|
Home
BEMR
Contents
U.S.
Map
The currently active Ohio sites within the Formerly Utilized Sites Remedial
Action Program (FUSRAP) are B&T Metals, Baker Brothers, Luckey, and
Painesville. FUSRAP was established in 1974 under the provisions of the Atomic
Energy Act to identify, investigate, and clean up or otherwise control
previously decontaminated Manhattan Engineer District and Atomic Energy
Commission sites, as well as other sites that Congress has assigned to the U.S.
Department of Energy, where residual radioactive contamination exceeds current
guidelines.
FUSRAP encompasses 46 sites in 14 states and is funded through the Oak Ridge
Operations Office. For a general discussion of FUSRAP and associated costs, see
the overview of the program presented in the Tennessee section of this report.
The scope of environmental restoration provides for all costs for waste
management activities, program management, and relevant landlord activities
attributable to the Department of Energy. There are no FUSRAP sites with either
current or planned nuclear material and facility stabilization activity needs.
Funding for all sites is 100 percent nondefense.
B&T Metals
The B&T Metals site is located at 425 West Town Street on the
southwestern side of Columbus, Ohio. The site consists of three buildings that
occupy approximately one city block: the main office, a storage building, and
an extrusion building that did not exist at the time of Manhattan Engineer
District activities.
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
|
|
FY 1996 |
1999 |
2000 |
|
|
|
| Environmental Restoration
|
2,850
|
123
|
|
|
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
2,893
|
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
130
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
|
|
2005
|
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
594 |
|
|
|
|
|
|
2,969
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
In February 1943, the DuPont Company, acting as an agent for the Manhattan
Engineer District, contracted B&T Metals to extrude rods from uranium metal
billets. Production-scale extrusion began in March and continued through August
1943. The work for the Manhattan Engineer District was conducted in the
northwestern corner of the main office building. Reportedly, uranium shavings
may have been dumped outside in what is now a parking area west of this
building. Machinery used for processing uranium has been sold or removed, and
there are no records of its final disposition. The source of radioactive
contamination is processed uranium metal from Manhattan Engineer District
operations at the site. The primary contaminant of concern is uranium238.
SITE MAP
The risk to the public from the residual radioactive contamination at the site
is minimal; the contamination is very localized and limited in extent, and
individuals who access the contaminated areas would not receive significant
radiation exposure under current use conditions.
FUTURE USE
After remediation, the site will be released for unrestricted use. This report
assumes that use of the property will be Industrial/Commercial.
ENVIRONMENTAL RESTORATION
The Department of Energy has not conducted any remedial action at this site. A
designation survey conducted in 1990 indicated the presence of uranium238
in outdoor soils. No additional characterization has been performed since the
1990 designation survey. When characterization activities are completed, an
Engineering Evaluation/Cost Analysis describing the preferred method of site
restoration will be developed.
Key regulators for the B&T Metals site include the Ohio Environmental
Protection Agency and the local health department.
Major Environmental Restoration Activity Milestones
| Assessment (Engineering Evaluation/Cost Analysis
with Action Memorandum)
|
1996
|
|
Remedial Action
|
1997
|
ASSESSMENT
A review of past records indicated that part of the facility's extrusion and
machining process involved "blowing out" the heating cylinders on the extrusion
press. As a result, large quantities of uranium-bearing material were blown
into the main office building. Measurements taken in March and April 1943
indicated excessive amounts of airborne metals near the rolling table,
extrusion trough, and furnace. See the Site Map for the location of
contamination.
A radiological survey of interior and exterior portions of the buildings in
1990 confirmed the presence of uranium238 above guidelines in the main
office building (at three locations on the floor, in the drain system beneath
the floor, and on support beams) and in one outdoor area where shavings from
Manhattan Engineer District operations had reportedly been dumped.
Concentrations of radium226 and thorium232 were within acceptable
limits.
REMEDIAL ACTION
The Department of Energy has performed no remedial action at the site. The
scenario used for the Baseline Environmental Management Report cost estimate
assumes building remediation (decontamination of the main office building),
limited soil excavation, transportation via rail car, and disposal at an
existing outofstate commercial disposal facility. The cost estimate
assumes a total waste volume of 1,150 cubic meters (1,500 cubic yards). Current
plans are to complete all characterization and remediation in FY 1997.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
|
|
2005
|
2010
|
2015
|
2020
|
2025
|
2030
|
| FUSRAP - B&T Metals Site
|
|
|
|
|
|
|
|
|
| Assessment
|
20
|
|
|
|
|
|
|
100
|
| Remedial Action
|
574 |
|
|
|
|
|
|
2,869
|
| Total
|
594 |
|
|
|
|
|
|
2,969
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FUNDING ESTIMATE
The following table presents estimated funding information for the B&T
Metals site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
|
|
2005
|
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
594 |
|
|
|
|
|
|
2,969
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|
 |