|
Home
BEMR
Contents
U.S.
Map
Back to Section 1
Facility Decommissioning
Decommissioning costs for each of the more than 400 structures at Rocky Flats
was parametrically estimated against the Building 865 model based on the square
foot factors for each of the nine major activities: Project Management,
Surveillance and Maintenance, Characterization, Environmental/Safety and
Health, Engineering, Internal Deactivation and Decommissioning, and Closeout
and Verification. Five variable factors were applied to modify the cost
estimates to more accurately reflect complexity: building type (plutonium,
nonplutonium, or general support), accessibility, occupancy, and square feet of
facility floor space. The cost assumes that all buildings will be dismantled or
demolished. Costs are also estimated for removal of under-building
contamination.
PLUTONIUM BUILDING DECOMMISSIONING
This activity covers the decontamination and decommissioning of facilities at
Rocky Flats that have been, or are suspected to be, contaminated with plutonium
residues. Decommissioning of plutonium-contaminated facilities involves a
process consisting of multiple activities that must be tailored to meet
specific planning criteria for the desired end state.
Plutonium buildings functioned at Rocky Flats as principal production,
processing, developmental laboratory, and plutonium recovery facilities in
support of weapon pit-components production. Primary contaminants of concern
include plutonium, uranium, beryllium, and hazardous chemicals. The
laboratories, process equipment, gloveboxes, and piping may require cleaning
using various methods, including high-efficiency particulate air vacuuming,
chemical cleaning (solvents), physical cleaning (wiping, steam), scabbling of
concrete surfaces, and water rinsing. In addition, electropolishing may be used
to decontaminate portable, irregularly shaped surfaces (such as glovebox
components). After decontamination, equipment and structures may be
volume-reduced, separated, and packaged and stored as waste, or reused,
recycled, or stockpiled for reuse at other facilities. After removing the
equipment and decontaminating the interior of the facility, verification
samples will be taken to ensure that the risk of release is insignificant prior
to breaking the envelope of the structure to initiate structural and subgrade
dismantlement.
NONPLUTONIUM BUILDING DECOMMISSIONING
This activity covers the decommissioning of facilities at Rocky Flats that have
been, or are suspected to be, contaminated with nonplutonium radioactive
residues, such as depleted or enriched uranium. Decommissioning of
nonplutonium-contaminated facilities involves a process consisting of multiple
levels of detailed activities that must be tailored to meet specific planning
criteria for the desired end state.
Nonplutonium buildings functioned as principal uranium and beryllium
metallurgical development laboratories, depleted uranium production facilities,
nuclear safety laboratories, nonplutonium production facilities, and
functionally related support facilities. Primary contaminants of concern
include uranium, beryllium dust, and hazardous chemicals used in production
processes. The production, laboratories, process equipment, and piping will
require cleaning using various methods, including high-efficiency particulate
air vacuuming, chemical cleaning (solvents), physical cleaning (wiping, steam),
scabbling of concrete surfaces, and water rinsing. In addition,
electropolishing will be used to decontaminate porable, irregularly shaped
surfaces (such as glovebox components). After decontamination, equipment and
structures will be volume-reduced, separated, and either packaged and stored as
waste or reused, recycled, or stockpiled for reuse at other facilities. After
removing the equipment and decontaminating the interior of the facility,
verification samples will be taken to ensure that the risk of release is
insignificant prior to breaking the envelope of the structure to initiate
structural and subgrade dismantlement.
GENERAL SUPPORT BUILDING DECOMMISSIONING
This activity covers the decommissioning of facilities at Rocky Flats that have
been, or are suspected to be, contaminated with nonradioactive, hazardous
substances, or uncontaminated. Decommissioning of general support facilities
involves a process consisting of multiple levels of detailed activities that
must be tailored to meet specific planning criteria for the desired end state.
General support buildings/facilities/structures serve the overall site
infrastructure and include administrative trailers, offices, water and fuel
storage tanks, towers, ranges, garages, the fire station, electrical
substations, and other facilities which collectively make up the administrative
and utility lifeline at Rocky Flats. The primary contaminants of concern
include nonradioactive, hazardous substances including virgin petroleum
products stored for future use and chemical solvents. Contaminated areas will
require cleaning through various methods, including high-efficiency particulate
air vacuuming, chemical cleaning (weak acids), physical cleaning (wiping,
steam), scabbling of concrete surfaces, and water rinsing. After
decontamination, equipment and structures will be volume-reduced, separated,
and either packaged and stored as waste or reused, recycled, or stockpiled for
reuse at other facilities. After removing the equipment and decontaminating the
interior of the facility, verification samples will be taken to ensure that the
risk of release is insignificant prior to breaking the envelope of the
structure to initiate structural and subgrade dismantlement.
Environmental Restoration Waste Type and Volume Table
|
Transuranic Mixed
|
1,237
|
|
Transuranic
|
662
|
|
Low-Level Mixed
|
36,935
|
|
Low-Level
|
35,131
|
|
Hazardous
|
13,681
|
|
Sanitary
|
180,266
|
Direct Program Management/Support
Program management support is required to provide planning, control and
reporting, coordination, and oversight for all subprojects of the Environmental
Restoration Project, as defined in the Environmental Restoration Rocky Flats
Environmental Technology Site Project Management Plan. It also encompasses
environmental restoration quality assurance, information management, project
services, Administrative Record functions, and dedicated community relations
support and computer systems assistance.
ENVIRONMENTAL RESTORATION SITE-WIDE OPERATIONS
The scope of site-wide operations is to oversee and provide facilities, space,
equipment, maintenance, equipment inventory, computer security, and building
staff in support of all ongoing Interagency Agreement directed activities. This
includes day-to-day management of over 3,000 inventoried items including radios
for daily field communication, field vehicles, onsite buildings and one offsite
building. The Department operates and maintains two decontamination facilities
to prevent cross-contamination to uncontaminated areas by decontaminating all
equipment (e.g., drill rigs, augers, sampling utensils) used to conduct
remedial investigations and remedial action fieldwork at the 16 operable units
onsite. The Site-Wide Water Treatment Facility is operated and maintained as
required by the Interagency Agreement to treat various operable unit-generated
waters as well as incidental waters, purge waters, and decontamination waters
as acceptance criteria allow. Site-wide operations also include the management
of environmental restoration-generated waste in Resource Conservation and
Recovery Act units, staff for offsite certification, onsite packaging and
handling practice, and spill responses. Personal protective equipment disposal
and Hazardous Waste Compliance program implementation are also included under
site-wide operations.
