|
Home
BEMR
Contents
U.S.
Map
The currently active New Jersey sites within the Formerly Utilized Sites
Remedial Action Program (FUSRAP) are DuPont & Company, Maywood, Middlesex
Sampling Plant, New Brunswick, and Wayne. Completed FUSRAP sites in New Jersey
are Kellex/Pierpont and the Middlesex Municipal Landfill. For a brief
discussion of these sites and the remedial actions undertaken at them, refer to
the FUSRAP narrative in the Tennessee section of this report. FUSRAP was
established in 1974 under the provisions of the Atomic Energy Act to identify,
investigate, and clean up or otherwise control previously decontaminated
Manhattan Engineer District and Atomic Energy Commission sites where residual
radioactive contamination exceeds current guidelines, and other sites assigned
to the U.S. Department of Energy by Congress.
The New Jersey FUSRAP sites do not share any common elements other than
Department of Energy ownership of the Maywood Interim Storage site, the Wayne
Interim Storage site, the Middlesex Sampling Plant, and the New Brunswick site.
The Maywood and Wayne sites have separate Federal Facilities Agreements, to
which the Department of Energy and the Environmental Protection Agency are
signatories. The Department of Energy is using the Comprehensive Environmental
Response, Compensation, and Liability Act process to identify the appropriate
remedy for each of the sites. Although FUSRAP is striving for consistency in
the decisionmaking process for all sites, each site's unique conditions,
characteristics, and process of sharing information with stakeholders require
sitespecific environmental analysis.
FUSRAP encompasses 46 sites in 14 states and is funded through the Oak Ridge
Operations Office. For a general discussion of FUSRAP and associated costs, see
the overview of the program presented in the Tennessee section of this report.
All costs for waste management activities, program management, and relevant
landlord activities attributable to the Department of Energy are provided for
within the scope of environmental restoration. No FUSRAP sites have either
current or planned nuclear material and facility stabilization activity needs.
Funding for all sites is 100 percent nondefense.
DuPONT & COMPANY
The E.I. du Pont de Nemours & Company (DuPont) site is located in the
Townships of Pennsville and Carneys Point on the southeastern shore of the
Delaware River, adjacent to the residential community of Deepwater, New Jersey.
The site is bordered on the north by another DuPont property referred to as the
Carneys Works, on the east by U.S. Route 130, on the south by Salem
Canal, and on the west by the Delaware River, across from Wilmington, Delaware
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
|
|
|
|
|
| Environmental Restoration
|
|
2
|
1 |
1
|
1 |
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
0 |
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
2
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
|
|
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
1 |
1,511
|
|
|
|
|
|
7,560
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The DuPont Chambers Works plant is an active chemical plant that manufactures
primarily organic chemicals. In the 1940s, DuPont conducted research involving
uranium hexafluoride, first for the U.S. Office of Scientific Research and
Development and later under contract to the Manhattan Engineer District and the
Atomic Energy Commission. Operations involving uranium began in 1942; research
for the Atomic Energy Commission continued until late 1947.
DuPont conducted activities for the Manhattan Engineer District and Atomic
Energy Commission in six separate areas onsite: Building 845, the central
drainage ditch, the F Corral parking area (former location of
Building 708), the Building J26 area, the east burial area, and
Lagoon A. Manhattan Engineer District activities were conducted in three
buildings, but only Building 845 remains; it is now a warehouse for
miscellaneous storage.
In 1945, part of Building 708 was demolished and removed from the site.
The remainder of the building was removed in 1953, along with several feet of
underlying soil, all of which was disposed of in the Lagoon A area.
In 1948 and 1949, the Atomic Energy Commission conducted radiological surveys
and decontamination activities at the site. Decontamination included
sandblasting, vacuuming, and washing building surfaces. The Atomic Energy
Commission released the buildings to DuPont in 1949, based on existing
criteria. After the site was released, DuPont demolished Building J16
and disposed of it in the Lagoon A area. A new building, J26, now stands
in its place.
The east burial area contains some equipment that was used in building
demolition, various chemical waste, and small amounts of State-approved
low-level radioactive material.
The central drainage ditch is located approximately where it was in the 1940s.
The primary purpose of the ditch is to carry residual wastes from chemical
operations. Residual wastes from Building 845 were discharged into a
wooden trough east of the building. The trough dumped the waste into the ditch
approximately 45 meters (150 feet) north of Building 845. The ditch
flows to the northeast, adjacent to the northwestern corner of
Building 845, and drains into the eastern corner of Lagoon A. The
composite from Lagoon A is then pumped into the onsite water treatment facility
for chemical processing of the waste.
Today, the site is an operating chemical plant, and the Department of Energy
has no onsite presence.
FUTURE USE
The site is expected to continue to be used in an industrial/commercial
capacity as a chemical processing facility.
