|
Home
BEMR
Contents
U.S.
Map
The Hallam Nuclear Power Facility is located on a small portion of the
260-hectare (640-acre) site of the Sheldon Power Station in Lancaster County,
Nebraska, approximately 30 kilometers (19 miles) south of Lincoln, Nebraska.
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
|
|
|
|
| Environmental Restoration
|
22
|
21
|
24
|
25
|
26
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
0 |
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
0
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
|
|
|
| Environmental Restoration
|
22
|
23
|
23
|
7
|
7 |
7
|
7 |
|
|
|
|
| Environmental Restoration
|
7 |
7
|
7 |
7
|
7 |
7
|
7 |
|
|
|
2095
|
2100
|
| Environmental Restoration
|
7 |
7
|
7 |
7
|
7 |
|
|
901
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The Hallam Nuclear Power Facility was a 240-megawatt (thermal) sodium-cooled
graphite-moderated nuclear reactor built and operated as a demonstration
project by the Atomic Energy Commission between 1962 and 1964. In 1965, the
Atomic Energy Commission terminated its agreement with the Consumers Public
Power District for operation of the facility, and in 1967, the Nebraska Public
Power District (formerly the Consumers Public Power District) was authorized to
decommission and dismantle the facility. Decommissioning and dismantlement
activities at the facility concluded in 1969, and the Atomic Energy Commission
retired the facility in 1971. As a successor agency to the Atomic Energy
Commission, the Department of Energy currently maintains responsibility for the
remaining buildings at the Hallam Nuclear Power Facility. However, the Nebraska
Public Power District owns the facility property and is responsible for all
landlord costs.
SITE MAP
The Hallam Nuclear Power Facility has no current mission. Activities at the
site are limited to semi-annual surveillance and monitoring, which is expected
to end in FY 2090.
FUTURE USE
This estimate assumes that the Hallam Nuclear Facility will be transferred to
the Nebraska Public Power District in FY 2005. Because of known contaminated
buried materials, this estimate assumes that future use of this facility will
be limited to Controlled Access.
ENVIRONMENTAL RESTORATION
Currently, there is no known environmental contamination at the Hallam Nuclear
Power Facility. All potential contaminants at the site are contained within the
entombment structure in Area 1 (reactor vessel and vessel containment
structures), Area 2 (fuel storage pit 3 thimbles), or Area 3 (moderator element
storage cells). These contaminants include nickel-63, cobalt-60, iron-55,
manganese-54, samarium-151, cesium-137, strontium-90, and tritium. The
contaminants within the structure consist of activation products in the
stainless steel reactor vessel and its internals. Lesser amounts of activation
products are dispersed in the carbon steel thermal shield and guard vessel
surrounding the reactor vessel and in the compartment liner itself. See the
Site Map for the location of Environmental Restoration program activities.
At the time the reactor was decommissioned and dismantled, the core and most of
the radioactive materials were removed from the site. All bulk sodium was also
removed from the site, and residual sodium was reacted with steam to form
sodium hydroxide, removing the potential for hydrogen formation at a later date
should water leak into the facility. The reactor vessel and surrounding guard
vessel, with associated double-walled piping, and most of the reactor vessel
internals, remain within the compartment.
Fuel Storage Pit 3 contains a number of stainless steel thimbles formerly used
to store spent fuel elements. The storage pool was drained, and the thimbles
now contain process tubes, control rod tubes, dummy elements, and a spent
neutron source. To prevent leaks, closures and dust covers for each thimble
have been welded in place and the interspace has been filled with expanding
concrete.
Storage Area 3 consists of 12 storage cells containing three canistered
moderator elements that experienced cladding failures during reactor operation.
A number of parts, such as pumps, valves, and segments of piping are stored in
these cells. The moderator cells were sealed by welding the plug casings to the
cell liners and filling the space above the plugs with expanding concrete.
The basement level of the facility contained radioactive waste disposal
equipment, all of which has either been removed or decontaminated, as
appropriate. All reactor compartments have been sealed, and the surface of the
below-grade concrete structure was covered with sand, a waterproof polyvinyl
membrane, and a covering of earth. The cover was sloped for proper drainage,
and drain tile was installed at the periphery. Above-grade structures have been
weatherproofed by a layer of polyvinyl and a protective cover of concrete.
Currently, the Department of Energy is conducting semi-annual surveillance and
monitoring as part of an agreement with the Nebraska Department of Health to
monitor the release of radioactivity and monitor ground water. There are no
current or planned activities related to assessment, remedial action,
stabilization, or additional decommissioning at the Hallam Nuclear Power
Facility.
