|
Home
BEMR
Contents
U.S.
Map
The Falls City former processing site is one of 24 uranium mill processing sites
designated by the Uranium Mill Tailings Radiation Control Act for remediation
by the Department of Energy. During the 1960s, private firms processed most of
the uranium ore mined in the United States for the Atomic Energy Commission, a
predecessor of the Department of Energy. Congress passed the Act in 1978 in
response to public concern regarding potential health hazards from long-term
exposure to uranium mill tailings. It authorized the Department of Energy to
stabilize, dispose of, and control uranium mill tailings and other contaminated
material at 24 uranium mill processing sites and vicinity properties. For a
general discussion of the UMTRA Program, see the overview presented in the New
Mexico section of this report.
The cost estimate model used for this report provides costs for each of the
UMTRA sites. All costs for waste management activities, program management, and
relevant landlord activities attributable to the Department are provided for
within the scope of environmental restoration. There are no Uranium Mill
Tailings Radiation Control Act sites with either current or planned nuclear
material and facility stabilization activity needs. Funding for all sites is
100 percent nondefense.
Pursuant to the Uranium Mill Tailings Radiation Control Act, the Department of
Energy entered into a Cooperative Agreement in 1987 with the State of Texas.
The agreement outlines the roles and responsibilities of each party. It also
delineates the cost sharing arrangement, which makes the Department of Energy
responsible for 100 percent of the assessment costs and 90 percent of the
remediation costs, and the State responsible for the remaining 10 percent of
the remediation costs. In addition, the Department of Energy is responsible for
paying 90 percent of the State*s ten percent, and the State is
responsible for the remaining 10 percent of these costs (one percent of the
total remediation costs). The Nuclear Regulatory Commission concurred on the
original agreement and must concur on all major modifications.
FALLS CITY, TEXAS (UMTRA SITE)
The former Falls City mill and tailings site is located in Karnes County, 74
kilometers (46 miles) southeast of San Antonio and approximately 13 kilometers
(eight miles) southwest of Falls City, Texas. It covers 240 hectares (593
acres) on two parcels.
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
| |
|
|
|
| Environmental Restoration
|
1,670
|
546
|
553
|
1,058
|
1,397
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
1,654 |
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
458
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
986
|
120
|
|
|
|
|
|
5,529
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The mission of the Falls City mill site was to provide uranium for the United
States Government. The source of contamination was the residual tailings
remaining after the uranium was extracted during the milling process. The
original mill was built and operated by Susquehanna-Western, Inc. of San
Antonio, Texas from 1961 to 1973. Between 1978 and 1982, Solution Engineering,
Inc. conducted secondary solution mining from four tailings piles. In 1982, all
the piles were covered with about one and one-half feet of soil, and
revegetated.
SITE MAP
The Environmental Management Program is responsible for cleaning up surface-
and ground-water contamination at the UMTRA sites. The Uranium Mill Tailings
Radiation Control Act designated the residual radioactive material found at
this site for cleanup and stabilization. The Act directed the Environmental
Protection Agency to promulgate standards (Code of Federal Regulations, Title
40, Part 192) and the Department of Energy to perform the cleanup. It also
assigned the Nuclear Regulatory Commission to oversee and certify the cleanup,
and license the completed disposal cell.
FUTURE USE
Upon Nuclear Regulatory Commission site certification, the State will transfer
the deed to the disposal site to the Federal Government under the custody of
the Department of Energy. It will be monitored and maintained in accordance
with the Long-Term Surveillance Plan approved by the Nuclear Regulatory
Commission. Public access to the disposal site will be controlled. The State of
Texas will retain a larger tract of land adjacent to the disposal site. The
site will be transferred from the Department of Energy to the State of Texas
pending Nuclear Regulatory Commission certification under the UMTRA Surface
Project. In the future, the State of Texas will offer this site for private
sale with some controlled access conditions.
ENVIRONMENTAL RESTORATION
Surface remedial action has been completed and the source of contamination has
been stabilized. However, residual milling-related contaminated ground water
remains.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2010
|
2015
|
2020
|
2025
|
2030
|
| UMTRA Surface
|
|
|
|
|
|
|
|
|
| Assessment
|
23
|
|
|
|
|
|
|
114
|
| Remedial Action
|
183
|
|
|
|
|
|
|
913
|
| UMTRA Ground water
|
|
|
|
|
|
|
|
|
| Assessment
|
182
|
34
|
|
|
|
|
|
1,084
|
| Remedial Action
|
42
|
|
|
|
|
|
|
210
|
| Direct Program Management/Support
|
556
|
85
|
|
|
|
|
|
3,208
|
| Total |
986
|
120
|
|
|
|
|
|
5,529
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Surface Project
Remedial action began under the UMTRA Surface Project in 1992 and was completed
in July 1994. The cleanup involved consolidation of seven tailings piles of
residual radioactive material into a single stabilized disposal cell.
