|
Home
BEMR
Contents
U.S.
Map
The Kansas City Plant is part of the Bannister Federal Complex, a 120-hectare
(300-acre) site 19.2 kilometers (12 miles) south of downtown Kansas City,
Missouri. The Department of Energy occupies 56.4 hectares (141 acres) of this
reservation. The complex is zoned by local government for heavy industry. The
surrounding area consists of single- and multiple-family residences, commercial
establishments, industrial districts, and public-use lands.
LOCALITY MAP
Estimated Site Total
|
(Thousands of Current Year Dollars)
|
| |
|
|
|
| Environmental Restoration
|
6,697
|
5,059
|
5,429
|
6,340
|
2,603
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| Waste Management
|
6,067
|
10,976
|
9,461
|
5,990
|
6,142
|
|
| Total
|
12,764
|
16,035
|
14,890
|
12,330
|
8,745
|
|
| 1996 Appropriation
|
14,620
|
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
13,380
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
|
| Environmental Restoration
|
4,968
|
648
|
|
|
|
|
|
|
| Waste Management
|
7,316
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
|
| Total
|
12,284
|
6,107
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
|
| |
|
| Environmental Restoration
|
|
|
|
|
|
|
|
|
| Waste Management
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
|
| Total
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
|
| |
2075
|
2080
|
2085
|
2090
|
2095
|
2100
|
| Environmental Restoration
|
|
|
|
|
|
|
|
28,081
|
| Waste Management
|
5,459
|
|
|
|
|
|
|
418,710
|
| Total
|
5,459
|
|
|
|
|
|
|
446,791
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The Kansas City Plant was constructed in 1942 to build aircraft engines for the
Navy. After World War II, it was used for storage, and in 1949 it was selected
for its current mission, manufacturing nonnuclear components for nuclear
weapons. Electrical, electromechanical, mechanical, and plastic components are
manufactured or procured by this facility.
SITE MAP
Various spills and leaks from production activities have resulted in soil and
ground-water contamination. Ground-water contamination is mainly
trichloroethylene and its degradation products 1,2-dichloroethylene, and vinyl
chloride. Soil is contaminated with volatile organic compounds, polychlorinated
biphenyls, and petroleum products. The approximate surface area of
contamination is 310,000 square meters (76.6 acres) for ground water and 70,000
square meters (17.3 acres) for subsurface soil. An interceptor trench and wells
are used to contain contaminated ground water. Although no immediate risk to
employees or the public exists, the plant has been aggressively cleaning up its
environmental problems. Cleanup activities are driven by a Consent Order
Agreement with the Environmental Protection Agency.
The Environmental Management program began providing funding for environmental
restoration and waste management activities in 1990. The Office of Defense
Programs is the landlord for the site, and this report assumes it will continue
in that capacity indefinitely. Environmental management activities contribute
to landlord costs through an indirect burden rate captured in each of the
activity estimates. There are no current or planned nuclear material and
facility stabilization projects at this site.
The Waste Management program, which supports environmental restoration
activities, as well as the Office of Defense Programs, includes primarily
hazardous waste storage in preparation for offsite treatment or disposal. These
activities include providing containers to waste generators, characterization,
packaging, transportation, treatment, storage, and disposal, as applicable.
Small quantities of lowlevel radioactive waste are also generated. There
is no onsite waste disposal. Treatment operations are limited to industrial
wastewater pre-treatment. The Office of Defense Programs, as landlord, disposes
of sanitary waste consisting of normal garbage and sewage.
FUTURE USE
The Kansas City Plant has been selected as the nonnuclear manufacturing
facility for the nuclear weapons complex. This report assumes that this mission
will continue indefinitely.
Alternatives for the future use of the land occupied by the entire federal
complex have been reviewed and a proposal has been developed. The proposal was
presented to other occupants of the federal complex and a community involvement
group for stakeholder input on April 11, 1995. The community involvement group
consists of representatives of local government, community groups, business
groups, and environmental organizations. The consensus opinion of all parties
was that the entire federal complex will continue to be used for industrial
purposes for the foreseeable future.
ENVIRONMENTAL RESTORATION
The purpose of the Environmental Restoration program is to evaluate potentially
contaminated areas and to clean up areas found to be a threat to human health
or the environment. Forty-one sites have been identified and investigated under
a Consent Order Agreement between the Department of Energy and the
Environmental Protection Agency. The agreement requires the Department of
Energy to analyze the extent and type of contamination, evaluate cleanup
alternatives, and implement the selected cleanup alternative at each site.
Prior to selecting the cleanup alternative, the Environmental Protection Agency
provides the public with the opportunity to comment on the recommended
alternative. Although the Environmental Protection Agency is the only regulator
for the Environmental Restoration program, all regulatory documents are
provided to the State of Missouri for review and comment.
ENVIRONMENTAL RESTORATION MAP
The main sources of contamination are accidental spills and leaks from
manufacturing processes. Soil has been contaminated with volatile organic
compounds, polychlorinated biphenyls, and petroleum hydrocarbons. Some of the
contaminants, mainly the volatile organics, have migrated through the soil and
have contaminated the ground water. To control the migration of contaminated
ground water, a treatment system was installed and has been operating since
1988. Source contaminant migration is monitored by periodic sampling of an
extensive array of wells.
The 41 sites were grouped into ten projects, primarily by geographic areas, and
the Department has investigated all of them. Fifteen sites have either been
cleaned up or found not to require cleanup. Typically, cleanup has involved
excavating contaminated soil and disposing of it in a certified offsite
landfill. The Department is currently evaluating cleanup alternatives for the
remaining sites. The evaluation of the alternatives considers the future land
use of the site, exposure risk, cost, and technological feasibility.
Existing down gradient ground-water monitoring wells will be sampled
semiannually to ensure that the contamination does not migrate offsite.
Monitoring costs are shown in the site-wide ground-water treatment and
monitoring project. For estimating purposes, this report has assumed a
monitoring duration of 30 years.