Long-Term Surveillance and Monitoring
Although the potential for transport of radioactive materials stored in the
isolation structure to the environment is minimal, the Department's Chicago
Operations Office has agreed with the Nebraska Department of Health to conduct
semi-annual environmental radiological surveillance and monitoring to verify
that no radioactivity is being released to the environment. The basis for
radiological surveillance and monitoring was previously established while a
contract termination agreement was in effect that involved the Nebraska Public
Power District and the Atomic Energy Commission.
In addition, the Chicago Operations Office and the Nebraska Department of
Health agreed to install a shallow ground-water monitoring system as part of
the long-term environmental surveillance and monitoring program. Installation
of this system was completed in FY 1995 and this report assumes monitoring will
continue until FY 2090.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
|
|
|
| Long-Term Surveil. and Monitoring
|
22
|
23
|
23
|
7
|
7
|
7
|
7
|
|
|
|
|
| Long-Term Surveil. and Monitoring
|
7
|
7
|
7
|
7
|
7
|
7
|
7
|
|
|
|
2095
|
2100
|
| Long-Term Surveil. and Monitoring
|
7
|
7
|
7
|
7
|
7
|
|
|
901
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Direct Program Management/Support
Program management and support costs for the Hallam Nuclear Power Facility are
relatively small and revolve around the planning and implementation activities
necessary to conduct the biannual surveillance and maintenance activities, and
data review and analysis. Chicago Operations Office personnel conduct these
activities on a level-of-effort basis. Geoscientists are monitoring wells
around the entombed reactor for ground-water conditions and radiological
contaminants. The monitoring is required to occur for one month every year. All
program management and support costs are included within the estimates for
Long-Term Surveillance and Monitoring.
| STAKEHOLDER INTERACTIONS
No public participation activities were conducted for the Baseline Report
concerning the Hallam Nuclear Power Facility. If you would like more
information about the report or have questions about the results for this site,
please contact:
|
Public Participation
Mary Jo Acke
(708) 252-8796 maryjo.acke@ch.doe.gov
|
Technical Liaison
Michael Ferrigan
(708) 252-2570 michael.ferrigan@ch.doe.gov
|
Public Affairs
Brian Quirke
(708) 252-2423
brian.quirke@ch.doe gov
|
DESCRIPTION OF PERSONNEL
Because of the limited personnel needs, personnel estimates for the Hallam
Nuclear Power Facility are included within the personnel estimates in the
Chicago Operations Office Site Summary.
| CONTRACTING OPPORTUNITIES
If you would like more information about performing work for the Department of
Energy's Environmental Management program at this site, please contact:
|
Major Procurements
John Greenwood
Acquisition and Assistance Group Manager
United States Department of Energy
Chicago Operations Office
9800 South Cass Avenue
Argonne,IL 60439
p: (708) 252-1912
f: (708) 252-5045
|
Small Business Procurements
Larry Thompson
United States Department of Energy
Chicago Operations Office
9800 South Cass Avenue
Argonne, IL 60439
(708) 252-2711
(708) 252-5045
|
FUNDING ESTIMATE
The following table presents estimated funding information for the Hallam
Nuclear Power Facility.
Defense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
|
|
|
| Environmental Restoration
|
22
|
23
|
23
|
7
|
7
|
7
|
7
|
|
|
|
|
| Environmental Restoration
|
7
|
7
|
7
|
7
|
7
|
7
|
7
|
|
|
|
2095
|
2100
|
| Environmental Restoration
|
7
|
7
|
7
|
7
|
7
|
|
|
901
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
COMPARISON WITH PREVIOUS ESTIMATE
The costs for the Hallam Nuclear Power Facility in the FY 1996 Baseline
Environmental Management Report reflect no major changes in scope or technical
approach from information presented in the FY 1995 report. However, the
duration of long-term surveillance and monitoring requirements in the FY 1996
estimate reflects costs through FY 2090. The FY 1995 estimate included
activities only through FY 2030. This 60-year increase accounts for most of the
approximately 275 percent increase in the life-cycle cost. See the comparison
table on the following page for additional life-cycle cost information.
Comparison Table
|
Thousands of Dollars
|
|
| Nuclear Mat. & Fac. Stab.
|
- |
-
|
- |
-
|
- |
| Environmental Restoration
|
261 |
21
|
901 |
661
|
275 |
| Waste Management |
-
|
- |
-
|
- |
-
|
| Landlord |
-
|
- |
-
|
- |
-
|
| Program Management 2
|
- |
-
|
- |
-
|
- |
| Site Total |
261
|
21 |
901
|
661 |
275
|
1 The FY 1995 life-cycle and annual costs are provided
to determine the corrected FY 1995 cost.
2 Program Management was reported in an independent cost table last year, but
is reported as a line item in the relevant program (Nuclear Material and
Facility Stabilization, Environmental Restoration, and Waste Management)
activity cost estimate tables for the FY 1996 Baseline Report.
|
|
 |