Approximately 4.6 million cubic meters (6 million cubic yards) of contaminated
material, including 13 vicinity properties, were remediated. The site is
expected to be certified by the Nuclear Regulatory Commission in August 1996,
and the disposal cell licensed by the Nuclear Regulatory Commission in January
1997.
Major Surface Project Milestones
| Nuclear Regulatory Commission Issues General
License
|
1997
|
|
Transfer to Grand Junction Projects Office's Long-Term Surveillance and
Maintenance Program
|
1997
|
The Falls City, Texas Remedial Action Plan, concurred upon by the Nuclear
Regulatory Commission in November 1992, outlines the contaminant distribution
and necessary remediation. The UMTRA Surface Project will conduct surveillance
and maintenance of the disposal cell after completion of remedial action and
prior to its transfer to the Grand Junction Projects Office's Long-Term
Surveillance and Maintenance program in FY 1997.
Ground-Water Compliance Project
The Department is developing a Programmatic Environmental Impact Statement
pertaining to all 24 UMTRA sites. For a discussion of the Programmatic
Environmental Impact Statement, see the UMTRA program narrative in the New
Mexico section of this report. Site-specific National Environmental Policy Act
documentation will be developed to propose an appropriate ground-water
compliance strategy and reasonable alternatives for the Falls City site once
the Programmatic Environmental Impact Statement is completed.
This report assumes demonstrated compliance with additional characterization
and application of supplemental standards. For all types of ground-water
compliance strategies, once the Nuclear Regulatory Commission determines the
site to be in compliance with Subpart B of the Environmental Protection Agency
Standards and the site is certified, no additional long-term surveillance or
monitoring will be conducted.
The total volume of contaminated ground water has not been assessed, but the
contaminant plume extends offsite. The ground-water contaminants of potential
concern are cadmium, cobalt, fluoride, iron, nickel, sulfate, and uranium.
The following milestone dates have been established for planning purposes.
Major Ground-Water Compliance Project Milestones
| Baseline Risk Assessment
|
1994
|
|
Site Observational Work Plan
|
1998
|
|
Publish Environmental Assessment/Finding of No Significant Impact
|
1999
|
|
Publish Remedial Action Plan
|
2000
|
|
Licensing
|
2001
|
Ground and surface water have been monitored at the Falls City site since 1986.
Ground-water sampling is conducted biannually. This sampling will allow
continued evaluation of trends in ground-water flow conditions, and it will
allow adequate characterization of hydrogeological conditions and ground-water
quality.
A hydrological, geochemical, and statistical analysis of ground-water quality
data for the period of 1989 through 1993 indicates widespread tailings-related
contamination in the Deweesville/Conquista aquifer and significantly less
contamination in the Dilworth aquifer.
In 1994, ground-water monitoring consisted of sampling 17 wells screened in the
upper Deweesville/Conquista aquifer and two wells screened in the underlying
Dilworth aquifer. Ground-water sampling in the Dilworth aquifer involved
monitoring background and downgradient ground-water quality conditions. Eight
local livestock wells were also sampled. The sampled wells ranged from
approximately 9 to 134 meters (30 to 440 feet) deep and are situated
upgradient, crossgradient, and downgradient of the site.
Ground-water geochemistry at the Falls City site is complex because no single
ground-water quality parameter can quantify the extent of ground-water
contamination. Therefore, several indicator parameters related to uranium
processing activities were selected for analysis: aluminum, calcium, pH,
sulfate, and uranium.
The depth and location of background water quality varies greatly because it
occurs within the uranium ore body. The background ground water is classified
as limited use, based on high average uranium concentrations and activities of
net gross alpha and radium that render the water untreatable by methods
reasonably employed by public water systems in the region.
Direct Program Management/Support
Program management supports management efforts for the National Environmental
Policy Act process, site characterization and licensing, public
information/participation, applicable state and federal regulator costs,
quality assurance audits, program and management support for the technical
assistance contractor, special studies, document control, technical assistance
contractor site and technical management, cost and schedule controls, planning
and preparation of the federal budget, and the Environmental Management
Progress Tracking System.
FUNDING ESTIMATE
The following table presents estimated funding information for the Falls City
site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
986
|
120
|
|
|
|
|
|
5,529
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|