental Restoration
The 1996 life-cycle cost estimate for the Environmental Restoration program is
$2.2 billion, which is an increase of approximately 47 percent over the FY 1995
report. The increase in costs associated with major Environmental Program
activities, that is, Contaminated Soils, Industrial Sites, Underground Test
Areas, and Surveillance and Monitoring, are primarily associated with
redefinitions of program scope, schedule revisions, and more refined cost
estimating techniques. However, in contrast to the FY 1995 report, the Tonopah
Test Range was included in the Nevada Test Site for the FY 1996 report.
Applicable program management costs have also been added.
Waste Management
The 1996 life-cycle cost estimate for the Waste Management program is $708
million, about $413 million less than the 1995 estimate. A comparison of this
year's Baseline Environmental Management Report estimates with those of the FY
1995 Baseline Environmental Management Report indicates considerable
differences in waste management activities resulting in these estimated
reductions in life-cycle costs. For comparison, an analysis was conducted using
the same criteria as last year. Under treatment activities, the construction of
a Transuranic Waste Examination Facility will be built in FY 1996. The
construction of the liquid waste treatment system has been postponed while
project needs are being reviewed and reevaluated. Under storage activities, the
construction of an expanded hazardous waste storage pad was put on hold
indefinitely because the Nevada Division of Environmental Protection issued a
revision to the Hazardous Waste Permit on May 1, 1995. The revision extended
the storage of hazardous waste on the existing pad from 90 days to one year.
The construction of a mixed waste storage pad scheduled for FY 1996 was put on
hold because of the lack of identified need. The disposal activities at the
Nevada Test Site also show a decline in shipments of low-level waste to the
Nevada Test Site in the outyears.
|
 |