|
Home
BEMR
Contents
U.S.
Map
The Rulison and Rio Blanco sites are administered at the Nevada Operations
Office. A more thorough description of the environmental activities managed by
the Nevada Operations Office can be found in the Nevada
Offsite narrative. The Rulison site is located 22 kilometers (14
miles) southwest of Rifle, Colorado. The Rio Blanco site is located 58
kilometers (36 miles) northwest of Rifle, Colorado.
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
| |
|
|
|
| Environmental Restoration
|
637
|
2,118
|
206
|
1,934
|
98
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
675
|
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
128
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2030
|
| Environmental Restoration
|
949
|
314
|
27
|
22
|
12
|
8
|
|
6,657
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The Department conducted the Rulison and Rio Blanco tests under the Plowshare
Program, which was a series of nuclear and conventional tests conducted by
Atomic Energy Commission to explore peacetime uses of nuclear explosives. The
Rio Blanco and Rulison tests were designed to increase natural gas production
from low-permeability sandstone. The Project Rulison detonation took place in
September 1969 at a depth of 2,568 meters (8,426 feet) in a sandstone formation
near Rifle, Colorado. The shot was the second of the gas production stimulation
experiments in the Plowshare Program. The Project Rio Blanco test, which was
located approximately 36 miles northwest of Rifle, consisted of the nearly
simultaneous detonation of three 33-kiloton devices in a 2,130 meter (7,000
feet) well in May 1973. The Rio Blanco test was the third gas production
stimulation experiment in the Plowshare Program. Contamination is present as a
result of the activities conducted on the sites in conjunction with the gas
stimulation testing and gas flaring operations.
At the Rio Blanco site, contamination consists of radioactive contamination of
the deep bedrock around the shot cavities; contamination of a deep zone in FCG
Well No. 1, in which contaminated water from the production testing and
decontamination operations was injected; possible surface contamination from
the gas flaring activities; and near-surface hazardous waste contamination from
the closed mud pits. Ground water is the most likely transport medium for the
deep contamination; however, because of the depth of the contamination (in
excess of 1,500 meters [5,000 feet]), exposure to humans from this material is
unlikely. The Department has not confirmed the existence of the surface and
near-surface contamination. The Department cleaned up the site in 1976, and all
surface contamination was reported to have been shipped to the Nevada Test Site
for disposal. However, this cleanup was not well documented and may not meet
today's standards.
The Rulison site includes radioactive contamination of the deep bedrock around
the shot cavity, possible surface contamination from the gas flaring and
decontamination activities, and near-surface hazardous waste contamination from
the closed mud pits. Ground water is the most likely transport medium for the
deep contamination; however, because of the depth of the contamination (in
excess of 2,568 meters [8,426 feet]), exposure to humans from this material is
unlikely. There has been no confirmation of the existence of surface
contamination from the gas flaring and decontamination operations or the
abandoned drill-back mud pit. The site was remediated in 1972 and again in
1976, and all surface contamination was reportedly cleaned up and shipped to
the Nevada Test Site for disposal. However, the Department has confirmed
additional contamination is present. It consists of diesel fuel and heavy
metals in the pre-shot drilling mud pit. The Department is currently in the
process of addressing this additional contamination. Surface water and
near-surface ground water are the most likely transport mechanisms for the
surface contamination; however, no domestic wells use the near-surface aquifer,
and the site uses surface water primarily for irrigation.
FUTURE USE
The only negotiations the Department has conducted with the State of Colorado
have concerned remediation goals for the pond at the Rulison site. The
Department has not completed a definitive plan or an agreement with the State
for either Rulison or Rio Blanco. However, this report assumes the surface of
the sites will be cleaned to a level that permits Recreational use. The
subsurface of the sites will remain Controlled Access. The Department of Energy
will maintain institutional control of the subsurface and retain all mineral
rights; any disturbance of the subsurface (for example, well drilling, mining,
excavation) will require Department approval. The final future use will be
negotiated with the State of Colorado. The Department will maintain both sites
under a mix of Industrial, Open Space, and Controlled Access use until remedial
action is complete.
ENVIRONMENTAL RESTORATION
The cleanup strategy will be to characterize ground-water flow and area of
contamination, assess risk, and model contaminant movement away from the shot
cavities. The focus will be on tritium, since it is the most mobile of the
potential radiological contaminants. Attenuation characteristics provide for
little migration of other radionuclides. However, other radionuclides will be
evaluated if tritium migration indicates that they need to be included in the
source evaluation. Maximum use will be made of existing data, including
monitoring data collected from the Long-Term Hydrologic Monitoring Program well
networks.
Cost estimates for this report assume subsurface waste in and around the shot
cavities will not be removed, and long-term monitoring will continue. Surface
remediation activities will depend on the type and quantity of contamination
and the available remediation technologies and their effectiveness. This report
also assumes hazardous waste will be shipped to a commercial facility for
disposal.
