|
Home
BEMR
Contents
U.S.
Map
RMI Titanium Company Extrusion Plant (formerly known as Reactive Metals, Inc.)
is located in northern Ashtabula County, Ohio, about 5 kilometers (three miles)
northeast of the center of the City of Ashtabula and approximately one mile
south of Lake Erie. The plant is in a sparsely populated and highly
industrialized area. Several chemical production and metal conversion plants
are located nearby.
LOCALITY MAP
FACILITY MISSION
The RMI Titanium Company Extrusion Plant is a privately owned facility. From
1962 to 1988, the company received uranium billets and refined them into
various shapes for fuel and target fabrication use by the Department of Energy
and its predecessors. RMI also performed work for the Department of Defense and
a number of commercial entities under a Nuclear Regulatory Commission License.
Twenty-six years of handling, extruding, forging, and machining uranium at the
facility have resulted in onsite and offsite contamination of buildings and
environmental media. Contaminants consist of solvents and low-level
radionuclides.
SITE MAP
In 1990 all extrusion operations ceased and the project was transferred to the
Environmental Management program for environmental restoration. Decommissioning
and remediation activities at the site are projected to be complete in FY 2002.
Environmental restoration activities include remediation of local ground water,
surface soils, buildings, and associated processing equipment, as well as
landlord activities attributable to the Department of Energy. Areas needing
cleanup are being carefully monitored and, to date, pose no threat to the
health and safety of workers, the public, or the environment.
Remediation of the soil and ground water will be conducted in compliance with
the Resource Conservation and Recovery Act under the jurisdiction of the
Environmental Protection Agency, while decommissioning and dismantlement of the
facility will be conducted under the jurisdiction of the Nuclear Regulatory
Commission.
All waste management activities at the facility are performed within the scope
of the Environmental Restoration program. There are no current or planned
nuclear material and facility stabilization activities.
FUTURE USE
The overall goal of the project is to decontaminate facility equipment
buildings and release the facility and surrounding areas to the owner (RMI) for
Industrial/Commercial use in FY 2002. At that time, Department of Energy
liability at the site will end, and all future use decisions will rest with
RMI. Buildings below the free release criteria for the radiological
contaminants may be left onsite. Most will be disassembled and removed from the
site.
ENVIRONMENTAL RESTORATION
Environmental restoration activities at the RMI site currently include three
release sites: Corrective Action Management Unit ground-water and soils
cleanup, building and equipment decontamination and removal, and removal or
treatment of uranium-contaminated soils and restoration of the surrounding area
to "green field" status. It is estimated that remedial action and
decommissioning activities will generate approximately 38,781 cubic meters
(50,803 cubic yards) of low-level waste and 55 cubic meters (72 cubic yards) of
low-level mixed waste. See the Site Map for the location of Environmental
Restoration program activities.
Since the regulatory driver at RMI is not the Comprehensive Environmental
Response, Compensation, and Liability Act, there is no Record of Decision or
Compliance Agreement with any regulatory agency. Decommissioning activities are
being performed in accordance with the site decommissioning plan, which the
Nuclear Regulatory Commission approved. The RMI site maintains Resource
Conservation and Recovery Act permits for hazardous waste storage.
The Department of Energy has prepared a Site Treatment Plan under the Federal
Facility Compliance Act for treatment of mixed waste generated during the
environmental restoration of the RMI Facility. In October 1995, the Ohio
Environmental Protection Agency issued direction to the Department regarding
compliance with the Federal Facility Compliance Act.
Major Environmental Restoration Activity Milestones
| Corrective Action Management Unit
|
| Remedial Action Soils
|
2002
|
|
Remedial Action Ground Water
|
2015
|
|
Decommissioning
|
2002
|
|
Non-Corrective Action Management Unit Remedial Action
|
2002
|
Corrective Action Management Unit
RMI is undertaking a corrective action to remediate an area of soil and
ground-water contamination associated with the operation of the former
evaporation and seepage ponds. This area is a proposed Corrective Action
Management Unit and is regulated by Region V of the Environmental Protection
Agency.
ASSESSMENT
The RMI Plant Resource Conservation and Recovery Act permit required the plant
to complete a Facility Investigation on the Corrective Action Management Unit.
The issuance of the Resource Conservation and Recovery Act Facility
Investigation Equivalency document and the Supplemental Hydrogeological
Assessment in 1989, together with the Summary of Revised Estimates and Proposed
Cleanup Levels in 1991, satisfied this requirement.
Based on existing characterization information for this area, the
concentrations of radiological and hazardous contaminants in the Corrective
Action Management Unit exceed the proposed soil cleanup criteria. Uranium,
trichloroethylene, and technetium-99 are the contaminants of concern in the
soils and ground water.
