|
Home
BEMR
Contents
U.S.
Map
NEW MEXICO UMTRA SITES
The Ambrosia Lake and Shiprock former processing sites are two of 24 uranium
mill processing sites designated by the Uranium Mill Tailings Radiation Control
Act for remediation by the Department of Energy. During the 1960s, private
firms processed most of the uranium ore mined in the United States for the
Atomic Energy Commission, a predecessor of the Department of Energy. Congress
passed the Act in 1978 in response to public concern regarding potential health
hazards from long-term exposure to uranium mill tailings. It authorized the
Department of Energy to stabilize, dispose of, and control uranium mill
tailings and other contaminated material at 24 uranium mill processing sites
and vicinity properties. For a general discussion of the UMTRA Program, see the
overview presented in the New Mexico section of this report.
The cost estimate model used for this report provides costs for each of the
UMTRA sites. All costs for waste management activities, program management, and
relevant landlord activities attributable to the Department are provided for
within the scope of environmental management. There are no Uranium Mill
Tailings Radiation Control Act sites with either current or planned nuclear
material and facility stabilization activity needs. Funding for all sites is
100 percent nondefense.
Pursuant to the Uranium Mill Tailings Radiation Control Act, the Department of
Energy entered into a Cooperative Agreement in 1985 with the State of New
Mexico. The agreement outlines the roles and responsibilities of each party.
The agreement also delineates the cost sharing arrangement which states that
the Department of Energy is responsible for 100 percent of the assessment costs
and 90 percent of the remediation costs, and the state is responsible for the
remaining 10 percent of the remediation costs. The Nuclear Regulatory
Commission concurred on the original agreement and is required to concur on all
major modifications thereafter.
AMBROSIA LAKE (UMTRA SITE)
The former Ambrosia Lake mill and tailings site is located in McKinley County in
northwest New Mexico approximately 40 kilometers (25 miles) north of Grants and
137 kilometers (85 miles) northwest of Albuquerque. The tailings covered
approximately 42 hectares (105 acres). Wind and water erosion spread some of
the tailings across a 231-hectare (570-acre) area.
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
| |
|
|
|
| Environmental Restoration
|
511
|
391
|
150
|
128
|
54
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
573
|
|
|
These levels reflect the current
estimates for compliance with applicable statutes and agreements (as of March
1996), see Readers' Guide.
|
| 1997 Congressional Request
|
|
171
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
| Environmental Restoration
|
239
|
|
|
|
|
|
|
1,197
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The mission of the Ambrosia Lake mill site was to provide uranium for the
United States Government. The sources of contamination were the residual
tailings and discharged process water remaining after the uranium was extracted
during the milling process. Phillips Petroleum Company originally operated the
mill, which was built in 1957. United Nuclear Corporation purchased and
operated the mill for a brief period in 1963. United Nuclear Corporation shut
down milling operations in 1963 but retained ownership of the site. In the late
1970s and early 1980s, United Nuclear Corporation operated an ion exchange
system, extracting uranium from mine water. Homestake Mining purchased United
Nuclear Corporation's interest in 1981. The State of New Mexico currently owns
the site.
SITE MAP
The Environmental Management program is responsible for cleaning up surface-
and ground-water contamination at the UMTRA sites. The Uranium Mill Tailings
Radiation Control Act designated the residual radioactive material found at
this site for cleanup and stabilization. The Act directed the Environmental
Protection Agency to promulgate standards (Code of Federal Regulations Title
40, Part 192) and the Department of Energy to perform the cleanup. It also
assigned the Nuclear Regulatory Commission to oversee and certify the cleanup
and license the completed disposal cell.
FUTURE USE
The State of New Mexico currently owns the former processing site. When the
Nuclear Regulatory Commission certifies that remedial action is complete, the
State will transfer the deed for this site to the Federal Government under the
custody of the Department of Energy. Access to the facility will remain
restricted, and it will be monitored and maintained in accordance with the
Nuclear Regulatory Commission approved-Long-Term Surveillance Plan.
