|
Home
BEMR
Contents
U.S.
Map
The Portsmouth Gaseous Diffusion Plant is located in south central Ohio,
approximately 32 kilometers (20 miles) north of Portsmouth, Ohio, and 112
kilometers (70 miles) south of Columbus, Ohio. The site is situated on a
1,483-hectare (3,708-acre) federal reservation approximately 6.5 kilometers (4
miles) south of the Village of Piketon.
LOCALITY MAP
Estimated Site Total
|
(Thousands of Current Year Dollars)
|
| |
|
|
|
|
Environmental Restoration
|
76,089
|
75,458
|
56,535
|
62,082
|
78,239
|
Grey shaded area reflects annual cost estimates for the first five years of
the site BEMR Base Case (as of October 1995) and includes 3% annual inflation,
see Readers' Guide.
|
|
1996 Appropriation
|
58,955
|
|
|
These levels reflect the current estimates for compliance with applicable
statutes and agreements (as of March 1996), see Readers' Guide.
|
|
1997 Congressional Request
|
|
60,837
|
|
|
|
(Five-Year Averages, Thousands of Constant 1996 Dollars)
|
| |
|
|
Environmental Restoration
|
65,793
|
65,593
|
274,333
|
301,952
|
5,945
|
63,346
|
14,557
|
|
| |
2040
|
2045
|
2050
|
2055
|
2060
|
2065
|
|
Environmental Restoration
|
414
|
|
|
|
|
|
|
3,959,670
|
|
* Total Life Cycle is the sum of the annual costs in constant FY 1996
dollars.
|
FACILITY MISSION
Construction of the Portsmouth Gaseous Diffusion Plant began in late 1952 to
expand the Federal Government's gaseous diffusion program already in place at
Oak Ridge, Tennessee and Paducah, Kentucky. The facility was built to increase
the production of enriched uranium at rates substantially above the other two
facilities because highly-enriched uranium was required for use in nuclear
submarine reactors, and low-enriched uranium was needed for commercial nuclear
power plants. The first process cell went online in September 1954. A gas
centrifuge uranium enrichment program was initiated in the early 1980s at
Portsmouth. However, full operation was never implemented for the centrifuge
process.
SITE MAP
Currently, the Portsmouth Gaseous Diffusion Plant has two primary missions. The
first mission continues to be the enrichment of uranium by a gaseous diffusion
process. Since 1991, the plant has produced only low-enriched uranium for use
as fuel in commercial nuclear power plants. On July 1, 1993, the United States
Enrichment Corporation, a government corporation formed under the Energy Policy
Act of 1992, assumed operations of the production portion of the plant. The
Department of Energy retained responsibility for environmental restoration and
related waste management activities which comprise the second primary mission
of the plant. These activities focus on environmental remediation efforts;
environmental compliance; storage, treatment, and/or disposition of waste; and
the decommissioning of inactive and surplus facilities.
This estimate for decommissioning the Portsmouth Gaseous Diffusion facilities
assumes an approach for recycling process equipment and other radioactive
metals into usable products and onsite disposal of low-level and mixed
radiological waste from decommissioning activities. Although this estimate is
preliminary, and not yet in the Environmental Restoration life-cycle baseline,
it adopts a simpler and less restrictive approach to dealing with these
radiologically contaminated facilities. This estimate assumes that the plant
will discontinue production in FY 2005, and that decommissioning work can begin
as early as FY 2007. However, the actual timing of the shutdown of operations
has not been decided. This estimate assumes that the Department's Environmental
Management program will assume landlord responsibilities at the site in FY 2005
and will continue in this capacity until decontamination and decommissioning
activities are complete. All waste management activities at the Portsmouth
Gaseous Diffusion Plant are included within the scope of the Environmental
Restoration program.
Landlord activities are the responsibility of the Department of Energy's Uranium
Enrichment program's. This report assumes that responsibility will continue
until the shutdown of operations, when it will transfer to the Environmental
Restoration program.
FUTURE USE
Future land use of the site will be determined at a later date. However, since
long-term surveillance, maintenance, and institutional controls will continue
indefinitely, limiting future uses, this report assumes that the Federal
Government will use the site for some type of Industrial use.
FUTURE USE MAP
The decommissioning estimate in this report assumes that all gaseous diffusion
facilities will be removed to grade. The site landscape will be significantly
changed; low disposal mounds will be located where former structures stood. To
the extent practical, auxiliary building rubble will be placed in one of the
process building mounds. An onsite disposal cell for decommissioning waste will
undergo closure and will be under long-term monitoring. Other facilities (e.g.,
centrifuge facilities) will be reused for other restricted activities
consistent with the stakeholders' land-use decision for the site.
|
CURRENT USES OF THE PORTSMOUTH FACILITIES
Approximately 250 of the 320 facilities at the plant are currently being
used for uranium enrichment production by the United States Enrichment
Corporation under a 6-year lease agreement signed in 1993 with Department of
Energy. If the corporation decides to return these leased facilities to the
Department, a two-year notification will be required. In addition, the
Department has signed lease agreements with the Ohio National Guard and the
Defense Logistics Agency allowing them to use some of the former gas centrifuge
enrichment plant facilities onsite. The Ohio National Guard occupies a mobile
equipment garage, approximately 40 percent of the gas centrifuge plant's Feed
and Withdrawal Building, and some outside areas to store equipment on the plant
site. More than 70 employees are engaged in Ohio National Guard activities to
refurbish vehicles from the European Theater for the U.S. Army. The Defense
Logistics Agency has leased one of the two gas centrifuge plant's process
buildings to store equipment. No full-time employees are involved in the
Defense Logistics Agency's activities onsite.
|
ENVIRONMENTAL RESTORATION
Corrective actions are being performed at the Portsmouth facility in compliance
with the Resource Conservation and Recovery Act, under the oversight of the
Environmental Protection Agency and the Ohio Environmental Protection Agency.
