|
Home
BEMR
Contents
U.S.
Map
The currently active Massachusetts sites within the Formerly Utilized Sites
Remedial Action Program (FUSRAP) are the Shpack Landfill and Ventron. Chapman
Valve is a completed FUSRAP site. FUSRAP was established in 1974 under the
provisions of the Atomic Energy Act to identify, investigate, and clean up or
otherwise control previously decontaminated Manhattan Engineer District and
Atomic Energy Commission sites, together with other sites assigned to the U.S.
Department of Energy by Congress, where residual radioactive contamination
exceeds current guidelines.
FUSRAP encompasses 46 sites in 14 states and is funded through the Oak Ridge
Operations Office. For a general discussion of FUSRAP and associated costs, as
well as a discussion of completed FUSRAP sites, see the overview of the program
presented in the Tennessee section of this report. All costs for waste
management activities, program management, and relevant landlord activities
attributable to the Department of Energy are provided for within the scope of
environmental restoration. There are no FUSRAP sites with either current or
planned nuclear material and facility stabilization activity needs. Funding for
all sites is 100 percent nondefense.
SHPACK LANDFILL
The Shpack Landfill site covers approximately 3.2 hectares (8 acres); about
2.2 hectares (5.5 acres) are in the corporate limits of Norton,
Massachusetts, about 65 kilometers (40 miles) southwest of Boston. The
remainder [about 1 hectare (2.5 acres)] are within the corporate limits of
Attleboro, Massachusetts. The site is bordered on the northwest by Peckham
Road; on the north by Union Road; on the south and west by the Attleboro
Landfill, operated by Attleboro Landfill, Inc.; and on the east by open fields.
There are no onsite structures.
LOCALITY MAP
Estimated Site Total
|
(Thousands of Current Year Dollars)
|
| |
1999
|
2000
|
|
|
|
| Environmental Restoration
|
93
|
179
|
115
|
|
|
Grey shaded area reflects annual cost estimates for the
first five years of the site BEMR Base Case (as of October 1995) and includes
3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
39
|
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
35
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2005
|
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
75
|
|
|
|
|
|
|
375
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The Shpack Landfill began operating as a private landfill in the early 1960s
and received both industrial and domestic wastes. The landfill was closed in
1965 under court order. In 1978, a concerned citizen who had detected elevated
radiation levels at the site contacted the Nuclear Regulatory Commission. The
Commission investigated the site and confirmed the presence of radioactivity in
excess of natural background levels for the area.
SITE MAP
Exactly when these contaminants were deposited at the site is not known.
However, the Nuclear Regulatory Commission determined that the Texas
Instruments plant (formerly M&C Nuclear, Inc.) of Attleboro had used the
landfill to dispose of trash and other materials. The Nuclear Regulatory
Commission concluded that the contaminants probably resulted from this waste
stream.
After the Nuclear Regulatory
Commission investigation, the landfill was considered as a candidate for
inclusion in FUSRAP. In 1980, The Oak Ridge National Laboratory conducted a
radiological characterization of the site, confirmed the Nuclear Regulatory
Commission findings, and defined the general areas of contamination. Based on
the results of this survey, the former Shpack Landfill was designated for
cleanup under FUSRAP. However, the Department of Energy has determined that the
Texas Instruments plant is excluded from FUSRAP because activities at the
facility were licensed by the Nuclear Regulatory Commission.
The Town of Norton purchased the site in 1981. It is fenced and posted with "no
trespassing" signs, and the Town of Norton and the New England Power Company
control access to it. Risk to the public from radioactive materials at the site
is minimal because of the low levels of gamma radiation and the distance
between the site and inhabited dwellings. Also, the principal sources of
surface contamination were removed in 1980 during radiological surveys. Because
of the relative physical and chemical stability of the radioactive
contamination, cleanup could be deferred without harmful effects on human
health or the environment.
FUTURE USE
The Town of Norton now owns the Shpack Landfill site, which is no longer used
as a landfill. The adjacent Attleboro Landfill is now in the process of State
closure. The Department of Energy has no active role in the disposition of the
site after any remedial action.