ENVIRONMENTAL RESTORATION
Surface remedial action has been completed, and the source of contamination has
been stabilized. However, residual milling-related contaminated ground water
remains.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
| UMTRA Surface
|
|
|
|
|
|
|
|
|
| Assessment
|
23
|
|
|
|
|
|
|
114
|
| Remedial Action
|
4
|
|
|
|
|
|
|
21
|
| UMTRA Ground water
|
|
|
|
|
|
|
|
|
| Assessment
|
22
|
|
|
|
|
|
|
109
|
| Remedial Action
|
10
|
|
|
|
|
|
|
49
|
| Direct Program Management/Support
|
181
|
|
|
|
|
|
|
904
|
| Total |
239
|
|
|
|
|
|
|
1,197
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Surface Project
Remedial action was completed at the Ambrosia Lake former processing site in
July 1995. The remedial action involved consolidating approximately 4.6 million
cubic meters (6 million cubic yards) of residual radioactive material onsite in
a 36-hectare (88-acre) disposal cell and remediating the five vicinity
properties. This report assumes that the Nuclear Regulatory Commission will
certify the remedial action in June 1996 and licence the disposal cell in June
1997. Administration of the site will transfer to the Grand Junction Projects
Office Long-Term Surveillance and Maintenance program in September 1997.
Major Surface Project Activity Milestones
| Nuclear Regulatory Commission Issues General
License |
1997
|
| Transfer to Grand Junction Projects Office
Long-Term Surveillance and Maintenance Program
|
1997
|
The Ambrosia Lake Remedial Action Plan outlines the contaminant distribution
and the required remedial action. The Remedial Action Plan, which requires
Nuclear Regulatory Commission concurrence, was published in January 1992.
Remedial action at the site was performed in two phases. Phase I began in late
1986 and included construction of decontamination facilities, asbestos removal,
demolition of the mill building, and other site preparation activities. Phase
II remedial action began in September 1992 and involved excavating and
consolidating residual radioactive material, including the existing tailings,
and stabilizing these materials at the present tailings location.
The UMTRA Surface Project will conduct surveillance and maintenance of the
disposal cell after completion of remedial action and prior to its transfer to
the Grand Junction Projects Office's Long-Term Surveillance and Maintenance
program in FY 1997.
Ground-Water Compliance Project
The Department is developing a Programmatic Environmental Impact Statement
pertaining to all 24 UMTRA sites. For a discussion of the Programmatic
Environmental Impact Statement see the UMTRA program narrative in the New
Mexico section of the report. After completion of the Programmatic
Environmental Impact Statement, site-specific National Environmental Policy Act
documentation will be developed to propose an appropriate ground-water
compliance strategy and reasonable alternatives for the Ambrosia Lake site.
The cost estimates for this report assume that a compliance strategy requiring
no further action will be selected. For all types of ground-water compliance
strategies, once the Nuclear Regulatory Commission determines a site to be in
compliance with Subpart B of the Environmental Protection Agency Standards and
it is certified, no additional long-term surveillance or monitoring will be
conducted.
The volume of contaminated ground water has not been assessed because the
aquifer has been designated a limited use (class III) aquifer. Leach processing
activities and the tailings left on the site were the sources of the
contaminants. The uppermost aquifer at the site was created by past milling
activities. The contaminants of potential concern are radium-226, selenium and
natural uranium. The volume of contaminated ground water should diminish with
time. Ground-water underflow and recharge in the area is minimal.
Major Ground-Water Compliance Project Milestones
| Site Observational Work Plan |
1996
|
|
Publish Environmental Assessment/Findings of No Significant Impact
|
1997
|
|
Publish Remedial Action Plan |
1999
|
|
Licensing
|
2000
|
To define the extent of ground-water contamination, the Department of Energy
collected water samples from 1980 through 1995. Results from the 1994 sampling
event show that concentrations of molybdenum, nitrate, selenium, and uranium
exceeded the Environmental Protection Agency maximum concentration limits for
ground water in the alluvium and weathered Mancos Shale. Ground water in lower
aquifers does not appear to have been contaminated by seepage from the
contaminated ground-water units beneath the Ambrosia Lake site.
All water contained in the alluvium and weathered Mancos Shale at the site was
initially derived from mining-related activities; therefore, no background
water existed to be sampled. There are no potential receptors in the vicinity
of the site because ground water in the uppermost water-bearing zone is not
used for domestic or agricultural purposes. Based on existing data collection
activities, it appears that the residual milling ground-water contamination has
not spread offsite.
Direct Program Management/Support
Program management supports management efforts for the National Environmental
Policy Act process, site characterization and licensing, public
information/participation, applicable state and federal regulator costs,
quality assurance audits, program and management support for the technical
assistance contractor, special studies, document control, technical assistance
contractor site and technical management, cost and schedule controls, planning
and preparation of the federal budget, and the Environmental Management
Progress Tracking System.
FUNDING ESTIMATE
The following table presents estimated funding information for the Ambrosia
Lake site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
| Environmental Restoration
|
239
|
|
|
|
|
|
|
1,197
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|