|
Home
BEMR
Contents
U.S.
Map
Belfield and Bowman are two of the 24 uranium mill processing sites designated by
the Uranium Mill Tailings Radiation Control Act for remediation by the
Department of Energy. During the 1960s, private firms processed most of the
uranium ore mined in the United States for the Atomic Energy Commission, a
predecessor of the Department of Energy. Congress passed the Act in 1978 in
response to public concern regarding potential health hazards from long-term
exposure to uranium mill tailings. It authorized the Department of Energy to
stabilize, dispose of, and control uranium mill tailings and other contaminated
material at 24 uranium mill processing sites and vicinity properties. For a
general discussion of the UMTRA Program, see the overview presented in the New
Mexico section of this report.
The cost estimate model used for this report provides costs for each of the UMTRA
sites. All costs for waste management activities, program management, and
relevant landlord activities attributable to the Department are provided for
within the scope of environmental restoration. There are no Uranium Mill
Tailings Radiation Control Act sites with either current or planned nuclear
material and facility stabilization activity needs. Funding for all sites is
100 percent nondefense.
Pursuant to the Uranium Mill Tailings Radiation Control Act, the Department of
Energy entered into a Cooperative Agreement in 1983 with the State of North
Dakota. The agreement outlines the roles and responsibilities of each party. It
also delineates the cost sharing arrangement that states that the Department of
Energy is responsible for 100 percent of the assessment costs and 90 percent of
the remediation costs, and the State is responsible for the remaining 10
percent of the remediation costs. In addition, the Department of Energy is
responsible for paying 90 percent of the State's 10 percent, and the State is
responsible for the remaining 10 percent of these costs (one percent of the
total). The Nuclear Regulatory Commission concurred on the original agreement
and is required to concur on all major modifications thereafter.
Based on a letter received from the State of North Dakota in March 1995
requesting that the Department of Energy remove the Belfield and Bowman sites
from designation under the Uranium Mill Tailings Radiation Control Act, the
Project has suspended all activities for these sites. Preliminary documents
have been prepared to notify Congress and to initiate a Federal Register notice
to remove the sites from designation under the Act. The sections that follow
represent planning prior to the State's request.
BELFIELD, NORTH DAKOTA (UMTRA SITE)
The Belfield site is located in southwestern North Dakota, 1.6 kilometers (one
mile) southeast of the Town of Belfield in Stark County. The former ashing site
occupies 4.3 hectares (10.7 acres).
LOCALITY MAP
Estimated Site Total
|
(Thousands of Current Year Dollars)
|
|
|
|
|
|
| Environmental Restoration |
11,992 |
2,505 |
453 |
361 |
577 |
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
0
|
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
0
|
|
|
|
(Five-Year Averages, Thousands of Constant 1996 Dollars)
|
|
|
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
3,139
|
629
|
|
|
|
|
|
18,840
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The mission of the Belfield site was to provide uraniferous ash for processing
at the Ambrosia Lake, New Mexico and Rifle, Colorado mill sites for the United
States Government. The source of contamination was the residual radioactive
material that remained after a lignite coal ashing process concentrated the
uranium found in the coal. The ash from this process is different from the
usual mill tailings found at the other UMTRA sites. Currently, a construction
company uses the site to store and service equipment.
SITE MAP
The Environmental Management program is responsible for cleaning up surface- and
ground-water contamination at the UMTRA sites. The Uranium Mill Tailings
Radiation Control Act designated the residual radioactive material found at
this site for cleanup and stabilization. The Act directed the Environmental
Protection Agency to promulgate standards (Code of Federal Regulations Title
40, Part 192) and the Department of Energy to perform the cleanup. It also
assigned the Nuclear Regulatory Commission to oversee and certify the cleanup,
and license the completed disposal cell.
FUTURE USE
Remedial action at the former Belfield processing site would be performed under
a Remedial Action Agreement among the Department of Energy, the State of North
Dakota, and the private land owners. Upon completion of surface- and
ground-water remedial action, Nuclear Regulatory Commission site certification,
and certification of compliance with the Environmental Protection Agency
ground-water standards, ownership of the former processing site will be
returned to the private landowners. The future use of the site is likely to be
Agricultural or light Industrial.
ENVIRONMENTAL RESTORATION
Although no discernible pile remains, the former ashing site contains
ash-contaminated soil. Windblown stack-released ash has contaminated 8.5
hectares (21 acres). Residual milling related contaminated ground water is also
present.
Environmental Restoration Activities Cost Estimate
|
(Five-Year Averages, Thousands of Constant 1996 Dollars)
|
|
|
2010
|
2015
|
2020
|
2025
|
2030
|
| UMTRA Surface
|
|
|
|
|
|
|
|
|
| Assessment
|
187
|
98
|
|
|
|
|
|
1,425
|
| Remedial Action
|
2,644
|
11
|
|
|
|
|
|
13,275
|
| Direct Program Management/Support
|
309
|
519
|
|
|
|
|
|
4,140
|
| Total
|
3,139
|
629
|
|
|
|
|
|
18,840
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Surface Project
In the proposed surface remedial action, which is scheduled to start in FY
1996, all residual radioactive material from the Belfield site will be
relocated 97 kilometers (60 miles) south, to the Bowman, North Dakota site, for
co-disposal.