Although alternatives for the remaining sites have not been selected or agreed
to by the regulators, selection assumptions have been made in developing costs
for this report. Specifically, this report assumes that contaminated sites with
minimal exposure risk will require No Further Action other than implementing
procedural controls. If cleanup of these sites is required, the cost will
increase significantly. This report assumes that no contamination will be found
in addition to the material identified in the assessments subsections for the
active environmental projects discussed below, and there are no decommissioning
activities needed. The cost for characterizing, storing, treating, transporting
and disposing of waste generated during remedial action is included within the
Environmental Restoration program costs.
Major Environmental Restoration Activity Milestones
| Miscellaneous Soils Remediation
|
1996
|
|
Miscellaneous Polychlorinated Biphenyls Sites Remediation
|
1996
|
|
Department 27 Remediation
|
1997
|
|
Department 26 Remediation
|
1998
|
|
NE Area and Outfall 001 Remediation
|
1998
|
|
Vehicle Repair Shop Sump Remediation
|
1998
|
|
Plating Building Remediation
|
2000
|
|
TCE Still Area Remediation
|
2000
|
|
Ground-Water Treatment and Monitoring
|
2001
|
|
South Lagoon Remediation
|
2001
|
Department 26: Southeastern Quadrant Beneath Main Manufacturing Building
ASSESSMENT
Polychlorinated biphenyls contamination of subsurface soils was suspected
because of the heat-transfer fluid (Therminol FR-1) previously used in the
plastic molding operations. Polychlorinated biphenlys were released by piping
system leaks. The heat-transfer fluid was replaced with a nonpolychlorinated
biphenlys-bearing fluid in 1974. Investigation of this site is complete and
soil sample analysis confirmed significant areas of polychlorinated
biphenyls-contamination. The contamination is primarily under the main
manufacturing building and extends approximately 40 feet down to bedrock.
Approximately 7,325 cubic meters (9,600 cubic yards) of soil is contaminated.
The Environmental Protection Agency has approved the Resource Conservation and
Recovery Act Facilities Investigation report and the corrective measures study
is being developed. The assessment phase for this project is approximately 92
percent complete, with a projected completion date of July 1996.
REMEDIAL ACTION
Remediation alternatives are being evaluated. The contamination is primarily
under the main manufacturing building, and there is little exposure risk.
However, removing the contamination could endanger workers and damage the
structural integrity of the building. Technology to treat the contamination
without removing the soil does not exist. Therefore, this report assumes that
the remediation alternative selected will leave the contamination in place
until the building is demolished or a technology is developed to treat the
contamination without removing the soil. The final selection will not be made
until the proposal is submitted to the regulators and the public has been given
the opportunity to provide comments. Monitoring of down gradient ground-water
wells will be conducted to ensure that contamination does not migrate. The
estimate assumes remediation will be complete in FY 1998.
Department 27 (Inside): Northeastern Quadrant Beneath Main Manufacturing
Building
ASSESSMENT
The presence of polychlorinated biphenyls was suspected in the soil beneath
this quadrant because of the past use of Therminol FR-1 to control the
temperature of molds used to form rubber and plastic components. Leaks in the
heat transfer system were thought to have allowed the polychlorinated biphenyls
to seep into the underlying soil through joints and cracks in equipment
foundation pits. Therminol FR-1 was replaced with a nonpolychlorinated
biphenyls-bearing fluid in 1974. Investigation of this site is complete, and
soil sample analysis found approximately 100 cubic meters (130 cubic yards) of
minor polychlorinated biphenyls contamination. However, the level of
contamination found is not above cleanup levels. Ground-water volatile organic
compound contamination was detected because of up gradient soil contamination.
Low levels of petroleum hydrocarbon contamination were also detected. The
Environmental Protection Agency has approved the Resource Conservation and
Recovery Act Facilities Investigation report and the corrective measures study
is being developed. The assessment phase for this project is approximately 91
percent complete with a projected completion date of July 1996.
REMEDIAL ACTION
The Department is evaluating remediation alternatives. The contamination is
primarily under the main manufacturing building and there is little risk of
exposure. However, removing the contamination could endanger workers and damage
the structural integrity of the building. Technology to treat the contamination
without removing the soil does not exist. Therefore, this report assumes that
the remediation alternative selected will leave the contamination in place and
use institutional controls to manage the risk. Institutional controls will
ensure that any soil excavated from this area will be handled in a manner that
protects employees and the public and will be disposed of in accordance with
applicable regulations. The final remedial action alternative will not be
selected until the proposal is submitted to the regulators and the public has
been given the opportunity to provide comments. Monitoring of down gradient
ground-water wells will be conducted to ensure contamination does not migrate.
The estimate assumes remediation will be complete in FY 1997.
Miscellaneous Contaminated Soils
ASSESSMENT
Four potentially contaminated areas were investigated as a part of this
project, the North Lot, Building 16, the abandoned fuel lines, and the fuel oil
tank loading and unloading area. Old aerial photographs indicate the northwest
corner of the north parking lot was used as a staging area for drums prior to
being paved. The contents of the drums, the occurrence of any leaks, and their
final disposition is unknown.
Building 16 houses an in-ground centrifuge used to test weapons components and
a mold-flushing facility. The concrete centrifuge chamber has a sump where
water and hydraulic fluid from equipment leaks have accumulated. The
mold-flushing facility includes a below-grade storage area for spent flushing
solvents. A 11,300-liter (3,000-gallon) steel tank is buried outside the
building to capture fire-sprinkler water from mold flushing.
The abandoned fuel lines were installed when the plant was constructed to
transfer fuels, kerosene, oils, rust inhibitors, and solvents from truck and
railcar unloading stations to underground storage tanks and from tanks to the
main manufacturing building.
