|
Home
BEMR
Contents
U.S.
Map
Baker Brothers
The Baker Brothers site is located in Toledo, Ohio, at the intersection of
Harleau Place and Post Street. The area is bordered by Interstate 75 on the
west, State Route 120 on the north, and U.S. Highway 24 on the
east. Surrounding the site are commercial businesses to the north and south,
residences to the east, and railroad tracks with residences beyond the tracks
to the west. The site includes four buildings with saw-tooth roofs and concrete
floors where the Baker Brothers Company machined natural uranium metal in
support of Manhattan Engineer District operations in the early 1940s; paved
parking areas; and a partially enclosed courtyard in front of the main
building, where most of the outdoor contamination was found. The property is
partially fenced. The exterior ground cover at the site is mostly asphalt or
concrete with small patches of grass near the roads.
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
| |
|
|
|
| Environmental Restoration
|
67
|
|
|
|
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
107 |
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
0
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
| Environmental Restoration |
13
|
|
|
|
|
|
|
67
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
Between June 1943 and July 1944, DuPont and the University of Chicago
subcontracted the Baker Brothers Company to machine roll metal rods into
uranium slugs to support Manhattan Engineer District work. Baker Brothers slugs
fueled the world's first nuclear production reactors in Oak Ridge, Tennessee
and Hanford, Washington. At contract termination, the site was decontaminated
to meet existing health guidelines. The Department conducted radiological
surveys in the 1980s that detected the presence of uranium residues at levels
exceeding current federal guidelines; results of a detailed radiological study,
which the Department conducted in 1995, were used to design the cleanup.
SITE MAP
The primary contaminant at the site is uranium238; metallic uranium was
the only radioactive substance known to have been handled at the Baker Brothers
site, and uranium was the only radioactive constituent of concern that surveys
and investigations identified at the site.
Contaminated media include soil, concrete, and miscellaneous debris. Potential
contaminant transport pathways include soil, air, and ground water containing
uranium leached from site soils. Potential radiation exposure scenarios include
current workers at the site, future renovation workers who could be engaged in
renovation of buildings and outdoor areas at the site, and future residents of
nearby properties who might drink water from wells that could later be
installed. Potential exposure pathways for current or future workers include
exposure to external gamma radiation from contaminated soils, inhalation of
uranium dust and radon, and ingestion of contaminated soils or other materials
at the site.
Baker Brothers assets were eventually liquidated, and the machinery and
equipment were sold at auction.
FUTURE USE
The site is now two separate properties that support ongoing commercial
enterprises. The property is still privately owned and is currently occupied by
a used motor brokerage and an electrical services company. Future use of the
Baker Brothers site is assumed to remain Industrial/Commercial.
The Baker Brothers site is in an urban setting. It is not located in the flood
plain of any stream or waterway, and includes no wetlands. Under current site
conditions and land use, the radioactive contamination does not present a
health risk to the public or to individuals who work at the site; however,
without site remediation, it could pose increased health risks should land use
at the site change. The site is being cleaned up to comply with current
guidelines and will be released for use with no radiological restrictions after
cleanup is completed. This report assumes that future land use will remain
Industrial/Commercial.
ENVIRONMENTAL RESTORATION
The Baker Brothers site is being cleaned up under the Comprehensive
Environmental Response, Compensation, and Liability Act and the Department's
FUSRAP. Key regulators are the Ohio Environmental Protection Agency and local
governments, as appropriate.
Work crews mobilized at Baker Brothers in July 1995. The cleanup is
expected to last about three months and will cost an estimated
$3 million. Waste will be containerized, loaded onto trucks, and
transported to a rail yard elsewhere in Ohio. After transfer to rail cars, the
material will be shipped to Envirocare of Utah for disposal.
Pollution control measures include the use of plastic sheeting to prevent
spillage and facilitate cleanup of spills during loading of waste for
transport, misting soils with water to reduce spread of airborne contaminants,
surveying exteriors of vehicles for radioactivity, and decontaminating vehicles
if necessary. To avoid contact with soils, subflooring, and other contaminated
materials during remedial action, Department of Energy workers wear protective
clothing and use personal protective equipment. The use of dust suppression
techniques and barriers to prevent movement of exposed dirt offsite during
rainstorms minimizes the effects of wind and water erosion in disturbed areas
outdoors. Strict adherence to federal safety guidelines, backed up by
continuous environmental surveillance, will ensure that no contaminants migrate
from the controlled area during cleanup.
Major Environmental Restoration Activity Milestones
| Remedial Action |
1996
|
ASSESSMENT
Field investigations to determine the nature and extent of contamination at
Baker Brothers included radiological surveys and sampling and analysis of
surface and subsurface soil, air, and dust and floor debris in buildings.
Surveys and sampling identified four outdoor areas with soil containing uranium
contamination above cleanup guidelines. Elevated uranium levels were also
detected in isolated areas within buildings. This report assumes that all
assessment activities are complete at this site.
