|
Home
BEMR
Contents
U.S.
Map
The Ventron site is located on Congress Street in Beverly, Massachusetts, at the
confluence of the Bass and Danvers Rivers, which border the site on the west
and south, respectively, approximately 25 kilometers (15 miles) northeast
of Boston. The site adjoins a residential area to the north and the Boston and
Maine Railroad to the east and comprises approximately 1.2 hectares
(3 acres). Buildings and other manmade structures cover about two-thirds
of the site.
LOCALITY MAP
Estimated Site Total
|
(Thousands of Current Year Dollars)
|
| |
1999
|
2000
|
|
|
|
| Environmental Restoration
|
6,334
|
6,092
|
146
|
|
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
4,365
|
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
213
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2005
|
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
2,477
|
|
|
|
|
|
|
12,387
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
From 1942 to 1948, the Metal Hydrides Corporation, then located at the Ventron
site, was under contract to the Manhattan Engineer District and the Atomic
Energy Commission to convert uranium oxide to uranium metal powder. This
procedure, as well as later operations to recover uranium from scrap and
turnings from a fuel fabrication plant at Hanford, Washington, was conducted at
a foundry at the site.
SITE MAP
During contract operations, three buildings were used for uranium work. Two
wooden buildings that housed the foundry facilities were demolished between
1948 and 1950, and two other buildings have since been erected in their places.
The remaining original building contained furnace and leaching facilities, a
mixing room, a drying room, and an analytical laboratory.
In 1948, the Atomic Energy Commission conducted a radiological survey of the
facility. The survey detected contamination in two foundry buildings and
various pieces of equipment and the Commission recommended cleanup. The Metal
Hydrides Corporation became the Ventron Corporation in 1965. In late 1976,
Morton Thiokol, Inc. acquired control of the company.
Morton International (formerly Morton Thiokol) now owns the plant. The site is
an operating research and development facility.
FUTURE USE
Morton International is currently undergoing closure actions for the Ventron
facility. Since future use of this property could remain Industrial/Commercial
or become Residential, the assumption for the cost estimate defaults to the
more conservative post-remedial action Residential use scenario.
ENVIRONMENTAL RESTORATION
Environmental restoration activities at the site focus on identifying and
evaluating contaminated areas, devising cleanup strategies, and conducting
remediation as needed. Key regulators include Environmental Protection Agency
Region I, the Massachusetts Department of Environmental Protection, and
the local health department.
The Department will coordinate removal activities with Morton International.
The site owner wants the property decontaminated for use with no radiological
restrictions. The Department estimates that 1,150 cubic meters
(1,500 cubic yards) of contaminated soil and approximately 380 cubic
meters (500 cubic yards) of material from building demolition will need to
be removed from the site to meet guidelines for release. Cleanup will involve
decontamination of structural surfaces in buildings, followed by building
demolition and excavation of soils using standard construction/excavation
equipment. This report assumes that all of the collected waste will be
transported via truck or rail to an outofstate commercial disposal
facility.
Site characterization data will be used to support an Engineering
Evaluation/Cost Analysis for planned site response actions. After review of the
document, the Department of Energy will issue an Action Description Memorandum
in accordance with Comprehensive Environmental Response, Compensation and
Liability Act documentation requirements. Also, a Memorandum to Files or a
"Finding of no Significant Impact" will be issued to satisfy National
Environmental Policy Act documentation requirements. The Comprehensive
Environmental Response, Compensation, and Liability Act Engineering
Evaluation/Cost Analysis will incorporate National Environmental Policy Act
values to satisfy National Environmental Policy Act documentation requirements.
Major Environmental Restoration Activity Milestones
| Assessment (Engineering Evaluation/Cost Analysis with Action
Memorandum)
|
1996
|
|
Remedial Action
|
1998
|
ASSESSMENT
The Department of Energy and Oak Ridge National Laboratory conducted a
screening survey of the site in 1977. Based on exploratory measurements, the
Department determined that a radiological survey of the entire site was
required.
In 1980 and 1982, Oak Ridge National Laboratory conducted radiological surveys
of the site grounds, buildings, and other structures. Based on results of these
surveys, Oak Ridge presented a preliminary report recommending consideration of
remedial action to the Department of Energy in 1986, when the site was
designated for inclusion in FUSRAP.
The survey results verified the presence of residual radioactive contamination,
largely uranium, with lesser amounts of thorium and radium, in outdoor soil and
in fill material beneath four buildings. Some surface contamination exceeding
current guidelines was found in two buildings on roofs, floors, walls, and
overhead surfaces and in crawl spaces. Radionuclide analyses of sediment
samples collected from storm sewer manholes indicated concentrations of
thorium232 exceeding naturally occurring background levels, which can be
attributed to Morton's commercial activities involving radioactive materials;
these activities are unrelated to Manhattan Engineer District/Atomic Energy
Commission contract work.
In 1986, FUSRAP provided radiological support to Ventron during renovation
activities at the site. Support included removing an underground storage tank
and general maintenance activities. FUSRAP performed a radiological
characterization of the site in 1992 that employed the Streamlined Approach for
Environmental Restoration as a pilot project. Implementation of this method
based on earlier characterization by Oak Ridge National Laboratory allowed the
Department to realize substantial cost savings. FUSRAP provided additional
radiological support in 1993 during Morton's investigations of mercury
contamination in the harbor adjacent to the site. Support included providing
health physics technicians to survey sediment samples that Morton had collected
for elevated levels of radioactivity.
An environmental compliance assessment of the site included a review of
applicable portions of the Resource Conservation and Recovery Act, the Toxic
Substances Control Act, the Clean Air Act, and the Clean Water Act. The
assessment included review of records, reports, and files and consultation with
FUSRAP personnel. Based on review of the site history, it is unlikely that
listed hazardous waste has been mixed with radiological residues. Currently,
the Department of Energy does not generate any hazardous waste at the site.
REMEDIAL ACTION
Cleanup of the site will proceed in accordance with a preferred remedy outlined
in the Engineering Evaluation/Cost Analysis. The owner will demolish five
buildings, including two buildings that will be decontaminated before
dismantlement. In addition to remedial actions to decontaminate and dismantle
buildings and other structures and to excavate onsite soils for transportation
and disposal, excavation of sediments in the adjacent waterways will be
necessary.
The scenario used for the Baseline Environmental Management Report cost
estimate assumes complete excavation of contaminated soil and sediments,
demolition and removal of buildings, and disposal at an existing commercial
disposal facility. The waste volume assumed for the cost estimate is 1,530
cubic meters (2,000 cubic yards) including 1,150 cubic meters
(1,500 cubic yards) of contaminated soil, and approximately 380 cubic
meters (500 cubic yards) of building rubble.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2005
|
2010
|
2015
|
2020
|
2025
|
2030
|
| FUSRAP - Ventron Site
|
|
|
|
|
|
|
|
|
| Assessment
|
20
|
|
|
|
|
|
|
100
|
| Remedial Action
|
2,457
|
|
|
|
|
|
|
12,287
|
| Total
|
2,477
|
|
|
|
|
|
|
12,387
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FUNDING ESTIMATE
The following table presents estimated funding information for the Ventron
site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2005
|
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
2,477
|
|
|
|
|
|
|
12,387
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|
 |