The site has not been placed on the National Priorities List; therefore, the
Comprehensive Environmental Response, Compensation, and Liability Act is not
the primary driver for cleanup actions.
The cleaning and changeout of process equipment at the Portsmouth Plant
generated spent solvents and other contaminants that were disposed of in onsite
landfills and surface impoundments. The contaminants include chlorinated
solvents, such as trichloroethylene, chlorinated solvents mixed with
radionuclides in low concentrations, metals, and polychlorinated biphenyls.
Additional sources of contamination are uranium deposits in process equipment
and radionuclides in buildings, cooling towers, burial grounds, and wastewater
ponds. Trichloroethylene is the main contaminant of concern in the ground-water
systems at the Portsmouth site. To date, no ground-water contamination has
migrated offsite.
To facilitate the remediation and restoration process, the site was divided into
four quadrants, based in large part on ground-water flow. Quadrants with
greater potential risk from ground-water contamination were designated as
higher priority and were investigated first. Since the development of
investigation and corrective measures, the regulatory agencies have begun to
approach remediation on a unit-by-unit basis; therefore, the site will be
described below as a whole.
The scope of the Environmental Restoration program incudes the costs associated
with characterizing, packaging and shipping waste. The treatment, storage, and
disposal of waste shipped offsite to commercial facilities is also included
within the scope of the Environmental Restoration program at Portsmouth.
Major Environmental Restoration Activity Milestones
|
Quadrants I-IV
|
|
Assessment
|
2020
|
|
Remedial Action
|
2035
|
|
Decommissioning
|
|
Assessment
|
2009
|
|
Decommissioning
|
2025
|
Quadrants I-IV
ASSESSMENT
All four quadrants at the Portsmouth Gaseous Diffusion Plant have been
characterized through sampling from more than 550 ground-water monitoring wells
and over 400 soil borings. A second, confirmatory phase of the investigation
was completed at the plant in 1994. Other investigations have also been
completed in conjunction with the Resource Conservation and Recovery Act
corrective action process. An extensive air quality investigation was conducted
where a total of 15 ambient air samplers and 7 radionuclide samplers were
installed at onsite and offsite locations to collect data on air quality. A
baseline ecological risk assessment was conducted to study the creeks, aquatic
life, surface waters and sediment toxicity, plants, animals, endangered
species, and wetlands at and near the plant. A study to determine background
levels of naturally occurring radionuclides and metals was conducted in FY 1994
to assess environmental conditions surrounding the plant. Samples were taken
from 20 different locations that were pre-approved by the regulatory agencies,
to provide information on radionuclides and metals and help determine
background levels in establishing cleanup levels at the plant.
Sampling performed as part of the environmental restoration efforts has
determined that soil and ground water underlying some areas of the plant have
been contaminated with various solvents, such as trichloroethylene, that were
commonly used to degrease equipment. To a lesser degree, uranium, technetium,
and metals have also been detected in soils and ground water. Two aquifers
beneath the plant store and supply ground water; one is shallow and one is
deep. To date, studies indicate that ground-water contamination is limited to
the shallow aquifer, which is not of sufficient volume to be used for drinking
water. Offsite sampling has shown residual minor levels of radiological
contamination in some stream sediments but not at concentrations that pose a
health risk to the public. Risk assessors have determined that remediation of
these low levels of contaminants would cause more negative impact to the
ecosystems in the streams than would leaving the soils undisturbed. Offsite
residential well sampling has not detected any contamination. The air study
showed no unacceptable risks to humans or the environment.
A ground-water protection program has been established for the Portsmouth site.
Its purpose is to coordinate and support environmental restoration projects
concerned with or affecting the ground water. This program is also responsible
for operating and maintaining the ground-water treatment facilities at the
Portsmouth Plant. This program also manages any interim actions required to
stop the migration of ground water offsite. Ground water is sampled at specific
wells installed in and around the plant to determine the extent of any
contamination, to identify the contaminants, and to determine their sources.
The potential release site investigations performed for the environmental
restoration activity helped the characterization effort. Additional
ground-water sampling and modeling have also been performed to monitor the rate
of contaminants and to determine the extent of contamination. A ground-water
remediation project currently under construction will test different methods of
passive contaminated ground-water treatment. Upon completion of the
treatability tests, a plan for enhanced ground-water remediation will be
prepared. This report assumes that all assessments for Quadrants I-IV will be
completed by FY 2020.
REMEDIAL ACTION
Soon after environmental restoration started, five of the potential release
sites were identified as requiring no further action. Since then, eight more
sites (chromium sludge lagoons, a landfill for the disposal of contaminated
materials, a landfill for the disposal of classified materials, an incinerator,
chromium sludge monocells, a restricted waste storage facility, a waste oil
tank, and a storage facility) have been certified for closure. Remedial actions
have been completed at four other sites (an unrestricted waste storage
facility, a chromic acid tank, a solid waste landfill, and an engineered cap
over a landfill). Interim measures were implemented to contain contaminants,
including construction of an in-ground slurry wall and a seep collection
system.
Ten underground and above-ground storage tanks were within the scope of the
environmental restoration activity at Portsmouth. Three of these tanks were
never placed into service and were removed. One underground storage tank did
not pass tightness tests and has been removed. Six abandoned above-ground
storage tanks were also demolished. Surrounding soils were characterized and,
where necessary, excavated and treated according to regulatory limits on
petroleum contamination in soil.