Environmental Restoration Activities Cost Estimate
|
(Five-Year Averages, Thousands of Constant 1996 Dollars)
|
| |
|
| OU-1: 881 Hillside |
|
|
|
|
|
|
|
|
| Assessment |
43 |
|
|
|
|
|
|
|
| OU-2: 903 Pad, Mound, E. Trenches |
|
|
|
|
|
|
|
|
| Assessment |
2,358 |
199 |
|
|
|
|
|
|
| Remedial Action |
4,685 |
303 |
|
|
|
|
|
|
| OU-3: Offsite Areas |
|
|
|
|
|
|
|
|
| Assessment |
211 |
|
|
|
|
|
|
|
| OU-4: Solar Ponds |
|
|
|
|
|
|
|
|
| Remedial Action |
21,419 |
|
|
|
|
|
|
|
| OU-5: Woman Creek |
|
|
|
|
|
|
|
|
| Assessment |
883 |
|
|
|
|
|
|
|
| OU-6: Walnut Creek |
|
|
|
|
|
|
|
|
| Assessment |
536 |
|
|
|
|
|
|
|
| OU-7: Present Landfill |
|
|
|
|
|
|
|
|
| Remedial Action |
5,960 |
|
|
|
|
|
|
|
| Industrial Area Operable Units |
|
|
|
|
|
|
|
|
| Assessment |
10,474 |
5,955 |
1,721 |
304 |
|
|
|
|
| Remedial Action |
1,155 |
2,231 |
5,518 |
2,550 |
|
|
|
|
| OU-11: West Spray Field |
|
|
|
|
|
|
|
|
| Assessment |
52 |
|
|
|
|
|
|
|
| OU-15: Inside Building Closures |
|
|
|
|
|
|
|
|
| Assessment |
52 |
|
|
|
|
|
|
|
| Corrective Action Management Unit |
14,263 |
2,315 |
|
|
|
|
|
|
| Facility Decommissioning |
|
21,157 |
38,793 |
45,786 |
84,614 |
120,056 |
186,004 |
|
| Long-Term Surveil. and Monitoring |
10,975 |
13,762 |
22,225 |
27,735 |
24,282 |
18,864 |
17,140 |
|
| Direct Program Management/Support |
24,493 |
23,357 |
23,357 |
23,357 |
23,357 |
23,357 |
23,357 |
|
| Total |
97,560 |
69,281 |
91,614 |
99,732 |
132,253 |
162,277 |
226,501 |
|
| |
2060 |
2065 |
| OU-1: 881 Hillside |
|
|
|
|
|
|
|
|
| Assessment |
|
|
|
|
|
|
|
217 |
| OU-2: 903 Pad, Mound, E. Trenches |
|
|
|
|
|
|
|
|
| Assessment |
|
|
|
|
|
|
|
12,788 |
| Remedial Action |
|
|
|
|
|
|
|
24,940 |
| OU-3: Offsite Areas |
|
|
|
|
|
|
|
|
| Assessment |
|
|
|
|
|
|
|
1,056 |
| OU-4: Solar Ponds |
|
|
|
|
|
|
|
|
| Remedial Action |
|
|
|
|
|
|
|
107,093 |
| OU-5: Woman Creek |
|
|
|
|
|
|
|
|
| Assessment |
|
|
|
|
|
|
|
4,416 |
| OU-6: Walnut Creek |
|
|
|
|
|
|
|
|
| Assessment |
|
|
|
|
|
|
|
2,680 |
| OU-7: Present Landfill |
|
|
|
|
|
|
|
|
| Remedial Action |
|
|
|
|
|
|
|
29,799 |
| Industrial Area Operable Units |
|
|
|
|
|
|
|
|
| Assessment |
|
|
|
|
|
|
|
92,273 |
| Remedial Action |
|
|
|
|
|
|
|
57,273 |
| OU-11: West Spray Field |
|
|
|
|
|
|
|
|
| Assessment |
|
|
|
|
|
|
|
260 |
| OU-15: Inside Building Closures |
|
|
|
|
|
|
|
|
| Assessment |
|
|
|
|
|
|
|
260 |
| Corrective Action Management Unit |
|
|
|
|
|
|
|
82,893 |
| Facility Decommissioning |
126,616 |
49,737 |
41,505 |
7,721 |
1,124 |
|
|
3,615,564 |
| Long-Term Surveil. and Monitoring |
5,000 |
5,000 |
5,000 |
5,000 |
1,000 |
|
|
779,909 |
| Direct Program Management/Support |
18,200 |
11,600 |
8,300 |
8,300 |
1,520 |
|
|
1,062,776 |
| Total |
149,816 |
66,337 |
54,805 |
21,021 |
3,644 |
|
|
5,874,197 |
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars. |
INTEGRATED TECHNICAL PROGRAM (TECHNICAL SERVICES)
The Environmental Restoration Integrated Technical program encompasses tasks
supporting all of the operable units and includes a variety of plans,
procedures, reports, studies, and other activities required by the Interagency
Agreement, the Department of Energy Orders, and/or site policy. These
activities apply to all site environmental restoration activities and include,
but are not limited to, the Integrated Technical program characterization
studies for background soils characterization and field sampling. These studies
continue to monitor the migration of plutonium and americium in soils in the
vadose zone. They monitor runoff transport and assess radionuclides and metals
in the ground water near the eastern site boundary.
The Industrial Area Interim Remedial Action program coordinates the development
of decision documents and prepares for the implementation of the selected
alternatives. This program also includes monitoring activities for
decommissioning.
The Geologic Characterization program develops data and interpretations
pertaining to lithologies, stratigraphy, and the structure of Rocky Flats, as
required to support characterization of the individual operable units. This is
accomplished through background surficial soils characterization, stable
isotope investigations, aquifer testing, seep-flow measurement, hydrogeology
modeling, core radiography, and soil assessment.