Approximately 44,080 cubic meters (58,000 cubic yards) of contaminated
materials from the Belfield site are scheduled to be transported to the Bowman
disposal cell, where they will be stabilized. The residual radioactive
materials requiring remediation are only the contaminated soil, gravel, and
rubble from the site. Concurrent with site remediation, eight vicinity
properties will be remediated. During remedial actions, transportation of the
tailings over public roads will be accomplished under a special Department of
Transportation exemption. Remedial action is scheduled to be complete in FY
1997. Nuclear Regulatory Commission certification and licensing of the Bowman
disposal site will take place in FY 1998, with transfer to the Long-Term
Surveillance and Maintenance Program late in FY 1998.
Major Surface Project Milestones (On Hold)
| Finalize Environmental Assessment and Publish
Remedial Action Plan
|
1996 |
| Site and Vicinity Property Remedial Action
|
1997
|
The site has been fully characterized, and no further monitoring of any media
is occurring. No mill tailings pond or pile is present because the ash was
shipped to another location for processing during the 1960s.
The contaminant distribution and remediation needed is outlined in the
Belfield/Bowman, North Dakota Remedial Action Plan. The Remedial Action Plan,
which requires Nuclear Regulatory Commission concurrence, will be published in
the spring of 1996. The site Completion Report will be prepared and included as
part of the site Certification Report. Since the tailings will be removed, no
further surveillance of the site is required under the Surface Project once the
remedial action is completed.
Ground-Water Compliance Project
The Department is developing a Programmatic Environmental Impact Statement
pertaining to all 24 UMTRA sites. For a discussion of the Programmatic
Environmental Impact Statement see the UMTRA program narrative in the New
Mexico section of the report. Site-specific National Environmental Policy Act
documentation will be developed to propose an appropriate ground-water
compliance strategy and reasonable alternatives for the Belfield site once the
Programmatic Environmental Impact Statement is completed.
This report assumes a No Further Action compliance demonstration ground-water
strategy for the Belfield site. The high background concentrations of the
contaminants of concern should allow for supplemental standards based on
widespread ambient contamination and no threat to human health or the
environment. For all types of ground-water compliance strategies, once the site
is determined by Nuclear Regulatory Commission to be in compliance with Subpart
B of the Environmental Protection Agency Standards and it is certified, no
additional long-term surveillance or monitoring will be conducted.
The extent of ground-water contamination related to uranium processing
activities at the Belfield site is difficult to determine. The contamination
was minimal because of the low intensity of the processing activities (only the
physical process of burning lignite). In general, uranium processing activities
at the Belfield site have only slightly impacted the naturally poor quality of
the ground water.
The following milestone dates have been established for planning purposes.
Major Ground-Water Compliance Project Milestones
| Site Observational Work Plan
|
2002
|
| Publish Environmental Assessment/Finding of No
Significant Impact
|
2003
|
| Publish Remedial Action Plan
|
2004
|
| Licensing
|
2005
|
The indicator parameter for the Belfield site is uranium. It is the constituent
most likely related to the uraniferous lignite ashing activities at the site.
The processing operation did not use inorganic or organic chemicals, and none
are expected in ground water.
Water quality sampling was conducted at the Belfield site from 1986 to 1988 and
again in 1993. Investigators analyzed ground-water samples collected from
onsite and downgradient monitoring wells to determine the extent and magnitude
of ground-water contamination related to uranium processing activities. In the
upper zone downgradient of the site, analyses showed that only uranium
concentrations were elevated above background levels. However, the uranium does
not form a discrete plume in the upper zone downgradient from the processing
site. No contaminants were found in the lignite zone that exceeded background
concentrations.
Some constituents of concern (such as antimony, chromium, lead, molybdenum,
selenium, uranium, and vanadium) occur at naturally elevated concentrations in
shallow ground water adjacent to lignite zones in this region of North Dakota.
This has made it difficult to distinguish between ground water contamination
related to the former uranium processing activities at this site and the
naturally occurring concentrations of these constituents. Furthermore, farm
waste, septic tanks, sewage disposal ponds, and waste from current industrial
activities on the site may contribute some contaminants to the ground water in
the vicinity of the site.
Direct Program Management/Support
Program management supports management efforts for the National Environmental
Policy Act process, site characterization and licensing, public
information/participation, applicable state and federal regulator costs,
quality assurance audits, program and management support for the technical
assistance contractor, special studies, document control, technical assistance
contractor site and technical management, cost and schedule controls, planning
and preparation of the federal budget, and the Environmental Management
Progress Tracking System.
FUNDING ESTIMATE
The following table presents estimated funding information for the Belfield
site.
Nondefense Funding Estimate
|
(Five-Year Averages, Thousands of Constant 1996 Dollars)
|
|
|
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
3,139
|
629
|
|
|
|
|
|
18,840
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|
 |