The fuel oil tanks consist of two above-ground 1.5 million liter
(400,000-gallon) steel tanks, a loading and unloading area, and associated
piping. The tanks originally stored jet fuel and were later converted to store
fuel oil. The tanks were initially surrounded by an earthen berm to contain
spills. The berm has been replaced by concrete walls. The floor of the
containment area consists of unlined earth. Petroleum products were
occasionally spilled on the ground at the loading and unloading area. In-tank
steam coils used to heat the fuel oil leaked in 1989, causing the tank to
overflow onto the floor of the containment area.
Investigation of these sites is complete, and soil sample analysis found no
contamination at the north lot and Building 16 locations. These two sites have
received No Further Action designations from the Environmental Protection
Agency. Petroleum products were found in the soil at the abandoned fuel lines
and the fuel oil tanks. Additionally, volatile organics compounds were detected
in the soil at the abandoned fuel lines. Approximately 6,880 cubic meters
(9,000 cubic yards) of soil is contaminated. The Environmental Protection
Agency has approved the Resource Conservation and Recovery Act Facilities
Investigation report. The corrective measures study has been submitted to the
regulators and no comments were received from the public during the public
notice period. The assessment phase for this project is approximately 96
percent complete, with a projected completion date of May 1996.
REMEDIAL ACTION
The Department has evaluated remediation alternatives and recommended to the
regulators that it address the contamination in place and use institutional
controls to minimize the risk of exposure. Institutional controls will ensure
any soil excavated from this area will be managed in a manner that protects
employees and the public and will be disposed in accordance with applicable
regulations. The public has been given the opportunity to comment on this
recommendation, and no comments were received during the public notice period.
Monitoring of down gradient ground-water wells will be conducted to ensure
contamination does not migrate. The estimate assumes no further action after FY
1996 when the remediation should be completed.
Miscellaneous Polychlorinated Biphenyls Sites
ASSESSMENT
The Department believes that a lightning strike at an electrical substation may
have caused the release of polychlorinated biphenyls. The substation is housed
in a small containment structure attached to the north side of the
Manufacturing Support Building. There was additional polychlorinated biphenyls
contamination in an underground ductbank. The cable was insulated with
polychlorinated biphenyls-impregnated paper. Investigation of this site is
complete, and sample analysis confirmed the presence of polychlorinated
biphenyls contamination. Approximately 11 cubic meters (14 cubic yards) of
structures and equipment was contaminated. The Environmental Protection Agency
approved the recommendation made in the Resource Conservation and Recovery Act
Facilities Investigation report to clean up this site via the Interim Measures
process. The assessment phase for this project is complete.
REMEDIAL ACTION
Decontamination, demolition, and disposal of the containment structure and
electrical cables have been completed as outlined in the Interim Measures work
plan approved by the Environmental Protection Agency. Approximately 33 tons
(30,000 kilograms) of Toxic Substances Control Act-regulated waste were
generated and disposed of at a certified commercial landfill. A portion of the
wall shared with the Manufacturing Support Building and the concrete floor
could not be decontaminated below the cleanup standards. A proposal to
encapsulate the wall surface has been submitted to the Environmental Protection
Agency. This estimate assumes that the regulators will approve the proposal,
and the wall shared with the Manufacturing Support Building and floor will be
encapsulated to stabilize the residual polychlorinated biphenyls contamination.
The estimate assumes remediation will be complete in FY 1996.
Northeast Area and the Outfall 001 Raceway
ASSESSMENT
The Northeast Area encompasses the northeastern portion of the complex and
includes land administered by the General Services Administration, the Internal
Revenue Service, and the Union Pacific Railroad. The ground water in this area
is contaminated with volatile organic compounds. The source of this
contamination is unknown but is probably due to random dumping, leaking
pipelines, and a wastewater lagoon.
The Outfall 001 Raceway is the discharge point for the 001 Storm Sewer System
which drains the north-central and northeastern portions of the plant. It
passes through an area of ground-water and soil contamination derived from past
waste handling practices. The area has also been affected by past discharges
through the 001 Storm Water Outfall.
Old aerial photographs show ponds in and just north and west of the former
north lagoon. This area was originally low-lying and poorly drained.
Photographs indicate that material was dumped in the area from makeshift haul
roads.
Investigation of these sites is complete and soil sample analysis found
volatile organic compound and petroleum product contamination in soils
primarily at and below the water table in the area of the old ponds. The extent
of the contaminated ground-water plume was also defined. Approximately 2,220
cubic meters (2,900 cubic yards) of soil is contaminated. The Environmental
Protection Agency has approved the Resource Conservation and Recovery Act
Facilities Investigation report. The corrective measures study has been
submitted to the regulators and no comments were received from the public
during the public notice period. The assessment phase for this project is
approximately 95 percent complete, with a projected completion date of May
1996.
REMEDIAL ACTION
Remediation alternatives have been evaluated, and the recommendation has been
made to the regulators to address the contamination in place and minimize
exposure risk through institutional controls. Institutional controls will
ensure any soil excavated from this area will be handled in a manner to protect
employees and the public and will be disposed of in accordance with applicable
regulations. Since the contamination exists on non-Department of Energy
property, the procedures used for institutional controls will be developed with
other occupants. The public was given the opportunity to comment on this
recommendation, and no comments were received.
Contaminated ground water is being contained from migrating offsite by the
existing ground-water treatment system. In addition, the recommended
remediation alternative for ground-water contamination is to add another
production well in the Northeast Area to ensure plume containment. The
recommended alternative also provides for an increase in the interceptor trench
pumping rate, requiring construction of an additional production well in the
interceptor trench. The estimate assumes remediation will be complete in FY
1998.
The contaminated ground-water plume is near the property boundary of the
federal complex. To keep the contamination from migrating into the nearby Blue
River, an interceptor trench and production wells were installed in 1988.
Ground water is pumped from these wells to an Ultraviolet/Hydrogen Peroxide
treatment system. This system eliminates 99.7 percent of the contamination in
the ground water. The resulting effluent is discharged into the city sanitary
sewer. This project is part of the ground-water treatment and monitoring
program.