A preliminary radiological survey conducted by the Department of Energy and
Argonne National Laboratory in 1981 detected a small amount of isolated
radioactive material in a wooden shelf bin in one building and surface
radioactivity on the floor and walls in another building. There was no evidence
of radioactive contamination on the ceiling or roof.
Although radioactive material was found only in small, isolated areas, the
Department ordered a comprehensive radiological investigation. The site was
assigned low priority because of the limited quantity and distribution of
residual radioactive materials and the relatively low risk of exposure of site
workers and the general public to radiation. Radiological surveys and sampling
included surface gamma walkover surveys in all accessible areas of the
property; direct gamma exposure measurements; sampling and analysis of indoor
floor debris, overhead beam dust, and outdoor surface and subsurface soil;
direct measurement of fixed and removable alpha and beta/gamma activity levels
on indoor surfaces and on the roof; and air sampling in selected building
areas.
Radiological surveys in 1988, 1989, and 1990 confirmed that uranium was present
at levels exceeding current guidelines both outdoors (in the enclosed gravel
courtyard and in a few isolated spots in the paved parking lot and near the
property line) and on a number of indoor surfaces. In 1995, the Department
performed a detailed site characterization; the resulting radiological data
were used to design a safe, thorough, and cost-effective cleanup. An
Engineering Evaluation/Cost Analysis evaluated potential cleanup options in
1995. The option selected consists of building decontamination and removal of
approximately 380 cubic meters (500 cubic yards) of soil, concrete, and
other contaminated debris.
The effectiveness of a cleanup option depends on how well it protects human
health and the environment from contaminant-associated risks both during and
after implementation. The Engineering Evaluation/Cost Analysis for cleanup at
Baker Brothers included a radiological dose assessment to determine potential
health effects associated with each option under current and future conditions.
Three exposure scenarios were evaluated: the current worker, the future
renovation worker, and future residential receptors ingesting ground water from
a well at the site boundary.
Radiological dose estimates for current workers under all exposure conditions
evaluated were well below guidelines; however, if future work at the site
included renovation of buildings and/or outdoor areas, the maximum potential
dose received by a future renovation worker could exceed the established public
dose limit. Potential exposure routes for the hypothetical future renovation
worker are direct external gamma radiation from uranium in subsurface soils,
ingestion of uraniumcontaining soils or other materials, and inhalation of
uranium dust or radon. For future residents of nearby properties drinking water
from wells that might later be installed, modeling has shown that since the
drinking water aquifer in the area is 30 to 45 meters (100 to 150 feet)
below land surface, uranium from the site would not impact this pathway within
the next 1,000 years.
REMEDIAL ACTION
Three cleanup options were evaluated in the Engineering Evaluation/Cost
Analysis for Baker Brothers: (1) no action, representing a baseline of
current conditions; (2) institutional controls/site monitoring, which
would restrict access to contaminated areas and provide long-term monitoring;
and (3) soil removal and building decontamination, which would remove
contamination above current guidelines. The selected option for site cleanup,
soil removal and building decontamination will protect human health and the
environment and will allow future use of the property with no radiological
restrictions. The materials removed will be transported to Envirocare of Utah
for disposal. The Baseline Environmental Management Report cost estimate
assumes this cleanup scenario and a total waste volume of 380 cubic meters
(500 cubic yards). Waste will be packaged and shipped in accordance with
disposal facility waste acceptance criteria and Department of Energy and
Department of Transportation requirements. Transportation routes will be
established, and an emergency response plan will be developed.
In November 1991, soil and concrete were excavated and removed from the
courtyard at the Baker Brothers property without the Department of Energy's
knowledge or consent; the courtyard was then backfilled with gravel. This area
is now used for storage of used electric motors and transformers. The soils
excavated from the courtyard were used as backfill and topsoil at a private
residence in Ottawa Lake, Michigan. The Department of Energy removed those
soils in a separate cleanup action, representing remediation of a Baker
Brothers site vicinity property.
This report expects remedial action at Baker Brothers to be completed during
calendar year 1995 (FY 1996). Activities still to be completed include loading
and packaging of waste materials into bimodal containers; transportation of the
waste to Envirocare of Utah for permanent disposal; verification sampling and
decontamination following cleanup (including analysis of soil and debris
samples from the excavated areas to confirm compliance with cleanup
requirements); and site restoration activities such as filling, reseeding, or
paving as necessary to restabilize the excavated areas.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2005 |
2010 |
2015 |
2020 |
2025 |
2030 |
| FUSRAP - Baker Brothers Site
|
|
|
|
|
|
|
|
|
| Remedial Action
|
13
|
|
|
|
|
|
|
67
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FUNDING ESTIMATE
The following table presents estimated funding information for the Baker
Brothers site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2005 |
2010 |
2015 |
2020 |
2025 |
2030 |
| Environmental Restoration
|
13
|
|
|
|
|
|
|
67
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|