|
Home
BEMR
Contents
U.S.
Map
The former Mexican Hat mill and tailings site covered approximately 95 hectares
(235 acres) and is located on Navajo Nation land at Halchita, Utah, about 2.4
kilometers (1.5 miles) southwest of Mexican Hat, Utah. Before remedial action,
the site contained two adjacent piles of tailings. One covered 10 hectares (25
acres) and the other covered 19 hectares (48 acres). The site also contained
seven mill buildings and associated debris, a concrete pad, contaminated soil,
and wind-blown material.
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
| |
|
|
|
| Environmental Restoration
|
924
|
333
|
348
|
985
|
167
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
757
|
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
523
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2020
|
2025
|
2030
|
| Environmental Restoration
|
525
|
51
|
48 |
50
|
|
|
|
3,367
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The mission of the Mexican Hat mill site was to provide uranium for the United
States Government. The source of contamination was the residual tailings that
remained after the milling process extracted the uranium. Texas-Zinc Minerals
Corporation built the Mexican Hat plant in 1957 and operated it under a lease
with the Navajo Nation until 1963, when it was sold to Atlas Corporation. Atlas
operated the mill for two years and shut it down in 1965. When the Atlas lease
expired in 1970, control of the site reverted to the Navajo Nation.
SITE MAP
The Environmental Management program is responsible for cleaning up surface-
and ground-water contamination at the UMTRA sites. The Uranium Mill Tailings
Radiation Control Act designated the residual radioactive material found at
this site for cleanup and stabilization. The Act directed the Environmental
Protection Agency to promulgate standards (Code of Federal Regulations Title
40, Part 192) and the Department of Energy to perform the cleanup. It also
assigned the Nuclear Regulatory Commission to oversee and certify the cleanup
and license the completed disposal cell. The affected Tribes will participate
in decisionmaking.
Pursuant to the Uranium Mill Tailings Radiation Control Act, the Department of
Energy entered into a Cooperative Agreement in 1983 with the Navajo Nation. The
agreement outlines the roles and responsibilities of each party. The Department
of Energy pays 100 percent of all costs (assessment and remediation) when the
UMTRA site is on Indian land. In addition, the Department of Energy is
responsible for paying 100 percent of the Tribe's costs. The Nuclear Regulatory
Commission concurred on the original agreement and is required to concur on all
major modifications.
FUTURE USE
The Mexican Hat disposal site is located on Navajo Nation land. However, the
long-term surveillance of the disposal cell is the responsibility of the
Department of Energy through a Custodial Access Agreement between the Navajo
Nation and the Federal Government. Provisions of the Custodial Access Agreement
will allow the Department to have permanent access to the disposal cell and
will likely include restrictions, as necessary, to protect the public health,
safety, and the environment.
ENVIRONMENTAL RESTORATION
Surface remedial action has been completed and the source of contamination has
been stabilized. However, residual milling-related contaminated ground water
remains.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2020
|
2025
|
2030
|
| UMTRA Surface
|
|
|
|
|
|
|
|
|
| Assessment
|
42
|
|
|
|
|
|
|
208
|
| UMTRA Ground water
|
|
|
|
|
|
|
|
|
| Assessment
|
72
|
|
16 |
19
|
|
|
|
534
|
| Remedial Action
|
11
|
|
|
|
|
|
|
55
|
| Direct Program Management/Support
|
400
|
51
|
32 |
31
|
|
|
|
2,570
|
| Total |
525
|
51
|
48
|
50
|
|
|
|
3,367
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Surface Project
Remedial action under the UMTRA Surface project began at the site in 1988 and
was completed in February 1995. Remedial action involved consolidation of
approximately 2 million cubic meters (2.6 million cubic yards) of residual
radioactive material in place at the bottom of what is now the Mexican Hat
disposal cell, followed by placement of approximately 703,152 cubic meters
(925,200 cubic yards) of residual radioactive material from the Monument Valley
site in Arizona, for a total of approximately 2,647,080 cubic meters (3,483,100
cubic yards) of residual radioactive material. Eleven vicinity properties were
remediated concurrently with site remediation activities. This report assumes
that the Nuclear Regulatory Commission will certify the site in February 1997
and license the disposal cell in March 1997.
Major Surface Project Milestones
| Publish the Revised Remedial Action Plan
|
1996
|
|
Nuclear Regulatory Commission Issues General License
|
1997
|
|
Transfer to Grand Junction Projects Office's Long-Term Surveillance and
Maintenance Program
|
1997
|
The Mexican Hat Remedial Action Plan outlines the necessary tailings and
contaminant distribution and remediation. The revised Remedial Action Plan,
which requires Nuclear Regulatory Commission concurrence, will be published in
December 1995. The UMTRA Surface Project will conduct surveillance and
maintenance of the disposal cell after completion of remedial action and prior
to its transfer to the Grand Junction Projects Office's Long-Term Surveillance
and Maintenance program in FY 1997.
Ground-Water Compliance Project
The Department is developing a Programmatic Environmental Impact Statement
pertaining to all 24 UMTRA sites. For a discussion of the Programmatic
Environmental Impact Statement, see the UMTRA program narrative in the New
Mexico section of this report. Site-specific National Environmental Policy Act
documentation will be developed to propose an appropriate ground-water
compliance strategy and reasonable alternatives for the Mexican Hat site once
the Programmatic Environmental Impact Statement is completed.
This report assumes a strategy of demonstrated compliance, with additional
characterization and the application of supplemental standards based on
limited-use of ground water. For all types of ground-water compliance
strategies, once the Nuclear Regulatory Commission determines the site to be in
compliance with Subpart B of the Environmental Protection Agency Standards and
it is certified, no additional long-term surveillance or monitoring will be
conducted.
The following milestone dates have been established for planning purposes.
Major Ground-Water Compliance Project Milestones
| Site Observational Work Plan
|
1997
|
|
Publish Environmental Assessment/Finding of No Significant Impact
|
1998
|
|
Publish Remedial Action Plan
|
1999
|
|
Licensing
|
2115
|
Ground water is present in two units beneath the site, the Halgaito Shale
Formation and the Honaker Trail Formation. There is no ground-water
contamination in the Honaker Trail Formation. The ground water in the shallower
zone, the Halgaito Shale, is contaminated. It occurs over a limited area and
ground water in this formation is primarily the result of tailings seepage.
Controlled by fracture orientation, ground water within the Halgaito Shale
flows east at an approximate rate of 9 meters (30 feet) per year. Ground water
in the Halgaito Shale Formation exceeds the Environmental Protection Agency
maximum concentration limits for several constituents, including chromium,
molybdenum, net gross alpha, nitrate, and uranium. This contaminated ground
water does not affect domestic wells.
Direct Program Management/Support
Program management supports management efforts for the National Environmental
Policy Act process, site characterization and licensing, public
information/participation, applicable state and federal regulator costs,
quality assurance audits, program and management support for the technical
assistance contractor, special studies, document control, technical assistance
contractor site and technical management, cost and schedule controls, planning
and preparation of the federal budget, and the Environmental Management
Progress Tracking System.
FUNDING ESTIMATE
The following table presents estimated funding information for the Mexican Hat
site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2020
|
2025
|
2030
|
| Environmental Restoration
|
525
|
51
|
48 |
50
|
|
|
|
3,367
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|
 |