Remedial actions are under way or are being planned for seven other potential
release sites, including two holding ponds, a radiological storage yard, a
neutralization pit, a waste neutralization pit, a waste oil tank and facility,
and an oil biodegradation plot. Individual units that may require remediation
in the future are as follows.
The X-120 Goodyear Training Facility was part of the original construction of
the plant and included the training center, a paint shop, a welding shop, a
sheet metal shop, and two warehouses. All the structures associated with this
facility were demolished and removed during the Gas Centrifuge Enrichment Plant
construction activities in the early 1980s. Contaminants identified in the
investigation were arsenic and antimony in surface soil. If the regulatory
agencies decide that remediation is needed, this report assumes that activities
will be completed by FY 2025, and that soil will be excavated and moved to an
onsite landfill.
The X-626 Recirculating Cooling Water Pump House and Cooling Tower consists of
approximately 651-square meter (777 square yards) pump house and an eight-cell
cooling tower with associated catch basin. Surface soil contamination of
cadmium and beryllium was found in surface soil approximately 25 meters (33
yards) northwest of the pump house. This estimate assumes that the remedial
action will include excavating soil, with disposal to an offsite Resource
Conservation and Recovery Act landfill, solidification/stabilization and onsite
disposal, or soil washing and disposal onsite.
The 5-Unit Investigative Area consists of an area of ground-water contamination
under five solid waste management units in the central part of the plant
located east and south of the X-326 Process Building. Contaminants included
seven inorganics (antimony, arsenic, beryllium, cadmium, chromium, thallium,
and vanadium) and five organics (acrolein, chloroform, 1,1-dichloroethene,
tetrachloroethene, and trichloroethene). A decision regarding a specific
remedial action is not expected until FY 1996 or later. However, this estimate
assumes that ground-water remediation will include some form of collection and
treatment, with disposal through the plant water treatment system. Treatment
may require additional facilities beyond those presently operating at the
plant.
The X-747F Miscellaneous Materials Storage Yard is a 3.6-hectare (9.1-acre) area
located south of the X-720 Maintenance Building. It consists primarily of open
grassy areas, with some patches of asphalt and gravel. It is used to store
miscellaneous equipment and material. Ground-water contamination from
beryllium, cadmium, chromium, and vanadium was found during investigation. A
decision regarding a specific remedial action is not expected until FY 1996 or
later. However, this estimate assumes that the remedial action will include
some form of ground-water extraction and treatment. This approach would require
installing vertical or horizontal wells and might also require treatment
equipment not already available onsite.
The X-633 RCW Pump House/Cooling Towers have operated since 1955 and are located
northeast of the X-333 Process Building. Investigation found ground-water
contamination from 10 inorganics: (arsenic, beryllium, cadmium, chromium, lead,
nickel, silver, thallium, vanadium, and zinc). A decision regarding a specific
remedial action is not expected until FY 1996 or later. However, this estimate
assumes that the remedial method will include some form of ground-water
extraction and treatment. Installation of vertical or horizontal wells would be
needed as well as treatment equipment not presently in service at the plant.
The X-744G Bulk Storage Building, which was built as a pipe yard, is located
southeast of the X-333 Process Building. X-744G is an 8,184-square meter
(9,768-square yard) building that has been in service since 1956. From 1957 to
1992, it warehoused uranium hexafluoride cylinders. From the late 1960s until
1981, part of the facility was used to melt aluminum parts into aluminum
ingots. In 1992, all Resource Conservation and Recovery Act-hazardous waste was
removed from the building, and it has most recently been used for a waste
sorting project. Investigation showed ground-water contamination with seven
inorganics (arsenic, beryllium, cadmium, lead, nickel, thallium, and vanadium)
and one volatile organic compound (trichloroethane). A decision regarding a
specific remedial action is not expected until FY 1996 or later. However, this
estimate assumes that remedial action will include some form of ground-water
extraction and treatment. This approach would require installing vertical or
horizontal wells and might also require treatment equipment not already
available onsite.
The 7-Unit Area consists of seven facilities consolidated to investigate a plume
of ground-water contamination. The area includes the X-700 Chemical Cleaning
Facility, the X-700 TCE/TCA Outside Storage Tank, the X-700 Chemical and
Petroleum Storage Containment Tanks, the X-701C Neutralization Pit, the X-705
Decontamination Building, the X-720 Maintenance Building, and Process Waste
Lines from X-700 and X-705. These facilities have been used for over 30 years.
The ground water in the 7-Unit Area is contaminated by the following
substances: antimony, arsenic, beryllium, chromium, 1,1-dichloroethane,
1,4-dioxane, lead, nickel, technetium-99, trichloroethane, and vanadium. A
decision regarding a specific remedial action is not expected until FY 1996 or
later. However, this estimate assumes that the remedial action will include
some form of ground-water extraction and treatment. This approach would require
installing vertical or horizontal wells and might also require treatment
equipment not already available onsite.
The X-720 Maintenance and Storage Building was constructed in 1954. It is used
for carpentry, repair, and maintenance work. In addition to the ground-water
contamination noted in the previous paragraph, soil contamination by arsenic
was discovered approximately 2 meters (3 yards) south of the building near the
central portion of the building. A decision regarding a specific remedial
action is not expected until FY 1996 or later. However, this estimate assumes
that the remedial action will involve excavating soil and disposal in the
onsite landfill. Remedial action might also involve in situ
solidification/stabilization and deed restrictions.
The X-615 Abandoned Stationary Sewer Treatment Facility treated sewage from the
plant from inception until deactivation in 1982. The investigation determined
that potential contaminants associated with this unit include uranium and
polychlorinated biphenyls. A decision regarding a specific remedial action is
not expected until FY 1996 or later. However, this estimate assume that the
remedial action will involve extracting soil that could be disposed of in an
onsite landfill.