Plating Building
ASSESSMENT
The plating building was constructed in 1957 to provide onsite metal plating. A
new plating facility was constructed in 1987, and the old facility was removed
from service. Portions of its structure, including concrete floors and walls,
were found to contain heavy metals, polychlorinated biphenyls, cyanide, and
petroleum products. This project includes Building 57, the Waste Oil Tank,
Substation 18, and the Department 26 outside sites.
Building 57 was the original plating building, and demolition was completed
1990. Following demolition, the site was paved with asphalt.
An abandoned 98-cubic meter (26,000-gallon) waste oil tank is buried under the
north foundation wall of Building 57. This tank was originally installed to
recover spent anti-rust oil from operations in the main manufacturing building.
The tank was abandoned and filled with sand in the early 1950s. Sampling
indicated the tank contents are contaminated with polychlorinated biphenyls.
The soil immediately around the tank is also saturated with petroleum.
Substation 18 was constructed to provide electrical power for the plating
building. It included an oil-filled transformer containing a polychlorinated
biphenyls-based cooling oil (Aroclor 1260). Multiple spills occurred and
were cleaned up during the 30-year operation of the building. The
polychlorinated biphenyls transformer was removed from the substation when the
plating building was demolished. Polychlorinated biphenyls from this
transformer have contaminated the soil in this area.
A portion of the piping system for heating and cooling the Department 26
plastic molding operations was located between the main manufacturing building
and the plating building. A buried 37,800-liter (10,000-gallon) tank supplied a
polychlorinated biphenyls heat transfer fluid (Therminol FR-1) for the system.
Polychlorinated biphenyls from the tank and piping system have contaminated the
soil down to bedrock. The tank and piping system were removed and replaced with
a polychlorinated biphenyls-free system in 1983.
Investigation of these sites is complete. Approximately 2,935 cubic meters
(3,800 cubic yards) of soil is contaminated. The Environmental Protection
Agency has approved the Resource Conservation and Recovery Act Facilities
Investigation report, and the corrective measures study is being developed. The
assessment phase for this project is approximately 93 percent complete, with a
projected completion date of July 1996.
REMEDIAL ACTION
Remediation alternatives are being evaluated. For estimating purposes, the
assumed remediation strategy is to remove surface and shallow contamination
sources that have the potential of contaminating storm water. This will include
removing and disposing of the cyanide spill sump, the remains of the Building
57 foundation, Substation 18, the abandoned Waste Oil Tank, the Building 57
abandoned floor drain piping, the abandoned caustic/acid sump structure, and
the pipe gallery containment basin and 0.6 to 1.2 meters (2 to 4 feet) of
underlying soil. The estimates included in this report assume disposal of 2,060
cubic meters (2,700 cubic yards) of Toxic Substances Control Act-regulated soil
and debris, 233 cubic meters (305 cubic yards) of soil as sanitary waste, and
incineration of 2 cubic meters (2.6 cubic yards) of concrete, 6.5 cubic meters
(8.5 cubic yards) of other solids, and 11 cubic meters (14 cubic yards) of
waste oil regulated by the Toxic Substances Control Act.
An asphalt cap was placed over the soil after the old plating building was
demolished. An accelerated interim measures project is in process to remove the
underground Waste Oil Tank prior to conducting further remedial actions.
Remediation activities are assumed to be completed in FY 2000.
South Lagoon
ASSESSMENT
The South Lagoon is in the northeast quadrant of the Department of Energy
property. It was constructed in 1975 to assist the North Lagoon in receiving
industrial wastewaters from production activities and was used until 1988. The
wastewater consisted of rinse waters, drain input, and treated cooling water
from various manufacturing processes including electroplating and degreasing.
Sludge from the North and South Lagoons was removed in 1985 and 1988,
respectively. A nonpermeable cap was installed over both lagoons in 1988. The
Environmental Protection Agency has approved the Resource Conservation and
Recovery Act Facilities Investigation report and has agreed to monitor this
site in lieu of further ground-water remediation. The public has been given the
opportunity to comment on the recommendation to designate this site for No
Further Action. No comments have been received. Assessment activities are
assumed to be completed in FY 1998.
Trichloroethylene Still Area
ASSESSMENT
The Trichloroethylene Still Area contains multiple release sites: the former
trichloroethylene still, the classified waste burial trenches, the oil house,
Department 95, the former aluminum chip handling facility, the former sales
building, the waste transfer spill area, the abandoned sump, and the Department
20 sump.
Investigation of these sites is complete, and soil sample analysis found
volatile organic compound contamination above the water table at the oil house,
trichloroethylene still, classified waste burial trenches, Department 20 sump,
abandoned sump, and waste transfer spill area. Soil contamination above the
water table was also found at the abandoned sump/waste transfer spill area.
Petroleum product contamination was found in soil above the water table at the
abandoned sump and the waste transfer spill area. Soil contamination below the
water table was found at the oil house, trichloroethylene still, Department 20
sump, classified waste burial trenches, aluminum chip handling facility, sales
building, the abandoned sump, and waste transfer spill area. Approximately 884
cubic meters (1,160 cubic yards) of soil is contaminated. The Environmental
Protection Agency has approved the Resource Conservation and Recovery Act
Facilities Investigation report, and the corrective measures study is being
developed. The assessment phase for this project is approximately 94 percent
complete, with a projected completion date of July 1996.
REMEDIAL ACTION
The Department is evaluating remediation alternatives. For estimating purposes,
the assumed remediation strategy is partial excavation of contaminated soil at
the trichloroethylene still, oil house, abandoned sump, and Department 20 sump.
The report assumes that most waste will be disposed of in a certified
commercial landfill and some waste from the abandoned sump will have to be
incinerated. Three ground-water production wells will be added to further
control contaminated ground water. The Department will not select the final
remedial action alternative until the proposal is submitted to the regulators
and the public has been given the opportunity to provide comments. Monitoring
of down gradient ground-water wells will be conducted to ensure that the
contamination does not migrate. The estimates included in this report assume
disposal of 621 cubic meters (812 cubic yards) of Resource Conservation and
Recovery Act-regulated soil and remediation will be complete in FY 2000.