The Ground-Water Monitoring program monitors new wells, supports aquifer tests,
and phases in routine monitoring of existing wells. It evaluates techniques for
upgradient ground water, industrial area ground water, vertical gradient ground
water, and ground-water monitoring.
|
STAKEHOLDER INTERACTIONS
The Rocky Flats Operations Office distributed copies of a fact sheet about this
report at Citizens Advisory Board meetings and at the Rocky Flats Local Impacts
Initiative Board meeting. Presentations at a number of forums, including the
October 1995 Rocky Flats Public Meeting; the Waste Management Programmatic
Environmental Impact Statement tele-video conference; and meetings regarding
the Accelerated Site Action Project, Conceptual Site Vision, and other projects
at Rocky Flats, also provided information about the report. No official public
comments were received from state or local stakeholders; however, the Rocky
Flats Operations Office developed site-specific action items from comments
received at national Baseline Environmental Management Report stakeholder
meetings to ensure that recommendations were incorporated into the narrative
for the Rocky Flats Site. In response to these comments, a number of actions
were taken to clarify assumptions underlying the report process. Assumptions
were documented and cross-checked for consistency with those of other
documents, and regulatory assumptions were clearly defined. The narrative for
the 1996 report was also modified to clarify future land-use planning
processes. For more information about the report, please contact:
|
Public Participation
Mike Konczal
(303) 966-7095
michael.konczal@rfets.gov |
Technical Liaison
Gene Senat
(303) 966-3505 gene.senat@rfets.gov |
Public Affairs
Mariane Anderson
(303) 966-6088
mariane.anderson@rfets.gov |
WASTE MANAGEMENT
The goal of the Rocky Flats Waste Management program is to reduce, eliminate, or
mitigate environmental liabilities by managing waste safely and effectively.
The sources of waste are inventories from past production, as well as current
and future facility stabilization/deactivation activities. The Environmental
Restoration section addresses all treatment, storage, and disposal costs and
associated activities for waste generated by remedial action and
decommissioning. See theNuclear Material and
Facility Stabilization map for the location of waste management
activities.
The management of waste involves a four-step process: characterization,
treatment, storage, and disposal. This process is not necessarily sequential
for all waste streams. For example, some waste requires treatment before and
after storage, other waste may be sent directly to disposal. Six types of waste
are generated and/or stored at Rocky Flats: transuranic mixed waste,
transuranic waste, low-level mixed waste, low-level waste, hazardous waste, and
sanitary waste.
This estimate includes compliance with federal, state, and local environmental
laws, Department of Energy Orders, various agreements, and consent decrees that
protect the environment and public health. Site-specific agreements include the
Interagency Agreement and the 1995 Compliance Order resulting from the Site
Treatment Plan process under the Federal Facility Compliance Act.
Waste characterization encompasses sampling and analyzing waste, developing
analytical methods, and documenting and verifying waste streams. Much of the
waste generated in the past was characterized solely by process knowledge
(i.e., personal judgment based on experience with a particular process or
operation). For this reason, laboratory analysis is vital to waste
characterization. This report assumes that facilities will be modified to
address waste characterization needs.
Waste treatment costs encompass both existing and planned treatment systems, as
well as surveillance and maintenance of the major waste treatment facilities.
Existing waste treatment systems at Rocky Flats focus on reducing the volume of
liquid and solid waste forms and stabilizing other waste to produce a waste
form suitable for storage or disposal. These existing systems use technologies
that were initiated many years ago and were not designed to produce final waste
forms to meet current waste acceptance criteria. Treatment systems are being
developed and are described in the Site Treatment Plan for transuranic mixed
and low-level mixed waste.
Residue management at Rocky Flats is unique because the Nuclear Material and
Facility Stabilization program is responsible for treatment and the Waste
Management program is responsible for storage and disposal. This waste
management estimate classifies residues as transuranic mixed and transuranic
waste because of the way in which materials will be managed for disposal.
Most of the waste must be kept in interim storage pending the availability of
onsite or offsite disposal. Site plans call for the identification and
provision of timely interim waste storage capacity, particularly for
contaminated media and low-level mixed waste, sufficient to support remediation
and other scheduled mission activities. Rocky Flats will not be used as a
storage facility for materials imported from other sites in the weapons
complex.
This estimate assumes that waste shipment/disposal rates are equivalent to waste
generation rates after the year 2020. The waste will be shipped, packaged and
certified by the generator without treatment, precluding the need for
additional storage capacity.
Sanitary solid waste is currently the only waste disposed of onsite. However,
this estimate assumes that environmental restoration-generated waste will be
disposed of in an onsite Corrective Action Management Unit and pondcrete will
be disposed of in an adjacent Resource Conservation and Recovery Act Subtitle C
disposal cell. This estimate assumes that nonenvironmental restoration
generated low-level mixed waste and low-level waste will be disposed of at the
Nevada Test Site. Some forms of low-level mixed waste are currently being
disposed of at Envirocare of Utah.
Major Waste Mangement Projects Cost Estimate
|
(Five-Year Averages, Thousands of Constant 1996 Dollars)
|
| |
|
| Building 374 - Liquid Waste Treatment |
9,627 |
6,974 |
6,311 |
6,311 |
6,311 |
6,311 |
|
|
| Building 374/774 - PSTP System 2/4B |
3,766 |
1,161 |
1,544 |
2,320 |
1,675 |
582 |
|
|
| Building 664: Waste Storage & Shipping Fac. |
4,956 |
3,725 |
4,163 |
4,568 |
6,181 |
5,917 |
3,404 |
|
| Building 774 - Aqueous Waste Treatment |
2,522 |
2,522 |
2,018 |
|
|
|
|
|
| Building 776 - Solid Waste Processing |
3,585 |
|
|
|
|
|
|
|
| Building 995 - Sewage Treatment Plant |
315 |
255 |
255 |
|
|
|
|
|
| New Sanitary Landfill |
1,675 |
993 |
822 |
822 |
822 |
822 |
822 |
|
| PSTP Path F: Treatment of TRM |
300 |
2,308 |
1,680 |
1,310 |
1,558 |
517 |
60 |
|
| PSTP System 3: Misc. Immobilization |
3,883 |
1,342 |
1,863 |
1,863 |
2,343 |
735 |
|
|
| PSTP System 5: Surface Organic Contam. Rem. |
4,014 |
3,797 |
1,634 |
1,376 |
596 |
524 |
|
|
| RFETS: Hazardous Waste Storage |
2,068 |
3,077 |
1,113 |
1,113 |
1,429 |
261 |
181 |
|
| RFETS: Low Level Mixed Waste Storage |
12,444 |
6,135 |
9,481 |
9,953 |
9,415 |
7,044 |
2,093 |
|
| RFETS: Low Level Waste Storage |
10,315 |
11,263 |
10,716 |
8,966 |
10,598 |
3,462 |
4,976 |
|
| RFETS: RCRA Disposal Cell |
6,640 |
2,117 |
|
|
|
|
|
|
| RFETS: Transuranic Waste Storage |
1,574 |
982 |
624 |
499 |
524 |
201 |
396 |
|
| RFETS: Transuranic Mixed Waste Storage |
820 |
981 |
1,147 |
1,022 |
1,004 |
789 |
478 |
|
| |
2055 |
2060 |
2065 |
| Building 374 - Liquid Waste Treatment |
|
|
|
|
|
|
|
209,226 |
| Building 374/774 - PSTP System 2/4B |
|
|
|
|
|
|
|
55,243 |
| Building 664: Waste Storage & Shipping Fac. |
1,548 |
433 |
157 |
4 |
|
|
|
175,284 |
| Building 774 - Aqueous Waste Treatment |
|
|
|
|
|
|
|
35,313 |
| Building 776 - Solid Waste Processing |
|
|
|
|
|
|
|
17,925 |
| Building 995 - Sewage Treatment Plant |
|
|
|
|
|
|
|
4,125 |
| New Sanitary Landfill |
822 |
822 |
822 |
822 |
|
|
|
50,330 |
| PSTP Path F: Treatment of TRM |
|
|
|
|
|
|
|
38,663 |
| PSTP System 3: Misc. Immobilization |
|
|
|
|
|
|
|
60,144 |
| PSTP System 5: Surface Organic Contam. Rem. |
|
|
|
|
|
|
|
59,703 |
| RFETS: Hazardous Waste Storage |
122 |
241 |
204 |
13 |
|
|
|
49,108 |
| RFETS: Low Level Mixed Waste Storage |
1,828 |
902 |
301 |
14 |
|
|
|
298,050 |
| RFETS: Low Level Waste Storage |
2,118 |
650 |
214 |
|
|
|
|
316,388 |
| RFETS: RCRA Disposal Cell |
|
|
|
|
|
|
|
43,786 |
| RFETS: Transuranic Waste Storage |
65 |
7 |
|
|
|
|
|
24,367 |
| RFETS: Transuranic Mixed Waste Storage |
214 |
170 |
|
|
|
|
|
33,123 |
* Project costs represent a subset of total Waste
Management costs.