The Peter Kiewit Landfill, used from approximately 1953 to 1968, is located
about 61 meters (66 yards) east of the XT-847 Gaseous Centrifuge Enrichment
Plant Construction Warehouse and west of Big Run Creek. It was first used as a
salvage yard and trash disposal area during initial construction of the plant,
and subsequently as a sanitary landfill. The investigation determined the
presence of potential contaminants in surface seeps along the southeastern
boundary of the landfill. Interim remedial measures were undertaken at the
landfill in FY 1994 to relocate a section of Big Run Creek away from the
landfill and install a leachate collection system. Potential contaminants from
the landfill include arsenic, vinyl chloride, Aroclor 1260, benzo, a, pyrene,
and uranium in surface soil. No contaminants were identified in ground water
outside of the landfill area. However, since ground-water modeling indicates
potential ground-water interaction with the landfill material leading to the
formation of seeps and a potential for ground-water contamination, remedial
alternatives should consider the prevention of migration of contaminants into
ground water. A decision on corrective action is not expected until late 1995
or 1996. However, this estimate assumes that the remedial action will include
capping with possible vertical barriers to prevent ground-water flow through
the landfill.
The X-701B Holding Pond and Retention Basins include one unlined holding pond
and two unlined retention basins located southeast of the X-333 Process
Building. The holding pond was used from 1954 to 1988 to neutralize solutions
and wastewater containing acids, metals, and solvents. Beginning in 1972, the
wastewater was treated using a lime mixture to neutralize the acids, causing
sludges and solids to settle in the holding pond. When the holding pond reached
capacity, sludges and solids were dredged and placed in two adjacent retention
basins. The East Basin received waste from 1973 until 1980. The West Basin
received waste from 1980 through 1985. Resource Conservation and Recovery Act
closure of the unit began in FY 1989. Phase I was completed in FY 1991. It
consisted of removing the sludge from each of the ponds and subsequently
containerized. Phase II consists of constructing a ground-water pump and
treatment facility and in situ treatment of the soils in the bottom of the
holding pond. Soil treatment was not possible with the thermally enhanced vapor
extraction method and another remediation method is being evaluated. After
treatment, a permanent, multilayer clay cap is planned to cover the unit.
Ground-water contaminants include 10 inorganics (antimony, arsenic, beryllium,
cadmium, chromium, lead, nickel, selenium, thallium, and vanadium) and one
volatile organic compound (trichloroethane). A decision regarding a remedial
action will not be made until FY 1996 or later. However, this report assumes
that remedial action will include a combination of ground-water extraction and
treatment, as well as soil treatment and capping.
The X-611A Lime Sludge Lagoons consist of three unlined sludge retention lagoons
constructed in 1954 to receive waste lime sludge from the X-611 Water Treatment
Plant. Located northeast of the main plant facility near Little Beaver Creek,
the lagoons received sludge until 1960. For one to two years, the lagoons also
received recirculating cooling water and chromium-contaminated lime sludge.
Investigations indicated contaminants, including chromium, beryllium, and
polychlorinated biphenyls. Currently, the site is awaiting a Preferred Plan (a
pre-Record of Decision document issuing the recommended alternative) from the
Ohio and U.S. Environmental Protection Agencies. However, this estimate assumes
that the remedial action will involve filling the lagoons to establish a
modified prairie environment.
Other units may be included in a list of remediation sites by regulatory
direction. Decisions regarding other sites will not be made until FY 1996 or
later. This report assumes that all remedial actions for Quadrants I-IV will be
completed by FY 2035.
This baseline report assumes that approximately 3,914,589 cubic meters
(5,128,112 cubic yards) of hazardous ground water will be left in the area of
containment after the completion of remediation and surveillance and
maintenance. This report also assumes that 8,548 cubic meters (11,198 cubic
yards) of solid hazardous waste and 170 cubic meters (223 cubic yards) of solid
low-level mixed waste will be generated by these activities. However;
approximately 51,500 cubic meters (67,465 cubic yards) of hazardous ground
water will be removed and treated, along with 284 cubic meters (372 cubic
yards) of other hazardous liquids and 10,685 cubic meters (13,997 cubic yards)
of hazardous solids.
This report further assumes that 51,604 cubic meters (67,601 cubic yards) of
low-level radioactive waste solids and 375 cubic meters (491 cubic yards) of
low-level mixed waste solids will be removed, most of which is metal and
debris, and that approximately 439 cubic meters (575 cubic yards) of sanitary
waste will be generated as a part of the remedial action and surveillance and
maintenance activities. All costs associated with the transporting and
disposing of these materials is included within the scope of the Environmental
Restoration program.
Decommissioning
This report assumes that when uranium enrichment processes are no longer needed,
the Department of Energy will shut down and decommission the Portsmouth Gaseous
Diffusion Plant. Under the provisions in the United States Enrichment
Corporation lease, stabilization and shutdown activities are the responsibility
of the Enrichment Corporation, except for legacy contamination. During the
transition phase, the Department of Energy's Environmental Management program
will remove all polychlorinated biphenyl-contaminated oils, lube oils, freon,
and other hazardous materials and uranium deposits from the facilities.
The Department of Energy recently used several different scenarios to reevaluate
the estimate for decommissioning the gaseous diffusion facilities. The scenario
described in this report uses a new approach for recycling process equipment
and other radioactive metals into usable products. It also includes the onsite
disposal of low-level and mixed radiological waste.