Maintenance Vehicle Repair Shop Sump
ASSESSMENT
Three areas of concern are associated with maintaining the vehicle repair shop
sump: the sump pits, Building 54, and the test cell area.
The sump pits were built in 1970 to house a hydraulic vehicle lift. Plant
vehicles were washed on the lift before repair. The lift has been
decommissioned. Building 54 was constructed to test aircraft engines. The
building's basement housed electric motors used to circulate water through
cooling towers. The test cells were originally used to test aircraft engines.
It is likely that fuel, oils, and degreasers were used in the cells during
manufacturing.
Investigation of these sites is complete and although ground-water
contamination exists, no soil source contamination was found at the maintenance
vehicle repair shop sump, the sump pits, or Building 54. Significant areas of
petroleum product contamination were found at the test cell area. Approximately
1,000 cubic meters (1,300 cubic yards) of soil is contaminated. The
Environmental Protection Agency has approved the Resource Conservation and
Recovery Act Facilities Investigation report, and the corrective measures study
is being developed. The assessment phase for this project is approximately 92
percent complete, with a projected completion date of July 1996.
REMEDIAL ACTION
The Department is evaluating remediation alternatives. For estimating purposes,
the assumed remediation strategy is excavation and disposal of shallow
contamination sources that have the potential to contaminate storm water or
pollute ground water. The Department will not select the final remedial action
alternative until the proposal is submitted to the regulators and the public
has been given the opportunity to provide comments. Monitoring of down gradient
ground-water wells will be conducted to ensure contamination does not migrate.
The estimates included in this report assume disposal of 1,000 cubic meters
(1,300 cubic yards) of Resource Conservation and Recovery Act-regulated soil,
and incineration of 24 cubic meters (31 cubic yards) of liquid waste regulated
by the Toxic Substances Control Act. Remediation is assumed to be complete in
FY 1998.
Ground-Water Treatment and Monitoring
This project includes ground-water monitoring for the entire plant. An
extensive array of ground-water monitoring wells has been installed, and the
wells are sampled twice a year. The extent of ground-water plume contamination
was determined from assessment activities for other projects and from
monitoring well data.
Contaminated ground water is being contained by the ground-water
pump-and-treatment system. This system uses an ultraviolet/hydrogen peroxide
treatment system to break down the chemical bonds of the contaminants. This
project is also evaluating source remediation technologies, including deep soil
mixing and in situ microwave remediation.
Deep soil mixing uses a large diameter mixing blade modified to allow the
injection of reagents during the mixing process. The reagents will chemically
react with the contamination during the mixing process, thus immobilizing it or
reducing its toxicity. In situ microwave remediation uses down-hole antennae
selectively tuned to heat targeted contamination. The contamination will
vaporize, and it is extracted. Field studies to test the effectiveness of these
technologies are scheduled for FY 1996.
An alternate concentration limit petition is being prepared for submittal to
the Environmental Protection Agency. The petition proposes that ground-water
treatment can be discontinued with no significant impact on the environment. If
the Environmental Protection Agency agrees with the petition, ground-water
treatment will no longer be required. For estimating purposes, ground-water
treatment costs are included only through the year FY 2001.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2010
|
2015
|
2020
|
2025
|
2030
|
| Remediation Technology Evaluation
|
|
|
|
|
|
|
|
|
| Assessment
|
38
|
|
|
|
|
|
|
188
|
| Department 26
|
|
|
|
|
|
|
|
|
| Remedial Action
|
30
|
|
|
|
|
|
|
148
|
| Department 27
|
|
|
|
|
|
|
|
|
| Assessment
|
3
|
|
|
|
|
|
|
15
|
| Remedial Action
|
9
|
|
|
|
|
|
|
45
|
| Miscellaneous Contaminated Soils
|
|
|
|
|
|
|
|
|
| Assessment
|
2
|
|
|
|
|
|
|
10
|
| Remedial Action
|
8
|
|
|
|
|
|
|
39
|
| Miscellaneous PCB Sites
|
|
|
|
|
|
|
|
|
| Remedial Action
|
15
|
|
|
|
|
|
|
74
|
| Northeast Area and Outfall 001
|
|
|
|
|
|
|
|
|
| Assessment
|
5
|
|
|
|
|
|
|
26
|
| Remedial Action
|
47
|
|
|
|
|
|
|
234
|
| Plating Building
|
|
|
|
|
|
|
|
|
| Remedial Action
|
542
|
|
|
|
|
|
|
2,709
|
| South Lagoon
|
|
|
|
|
|
|
|
|
| Assessment
|
28
|
|
|
|
|
|
|
140
|
| Remedial Action
|
264
|
1
|
|
|
|
|
|
1,323
|
| Trichloroethylene Still Area
|
|
|
|
|
|
|
|
|
| Remedial Action
|
459
|
|
|
|
|
|
|
2,294
|
| Maintenance Vehicle Repair Shop Sump
|
|
|
|
|
|
|
|
|
| Assessment
|
2
|
|
|
|
|
|
|
8
|
| Remedial Action
|
378
|
|
|
|
|
|
|
1,892
|
| Ground Water Treatment and Monitoring
|
|
|
|
|
|
|
|
|
| Remedial Action
|
1,376
|
192
|
|
|
|
|
|
7,839
|
| Direct Program Management/Support
|
1,764
|
455
|
|
|
|
|
|
11,097
|
| Total
|
4,968
|
648
|
|
|
|
|
|
28,081
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Direct Program Management/Support
Program management and support functions cut across all environmental
restoration activities. Costs are included for personnel to develop and
validate cost estimates; manage project cost, schedule, and technical
baselines; formulate and execute budget requirements; develop performance
reports; ensure regulatory compliance; and support audits, reviews, and
validations.