** Total Life Cycle is the sum of the annual costs in constant FY 1996 dollars. |
Major Waste Management Activity Milestones
| Treatment
|
| Transuranic Mixed and Transuranic Waste |
2028
|
| Low-Level Mixed Waste |
2025
|
|
Disposal
|
| Transuranic Mixed and Transuranic Waste to Waste Isolation
Pilot Plant |
2039
|
|
Pondcrete to Proposed Resource Conservation and Recovery Act Disposal Cell |
2003
|
|
Low-Level Mixed Saltcrete to Envirocare |
2021
|
|
Low-Level Mixed and Low-Level Waste to Nevada Test Site |
2046
|
|
Sanitary Waste to New Sanitary Landfill |
2050
|
Transuranic Mixed Waste
GENERATION AND HANDLING
Transuranic mixed waste is transuranic waste with a hazardous waste constituent
or characteristic. This waste must be managed in accordance with appropriate
radioactive waste regulations and hazardous waste regulations. It is generated
from routine operations, residue stabilization, and Resource Conservation and
Recovery Act closure activities. Characterization of this waste is based
largely on process knowledge and limited sampling and analysis.
TREATMENT
Existing liquid processing treatment systems for volume reduction of transuranic
mixed liquid waste are Building 774, miscellaneous aqueous waste handling and
immobilization and the Building 374 liquid waste treatment facility. The
primary planned treatment methods for solid transuranic mixed waste are
immobilization of free liquids and particulate, neutralization and oxidation,
and repackaging to meet the Waste Isolation Pilot Plant waste acceptance
criteria.
STORAGE
Transuranic mixed waste must be stored in permitted Resource Conservation and
Recovery Act storage units. The available storage capacity for transuranic
mixed waste is expected to increase in the future as residues are processed and
residue storage space is transferred to transuranic mixed storage capacity.
Transuranic mixed and transuranic waste will be certified, staged, and shipped
out of Building 664.
DISPOSAL
Transuranic mixed waste is assumed to be disposed of at the Waste Isolation
Pilot Plant. Increased certification capacity for Rocky Flats is assumed to
support this disposal. Approximately 5,000 cubic meters (6,600 cubic yards) of
waste will be shipped for disposal at the Waste Isolation Pilot Plant between
FY 1999 and FY 2039.
All disposal costs for transuranic mixed waste are included in the Waste
Isolation Pilot Program. The costs included in this estimate are for managing
transuranic mixed waste and include retrieval, characterization, treatment, and
packaging to meet the Waste Isolation Pilot Plant Waste Acceptance Criteria.
Transuranic Waste
GENERATION AND HANDLING
At Rocky Flats, transuranic waste is primarily contaminated with plutonium.
Contaminated media include combustibles, plastics, light metals, and sludges.
Characterization of this waste has been based largely on available process
knowledge.
TREATMENT
Treatment systems are divided into primary and in-process systems. In-process
systems focus on volume reduction and stabilization in preparation for safe
storage rather than on treating waste for final disposal. The primary existing
solid waste treatment system for transuranic waste is the Building 776 solid
waste reprocessing and repackaging system. Existing liquid processing treatment
systems for transuranic liquid waste are Building 371 caustic waste treatment,
Building 774 aqueous waste treatment, Building 774 miscellaneous aqueous waste
treatment, Building 374 liquid waste treatment facility, and Building 771
oxalate and hydroxide precipitation. The primary planned treatment for
transuranic waste includes immobilizing free liquids and particulate,
neutralizing and oxidating them, and repackaging the waste to meet the Waste
Isolation Pilot Plant Waste Acceptance Criteria.
STORAGE
Department of Energy Orders govern the storage of transuranic waste. Some waste
is currently stored in regulated transuranic mixed storage areas because very
few areas at Rocky Flats have been formally designated as storage areas for
non-Resource Conservation and Recovery Act-regulated waste. Commingling of
nonregulated waste containers with Resource Conservation and Recovery
Act-regulated waste containers is a legally acceptable practice but it
increases overall storage costs. Historically, transuranic waste was stored in
areas that are permitted for transuranic mixed and mixed residue waste because
these areas satisfied concerns for radiological safety and container
management. Also, the site lacks sufficient storage space overall to allow for
total segregation of transuranic waste. Transuranic mixed and transuranic waste
will be certified, staged, and shipped out of Building 664.
DISPOSAL
Transuranic waste will be disposed of at the Waste Isolation Pilot Plant in New
Mexico, which this report assumes will open in FY 1998. The report also assumes
that disposal of approximately 3,300 cubic meters (4,300 cubic yards) of
transuranic waste at the Waste Isolation Pilot Plant will begin in FY 1999 and
continue through FY 2039.
