|
Home
BEMR
Contents
U.S.
Map
ARIZONA UMTRA SITES
The Monument Valley and Tuba City former processing sites are two of 24 uranium
mill processing sites designated by the Uranium Mill Tailings Radiation Control
Act for remediation by the Department of Energy. During the 1960's, private
firms processed most uranium ore in the United States for the Atomic Energy
Commission, a predecessor of the Department of Energy. Congress passed the Act
in 1978 in response to public concern regarding potential health hazards from
long-term exposure to uranium mill tailings. It authorized the Department of
Energy to stabilize, dispose of, and control uranium mill tailings and other
contaminated material at 24 uranium mill processing sites and vicinity
properties. For a general discussion of the UMTRA Program, see the overview
presented in the New Mexico section of this report.
The cost estimate model used for this report provides costs for each of the
UMTRA sites. All costs for waste management activities, program management, and
relevant landlord activities attributable to the Department are provided for
within the scope of environmental restoration. There are no Uranium Mill
Tailings Radiation Control Act sites with either current or planned nuclear
material and facility stabilization activity needs. Funding for all sites is
100 percent nondefense.
MONUMENT VALLEY, ARIZONA (UMTRA SITE)
The former Monument Valley mill and tailings site is on Navajo Nation land
21 kilometers (13 miles) east of Monument Valley Tribal Park in Arizona. It is
located 27 kilometers (17 miles) south of the Mexican Hat site and is about
eight kilometers (five miles) south of the Utah-Arizona border. The site
covered approximately 37 hectares (90 acres); tailings were located in two
piles covering about 12 hectares (30 acres). The older heap-leach pile covered
about four hectares (10 acres). The newer tailings pile was cone-shaped, about
17 meters 55-feet) high, covered about eight hectares (20 acres) and contained
over two-thirds of the tailings at the site. The site also contained the old
mill building foundations, contaminated soil, and wind-blown material.
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
| |
|
|
|
| Environmental Restoration
|
569
|
789
|
724
|
1,520
|
2,076
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
639
|
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
1,087
|
|
|
| (Five-Year Averages, Thousands of Constant 1996 Dollars)
|
| |
2020
|
2025
|
2030
|
| Environmental Restoration
|
1,051
|
4,921
|
5,934
|
10,620
|
|
|
|
112,626
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The mission of the Monument Valley, Arizona mill site was to provide uranium
for the United States national defense program. The source of contamination was
the residual tailings remaining after the uranium was extracted during the
milling process. The mill was constructed in 1955 by Vanadium Corporation of
America, and its successor, Foote Mineral Company, operated it through 1968.
Before and during the milling operations, the site was leased from the Navajo
Nation. When the lease expired in 1968, control of the site reverted to the
Navajo Nation.
SITE MAP
The Environmental Management program is responsible for cleaning up surface and
ground-water contamination at the UMTRA sites. The Uranium Mill Tailings
Radiation Control Act designated the residual radioactive material found at
this site for cleanup and stabilization. The Act directed the Environmental
Protection Agency to promulgate standards (Code of Federal Regulations Title
40, Part 192) and the Department of Energy to perform the cleanup. It also
assigned the Nuclear Regulatory Commission to oversee and certify the cleanup
and license the completed disposal cell.
Pursuant to the Uranium Mill Tailings Radiation Control Act, the Department of
Energy entered into a Cooperative Agreement in 1983 with the Navajo Nation. The
agreement outlines the roles and responsibilities of each party. The Department
of Energy pays 100 percent of all costs (assessment and remediation) when the
UMTRA site is on Tribal land. In addition, the Department of Energy is
responsible for paying 100 percent of the Tribe's costs. The Nuclear Regulatory
Commission concurred on the original agreement and must concur on all major
modifications.
FUTURE USE
The Monument Valley site is located on Navajo Nation land and will remain under
the ownership of the Navajo Nation following Nuclear Regulatory Commission site
certification. A Custodial Access Agreement between the Federal Government and
the Navajo Nation will allow access to the site by the Department of Energy to
carry out the UMTRA Ground-Water Compliance Project. The affected Tribes will
participate in any decisions made.
