|
Home
BEMR
Contents
U.S.
Map
The Middlesex Sampling Plant is located in the Borough of Middlesex,
New Jersey, in Middlesex County, approximately 56 kilometers
(35 miles) northeast of Trenton and 42 kilometers (26 miles) southwest of
Newark. The 3.9 hectare (9.6 acre) site is bordered on the east by residential
properties on Mountain Avenue, on the south by William Street, and on the north
by the Lehigh Valley Railroad line.
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
| |
|
|
|
| Environmental Restoration
|
2,834
|
2,909
|
1,113
|
7,402
|
5,818
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
3,418
|
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
2,797
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
3,730
|
1,225
|
|
|
|
|
|
24,774
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The Manhattan Engineer District established the sampling plant in 1943 to
sample, store, and ship uranium, thorium, and beryllium ores. Manhattan
Engineer District operations at the site ceased in 1955, but the Atomic Energy
Commission later used the site for storage and limited sampling of thorium
residues. All Atomic Energy Commission activities at the site ended in 1967.
Onsite structures were decontaminated to levels acceptable at the time.
SITE MAP
From 1969 to 1979, the site was a training center for the U.S. Marine
Corps. In 1980, it was returned to the Department of Energy, as the Atomic
Energy Commission's successor agency, and designated for cleanup under FUSRAP.
Today, the Department of Energy monitors and maintains the site, which includes
two soil storage piles containing approximately 51,000 cubic meters
(66,300 cubic yards) of material; an office building; an old boiler house;
and the former process building, which is used as an archive facility for
radiological media samples. Addition of approximately 17,000 cubic meters
(22,000 cubic yards) of building materials and in situ soil and asphalt brings
the total site waste volume to an estimated 68,000 cubic meters
(89,000 cubic yards).
The Department of Energy stores material from past area cleanups at the site in
two piles. The larger pile, which was constructed in 1981, contains
approximately 27,000 cubic meters (35,100 cubic yards) of radioactively
contaminated soil and debris (low-level waste) generated during residential
cleanups. The second pile, built between 1984 and 1986, contains approximately
24,000 cubic meters (31,200 cubic yards) of waste from cleanup of the
Middlesex Municipal Landfill. In addition to radioactive constituents, the
landfill pile also contains metals such as lead and cadmium.
FUTURE USE
Future use of the property will depend on the final remedy chosen for the site.
The Department of Energy is considering treatment, capping in place, or
excavation and transportation of materials to an offsite disposal facility.
This estimate assumes that the final remedy will involve excavation and onsite
capping of soils, with controlled access including long-term monitoring and
maintenance.
ENVIRONMENTAL RESTORATION
Environmental restoration activities at the site are designed to identify and
evaluate contaminated areas through surveying and sampling, to devise cleanup
strategies, and to conduct cleanups as needed. Activities will focus on site
grounds; four onsite buildings; two soil storage piles created during past
cleanup of area properties, including the Middlesex Municipal Landfill; and a
drainage ditch that exits on the southern end of the site.
All activities are coordinated with key regulators, including Environmental
Protection Agency Region II, the New Jersey Department of Environmental
Protection, and the local health department. Environmental documentation for
the remaining actions to be taken at the Middlesex Sampling Plant will include
an engineering evaluation/cost analysis and will incorporate National
Environmental Policy Act values.
Material within the storage piles is contained by synthetic coverings that are
sealed, secured around the edges, and fastened with helical anchors. The cover
on the oldest pile, which was created during cleanup of nearby residential and
commercial properties in 1981, was replaced in 1992. Asphalt, concrete, or
grass covers contaminated soils on the site grounds. A settling basin at the
site outfall allows sediments to precipitate out of water before it exits the
site. A concrete berm surrounding the piles directs runoff water into drains
that feed the settling basin.
Major Environmental Restoration Activity Milestones
| Assessment (Engineering Evaluation/Cost Analysis with Action
Memorandum)
|
1998
|
|
Remedial Action
|
2003
|
|
Transfer Site to Grand Junction Projects Office Long-Term Surveillance and
Monitoring Program
|
2004
|
ASSESSMENT
Several radiological investigations have been conducted at the Middlesex
Sampling Plant. In 1967, after initial decontamination and before the Atomic
Energy Commission released it, the site was surveyed and determined to be
suitable for release according to the standards then in effect. When the site
was resurveyed in 1976, the results identified contamination above relevant
guidelines both onsite and offsite. The Department of Energy conducted cleanup
of offsite residential properties in 1980 and 1981 and cleaned up the Middlesex
Municipal Landfill between 1984 and 1986. A third radiological survey was
conducted in 1983 to prepare for an engineering evaluation for future cleanup
of the site in its entirety.