Transportation of transuranic mixed and transuranic waste by truck to the Waste
Isolation Pilot Plant will require using the Transuranic Package Transporter
(TRUPACT II) shipping vessel. Each shipping vessel can contain 14 0.2- cubic
meter (55-gallon) drums or two standard metal boxes, and each truck trailer can
carry three vessels.
All disposal costs for transuranic waste are included in the Waste Isolation
Pilot Program. The costs included in this estimate are for managing transuranic
waste and include retrieval, characterization, treatment, and packaging to meet
the Waste Isolation Pilot Plant Waste Acceptance Criteria.
Low-Level Mixed Waste
GENERATION AND HANDLING
Low-level mixed waste includes combustibles, plastics, light metal, soils, and
liquids as well as treated waste such as cemented solar pond sludge (pondcrete)
and cemented aqueous process waste salts (saltcrete).
TREATMENT
The primary existing treatment system for low-level mixed waste is the Building
374 liquid waste treatment facility. Planned treatment for low-level mixed
waste includes Diversified Scientific Services, Inc., the Advanced Mixed Waste
Treatment Project in Idaho, and several onsite treatment systems. All waste
will be treated to meet land disposal restrictions.
|
ONSITE TREATMENT SYSTEMS
System 3-Miscellaneous Waste Immobilization will use cementation or
polymer solidification to immobilize metals and organic compounds. It will
operate between FY 2003 and FY 2019, processing approximately 1,500 cubic
meters (2,000 cubic yards) of waste.
System 5-Surface Organic Contaminant Removal will use thermal desorption
or supercritical carbon dioxide extraction to separate organic compounds from
the waste matrix. Subsequent destruction of the organics using nonthermal
oxidation or separation technology for mercury and cyanides will also be used.
It will operate between FY 2008 and FY 2017 and process approximately 400 cubic
meters (500 cubic yards) of waste.
System 3/5 Combination combines Systems 3 and 5 described above. It will
operate between FY 2005 and FY 2020, processing approximately 6,000 cubic
meters (8,000 cubic yards) of waste.
System 6-Pondcrete/Solar Pond Sludge will reprocess the pondcrete by
using some form of size reduction, followed by immobilization. It will operate
between FY 1999 and FY 2000, processing approximately 11,500 cubic meters
(15,100 cubic yards) of waste.
|
STORAGE
A Resource Conservation and Recovery Act Permit regulates the storage of
low-level mixed waste at Rocky Flats. Current projections indicate that the
addition of Building 440 storage will provide sufficient storage capacity for
future needs until onsite treatment begins.
DISPOSAL
Low-level mixed waste must meet land disposal restriction standards prior to
disposal. This report assumes that 9,700 cubic meters (12,800 cubic yards) of
saltcrete will continue to be shipped to Envirocare of Utah until FY 2021. This
estimate also assumes that 12,000 cubic meters (16,000 cubic yards) of
pondcrete will be placed in the proposed onsite Resource Conservation and
Recovery Act Subtitle C disposal cell from FY 1999 through 2000, which will
close in FY 2003. Approximately 700 cubic meters (900 cubic yards) of low-level
mixed waste will be disposed of at commercial facilities between FY 1999 and
2046, and between FY 1999 and 2044, an additional 28,000 cubic meters (37,000
cubic yards) will be shipped to the Nevada Test Site.
Low-Level Waste
GENERATION AND HANDLING
Low-level waste includes combustibles, plastics, light metals, soils, and
liquids, as well as treated waste such as sewage sludge. Characterization of
this waste is based largely on process knowledge; however, laboratory analysis
to supplement process knowledge has been included in the cost estimate for
waste characterization.
TREATMENT
Primary existing treatment systems for low-level waste are Low-level Waste
Sewage Sludge Treatment, and Building 374 Liquid Waste Treatment Facility. The
primary planned treatments include drying, segregating, and repackaging to meet
waste acceptance criteria. There are no costs included in this estimate.
STORAGE
Low-level waste is stored in compliance with requirements set forth in
Department of Energy Orders. Some of this waste is currently stored in
regulated low-level mixed waste storage areas. Building 440 will be converted
to store low-level waste and will also provide the capability to stage and ship
the waste.
Rocky Flats currently stages and ships low-level waste out of Building 664. The
site has the capability to ship waste directly from the Centralized Waste
Storage Facility (Building 906) and 750 and 904 pads.
DISPOSAL
Low-level waste handled by the Waste Management program will be transferred to
the Nevada Test Site for disposal. Low-level sewage sludge will also be shipped
to the Nevada Test Site. Waste transferred to the Nevada Test Site is estimated
at approximately 36,000 cubic meters (47,000 cubic yards) and will take place
between FY 1996 and FY 2046. An additional 3,400 cubic meters (4,500 cubic
yards) will be disposed of at a commercial facility between FY 1997 and FY
2044.
Currently, 46 cubic meters (60 cubic yards) of asbestos-containing material are
stored in Building 666 and several other locations at Rocky Flats. Of the
total, 31 cubic meters (41 cubic yards) of asbestos-containing material are
contaminated with low levels of radioactive materials. Radioactive
asbestos-containing material is shipped to the Department of Energy's Hanford
Facility for landfill disposal. The remainder is shipped to an appropriate
offsite commercial facility.
Hazardous Waste
Hazardous waste management requirements are based on the Resource Conservation
and Recovery Act regulations and the Colorado Hazardous Waste Regulations.
Hazardous waste must be stored in permitted Resource Conservation and Recovery
Act storage units. Current projections indicate that existing storage capacity
will be sufficient for future needs.
This report assumes that the current practice of shipping nonenvironmental
restoration hazardous waste to commercial treatment, storage, and disposal
facilities will continue. This report also assumes that 3,000 cubic meters
(3,900 cubic yards) will be transferred to commercial facilities between FY
1996 and 2046.
Sanitary Waste
TREATMENT
The Sanitary Waste Program involves operating the Waste Water Treatment Plant
and the sanitary landfill. Sanitary waste is primarily generated by routine
operations, decontamination, and decommissioning activities. Liquid sanitary
waste is treated in a two-phase process. Resulting liquids are treated in an
activated carbon bed filtration system and resulting solids are handled as
low-level waste.
DISPOSAL
Solid sanitary waste is not stored or treated prior to being recycled
commercially or disposed of at the site landfill. The volume of solid sanitary
waste to be disposed at the site landfill is currently estimated at 6,500 cubic
meters (8,500 cubic yards) per year. Construction of the first cell of a new
sanitary landfill to replace the existing sanitary landfill began in FY 1994.