The regulatory strategy for decommissioning is based on the May 22, 1995 joint
Department of Energy and Environmental Protection Agency policy on
decommissioning under the Comprehensive Environmental Response, Compensation,
and Liability Act. This policy provided guidance that indicated a preferred
method of conducting decommissioning actions at Department of Energy sites,
namely that these activities would be conducted as nontime critical removal
actions with the associated Engineering Evaluation/Cost Analyses and Action
Memorandum prepared to document decisions. Under the Comprehensive
Environmental Response, Compensation, and Liability Act actions, the analyses
will have to incorporate National Environmental Policy Act values and comply
with the substantive provisions of all applicable or relevant and appropriate
requirements, including public involvement.
As noted in the National Contingency Plan, the Comprehensive Environmental
Response, Compensation, and Liability Act process provides for compliance with
the substantive provisions of "applicable or relevant and appropriate
requirements" unless compliance waivers are obtained from the appropriate
regulatory agencies. Onsite Comprehensive Environmental Response, Compensation,
and Liability Act actions are exempt from permits. In reference to
decontamination and decommissioning, this would mean that permits would not be
required for air emissions, wastewater dischargers, or similar activities.
Instead, the substantive portions of the laws governing these resources would
be applicable, and the removal process would not be delayed because of lengthy
permit review and approval requirements.
The first major phase of decontamination will be the removal of the major
components from the process buildings. These major components include motors;
cell housing and structural framing; compressors and converters; piping and
valves; instrumentation, instrument panels, and tubing; support equipment;
electrical equipment; utilities systems and ventilation systems. In general,
all equipment will be removed in one piece unless it is more efficient to
section it for removal. The process piping and equipment will be cut loose so
that it can be removed from the cell. This report assumes adequate purging and
the use of portable high-efficiency particulate air ventilation systems to
allow workers to perform without respirators.
Safeguards and security requirements, including nuclear material control and
accountability practices, for enriched uranium are streamlined to the extent
necessary to allow the equipment removal and recycle contractors to perform
their work unimpeded. Contamination control will be adhered to so that the
removal process does not cause trackout problems or additional cleanup work
before the structure can be demolished.
Following the removal of equipment, the Department will remove loose
contamination from the internal structure components (for example, walls,
floors, roofs) with a water spray and/or steam cleaning. The wash water will be
collected, recycled to the extent possible, treated, and discharged. The
Department will dispose of sludges in the onsite disposal cell.
Buildings constructed with transite siding will require removal of these
asbestos-containing materials prior to structural demolition. The transite
siding and other building materials will be wrapped and placed in storage prior
to the demolition of the above-grade structure.
All of the gaseous diffusion process buildings will be demolished down to their
concrete slabs. Nonprocess buildings, buildings that contain nonradiologically
contaminated equipment, and process buildings can be demolished by conventional
methods that use heavy equipment such as wrecking balls. In most cases,
segregation of structural steel for recycle will take place during or after
demolition, using heavy equipment. Demolition rubble will be used for in-place
backfill in cavities and/or will be left on the slabs-on-grade and covered with
a vegetative layer. All below-grade structures remain with utility lines
conduit, trenches, etc. capped off and left in-place. The demolition fill will
not be placed in a manner that will provide an adequate foundation for future
development. However, no free liquids will be left in the rubble. This report
assumes that approximately 269,178 cubic meters (352,623 cubic yards) of
low-level mixed waste metal and rubble/debris will be left in place.
The Department will transport metal materials removed from the buildings,
including structural steel removed during building demolition, to Nuclear
Regulatory Commission-licensed recyclers. The metal will be disassembled as
necessary, sized, smelted, milled, recycled where economically feasible,
rolled, and fabricated into use for products such as storage and disposal
boxes, barrels, and pallets. Melt slag and any unused metals will be
transported to back to Portsmouth for disposal. Radiologically contaminated
metal waste from recycling will be disposed of in the onsite disposal cells.
Certain metals or components, such as structural steel and electrical system
cables will be evaluated for release and recycle as not contaminated. Process
system electrical motors will be processed by licensed recyclers for
decontamination and released if deemed technically achievable and economically
advisable.
If generation of containers/products from the recycling process exceeds the
short-term demand, all excess inventory will be returned to the plant and
managed until needed. This estimate assumes that all decontamination and
decommissioning activities at the Portsmouth Gaseous Diffusion Plant will be
completed by FY 2025.
This report assumes that decommissioning activities at the Portsmouth facilities
will generate low-level mixed waste, low-level waste, hazardous waste,
polychlorinated biphenyl waste, asbestos waste and sanitary waste.
Metals removed from the buildings will be smelted, and the resulting slag will
be disposed of in the onsite cell. With proper metallurgical processes,
radioactive contaminants migrate to the slag during smelting, with the
exception of technetium-99 which migrates to the metal. Other materials and
debris that cannot be recycled will also be disposed of in the cell. All waste
that will be disposed of in the cell is either low-level waste and/or mixed
waste.
Small levels of fixed radioactive contamination will remain on building
structures (mainly concrete). An assessment of the amount of residual
contamination left at the building sites will be performed in the Streamlined
Risk Evaluation in the Engineering Evaluation/Cost Analysis to ensure that
contamination left onsite will not pose an unacceptable risk to human health
and the environment.
Treatment, Storage, and Disposal
The Environmental Restoration program directs the safe, treatment, storage, and
disposal of waste generated by past operations and current environmental
restoration projects. The United States Enrichment Corporation has operated the
Portsmouth Gaseous Diffusion Plant since July 1993 and is responsible for waste
from normal plant operations. Waste generated by operations prior to July 1993,
as well as environmental restoration-generated waste, remain the responsibility
of the Department of Energy.