ENVIRONMENTAL RESTORATION
In addition to radioactive contamination, the Shpack site contains
nonradioactive hazardous materials unrelated to Department of
Energysponsored work. The Environmental Protection Agency contacted the
other Potentially Responsible Parties in the summer of 1990 and issued an
Administrative Order by Consent for the potentially responsible parties to
conduct a Remedial Investigation/Feasibility Study. The Environmental
Protection Agency and the Department of Energy then began discussions regarding
the Department of Energy's role in the cleanup.
Key regulators include Environmental Protection Agency Region I, the
Massachusetts Department of Environmental Protection, and the local health
department. Because Shpack is on the Environmental Protection Agency's National
Priorities List for cleanup and the Environmental Protection Agency has
instructed the other Potentially Responsible Parties to perform a Remedial
Investigation/Feasibility Study, the Department of Energy does not plan to
prepare separate documents. Instead, the Department will support the efforts of
the other parties by submitting information as needed about the radiological
aspects of site remediation. FUSRAP has provided input for the remedial
investigation/feasibility study documents prepared by the other parties'
contractor and has supported the resolution of Environmental Protection Agency
comments on these documents.
Major Environmental Restoration Activity Milestones
| Assessment (Record of Decision by Environmental Protection
Agency/Potentially Responsible Parties
|
1996
|
|
Remedial Action
|
1998
|
ASSESSMENT
In 1978, the Nuclear Regulatory Commission investigated and confirmed the
presence of radioactivity in excess of natural background levels for the area.
The primary contaminants were radium226, uranium238, and
uranium235. A subsequent radiological survey by Oak Ridge National
Laboratory in 1980 confirmed these findings, defined the general areas of
contamination, and provided the basis for inclusion of the site in FUSRAP.
During this investigation, the principal sources of uranium235 surface
contamination were removed.
The 1980 survey measured beta-gamma dose rates and gamma exposure rates.
Samples were collected from surface and subsurface soils, surface and
subsurface water, and surface water in runoff areas of the site; these samples
were measured for radionuclides. Metal samples were also collected and
analyzed, and several were found to contain or to be contaminated with uranium
of various enrichments. Analytical results confirmed that radium and uranium
are the principal contaminants.
FUSRAP conducted a 1982 survey that provided a definitive description of
the boundaries of contamination identified in the 1980 investigations. This
survey determined that the distribution of onsite contamination is irregularly
spaced and uneven, both vertically and horizontally. Removal of this soil would
generate an estimated 7,170 cubic meters (9,370 cubic yards) of waste.
However, because of the relative physical and chemical stability of the
radioactive contamination, such a cleanup could be deferred without harmful
effect to humans or the environment.
The Potentially Responsible Parties are responsible for sampling from and
analyzing the ground-water monitoring wells, which the Department of Energy
installed in 1982, concurrently with the FUSRAP radiological survey.
REMEDIAL ACTION
Other than removal of uranium235 contamination and installation of the
boundary fence in 1980, the Department has not performed any remedial action at
the site. The Department has deferred the cleanup pending coordination with the
Environmental Protection Agency and potentially responsible parties as
appropriate. The scenario used for the Baseline Environmental Management Report
cost estimate, however, assumes remedial action by other potentially
responsible parties, with Department of Energy FUSRAP applying supplemental
standards as appropriate. Therefore, the Baseline Environmental Management
Report scenario assumes that the Department will not participate in any
remedial actions, but only in final report preparation.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2005
|
2010
|
2015
|
2020
|
2025
|
2030
|
| FUSRAP - Shpack Landfill Site
|
|
|
|
|
|
|
|
|
| Assessment
|
19
|
|
|
|
|
|
|
93
|
| Remedial Action
|
56
|
|
|
|
|
|
|
282
|
| Total |
75
|
|
|
|
|
|
|
375
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FUNDING ESTIMATE
The following table presents estimated funding information for the Shpack
Landfill site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2005
|
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
75
|
|
|
|
|
|
|
375
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|