This new landfill will consist of three individual cells and will have a
capacity of approximately 456,000 cubic meters (600,000 cubic yards) to meet
solid sanitary waste disposal requirements for the life cycle. Each cell will
be equipped with a double-liner system, a leachate collection system, a leak
detection system, a methane gas collection system, and a baler system to
enhance waste volume reduction and recycling. This report assumes that the new
landfill will operate until FY 2049. In addition, approximately 7,500 cubic
meters (9,800 cubic yards) of sanitary waste will be shipped to a commercial
facility for disposal.
Direct Program Management/Support
The purpose of direct program management support provided to waste management
activities is to ensure compliance with existing agreements and to reduce the
risk and costs associated with managing Rocky Flats's inventory of waste.
Program management activities include assessing and responding to regulatory
changes, exploring regulatory flexibility, developing strategies, planning
baselines, developing tracking, and reporting on budgets and performance. Waste
strategies include optimizing transuranic waste shipments and minimizing waste
through recycling.
Waste Management Activities Cost Estimate
|
(Five-Year Averages, Thousands of Constant 1996 Dollars)
|
| |
|
| Transuranic Mixed Waste |
|
|
|
|
|
|
|
|
| Treatment |
7,636 |
8,339 |
6,880 |
4,492 |
4,740 |
3,700 |
60 |
|
| Storage and Handling |
1,896 |
1,757 |
1,923 |
1,798 |
1,702 |
1,487 |
1,580 |
|
| Disposal |
77 |
133 |
194 |
194 |
194 |
194 |
111 |
|
| Transuranic Waste |
|
|
|
|
|
|
|
|
| Treatment |
4,814 |
3,466 |
3,128 |
3,128 |
3,128 |
3,128 |
|
|
| Storage and Handling |
6,235 |
1,759 |
1,400 |
1,275 |
1,222 |
899 |
1,026 |
|
| Disposal |
71 |
255 |
194 |
194 |
210 |
56 |
132 |
|
| Low-Level Mixed Waste |
|
|
|
|
|
|
|
|
| Treatment |
13,658 |
7,110 |
5,851 |
6,369 |
6,573 |
3,529 |
460 |
|
| Storage and Handling |
13,973 |
7,364 |
10,710 |
11,182 |
10,586 |
8,215 |
3,175 |
|
| Disposal |
8,537 |
3,588 |
1,919 |
2,375 |
2,836 |
2,530 |
952 |
|
| Low-Level Waste |
|
|
|
|
|
|
|
|
| Storage and Handling |
12,338 |
12,786 |
12,239 |
10,489 |
12,043 |
4,907 |
6,352 |
|
| Disposal |
1,584 |
1,723 |
1,723 |
1,723 |
1,723 |
1,723 |
1,723 |
|
| Hazardous Waste |
|
|
|
|
|
|
|
|
| Storage and Handling |
2,068 |
3,077 |
1,113 |
1,113 |
1,429 |
261 |
181 |
|
| Disposal |
133 |
133 |
123 |
72 |
60 |
48 |
26 |
|
| Sanitary Waste |
|
|
|
|
|
|
|
|
| Treatment |
315 |
255 |
255 |
|
|
|
|
|
| Disposal |
1,675 |
993 |
822 |
822 |
822 |
822 |
822 |
|
| Direct Program Management/Support |
29,650 |
28,777 |
28,656 |
28,564 |
28,622 |
24,633 |
13,320 |
|
| Total |
104,659 |
81,515 |
77,132 |
73,791 |
75,891 |
56,131 |
29,920 |
|
| |
2055 |
2060 |
2065 |
| Transuranic Mixed Waste |
|
|
|
|
|
|
|
|
| Treatment |
|
|
|
|
|
|
|
179,237 |
| Storage and Handling |
1,316 |
735 |
565 |
|
|
|
|
73,797 |
| Disposal |
15 |
104 |
|
|
|
|
|
6,085 |
| Transuranic Waste |
|
|
|
|
|
|
|
|
| Treatment |
|
|
|
|
|
|
|
103,965 |
| Storage and Handling |
694 |
572 |
565 |
|
|
|
|
78,236 |
| Disposal |
17 |
1 |
|
|
|
|
|
5,656 |
| Low-Level Mixed Waste |
|
|
|
|
|
|
|
|
| Treatment |
|
|
|
|
|
|
|
217,753 |
| Storage and Handling |
2,910 |
1,920 |
1,138 |
14 |
|
|
|
355,938 |
| Disposal |
413 |
117 |
72 |
2 |
|
|
|
116,700 |
| Low-Level Waste |
|
|
|
|
|
|
|
|
| Storage and Handling |
3,494 |
1,962 |
1,377 |
|
|
|
|
389,938 |
| Disposal |
1,085 |
176 |
55 |
|
|
|
|
66,189 |
| Hazardous Waste |
|
|
|
|
|
|
|
|
| Storage and Handling |
122 |
241 |
204 |
13 |
|
|
|
49,108 |
| Disposal |
18 |
35 |
30 |
2 |
|
|
|
3,395 |
| Sanitary Waste |
|
|
|
|
|
|
|
|
| Treatment |
|
|
|
|
|
|
|
4,125 |
| Disposal |
822 |
822 |
822 |
822 |
|
|
|
50,330 |
| Direct Program Management/Support |
10,197 |
7,798 |
6,742 |
4,485 |
|
|
|
1,057,214 |
| Total |
21,104 |
14,483 |
11,569 |
5,337 |
|
|
|
2,757,665 |
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars. |
LANDLORD ACTIVITIES
Landlord responsibility for Rocky Flats was transferred from the Office of
Defense Programs to the Office of Environmental Management in FY 1994. This
responsibility, which has been assumed by the Nuclear Material and Facility
Stabilization program, covers certain site-wide activities that are not
assigned to direct site programs. The landlord activities support the direct
programs and cover a wide range of site functions required for maintaining the
infrastructure at Rocky Flats. These functions include environmental
monitoring, infrastructure maintenance, safeguards and security, fire/security
system replacement, and health and safety.
Environmental monitoring includes monitoring and assessing air quality, chemical
tracking and reporting; surface water monitoring, assessment, and operations;
groundwater monitoring and geologic monitoring; ecology and National
Environmental Policy Act requirements for biological flora and fauna assessment
and protection; and environmental impact mitigation planning and documentation.
Numerous ongoing reporting activities maintain compliance with environmental
regulations.
Maintaining the infrastructure requires many types of refurbishment,
replacements, and upgrades. Because the facilities are aging, projects must be
completed to replace electrical, mechanical, or other infrastructure systems.