In October 1992 the plant submitted a Corrective Measures Study to the
Environmental Protection Agency for the cleanup of the Corrective Action
Management Unit. The Environmental Protection Agency commented on the
Corrective Measures Study in FY 1994. RMI responded to these comments in FY
1995. The Environmental Protection Agency is currently reviewing RMI's
responses to its comments.
REMEDIAL ACTION
The proposed remedial strategy for radiologically contaminated soils would
consist of (1) excavating those soils containing radiological contaminants in
excess of the proposed cleanup levels, (2) relocation of the material to the
RMI plant material staging area, (3) packaging and shipment of radioactive soil
(approximately 29,000 cubic meters [37,990 cubic yards]) to the Nevada Test
Site, and (4) backfilling the excavated areas with clean soil.
Onsite treatment will be required to remove the trichloroethylene from soils
and ground water in this area. Remediation will involve, (1) excavation of
soils, (2) placement and containment of the soils in a temporary enclosure, and
(3) removal of the trichloroethylene from the soil by active or passive
volatilization. Using this approach, the soil cleanup level would be achieved
in approximately two years. After the contaminated soils have been removed, the
affected area will be returned to its original condition by, (1) backfilling
the excavated areas with clean soil, (2) regrading the area to the approximate
original contours, and finally (3) revegetating the area with wetland species
via natural colonization or planting with commercial seed/root stocks. The
disturbed area would be reconstructed to possess similar hydrologic and
vegetative characteristics currently featured in this area. Remediation of the
soils will be completed in FY 2002.
Remediation of the contaminated ground water in the Corrective Action
Management Unit involves the collection of the ground water using a subsurface
drain system, transfer to an air stripping unit, and removal of the
trichloroethylene from the water to the gas phase by forcing atmospheric air
countercurrent to the ground-water flow in the air stripping unit. The off-gas
effluent would be treated, monitored, and discharged to the atmosphere. The
treated liquid effluent would be transferred to the existing RMI plant
wastewater treatment facility where the uranium isotopes would be removed to an
acceptably low level.
LONG-TERM SURVEILLANCE AND MONITORING
Surveillance and monitoring activities required as a part of this remedial
activity include an annual ground-water and surface-water monitoring campaign
throughout the duration of the remedial action, an annual perimeter air
monitoring campaign and an annual soil sampling campaign. Surveillance and
monitoring of the soils will be performed during the three to five years of the
remedial project. Surveillance and monitoring activities of ground water will
continue until ground-water cleanup meets Environmental Protection Agency
standards. The Department expects completion of this activity in FY 2015.
| TECHNOLOGY DEVELOPMENT
As a part of the Ohio Field Office Site Technology Coordination Group, the
Ashtabula Area Office is currently researching alternative technologies to the
proposed pump-and-treat operations for the ground-water contamination at RMI.
The project is also researching soil processing technologies to reduce the
volume of soils for disposal from the decommissioning project. To date, several
soils processing projects have been completed with promising results. The
previous plans included packaging 27,667 cubic meters (36,244 cubic yards of
soil into containers for shipment via truck to the Nevada Test Site. The
recently proposed plans to use new technologies to process and dispose of soils
reduces the volume to approximately 5,183 cubic meters (6,790 cubic yards).
This effort may reduce soil volumes by over 75 percent and reduce the cost of
transportation and disposal of waste soils by approximately $16 million.
|
Noncorrective Action Management Unit Area Soils
Previous sampling and analysis efforts have confirmed the presence of
radioactive contamination in onsite soils, as well as some offsite areas
adjacent to the RMI plant site. Similar to the building contamination, the
radioisotopes of concern in the soil include uranium-234, 235, 238 and
technetium-99. A number of locations to the east and north of the site have
been identified as containing total uranium concentrations above background.
The alternative treatment technologies for cleanup of radiologically
contaminated soils in the Noncorrective Action Management Unit areas have been
evaluated. This baseline report assumes that cleanup of the soils consists of
excavating those soils containing radiological contaminants in excess of the
proposed cleanup levels. This step will be followed by backfilling the area
with clean fill materials and revegetation to prevent erosion. No long-term
surveillance and maintenance activities will be necessary; all activity will be
complete in FY 2002.
This report estimates that the soils in the Noncorrective Action Management
Unit areas will be below free-release limits will be used as fill for the
excavated areas. If characterization determines that the soils exceed
free-release limits, the low-level waste will be packaged and shipped to
Envirocare of Utah.
DECOMMISSIONING
Characterization of the 25 buildings and structures at the RMI site indicate
that the most of the buildings, equipment, slabs and subslab soils are
contaminated to some extent with uranium.
Buildings below the free-release criteria for radiological contaminants may be
left onsite. Most of the buildings will be disassembled and removed from the
site. Contamination on the slab and subslab will also be removed. This report
expects that activities will be completed by FY 2002.