| STAKEHOLDER INTERACTIONS
The Kansas City Area Office presented draft baseline report information on the
Kansas City Plant to the Community Involvement Group. The group concurred with
the draft and had no additional comments. The office also included information
on the report in its quarterly newsletter, Focus on the Environment,
which is distributed to 3,000 households. If you would like more information
about the report or have questions about the results for this site, please
contact:
|
Public Participation
David Hampton
(816) 9977005
dhampton@kcp.com
|
Technical Liaison
Jim Orr
(505) 845-4734
jorr@doeal.gov
|
Public Affairs
Tami Toops
(505) 845-5264
ttoops@doeal.gov
|
WASTE MANAGEMENT
The Waste Management program conducts a waste acceptance certification program
to certify all waste generated at the Kansas City Plant. Waste is characterized
in the generating process and then transferred to temporary storage and
prepared for offsite shipment and disposal at permitted treatment, storage, and
disposal facilities. No waste is either treated or disposed onsite. Sanitary
waste disposal is the responsibility of the Office of Defense Programs in its
role as site landlord. In the future, waste generation from existing production
operations is expected to decrease as a result of downsizing. Costs for
transportation of waste appear in disposal costs for each waste type.
Waste Management provides technical guidance to other onsite programs for
proper management of waste generated from construction/remediation projects, as
well as for waste received from field return activities. Processes transferred
to the Kansas City Plant as the result of nonnuclear consolidation will
increase the volume of activities that generate sanitary, hazardous,
lowlevel, and low-level mixed waste. The most significant generation at
Kansas City is the hazardous waste resulting from the Office of Defense
Programs machining, plating, and etching processes. The Department will
ultimately manage any low-level mixed waste generated from these activities as
low-level waste after elementary neutralization.
WASTE MANAGEMENT MAP
The Environmental Protection Agency Region VII and Missouri Department of
Natural Resources are the federal and state agencies regulating the Kansas City
Plant. The plant has prepared and submitted a Resource Conservation and
Recovery Act Part B permit application and is currently operating under interim
status. The plant continues to operate in compliance with federal, state, and
local regulations.
Since FY 1994, the plant has aggressively pursued a plan to eliminate all mixed
waste in storage. To this end, the plant has used a chemical process to
segregate the radioactive and hazardous components from electronic assemblies.
This eliminated two mixed waste streams. In 1994, the plant established a
vendor return program for smoke detectors, thereby preventing the generation of
mixed waste containing transuranic radionuclides. These approaches will
continue to be applied in an effort to reduce the potential for creating mixed
waste.
The Department does not anticipate future generation of mixed waste. Therefore,
a Site Treatment Plan will not be required. However, mixed waste will be
generated from operations that will be integrated at this site from nonnuclear
reconfiguration activities beginning in FY 1998. Waste from these activities
will ultimately be managed as low-level waste after elementary neutralization.
In lieu of a Site Treatment Plan, the Mixed Waste Contingency Plan has been
submitted to and approved by the State of Missouri.
Technical support costs for development of the Mixed Waste Contingency Plan and
compliance with storage requirements are identified in low-level waste storage.
Costs for the chemical segregation process and offsite transportation and
disposal are identified in low-level waste disposal. No low-level radioactive
waste is treated onsite.
Low-Level Waste
GENERATION AND HANDLING
Small quantities of low-level radioactive waste are generated from the
disassembly and testing of irradiated components, the scheduled replacements of
exit signs containing small amounts of tritium for illumination, the
replacement or excess of X-ray sources. These sources are all from Defense
Programs activities.
STORAGE
The Kansas City Plant low-level waste storage area is located in the Waste and
Excess Property Management Department. The 23-square meter (250-square foot)
area is protected from inclement weather, unauthorized entry, and has secondary
containment. The maximum storage capacity is 96 0.2-cubic meter (55-gallon)
drums.
DISPOSAL
Low-level waste is shipped to the Nevada Test Site for disposal. Shipments are
made infrequently and only when a sizable quantity of waste accumulates.
Shipments were made in 1985 and 1995. At present, approximately 0.5 cubic
meters (0.65 cubic yards) of low-level waste is in storage. This report assumes
that approximately 30 cubic meters (39 cubic yards) will be transported to the
Nevada Test Site between now and FY 2070.
Hazardous Waste
GENERATION AND HANDLING
Principal hazardous substances include acids, alkalines, ignitable waste,
miscellaneous toxic waste, nonfriable asbestos, oil, polychlorinated biphenyls,
solvents, wastewater treatment sludge, and infectious waste from the employee
medical department. Waste from manufacturing processes is certified by process
prior to acceptance into the Waste Management program.
Numerous laboratories and small departments within the plant also generate
miscellaneous hazardous waste in small amounts. These items are combined, when
practical, for controlled disposal. Waste contaminated with polychlorinated
biphenyls and asbestos is also routinely generated in the decommissioning of
inactive facilities. Polychlorinated biphenyl waste is shipped offsite for
disposal within 30 days.
Several initiatives are currently being developed to reduce hazardous waste
volumes. A carbon dioxide separation system is being developed that will treat
oil- and solvent-contaminated waste. The Department plans to use fuel-blending
to recycle oils and solvents. Coolant recycling equipment has also been
procured to reuse and recycle coolants. The Department is also implementing a
process to treat acid/chromate and alkaline/cyanide solid debris streams
generated during plating operations. The Department expects this process to
reduce the amount of hazardous waste by 2.25 metric tons (2.5 tons).
In 1994, the hazardous waste generated at the plant totaled 850 cubic meters
(1,100 cubic yards), most of which, 510 cubic meters (670 cubic yards), was
waste regulated by the Toxic Substances Control Act, and 256 cubic meters (335
cubic yards) was waste regulated by the Resource Conservation and Recovery Act.