Major Environmental Restoration Activity Milestones
| Rio Blanco
|
| Preliminary Site Characterization Report
|
1996
|
|
Risk Assessment Report
|
1999
|
|
Work Plan for Assessment/Remediation
|
1999
|
|
Installation of Two Additional Monitoring Wells (Deep Aquifer)
|
2000
|
|
Remediation of Mud Pits
|
2000
|
|
Post-Closure Monitoring Program
|
2025
|
|
Rulison
|
| Preliminary Site Characterization Report
|
1996
|
|
Risk Assessment Report
|
1996
|
|
Remediation of Drilling Effluent Pond
|
1996
|
|
Installation of Two Additional Monitoring Wells (Low-Pressure Zone)
|
1997
|
|
Post-Closure Monitoring Program
|
2025
|
ASSESSMENT
Assessment activities will define the magnitude and extent of surficial
contamination and the associated risks to human health and the environment
through the evaluation of existing information on the two test areas. The
evaluation process will include characterization of the physical setting to
determine the presence of contamination and identification of pathways to
potential receptors. Evaluators will use standard risk assessment procedures to
calculate risks to receptors. If risks exceed acceptable limits, the Department
will establish the requirements for risk reduction through remediation or other
actions.
Completed activities include annual monitoring of the site, sampling the
drilling effluent pond at Rulison, dewatering the drilling effluent pond, and
stabilizing the sediment in the pond. The stabilized sediment at Rulison has
been hauled to the disposal facility. Assessment activities at the Rulison site
have found no ground water contamination; however, the mud pit contained
approximately 16,000 cubic meters (21,000 cubic yards) of sediment and soil
contaminated with metals and petroleum hydrocarbons (hazardous waste). Rio
Blanco assessment activities are scheduled to begin in FY 1996. This report
assumes results for the Rio Blanco site assessment will mirror those obtained
during the Rulison site assessment.
Since 1979, the Department has monitored the surrounding areas of the two sites
as part of the Long-Term Hydrologic Monitoring Program. Because ground water
has not been impacted by these sites, this program is assumed to continue
through the completion of assessment and remedial action (FY 2005). Monitoring
consists of sampling from selected ground-water and surface-water collection
locations around each site. Sampling requires approximately one week per year
per site, plus analyzing approximately 20 samples per site per year. The
Department funds the program, and the Environmental Protection Agency operates
it under a Memorandum of Understanding. Monitoring required as a result of
Resource and Conservation Act closure activities is discussed in the Long-Term
Surveillance and Monitoring section below.
REMEDIAL ACTION
Surface contamination at both facilities is the result of fallout from the gas
flaring and equipment decontamination operations and near-surface hazardous
waste contamination from the closed mud pits. Contamination consists of soil
contaminated with metals and petroleum hydrocarbons. This estimate assumes that
the remedial action at the sites will include removing the pond sediment from
the drilling mud pit at Rulison and removing contaminated surface soils
associated with drilling mud at Rio Blanco.
Remediation of the mud pit at Rulison began in FY 1995. Approximately 16,000
cubic meters (21,000 cubic yards) of hazardous waste (contaminated soils) was
generated when the sediment was exhumed and stabilized with kiln dust. The
waste was staged onsite and then sent offsite to an appropriately permitted
commercial disposal facility. All remedial action at this site will be complete
in FY 1996.
This report assumes the remedial action at Rio Blanco will be complete in FY
2005. Remedial actions will be based on a risk assessment approach that is
determined during the assessment and characterization of the site.
LONG-TERM SURVEILLANCE AND MONITORING
This report assumes post-closure monitoring of the sites will involve yearly
monitoring for an assumed duration of 30 years. This report assumes that
the approach will comply with the provisions of the Resource Conservation and
Recovery Act and will require the installation of two additional wells at each
site. However, the Department has not yet negotiated the monitoring strategy
with the state.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2030
|
| Nevada Offsite - Rio Blanco
|
|
|
|
|
|
|
|
|
| Assessment
|
92
|
77 |
|
|
|
|
|
846 |
| Remedial Action
|
721
|
220 |
|
|
|
|
|
4,705 |
| Nevada Offsite - Rulison
|
|
|
|
|
|
|
|
|
| Assessment
|
5
|
|
|
|
|
|
|
26
|
| Remedial Action
|
110
|
|
|
|
|
|
|
550
|
| Long-Term Surveil. And Monitoring
|
21 |
16
|
27 |
22
|
12 |
8
|
|
530 |
| Total
|
949
|
314 |
27
|
22 |
12
|
8 |
|
6,657 |
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FUNDING ESTIMATE
The following table presents estimated funding information for the Rio Blanco
and Rulison sites.
Defense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2030
|
| Environmental Restoration
|
949 |
314
|
27 |
22
|
12 |
8
|
|
6,657
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
COMPARISON WITH PREVIOUS ESTIMATE
Environmental Management program costs at the Rio Blanco and Rulison sites are
limited to Environmental Restoration program assessment, remediation, and
surveillance and monitoring costs. The 1996 life-cycle cost estimate is $6.6
million, a slight increase over the 1995 estimate of $5.1 million. The increase
reflects the inclusion of an environmental restoration contingency that was not
assumed in the 1995 estimate.
|
 |