The proposed decommissioning and remediation activities at the RMI plant will
be in compliance with the requirements of the Nuclear Regulatory Commission
regarding site cleanup. These activities will include: decontamination and
decommissioning of site structures and buildings, materials, and equipment;
remediation of contaminated soil beneath buildings; construction of temporary
onsite decontamination and decommissioning support structures and treatment
facilities; disposition of associated waste generated during the site
decontamination and decommissioning (including any new structures); and soil
and ground-water remediation.
Following completion of all onsite and offsite cleanup activities, the entire
facility will be subject to a final radiological survey required for license
termination. An independent survey commissioned by the Nuclear Regulatory
Commission will validate the results of this survey. The validated final survey
will confirm that the required cleanup levels and/or criteria for free release
have been attained.
The current focus of surveillance and maintenance activities includes
characterization, survey, and cleanup and removal of equipment in preparation
for decommissioning work. Also included are handling and disposal of existing
legacy waste stored at the RMI facility. Legacy waste will be removed prior to
the startup of any decommissioning activities. Approximately 610 cubic meters
(799 cubic yards) of low-level waste will be transported to the Nevada Test
Site. Fourteen cubic meters (18 cubic yards) of asbestos and 266 cubic meters
(350 cubic yards) of radioactive asbestos will be generated and disposed of at
the Nevada Test Site.
Low-level mixed waste will be managed in compliance with the requirements of
the Federal Facility Compliance Act Site Treatment Plan. Currently, the RMI
site stores 35 cubic meters (46 cubic yards) of mixed waste. This report
assumes an additional 20 cubic meters (26 cubic yards) will be generated.
Therefore, a total of 55 cubic meters (72 cubic yards) will be disposed of at
the Toxic Substances Control Act Incinerator at the K-25 Site at Oak Ridge
National Laboratory.
The decommissioning of the onsite hazardous waste storage structure will
proceed in accordance with the closure requirements of the Resource
Conservation and Recovery Act permit, as well as the RMI Decommissioning Plan
described above.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2020
|
2025
|
2030
|
| Reactive Metals, Inc.
|
|
|
|
|
|
|
|
|
| Assessment
|
2,432
|
793 |
|
|
|
|
|
16,121
|
| Remedial Action
|
14,478
|
6,585
|
75
|
271 |
|
|
|
107,043
|
| Direct Program Management/Support
|
1,168
|
457
|
|
|
|
|
|
8,125
|
| Total
|
18,078
|
7,834
|
75
|
271 |
|
|
|
131,289
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Direct Program Management/Support
Program management at RMI is concerned with decontamination and remediation
planning, project control and decommissioning management. RMI does not fund any
grants or Agreements-in-Principle at this time. RMI is listed as a Principal
Responsible Party for the remediation of the Fields Brook Superfund site and
has, to date, paid a share of Fields Brook costs. The Department of Energy is
not a Principal Responsible Party; however, the Department pays one-third of
the cost because the RMI Titanium Company Extrusion Plant is one of three RMI
sites with an outfall to Fields Brook.
| COST SAVINGS
In 1995 the Department of Energy listed RMI as one of 22 projects in the Small
Sites Acceleration Initiative, which was designed to accelerate the cleanup of
these sites and concentrate future Department resources on sites that require
more time, money and, effort. The Department expects the acceleration of the
project to result in substantial cost savings. Increased resources in the
earlier stages of the remedial action will allow the schedule to be shortened
by as much as two years and will save approximately $1.1 million from the costs
proposed in the Nuclear Regulatory Commission Site Decommissioning Plan.
|
Future activities will focus on procurement and management of architectural
engineering and major remediation subcontracts.
| STAKEHOLDER INTERACTIONS
The Ohio Operations Office had responsibility for public participation
activities for four Ohio sites: Battelle Columbus Laboratories, Fernald
Environmental Management Project, Mound Plant, and RMI Titanium Company. RMI
presented Baseline Environmental Management Report issues at meetings with the
Ashtabula Citizens Advisory Panel. In addition, the 1995 Baseline Environmental
Management Report was made available at the Kent State Ashtabula Campus
Library. If you would like more information about the report or have questions
about the results for these sites, please contact:
|
| Reactive Metals, Inc.
|
|
|
Public Participation
Ward Best
(216) 993-1944
ward4@aol.com
|
Technical Liaison
Pat Shirley
(513) 865-4298 patricia.shirley@em.doe.gov
|
Public Affairs
Ward Best
(216) 993-1944 wardb4@aol.com
|
LANDLORD ACTIVITIES
Landlord costs include security for buildings and grounds, maintenance and
testing of site equipment, maintenance of site utilities, and equipment
procurement. Landlord costs will end by FY 2005 when the remedial action
activities are completed and long-term surveillance and monitoring are under
way. This report assumes that after FY 2005, all landlord activities will be
the responsibility of the RMI Titanium Company.