The remaining waste was state-regulated waste. Hazardous waste generation is
expected to decline approximately five percent per year. Waste generated from
construction and environmental restoration activities is approximately 450
metric tons (500 tons) and is not expected to increase. The Kansas City Plant
expects to generate approximately 475 cubic meters (620 cubic yards) of
hazardous waste from production operations in FY 1995 and FY 1996. Legacy-
classified waste was sanitized onsite and shipped for disposal in FY 1995,
eliminating the inventory of classified waste.
TREATMENT
The Kansas City Plant does not treat any hazardous waste regulated by the
Resource Conservation and Recovery Act. The only treatment that is performed at
the site is the pre-treatment of wastewater from manufacturing under a City of
Kansas City, Missouri Clean Water Act pre-treatment permit. The pre-treatment
is performed at the industrial wastewater pre-treatment facility, which
destroys or removes hazardous chemicals like cyanide and chromium. The
pre-treatment facility also de-waters sludge, reducing its volume. Resource
recovery and recycling are performed at locations throughout the plant, with
the wastewater piped to the pre-treatment facility.
Future waste volumes, pre-treated by the Industrial Wastewater Pre-Treatment
Facility and generated from production operations, are anticipated to decrease
then remain constant as the result of downsizing, even though the mission at
the Kansas City Plant is assumed to continue indefinitely.
STORAGE
The Department stores hazardous waste at a tank farm and at various locations
in the plant. The tank farm consists of five bulk storage tanks: 23 cubic
meters (6,000 gallons) of acids, 23 cubic meters (6,000 gallons) of alkalines,
60 cubic meters (two 8,000-gallon tanks) of solvents, and 30 cubic meters
(8,000 gallons) of oil. Because of recent Department of Energy initiatives to
downsize the nuclear weapons complex, projects are being identified at the
Kansas City Plant to consolidate waste storage into vacated buildings.
The Kansas City Plant is currently under interim status as a treatment,
storage, and disposal facility. According to the permit, waste can be stored
for up to one year on specified waste management storage lots.
DISPOSAL
No hazardous waste is disposed of onsite. Disposal preparations include
packaging, repackaging, consolidating, and manifesting hazardous waste in
compliance with the Resource Conservation and Recovery Act and Department of
Transportation regulations. Hazardous waste is transported for offsite
treatment and disposal to approved commercial treatment and disposal
facilities. Shipments are made when a sizable quantity of waste accumulates.
This report assumes that 46,675 cubic meters (61,144 cubic yards) will be
disposed of at offsite commercial facilities between now and FY 2070.
Direct Program Management/Support
Program management and support functions cut across all waste management
activities. Costs are included for personnel to develop and validate cost
estimates; manage project cost, schedule, and technical baselines; formulate
and execute budget requirements; develop performance reports; ensure regulatory
compliance; and support audits, reviews, and validations. Each cost table shows
the program management cost associated with that program.
An Agreement-in-Principle has been reached with the Missouri Department of
Natural Resources for independent oversight of environmental and emergency
management programs. In FY 1996, this oversight will include state reviews of
the air, surface water, emergency management, and waste management programs.
Annual costs to support this agreement are approximately $200,000.
Waste Management Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
|
| Low-Level Waste
|
|
|
|
|
|
|
|
|
| Storage and Handling
|
73
|
66
|
66
|
66
|
66
|
66
|
66
|
|
| Disposal
|
100
|
115
|
115
|
115
|
115
|
115
|
115
|
|
| Hazardous Waste
|
|
|
|
|
|
|
|
|
| Treatment
|
1,283
|
1,260
|
1,260
|
1,260
|
1,260
|
1,260
|
1,260
|
|
| Storage and Handling
|
1,412
|
1,233
|
1,233
|
1,233
|
1,233
|
1,233
|
1,233
|
|
| Disposal
|
1,701
|
743
|
743
|
743
|
743
|
743
|
743
|
|
| Direct Program Management/Support
|
2,746
|
2,042
|
2,042
|
2,042
|
2,042
|
2,042
|
2,042
|
|
| Total
|
7,316
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
|
| |
|
| Low-Level Waste
|
|
|
|
|
|
|
|
|
| Storage and Handling
|
66
|
66
|
66
|
66
|
66
|
66
|
66
|
|
| Disposal
|
115
|
115
|
115
|
115
|
115
|
115
|
115
|
|
| Hazardous Waste
|
|
|
|
|
|
|
|
|
| Treatment
|
1,260
|
1,260
|
1,260
|
1,260
|
1,260
|
1,260
|
1,260
|
|
| Storage and Handling
|
1,233
|
1,233
|
1,233
|
1,233
|
1,233
|
1,233
|
1,233
|
|
| Disposal
|
743
|
743
|
743
|
743
|
743
|
743
|
743
|
|
| Direct Program Management/Support
|
2,042
|
2,042
|
2,042
|
2,042
|
2,042
|
2,042
|
2,042
|
|
| Total
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
|
| |
2075
|
2080
|
2085
|
2090
|
2095
|
2100
|
| Low-Level Waste
|
|
|
|
|
|
|
|
|
| Storage and Handling
|
66
|
|
|
|
|
|
|
4,985
|
| Disposal
|
115
|
|
|
|
|
|
|
8,552
|
| Hazardous Waste
|
|
|
|
|
|
|
|
|
| Treatment
|
1,260
|
|
|
|
|
|
|
94,616
|
| Storage and Handling
|
1,233
|
|
|
|
|
|
|
93,369
|
| Disposal
|
743
|
|
|
|
|
|
|
60,517
|
| Direct Program Management/Support
|
2,042
|
|
|
|
|
|
|
156,671
|
| Total
|
5,459
|
|
|
|
|
|
|
418,710
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
This report anticipates cost savings in program support activities through the
integration of the individual Environmental Restoration and Waste Management
programs into a single Environmental Management program Support Team. The
result should be reduced duplication of effort and will require fewer
employees.