The decision to proceed with infrastructure replacement projects is made when
the cost of maintaining the system exceeds the cost of replacing it. Projects
at Rocky Flats include replacing the main site electrical substation, which is
expected to be completed in FY 1998, and replacing specific portions of the
plutonium heating, ventilation, and air conditioning system. A project also is
under way to upgrade, replace, or close underground storage tanks to meet
current regulations and performance standards. This project will be completed
in FY 1999.
Another important landlord responsibility involves safeguards and security to
protect Special Nuclear Material and site personnel. Several projects are
scheduled to ensure continuing success in this area. A replacement of the plant
annunciation system will ensure worker safety through the site-wide sounding of
alarms and dissemination of information. This replacement will be completed in
FY 2000. The Master Safeguards and Security Agreement requires the completion
of various projects to protect Special Nuclear Material. These projects include
upgrading perimeter intrusion equipment and adding a glovebox line to
consolidate plutonium.
The fire/security system will be replaced by FY 2000. It will provide a new
security alarm and fire alarm, upgrade the central and secondary alarm
stations, and reduce the size of the Protected Area, and the personnel access
control systems. This project is necessary to meet National Fire Protection
Association requirements, protect government-owned assets, and ensure the
safety and security of the public, workers, and the environment. This project
is phased so that its scope can be adjusted as fire and security requirements
change in response to Rocky Flats' new mission.
Health and safety encompasses nuclear safety, emergency management, industrial
hygiene, occupational safety, and radiation protection. The Department plans
several capital projects to upgrade Rocky Flats. They include new equipment,
air monitoring improvements, and health physics improvements. New equipment
such as an alpha spectroscopy analysis system and an emergency body counter are
needed to ensure the ongoing success of radiological protection. Air monitoring
improvements include a representative effluent sampler system and ambient air
particulate sampler system, both of which are required to comply with current
standards for radionuclide air monitoring. In addition, replacing two
alarm/monitoring systems in plutonium processing and support buildings will
meet current requirements for airborne alpha radiation monitoring.
Landlord Cost Estimate
|
(Five-Year Averages, Thousands of Constant 1996 Dollars)
|
| |
|
| Directly Appropriated Landlord |
107,886 |
104,469 |
104,604 |
103,364 |
104,322 |
102,658 |
104,678 |
|
| |
2060 |
2065 |
| Directly Appropriated Landlord |
80,851 |
36,845 |
29,507 |
7,803 |
1,221 |
|
|
4,441,038 |
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars. |
DESCRIPTION OF PERSONNEL
Current Composition
Current staffing requirements represent a site-wide mix of federal and
contractor personnel, which is presented in the table below. The federal work
force consists primarily of managers, administrators, professionals, engineers,
and scientists. This mix supports the oversight of site operations and
management of the interface between regulators, Headquarters, and other
organizations required to accomplish the mission and vision at Rocky Flats. The
contractor work force is primarily a mix of professional staff and labor
personnel who conduct the day-to-day site operations and plan and perform the
remediation of the site.
Full-Time Equivalent Composition Table *

* The Projections for Full-Time Equivalent employees are based on FY 1996
planning baselines (see Reader's Guide).
Site Management Structure
Kaiser-Hill operates the Rocky Flats Environmental Technology Site for the
Department of Energy under a performance-based Integrating Management Contract,
which began in July 1995 and is in place for the next five years. As part of
contract reform, Kaiser-Hill is responsible for integrating all contractors at
Rocky Flats. These subcontracts are for specific tasks for which Kaiser-Hill
and the various subcontractors will share the rewards or penalties of cost and
schedule underruns and overruns. The Department of Energy expects to achieve
substantial cost savings through these control reforms.
Future Full-Time Equivalent Needs
Based on the current site mission and the future scope of work assumed for this
report, future personnel needs at the site will include an increase in project
managers, cost estimators, and engineers, and a decrease in administrative and
clerical personnel.
|
CONTRACTING OPPORTUNITIES
If you would like more information about performing work for the Department of
Energy's Environmental Management program at this site, please contact:
|
Major Procurements
Charles Dan
Director
Contracts and Services Division
United States Department of Energy
Rocky Flats Office
P. O. Box 928, Building T131
Golden, CO 80402
p: (303) 966-8485
f: (303) 966-2994 |
Small Business Procurements
Tammie Lawler
Contracts and Services Division
United States Department of Energy
Rocky Flats Office
P.O. Box 928, Building T131
Golden, CO 80402
p: (303) 966-6155
f: (303) 966-2994 |
FUNDING ESTIMATE
The following table presents estimated funding information for the Rocky Flats
Environmental Technology Site.
Defense Funding Estimate
|
(Five-Year Averages, Thousands of Constant 1996 Dollars)
|
| |
|
| Nuclear Material and Facility Stabilization |
241,396 |
165,054 |
141,680 |
111,127 |
82,448 |
46,346 |
31,264 |
|
| Environmental Restoration |
97,560 |
69,281 |
91,614 |
99,732 |
132,253 |
162,277 |
226,501 |
|
| Waste Management |
104,659 |
81,515 |
77,132 |
73,791 |
75,891 |
56,131 |
29,920 |
|
| Directly Appropriated Landlord |
107,886 |
104,469 |
104,604 |
103,364 |
104,322 |
102,658 |
104,678 |
|
| Total |
551,501 |
420,318 |
415,030 |
388,014 |
394,914 |
367,413 |
392,363 |
|
| |
2060 |
2065 |
| Nuclear Material and Facility Stabilization |
9,230 |
8,676 |
6,000 |
6,000 |
|
|
|
4,246,111 |
| Environmental Restoration |
149,816 |
66,337 |
54,805 |
21,021 |
3,644 |
|
|
5,874,197 |
| Waste Management |
21,104 |
14,483 |
11,569 |
5,337 |
|
|
|
2,757,665 |
| Directly Appropriated Landlord |
80,851 |
36,845 |
29,507 |
7,803 |
1,221 |
|
|
4,441,038 |
| Total |
261,001 |
126,342 |
101,881 |
40,161 |
4,865 |
|
|
17,319,010 |
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars. |
COMPARISON WITH PREVIOUS ESTIMATE
The 1996 life-cycle cost estimate for the Environmental Management program at
the Rocky Flats Environmental Technology Site is $17.3 billion. This estimate
is 52 percent less than the 1995 life-cycle cost estimate of $36.6 billion,
after taking FY 1995 expenditures into account. The $19.0 billion reduction in
the program's estimated life-cycle cost reflects site-wide changes in work
scope and facility operation schedules. These changes are in response to
Defense Nuclear Facilities Safety Board Recommendation 94-1 and the
Department's Plutonium Vulnerability Assessment, which stipulate that the
consolidation, stabilization, and repackaging of vulnerable materials be
accelerated. The accelerated schedules are dictating near-term, site-specific
reprioritization efforts to redirect resources from other site programs to
plutonium stabilization and related risk-reduction activities. These changes
emphasize early action, reduction in waste generation, and modifications to
waste management strategies. The following sections highlight the major
differences between the 1995 and 1996 cost estimates for the Nuclear Material
and Facility Stabilization program, the Environmental Restoration program, and
the Waste Management program at Rocky Flats.