All waste generated is characterized and labeled by type at the site of
generation. All waste shipped offsite for disposal must be certified to meet
the acceptance criteria for disposal at the particular disposal facility.
Because of the nature of the work performed at the Portsmouth Gaseous Diffusion
Plant, the following waste types are generated and stored at the onsite:
low-level radioactive waste, hazardous waste, low-level mixed waste,
polychlorinated biphenyl waste, polychlorinated biphenyl-radioactive waste,
asbestos waste, and conventional sanitary waste.
Waste minimization activities at the Portsmouth Gaseous Diffusion Plant consist
primarily of recycling projects and segregation techniques. Current recycling
projects involve cardboard, aluminum cans, waste office paper, and spent
fluorescent light bulbs. Projects being prepared are recycling polychlorinated
biphenyl materials, such as transformers and capacitors for the metal, and
recycling the lead metal waste stream from lead-acid batteries. Other projects
such as scrap metal recycling are still in the planning stages.
This report assumes that low-level waste and low-level mixed waste resulting
from remedial actions and Waste Management program activities will be
temporarily stored at Portsmouth until they can be transported to offsite
commercial facilities. This report assumes that low-level and low-level mixed
waste generated from the decommissioning of the gaseous diffusion facilities
will to be disposed in the onsite disposal cell. This estimate assumes that
approximately 88,904 cubic meters (116,464 cubic yards) of solid low-level
waste, 222 cubic meters (291 cubic yards) of solid low-level mixed waste and
14,507 cubic meters (19,004 cubic yards) of other unknown solids and liquids
are either currently in storage, or will be generated and sent to the Waste
Management program due to legacy and ongoing activities at Portsmouth awaiting
shipment applicable to offsite facilities.
Low-level and mixed radiological waste from decommissioning the Portsmouth
facilities will be disposed of in an engineered facility. The engineered
disposal facility will be located onsite so that any resulting low-level waste
or mixed waste generated from the recycle process can be placed in the cell.
Instead of the traditional permitting process, a Comprehensive Environmental
Response, Compensation, and Liability Act Remedial Investigation/Feasibility
Study, followed by a Record of Decision will be performed as part of the
Comprehensive Environmental Response, Compensation, and Liability Act process.
One of the goals of this process is to pre-qualify the waste for placement in
the onsite disposal cell and to identify any waste streams that are not
appropriate for onsite disposal. This report assumes that approximately 651,562
cubic meters (853,546 cubic yards) of low-level waste metal and other solid
debris will be removed from the facilities.
Liquid hazardous waste is currently being sent to the K-25 Site in Oak Ridge,
Tennessee, where it is treated at the Toxic Substances Control Act Incinerator.
Disposal of the treatment residue is being handled by K-25 Site personnel.
Other hazardous waste will be shipped to permitted commercial treatment and
disposal facilities.
Liquid polychlorinated biphenyl waste is currently being sent to the K-25 Site
for treatment at the Toxic Substances Control Act Incinerator. Disposal of the
treatment residue is being handled by K-25 Site personnel. Solid
polychlorinated biphenyl waste is being stored onsite until it can be scheduled
for treatment at the Toxic Substances Control Act Incinerator. This report
assumes that approximately 24,921 cubic meters (32,647 cubic yards) of
polychlorinated biphenyl waste will be generated during the life cycle of this
estimate.
Asbestos waste will be contained but will not be treated and will be disposed of
in the onsite solid waste landfill or in the construction spoils area.
Solid sanitary waste is basically refuse and is disposed of in the onsite solid
waste landfill. Liquid sanitary waste includes sewage and industrial waste
treated at the site sewage treatment plant. Metal, wood, and rubbish will also
be disposed in the onsite solid waste landfill.
Long-Term Surveillance and Monitoring
All costs associated with long-term surveillance and monitoring are included as
one line item in this estimate. Major operations that will be accomplished as a
result of long-term surveillance and monitoring activities for Environmental
Restoration program support facilities, decommissioning program facilities, and
remedial action sites include: surveillance of facilities and remedial action
sites to determine status per standards; maintenance of facilities and sites to
retard degradation and correct deficiencies; post-remediation surveillance and
monitoring at sites to comply with regulations and regulatory agreements;
facility stabilization actions that improve operations or lower costs; and
facility and program management to ensure efficient, safe operations. This
report assumes that long-term surveillance and monitoring activities at the
Portsmouth Gaseous Diffusion Plant will continue until FY 2035.
Direct Program Management/Support
Program management functions provide essential administrative and oversight
assistance to the environmental restoration activities at the Portsmouth
Gaseous Diffusion Plant. This support focuses on ensuring proper
identification, characterization, remediation and revitalization of the
contaminated sites. Business management accounts for a large portion of the
program management. It includes progress tracking, contract management,
facility management, and financial management (budget preparation and control)
for the Portsmouth projects. Project management personnel for the Lockheed
Martin Energy System, Inc. and support groups provide project management
support skills as well as coordination with the other sites in the Oak Ridge
Operations Office.