DESCRIPTION OF PERSONNEL
Current Composition
There are federal and management and operating contractor employees funded by
the Environmental Management program at the Kansas City Plant. Approximately 68
of the management and operating contractor employees are directly funded by the
Environmental Management program. The remaining employees are funded indirectly
through a burden rate applied to environmental management activities. The
directly funded employees consist of managers, administrative personnel,
engineers, scientists, administrators and other professionals, technicians, and
laborers. The table below presents the federal and contractor work force by
labor category.
Full-Time Equivalents Composition Table *
* The Projections for Full-Time Equivalent employees are based on FY 1996
planning baselines (see Reader's Guide).
Site Management Structure
The Department of Energy owns the Kansas City Plant. Allied Signal operates the
facility through a cost-plus-award-fee management and operating contract which
expires in March 2000. The management and operating contract is structured to
provide financial incentives for waste volume reduction and productivity
savings. Some work is subcontracted to private companies or other federal
contractors through Integrated Contractor Orders. These contracts are usually
annual contracts or contracts for a specific portion of a project that may span
several years. Commercial contracts are competitively bid. Two of the primary
subcontracts for Environmental Management are for support of environmental
restoration assessment and ground water-related activities and for support of
the Industrial Wastewater Pre-treatment Facility.
| CONTRACTING OPPORTUNITIES
If you would like more information about performing work for the Department of
Energy's Environmental Management program at this site, please contact:
|
Major Procurements
William Meyers
Director
Contracts and Procurement Division
United States Department of Energy
Albuquerque Operations Office
P.O. Box 5400
Albuquerque, NM 87185-5400
p: (505) 845-5777
f: (505) 845-4210
|
Small Business Procurements
Greg Gonzales
Contracts and Procurement Division
United States Department of Energy
Albuquerque Operations Office
P.O. Box 5400
Albuquerque, NM 87185-5400
p: (505) 845-6182
f: (505) 845-4210
|
Future Full-Time Equivalent Needs
The number of Environmental Management Full-Time Equivalents at the Kansas City
Plant has peaked. The size of the Environmental Restoration staff will steadily
decline until work is complete in FY 2000.
FUNDING ESTIMATE
The following tables present estimated funding information for the Kansas City
Plant.
Defense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
|
| Environmental Restoration
|
4,968
|
648
|
|
|
|
|
|
|
| Waste Management
|
6,610
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
|
| Total
|
11,578
|
6,107
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
|
| |
|
| Environmental Restoration
|
|
|
|
|
|
|
|
|
| Waste Management
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
|
| Total
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
5,459
|
|
| |
2075
|
2080
|
2085
|
2090
|
2095
|
2100
|
| Environmental Restoration
|
|
|
|
|
|
|
|
28,081
|
| Waste Management
|
5,459
|
|
|
|
|
|
|
415,181
|
| Total
|
5,459
|
|
|
|
|
|
|
443,262
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2005
|
2010
|
2015
|
2020
|
2025
|
2030
|
| Waste Management
|
706
|
|
|
|
|
|
|
3,529
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
| WASTE MINIMIZATION/POLLUTION PREVENTION
An integral part of the Waste Management program is waste minimization and
pollution prevention. The focus of these efforts is to encourage methods to
avoid generating radioactive, hazardous, nonhazardous, and sanitary waste by
controlling procurement, using substitute materials, changing processes,
recycling unused chemicals and byproducts, and pre-treating potential waste
streams to reduce volumes, radioactive content, or toxicity. Solvent usage has
been reduced by 98 percent since 1988. Recycling streams have increased from
four to 20 since 1991. The Kansas City Plant has been named the Department of
Energy Center of Excellence for Pollution Prevention Opportunity Assessment
Training.
|
COMPARISON WITH PREVIOUS ESTIMATE
Significant changes have been incorporated into the cost estimates from the FY
1995 Baseline Environmental Management Report. Environmental Restoration costs
have decreased by 71 percent, and Waste Management costs have increased by 90
percent. The overall result for the site is an increase in estimated life-cycle
cost of approximately 4 percent. Also, note that program management costs have
been integrated into relevant activity costs and are not a separate category.
See the Comparison Table on the following page for additional life-cycle cost
information.
Comparison Table
|
Thousands of Dollars
|
|
| Nuclear Mat. & Fac. Stab.
|
-
|
-
|
-
|
-
|
-
|
| Environmental Restoration
|
99,822
|
3,478
|
28,081
|
68,263
|
71
|
| Waste Management |
226,898
|
6,116 |
418,710
|
197,928 |
90
|
| Landlord |
-
|
- |
-
|
-
|
-
|
| Program Management 2
|
113,377
|
2,225
|
-
|
-
|
-
|
| Site Total |
440,097
|
11,818 |
446,791
|
18,512 |
4
|
1 The FY 1995 life-cycle and annual costs are provided
to determine the corrected FY 1995 cost.
2 Program Management was reported in an independent cost table last year, but
is reported as a line item in the relevant program (Nuclear Material and
Facility Stabilization, Environmental Restoration, and Waste Management)
activity cost estimate tables for the FY 1996 Baseline Report.
|
Last year's report assumed all contamination would be excavated and disposed of
in certified offsite landfills, regardless of risk. The FY 1996 report contains
risk-based assumptions. Cleanup activities, like other construction projects,
have inherent safety risks. In evaluating cleanup alternatives for this report,
the risk of exposure at each site was also considered. At minimal risk sites,
the assumption was made that remedial action will not be required and exposure
risks could be minimized through procedural controls. As a result, the waste
volume projections and the costs associated with remedial action have been
significantly reduced.
Also, assumptions concerning the duration of the Waste Management program have
changed. Last year's Baseline Report assumed activities to cease in FY 2030;
this year they are assumed to end in FY 2070. Waste Management program cost
estimates also include a line item to replace industrial waste piping that was
not in last year's report. In FY 1998, lowlevel waste generation rates
increased significantly from previous estimates because nonnuclear
consolidation by the Department has increased the number of activities at the
Kansas City Plant that have the potential to generate low-level waste.
|
 |