ENVIRONMENTAL RESTORATION
The Atomic Energy Commission conducted limited restoration at the site during
the 1948 and 1949 decontamination effort. Additional remedial action, as
required for the site to meet current guidelines, will be conducted. Key
regulators for the site include Environmental Protection Agency Region II, the
New Jersey Department of Environmental Protection, and the local health
department.
During future remediation, the Department of Energy will use construction
equipment to excavate contaminated soils. It will restore the areas after
excavation and verification that the cleanup meets guidelines. Further
decontamination of Building 845 through washing, scrubbing, and vacuuming
areas of concern will also be necessary.
The total volume of low-level radioactive waste from the cleanup is estimated
at 6,325 cubic meters (8,270 cubic yards), which, under current plans,
will be consolidated for permanent onsite storage. The Department of Energy
will conduct a maintenance and monitoring program for two years after remedial
action is complete. It is assumed that the property owner will take over these
responsibilities at that time.
Major Environmental Restoration Activity Milestones
Assessment
Remedial Action
|
2003
2004
|
ASSESSMENT
Although the Atomic Energy Commission conducted limited site restoration during
the 1948-1949 decontamination effort, additional remedial work will be required
for the site to meet current guidelines. A radiological survey in 1977 revealed
elevated concentrations of uranium in rubble from the operations building and
in some surface and subsurface soil samples. Alpha and beta-gamma contamination
levels in some areas of Building 845 exceeded present federal guidelines.
However, under current site use, employees working at the site are not exposed
to radiation doses appreciably different from normal background levels. Under
different conditions of use, such as actions involving agitation or abrasion of
dry contaminated surfaces, employees and the public could be exposed to
low-level radiation.
A 1983 survey showed radioactive contamination exceeding current guidelines in
Building 845, the central drainage ditch, the F Corral parking area, and
the east burial area. In soil and water samples, the major contaminant was
uranium238. In some areas, subsurface contamination was detected at depths
greater than 2.7 meters (9 feet). Because of the high water table at the
site, contamination at depths below the saturation zone could not be
quantified. Based on these radiological surveys, the Department of Energy
determined in 1989 that the DuPont site warranted further remedial action.
REMEDIAL ACTION
Although portions of the site were remediated before Department of Energy
involvement, additional remediation is required to ensure compliance with
current guidelines. The scenario used for the Baseline Environmental Management
Report cost estimate assumes excavation of contaminated soils, further
remediation of Building 845, and disposal of waste by consolidation and
capping onsite. The cost estimate assumes a total waste volume of 6,325 cubic
meters (8,270 cubic yards). Remedial action will involve excavating
contaminated material from the exterior areas of the site and decontaminating
and demolishing Building 845. Open areas that are designated to be
excavated will be cleared. Brush and roots removed from each area will be
washed at the site's decontamination area and radiologically surveyed.
Contaminated soil will be excavated to predetermined depths, based on the
radiological survey and chemical characterization data. The excavated area will
be resurveyed to determine whether additional excavation will be necessary to
meet remedial action guidelines.
After excavation is completed, elevations and dimensions of the final cut will
be determined. Deep excavations may require a dewatering well point system or a
well sump. Appropriate water treatment and holding basins will be necessary to
allow excavation of this waste. The Department will fully restore excavated
areas; it will restore paved areas to accommodate vehicle traffic for which
they were originally designed, and it will fill and grade other areas with
clean, compacted soil. The Department will also restore fences and utility
lines to their condition immediately before remedial action or to a condition
acceptable to the property owner.
The Department plans to consolidate all waste for permanent storage onsite. If
this is the final remedy, transportation of waste will not be required. If all
waste and residues collected [estimated at 6,325 cubic meters
(8,285.75 cubic yards)] are consolidated in an onsite engineered waste
containment area, this containment area will be constructed of a clay liner
envelope structure that meets Environmental Protection Agency and Department of
Energy requirements for low-level radioactive waste and for mixed waste, if
present.
The Department of Energy will conduct a maintenance and monitoring program for
two years after remedial action is complete. During that period, the
Department will monitor ground water, air, surface water, and external gamma
radiation in accordance with applicable regulations. This report assumes that
at the end of the two-year period the property owner will take over these
responsibilities.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
|
|
2010
|
2015
|
2020
|
2025
|
2030
|
| FUSRAP - DuPont & Company Site |
|
|
|
|
|
|
|
|
| Assessment
|
1 |
72
|
|
|
|
|
|
367
|
| Remedial Action
|
|
1,439
|
|
|
|
|
|
7,193
|
| Total |
1 |
1,511
|
|
|
|
|
|
7,560
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FUNDING ESTIMATE
The following table presents estimated funding information for the DuPont &
Company site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
|
|
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
1 |
1,511
|
|
|
|
|
|
7,560
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|
 |