Federal employees oversee the contractors for the Portsmouth Gaseous Diffusion
Plant Environmental Restoration program. However, their costs are included in
the Oak Ridge Operations Office section of this report along with the
Integrating Contractor Central Operations Office support.
|
STAKEHOLDER INTERACTIONS
The Oak Ridge Operations Office conducted stakeholder activities for the
Portsmouth Gaseous Diffusion Plant. In addition to distributing informational
materials, the office sponsored a workshop on the report and future land-use
planning issues, which was attended by 38 stakeholders. If you would like more
information about the report or have questions about the results, please
contact:
|
|
Public Participation
Walter Perry
(423) 576-0885 perrywn@oro.doe.gov
|
Technical Liaison
Marianne Heiskell
(423) 576-0314 heiskellmm@oro.doe.gov
|
Public Affairs
Steve Wyatt
(423) 5760887 wyattsl@oro.doe.gov
|
Environmental Restoration Activities Cost Estimate
|
(Five-Year Averages, Thousands of Constant 1996 Dollars)
|
| |
|
|
Quadrants I-IV
|
|
|
|
|
|
|
|
|
|
Assessment
|
13,420
|
14,510
|
2,774
|
2,926
|
1,472
|
|
|
|
|
Remedial Action
|
8,046
|
7,240
|
14,453
|
4,750
|
3,693
|
45,493
|
14,489
|
|
|
Decommissioning Area Actions
|
|
|
|
|
|
|
|
|
|
Assessment
|
|
1,545
|
3,288
|
|
|
|
|
|
|
Facility Decommissioning
|
1,388
|
1,590
|
97,191
|
99,360
|
92
|
17,513
|
|
|
|
Treatment, Storage, and Disposal
|
36,550
|
30,418
|
155,182
|
193,978
|
|
|
|
|
|
Long-Term Surveil. and Monitoring
|
803
|
767
|
767
|
767
|
614
|
|
|
|
|
Direct Program Management/Support
|
5,587
|
9,522
|
678
|
171
|
75
|
340
|
68
|
|
|
Total
|
65,793
|
65,593
|
274,333
|
301,952
|
5,945
|
63,346
|
14,557
|
|
| |
2040
|
2045
|
2050
|
2055
|
2060
|
2065
|
|
Quadrants I-IV
|
|
|
|
|
|
|
|
|
|
Assessment
|
|
|
|
|
|
|
|
175,509
|
|
Remedial Action
|
364
|
|
|
|
|
|
|
492,640
|
|
Decommissioning Area Actions
|
|
|
|
|
|
|
|
|
|
Assessment
|
|
|
|
|
|
|
|
24,163
|
|
Facility Decommissioning
|
|
|
|
|
|
|
|
1,085,672
|
|
Treatment, Storage, and Disposal
|
|
|
|
|
|
|
|
2,080,646
|
|
Long-Term Surveil. and Monitoring
|
|
|
|
|
|
|
|
18,587
|
|
Direct Program Management/Support
|
50
|
|
|
|
|
|
|
82,453
|
|
Total
|
414
|
|
|
|
|
|
|
3,959,670
|
|
* Total Life Cycle is the sum of the annual costs in constant FY 1996
dollars.
|
LANDLORD ACTIVITIES
The Department of Energy's Uranium Enrichment Programs is the landlord for the
Portsmouth Gaseous Diffusion Plant. Because there are no directly appropriated
landlord costs at this site, funds for landlord activities are obtained through
the budget process for ongoing Environmental Restoration, Waste Management, and
Uranium Enrichment program activities or legacy activities at the plant. Each
year, all programs supported by the Paducah Gaseous Diffusion Plant landlord
provide planned budget requests based on prioritization. Landlord activities
include security, fire protection, emergency management, waste management,
corrective actions, general plant maintenance, roads and ground, and
decommissioning of property and facilities retained by the Department of
Energy. In addition, the landlord leases portions of the land and facilities to
the United States Enrichment Corporation for uranium enrichment production and
a portion of the plant and facilities to other government agencies, including
the Defense Logistics Agency and the Ohio Army National Guard.
This estimate assumes that, once production discontinues at the site. The
Department of Energy's Environmental Management program will be the landlord of
the facilities. The activities will involve surveillance and maintenance (e.g.,
fire protection and security) of the facilities until they can be
decommissioned. This estimate assumes that the time between discontinued
operations and start of decommissioning is two years.
DESCRIPTION OF PERSONNEL
Current Composition
As the managing contractor, Lockheed Martin Energy Systems, Inc. employs
personnel to support the Department's mission. In addition, Lockheed Martin
Energy Systems, Inc. is the integrating contractor for other Department of
Energy prime contractors and subcontractors working on the Department's program
at Portsmouth Gaseous Diffusion Plant. Department of Energy prime contractors
include Jacobs Engineering. Subcontractors working for Lockheed Martin Energy
Systems, Inc. at the site include MK-Ferguson, Foster-Wheeler, CDM Federal
Programs, Science Applications International Corporation, Theta Technologies,
Lockwood Greene, Afftrex, AC Inc., and several "8a" subcontracting firms. The
costs for the federal Full-Time Equivalents are included in the Oak Ridge
Operations Office section of this report. The following table presents the
contractor work force by skill mix.
Full-Time Equivalent Composition Table*
* The Projections for Full-Time Equivalent employees are based on FY 1996
planning baselines (see Reader's Guide).
Site Management Structure
Effective July 1, 1993, and in accordance with the Energy Policy Act, the
Department of Energy leased the plant production operations at Portsmouth
Gaseous Diffusion Plant to the United States Enrichment Corporation for six
years. The Department and the United States Enrichment Corporation negotiated
the lease of specific plant facilities, outlined in a Memorandum of Agreement,
which defines their respective roles under the lease, and developed the
administrative program elements necessary to support their respective roles.
Under these agreements, the Department of Energy retains the environmental
restoration and waste management functions at the Portsmouth Gaseous Diffusion
Plant, and Lockheed Martin Energy Systems, Inc. currently manages these
operations. The subsidiary corporation, Lockheed Martin Utility Services, Inc.,
currently manages plant production operations.
Lockheed Martin Energy Systems is the integrating contractor for the
environmental restoration activities at Portsmouth for the Department of
Energy. This contractor integrates its own work activities as well as those of
the Department of Energy prime contractors for technical support, engineering,
and construction, and its own subcontractors for site remedial investigation
work.