Landlord Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2010
|
2015
|
2020
|
2025
|
2030
|
| Directly Appropriated Landlord
|
1,597
|
245
|
|
|
|
|
|
9,214
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
DESCRIPTION OF PERSONNEL
Current Composition
The current work force mix of federal contractor and subcontractor employees is
presented in the table below. The federal work force is made up of managers,
administrative support and engineers. The contractors and subcontractors are a
mix of professional and labor personnel who conduct the day-to-day site
operations and plan and conduct site remediation.
Full-Time Equivalent Composition Table*
* The Projections for Full-Time Equivalent employees are based on FY 1996
planning baselines (see Reader's Guide).
Site Management Structure
The RMI site is privately owned and operated under a Decontamination and
Decommissioning Contract through the Department of Energy Ohio Field Office.
The site is unique in the Department's system because RMI is the landlord as
well as the contractor. The RMI Titanium company provides surveillance and
maintenance services for the privately owned facility. Architect-engineering
services are subcontracted, and other site services are managed on fixed price
subcontracts. The actual decontamination and decommissioning work will be
subcontracted to a qualified contractor using a fixed fee incentive contracting
strategy. Competing contracts support contract reform efforts to the greatest
extent possible and provide incentives for those agreements as appropriate.
| CONTRACTING OPPORTUNITIES
If you would like more information about performing work for the Department of
Energy's Environmental Management program at this site, please contact:
|
Major Procurements
Mona Snyder
Director
Procurement and Contracts Division
United States Department of Energy
Ohio Field Office
P.O. Box 3020
Miamisburg, OH 45343-3020
p: (513) 847-5295
f: (513) 865-3843
|
Small Business Procurements
Melissa Johnson
Procurement and Contracts Division
United States Department of Energy
Ohio Field Office
P.O. Box 3020
Miamisburg, OH 45343-3020
p: (513) 847-4569
f: (513) 865-3843
|
Future Full-Time Equivalent Needs
Decommissioning and remediation activities will begin in FY 1997. The personnel
mix will remain relatively constant through FY 2001 because the project will be
in the latter stages of completion. The number of Full-Time Equivalents will
decrease by approximately 50 percent in FY 2002, the final year of restoration
activities. This report expects this decrease to be evenly distributed across
all categories.
FUNDING ESTIMATE
The following table presents estimated funding information for the RMI Titanium
Company Extrusion Plant.
Defense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2020
|
2025
|
2030
|
| Environmental Restoration
|
18,078
|
7,834
|
75
|
271
|
|
|
|
131,289
|
| Directly Appropriated Landlord
|
1,597
|
245
|
|
|
|
|
|
9,214
|
| Total
|
19,675
|
8,080
|
75
|
271 |
|
|
|
140,503
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
COMPARISON WITH PREVIOUS ESTIMATE
The 1995 RMI Baseline Environmental Management Report Base Case did not reflect
the RMI Decommissioning Plan. The reported estimate was based on an independent
third-party evaluation. The 1996 RMI Base Case is consistent with the estimate
submitted with the RMI Nuclear Regulatory Commission Site Decommissioning Plan.
Improved remediation strategies and completion of characterization has
contributed to a more precise cost estimate. The Corrective Action Management
Unit has employed the newer strategy of shipping low-level soils to Envirocare
of Utah instead of shipping to the Nevada Test Site. Use of this strategy
produces a savings of approximately $156,000.
The previous cost estimate included costs for dismantlement, size reduction,
and packaging of the building materials into shipping containers. The packaged
material would be shipped via truck to the Nevada Test Site. The previous RMI
estimated costs for the building and equipment remediation were $57.7 million
over 15 years. In the current cost estimate, based on the Decommissioning Plan,
estimated costs are $56.7 million over seven years. This savings is based on
improved waste disposal methods and an accelerated schedule.
Incomplete characterization data for the Noncorrective Action Management Unit
soils led to the previous estimate of $47 million. Data, which was validated in
the 1995 RMI Site Characterization report, provided the foundation of an
amended estimate of $53.6 million. This estimate does not consider cost
efficiencies that may be realized from implementing new technologies. It does
include projected cost savings that will be realized by shipping the material
by rail to Envirocare of Utah.
Project planning has been revised to reflect an expedited project funding
scenario in line with the Department of Energy Small Sites Acceleration
Initiative. This initiative will result in the completion of RMI
decommissioning activities, with the exception of ground-water remediation, by
FY 2002. The previous estimate for program management was $16.5 million,
compared with the current estimate of $10.2 million, and the previous estimate
for landlord activities was $18.5 million, versus the current estimate of $11
million.
The revised management strategy, which includes reduced program management and
landlord costs, has resulted in an increase in surveillance and monitoring
costs from the previous estimate of $16.5 million to a current estimate of $18
million.
|