Nuclear Material and Facility Stabilization Program Overall Differences
The 1996 life-cycle cost estimate for the Nuclear Material and Facility
Stabilization program is $4.2 billion. This estimate is 78 percent higher than
the 1995 estimate of $2.6 billion, after taking FY 1995 expenditures into
account. The $1.9 billion increase in projected life-cycle cost is due to
accelerated schedules and expanded scope for facility stabilization activities,
the use of more accurate methods of cost estimating, and the inclusion of
direct program management costs.
The 1995 life-cycle estimate for Nuclear Material and Facility Stabilization
program activities was largely extrapolated from available complex-wide data
using a parametric modeling approach. This model assumed a 10-5-2 year schedule
for pre-stabilization surveillance and maintenance, deactivation/stabilization,
and post-stabilization surveillance and maintenance. The 1996 estimate is
predicated on assumptions developed at the site that more accurately reflect
and accommodate site requirements.
Although some of the 1996 assumptions reduced the program's projected life-cycle
costs, e.g., cost reductions directly tied to shortened surveillance and
maintenance schedules, more significant increases in stabilization and
deactivation costs offset these reductions. The projected increase in
stabilization costs primarily reflect the extension of the stabilization phase
to include removing Special Nuclear Material and Waste Management
program-stored waste.
Comparison Table
|
Thousands of Dollars
|
|
| Nuclear Mat. & Fac. Stab. |
2,598,336 |
207,709 |
4,246,111 |
1,855,484 |
78 |
| Environmental Restoration |
17,087,804 |
160,950 |
5,874,197 |
11,052,657 |
65 |
| Waste Management |
9,599,996 |
180,930 |
2,757,665 |
6,661,401 |
71 |
| Landlord |
2,796,494 |
117,900 |
4,441,038 |
1,762,444 |
66 |
| Program Management 2 |
4,528,573 |
36,780 |
- |
- |
- |
| Site Total |
36,611,203 |
704,350 |
17,319,010 |
18,587,843 |
52 |
1 The FY 1995 life-cycle and annual costs are provided
to determine the corrected FY 1995 cost.
2 Program Management was reported in an independent cost table last year, but
is reported as a line item in the relevant program (Nuclear Material and
Facility Stabilization, Environmental Restoration, and Waste Management)
activity cost estimate tables for the FY 1996 Baseline Report. |
Environmental Restoration Program Overall Differences
The 1996 life-cycle cost estimate for the Environmental Restoration program is
$5.9 billion. This estimate is 65 percent lower than the 1995 estimate of $17.1
billion. This $11.1 billion decrease in projected life-cycle cost is due
primarily to revised program assumptions, most of which have shortened the
program's projected life cycle.
The 1996 cost estimate assumes a more aggressive remediation schedule that is
largely predicated on applying risk-based cleanup standards. In contrast, the
1995 estimate assumed longer durations for assessment and remediation and used
residential level cleanup standards for most areas of the site, while deferring
decommissioning activities until the outyears. The reduction in cleanup targets
and added emphasis on remedial action rather than on assessment have
significantly lowered the remediation costs as well as the treatment, storage,
and disposal costs borne by the program.
Other factors that have contributed to lower projected costs in the 1996
estimate include: a reduction in the projected level of labor-intensive
decontamination before facilities are demolished, focusing remedial actions on
buffer zones and accessible areas that have been prioritized for cleanup, an
accelerated decommissioning schedule that reduces the amount of time the
facilities spend undergoing surveillance and maintenance prior to
decommissioning, and the anticipated use of an onsite Corrective Action
Management Unit and low-level waste disposal cell that would sharply reduce the
volume of waste requiring offsite shipment.
Waste Management Program Overall Differences
The 1996 life-cycle cost estimate for the Waste Management program is $2.8
billion. This estimate is 71 percent lower than the 1995 estimate of $9.6
billion, after taking FY 1995 expenditures into account. This $6.6 billion
decrease in projected life-cycle cost is primarily tied to major changes in
waste management strategies and significant reductions in waste stream
generation. In contrast to the 1995 cost estimate, the 1996 estimate plans for
fewer waste treatment facilities. The 1996 estimate assumes that storage will
occur outside the Protected Area, away from plutonium facilities, substantially
reducing the indirect support costs associated with environment, safety and
health activities, and security. The 1996 estimate also assumes that as
facilities are decommissioned some will be permitted or repermitted as storage
facilities, thereby avoiding new construction costs. In addition, the 1996
estimate assumes that onsite disposal will be conducted in a disposal facility
designed to meet Resource Conservation and Recovery Act performance standards,
leading to dramatic handling, shipping, and disposal cost reductions.
The 1996 estimated waste management life-cycle cost decreased substantially
because of a projected reduction in waste streams generation by stabilization
and remediation activities. This reduction is a result of the expedited
deactivation of buildings, reduced stabilization activities for residue
treatment, improved facility decommissioning strategies for decontaminating
metals, improved techniques for estimating decommissioning costs in the
outyears, and adopting a risk-based cleanup approach to remediation.
Nuclear Material and Facility Stabilization program and Environmental
Restoration program activities generate transuranic mixed and transuranic
waste. The combined total reduction in projected volumes of transuranic mixed
waste and transuranic waste is approximately 25 percent. The currently
projected volumes of low-level mixed and low-level waste that will be generated
by both programs are about 25 percent lower, respectively, than the 1995
estimate. The total reduction in projected volumes of hazardous waste is
approximately 25 percent. Similarly, the total reduction of the currently
projected volumes of sanitary waste is approximately 30 percent less than the
1995 estimate.
Landlord Overall Differences
The 1996 life-cycle cost estimate for Landlord costs is $4.4 billion. This
estimate is 66 percent higher than the 1995 estimate of $2.8 billion, after
taking FY 1995 expenditures into account.
|
 |