ENVIRONMENTAL RESTORATION
Surface remedial action has been completed and the source of contamination has
been stabilized. However, residual milling-related contaminated ground water
remains.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996 Dollars)
|
| |
2020
|
2025
|
2030
|
| UMTRA Surface
|
|
|
|
|
|
|
|
|
| Assessment
|
9
|
|
|
|
|
|
|
43
|
| UMTRA Ground water
|
|
|
|
|
|
|
|
|
| Assessment
|
373
|
169
|
108
|
267
|
|
|
|
4,579
|
| Remedial Action
|
2
|
1,204
|
1,200
|
645
|
|
|
|
15,254
|
| Direct Program Management/Support
|
668
|
3,548
|
4,626
|
9,708
|
|
|
|
92,750
|
| Total |
1,051
|
4,921
|
5,934
|
10,620
|
|
|
|
112,626
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Surface Project
Remedial action was completed in March 1994 at the Monument Valley former
processing site. The remedial action involved relocating approximately 703,152
cubic meters (925,200 cubic yards) of residual radioactive material from the
existing site to the disposal cell at the Mexican Hat site in Halchita, Utah.
The consolidated Mexican Hat and Monument Valley tailings were covered with a
radon barrier and a rock erosion protection layer to meet Environmental
Protection Agency standards for longevity, control of radon emanation and
ground-water protection. Four vicinity properties were remediated concurrently
with site remediation activities. This report expects the Nuclear Regulatory
Commission to license the disposal cell at Mexican Hat in March 1997.
Major Surface Project Milestones
| Assessment
|
1996
|
| Nuclear Regulatory Commission Licensing
|
1996
|
The Monument Valley Remedial Action Plan outlines the contaminant distribution
and necessary remediation. The Remedial Action Plan, which requires Nuclear
Regulatory Commission concurrence, was published in July 1988. The site
Completion Report will be included as part of the site Certification Report.
Since the tailings were removed, no further surveillance of the site is
required under the Surface Project.
Ground-Water Compliance Project
The Department is developing a Programmatic Environmental Impact Statement
pertaining to all 24 UMTRA sites. For a discussion of the Programmatic
Environmental Impact Statement, see the UMTRA program narrative in the New
Mexico section of this report. Site-specific National Environmental Policy Act
documentation will be developed to propose an appropriate ground-water
compliance strategy and reasonable alternatives for the Monument Valley site
once the Programmatic Environmental Impact Statement is completed.
This cost estimate assumes an active remediation ground-water compliance
strategy that involves extracting the contaminated ground water through pumping
wells and applying the ground water via land application to make beneficial use
of some ground-water contaminants. The successful application of this
technology must ensure the contaminated ground water does not create an
additional contaminant pathway. For all types of ground-water compliance
strategies, once the Nuclear Regulatory Commission determines that the site is
in compliance with Subpart B of the Environmental Protection Agency Standards
and the site is certified, no additional long-term surveillance or monitoring
will be conducted.
During operation of the processing site, an estimated total volume of 2.8
billion liters (750 million gallons) of ground water was contaminated and the
contaminant plume currently extends offsite. The ground-water contaminants of
potential concern are manganese, nitrate, strontium, sulfate, uranium, and
vanadium.
The following milestone dates have been established for planning purposes.
Major Ground-Water Compliance Project Milestones
| Baseline Risk Assessment
|
1995
|
| Site Observational Work Plan
|
2000
|
| Publish Environmental Assessment/Finding of No Significant
Impact
|
2001
|
| Publish Remedial Action Plan
|
2003
|
| Compliance Strategy
|
2014
|
| Licensing
|
2015
|
Samples were analyzed for several constituents, including nitrate, the primary
indicator of ground-water contamination. Several wells near the former mill and
tailings pile areas have the greatest concentration of nitrate. In addition,
these wells show relatively consistent nitrate concentrations over time,
demonstrating plume migration downgradient from the contaminant source. This
contaminated ground water has not affected domestic wells.
Direct Program Management/Support
Program management supports management efforts for the National Environmental
Policy Act process, site characterization and licensing, public
information/participation, applicable state and federal regulator costs,
quality assurance audits, program and management support for the technical
assistance contractor, special studies, document control, technical assistance
contractor site and technical management, cost and schedule controls, planning
and preparation of the federal budget, and the Environmental Management
Progress Tracking System.
FUNDING ESTIMATE
The following table presents estimated funding information for the Monument
Valley site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996 Dollars)
|
| |
2020
|
2025
|
2030
|
| Environmental Restoration
|
1,051
|
4,921
|
5,934
|
10,620
|
|
|
|
112,626
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|
 |