The Lockheed Martin Energy Systems contract has recently been extended for two
years. As a part of that contract, Lockheed Martin has committed to incentive
contracting as a part of contract reform. An increasing number of the Lockheed
Martin-managed activities will be task order contracts. The primary features of
these task order projects are as follows: contracting companies function as a
team, the Department of Energy and the team negotiate terms of the project, the
team collects an incentive fee for finishing under budget but absorbs a
percentage of any cost overrun, the Department of Energy shares the risk of
cost overruns, and streamlined bid specifications simplify the process and
reduce cost estimates.
This estimate assumes that a decommissioning project management contractor will
manage the decommissioning of the plant. This contractor will perform the
project management services necessary to execute the project and is the
contractor responsible for the overall success of the project. The estimate
assumes that the Department of Energy and the decommissioning project
management contractor will use an incentive contracting approach with various
subcontractors.
|
CONTRACTING OPPORTUNITIES
If you would like more information about performing work for the Department
of Energy's Environmental Management program at this site, please contact:
|
|
Major Procurements
Peter Dayton
Director Procurements and Contracts Division., AD-42
United States Department of Energy
Oak Ridge Operations Office
P.O. Box 2001
Oak Ridge, TN 37831-8755
p: (423) 576-0795
f: (423) 576-9189
|
Small Business Procurements
Chiquita Young
Procurements and Contracts Division., AD-42 United States Department of Energy
Oak Ridge Operations Office
P.O. Box 2001
Oak Ridge, TN 37831-8755
p: (423) 576-5657
f: (423) 576-9189
|
Future Full-Time Equivalent Needs
This baseline estimate assumes that the mix of needed Full-Time Equivalents
supported by the Environmental Management program will remain fairly stable,
even when operations are discontinued in FY 2005. At that time, remedial action
and waste management activities will continue to support the Environmental
Restoration program. However, in FY 2007, when decommissioning activities
begin, the number of Full-Time Equivalents and mix should change substantially.
The yearly budgets will be substantially higher and all areas of employment
will rise. As the buildings are cleared and demolished, heavy equipment
operators, laborers, health and safety personnel, and decontamination personnel
will be needed. The construction of the onsite disposal cell will also require
construction workers. According to this estimate, the permitting and reporting
activities will be streamlined, and the numbers of technical and administrative
personnel will not increase dramatically.
FUNDING ESTIMATE
The following tables present estimated funding information for the Portsmouth
Gaseous Diffusion Plant.
Defense Funding Estimate
|
(Five-Year Averages, Thousands of Constant 1996 Dollars)
|
| |
|
|
Environmental Restoration
|
65,545
|
65,142
|
274,333
|
301,952
|
5,945
|
63,346
|
14,557
|
|
| |
2040
|
2045
|
2050
|
2055
|
2060
|
2065
|
|
Environmental Restoration
|
414
|
|
|
|
|
|
|
3,956,178
|
|
* Total Life Cycle is the sum of the annual costs in constant FY 1996
dollars.
|
Nondefense Funding Estimate
|
(Five-Year Averages, Thousands of Constant 1996 Dollars)
|
| |
2010
|
2015
|
2020
|
2025
|
2030
|
|
Environmental Restoration
|
248
|
450
|
|
|
|
|
|
3,492
|
|
* Total Life Cycle is the sum of the annual costs in constant FY 1996
dollars.
|
COMPARISON WITH PREVIOUS ESTIMATE
The 1996 life-cycle estimate of $4.0 billion for the Portsmouth Gaseous
Diffusion Plant represents a 54 percent decrease from the 1995 estimate of $8.7
billion.
Comparison Table
| |
Thousands of Dollars
|
|
|
Nuclear Mat. & Fac. Stab.
|
-
|
-
|
-
|
-
|
-
|
|
Environmental Restoration
|
7,135,148
|
68,600
|
3,959,670
|
3,106,878
|
44
|
|
Waste Management
|
-
|
-
|
-
|
-
|
-
|
|
Landlord
|
-
|
-
|
-
|
-
|
-
|
|
Program Management 2
|
1,571,173
|
6,900
|
-
|
-
|
-
|
|
Site Total
|
8,706,321
|
75,500
|
3,959,670
|
4,671,151
|
54
|
|
1 The FY 1995 life-cycle and annual costs are provided to determine the
corrected FY 1995 cost.
2 Program Management was reported in an independent cost table last year, but
is reported as a line item in the relevant program (Nuclear Material and
Facility Stabilization, Environmental Restoration, and Waste Management)
activity cost estimate tables for the FY 1996 Baseline Report.
|
The FY 1995 Baseline Environmental Management Report used an estimate for the
decommissioning of the Portsmouth Gaseous Diffusion Plant that Ebasco
Corporation prepared in 1991 for the Department of Energy. That estimate was
for "clean closure" of the site. This included removing everything from the
buildings, treating the contents at major support facilities (low- and
high-assay decontamination facilities) and disposing of the waste offsite. The
new estimate assumes that much of the metal in the buildings and process
equipment will be recycled, and that waste will be disposed onsite. These
assumptions significantly reduce the cost and schedule for decommissioning the
facilities. The scope of the Environmental Restoration program now includes
program management.
A major difference between the FY 1995 Baseline Environmental Management Report
and this report is the period of time between the end of operations and the
start of the decommissioning activities. The FY 1995 estimate assumed that
there would be several decades of landlord activities and surveillance and
monitoring before the funds became available for decommissioning. In this
estimate, that duration is only two years. This change in schedule greatly
reduces the costs for maintenance activities at the site.
|
 |