In 1991, the New Jersey Department of Environmental Protection requested a
study to determine the nature and levels of radioactive and chemical
contamination in the storage piles and in situ soils. This state agency
selected and approved a systematic sampling approach for the investigation;
samples were collected in a manner that ensured representativeness of the
contained waste. Composite samples were analyzed to determine average activity
levels of uranium238, radium226, and thorium232 in the storage
pile material. Both the vicinity property pile and the landfill pile were
analyzed for Resource Conservation and Recovery Act characteristics and
toxicity characteristics leaching procedure constituents. The tests indicated
that the piles do not contain Resource Conservation and Recovery Act hazardous
waste; however, samples from the landfill pile exceeded the regulatory limit
for lead, and two samples exceeded the regulatory limit for cadmium.
In 1990 and 1991, the Department of Energy conducted an intensive phased
sediment investigation in and along the drainage ditch exiting the southern end
of the site. It supplemented this investigation with limited sampling in 1992.
During soil sampling along the bank, the guideline of five picocuries per
gram above background was exceeded in only one sample [collected 0.9 meter
(three feet) from the outfall]; however, sediment samples showed elevated
activity downstream for a distance of nearly 60 meters (200 feet) from the
outfall.
The Department must address approximately 68,000 cubic meters
(89,000 cubic yards) of material for the site to comply with guidelines.
This estimate includes approximately 13,000 cubic meters (17,000 cubic
yards) of asphalt/gravel and soil from the grounds, 3,650 cubic meters
(4,775 cubic yards) from dismantlement of the boiler house and process
building, and 51,300 cubic meters (67,000 cubic yards) of material stored
onsite. In addition, the Department of Energy must decontaminate parts of the
garage and the office building.
Since 1980, the Department has conducted quarterly environmental monitoring
activities to measure radioactive constituents in ground water and surface
water, radon in the air (building interiors and outdoors), and external gamma
radiation. In 1990, metals were added to the quarterly analyses of ground water
and surface water. In 1991, the Department initiated analyses for volatile and
semivolatile organic compounds, and conducted a radiological investigation of
the storage piles and site soils in conjunction with testing for chemical
constituents. The drainage ditch exiting the southern border of the site was
sampled for radioactive contaminants in 1990, 1991, and 1992.
In 1992, the Department modified the ground-water monitoring program. It
reduced the number of wells sampled, and changed the sampling frequency from
quarterly to annually. In mid1994, all but one of the existing wells were
plugged and abandoned, and seven new monitoring wells were installed. The
Department replaced the wells because (1) the older wells were unreliable, (2)
well installation technology has improved, (3) standards have become more
stringent, and (4) specific depths need to be reached for monitoring.
Through the environmental monitoring program, the Department monitors and
periodically samples air, ground water, and soil to detect any above-background
contamination associated with the site. An annual report compiles and
interprets the monitoring and sampling data from the previous year. During
activities such as pile removal, building dismantlement, or ditch excavation,
the Department conducts additional monitoring to ensure that no contaminants
are spread as a result of the work.
REMEDIAL ACTION
Required actions that have been completed include removing contamination from
residential and commercial properties in 1980 and 1981, removing contamination
from the Middlesex Municipal Landfill in 1984 and 1986, storing these materials
at the site, conducting environmental monitoring, and performing surveillance
and maintenance. After removal actions were conducted, the Department restored
the vicinity properties to their original condition.
The drainage ditch that exits the site contains isolated spots of elevated
radioactivity along the ditch line. The Department of Energy currently plans to
clean up these spots under a Comprehensive Environmental Response,
Compensation, and Liability Act removal action, using heavy equipment and
general construction/excavation protocols. The removal will probably require
construction of a haul road along the ditch line as a transportation route back
to the existing storage piles onsite.
The Department will plan the cleanup of the site storage piles and grounds
through an Engineering Evaluation/Cost Analysis. It is evaluating many options
for the final site remedy, including capping in place with cover, removal and
offsite disposal, and partial removal with some onsite disposal.
The scenario used for the Baseline Environmental Management Report cost
estimate assumes excavation and onsite capping of the contaminated soils. The
cost estimate also includes decontamination of two buildings (garage and
administration building) and demolition of two additional buildings (process
building and boiler house). The total waste volume assumed for the cost
estimate is 68,000 cubic meters (89,000 cubic yards). The Department will
transfer long-term surveillance and maintenance to the Grand Junction Projects
Office in FY 2004.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2010
|
2015
|
2020
|
2025
|
2030
|
| FUSRAP - Middlesex Sampling Plant Site
|
|
|
|
|
|
|
|
|
| Assessment
|
80
|
|
|
|
|
|
|
400
|
| Remedial Action
|
3,650
|
1,225
|
|
|
|
|
|
24,374
|
| Total |
3,730
|
1,225
|
|
|
|
|
|
24,774
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FUNDING ESTIMATE
The following table presents estimated funding information for the Middlesex
site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of
Constant 1996 Dollars)
|
| |
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
3,730
|
1,225
|
|
|
|
|
|
24,774
|
| * Total Life Cycle is the sum of the annual
costs in constant FY 1996 dollars.
|
|
 |