|
Home
BEMR
Contents
U.S.
Map
The Lowman former processing site is one of 24 uranium mill processing sites
designated by the Uranium Mill Tailings Radiation Control Act for remediation
by the Department of Energy. During the 1960s, private firms processed most of
the uranium ore mined in the United States for the Atomic Energy Commission, a
predecessor of the Department of Energy. Congress passed the Act in 1978 in
response to public concern regarding potential health hazards from long-term
exposure to uranium mill tailings. It authorized the Department of Energy to
stabilize, dispose of, and control uranium mill tailings and other contaminated
material at 24 uranium mill processing sites and vicinity properties. For a
general discussion of the UMTRA Program, see the overview presented in the New
Mexico section of this report.
The cost estimate model used for this report provides costs for each of the
UMTRA sites. All costs for waste management activities, program management, and
relevant landlord activities attributable to the Department are provided for
within the scope of environmental restoration. There are no Uranium Mill
Tailings Radiation Control Act sites with either current or planned nuclear
material and facility stabilization activity needs. Funding for all sites is
100 percent nondefense.
LOWMAN, IDAHO (UMTRA SITE)
The Lowman millsite, which covers 15 hectares (37 acres), is located
approximately 121 kilometers (75 miles) northeast of Boise, Idaho, in the Boise
National Forest. It is 0.8 kilometers (one-half mile) northwest of the Town of
Lowman. When the remedial action project started, piles of radioactive tailings
were scattered over a two-hectare (five-acre) parcel of the site. Other
contaminated areas on the site included the millyard, ore storage area,
evaporation ponds, and wind-borne and water-borne contaminated material. The
total amount of contaminated material onsite was more than 95,760 cubic meters
(126,000 cubic yards).
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
| |
|
|
|
| Environmental Restoration
|
3
|
3
|
3
|
3
|
3
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
27
|
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
0
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2005
|
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
3 |
|
|
|
|
|
|
15
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The mission of the Lowman mill site was to provide uranium for the United
States Government. The source of contamination was the residual tailings
remaining after the uranium was extracted during the milling process. Parker
Brothers Corporation of Boise was the original owner of the site, operating the
mill from 1955 until 1960. Following mill shutdown, Velsicol Chemical
Corporation, formerly known as the Michigan Chemical Corporation purchased the
site. The State of Idaho owned the site, but title has been transferred to the
Federal Government.
SITE MAP
The Environmental Management program is responsible for cleaning up surface-
and ground-water contamination at the UMTRA sites. The Uranium Mill Tailings
Radiation Control Act designated the residual radioactive material found at
this site for cleanup and stabilization. The Act directed the Environmental
Protection Agency to promulgate standards (Code of Federal Regulations Title
40, Part 192) and the Department of Energy to perform the cleanup. It also
assigned the Nuclear Regulatory Commission to oversee and certify the cleanup
and license the completed disposal cell.
FUTURE USE
The Federal Government owns the Lowman disposal site, which is under the
custody of the Department of Energy. The Department will monitor and maintain
the disposal cell under Controlled Access in accordance with the Nuclear
Regulatory Commission-approved Long-term Surveillance Plan. Under the
provisions of the Uranium Mill Tailings Radiation Control Act, public access to
the disposal site is restricted.
ENVIRONMENTAL RESTORATION
Surface remedial action has been completed, and the source of contamination has
been stabilized. There is no contaminated ground water at this site.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2005
|
2010
|
2015
|
2020
|
2025
|
2030
|
| Direct Program Management/Support
|
3 |
|
|
|
|
|
|
15
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Surface Project
Residual radioactive material (tailings and other contaminated materials) from
the processing site was stabilized on site in a controlled, engineered disposal
cell to preclude further release of contaminants into the environment,
including the ground water. Surface remedial action was completed in June 1992,
and the Nuclear Regulatory Commission licensed the site in September 1994. The
disposal site was transferred to the Grand Junction Projects Office's Long-Term
Surveillance and Maintenance program in March 1995.
Ground-Water Compliance Project
The Department is developing a Programmatic Environmental Impact Statement
pertaining to all 24 UMTRA sites. For a discussion of the Programmatic
Environmental Impact Statement, see the UMTRA program narrative in the New
Mexico section of the report. Site-specific National Environmental Policy Act
documentation will be developed to propose an appropriate ground-water
compliance strategy and reasonable alternatives for the Lowman site once the
Programmatic Environmental Impact Statement is completed.
This report assumes that the Lowman site will follow a No Further Action
ground-water compliance strategy. For all types of ground-water compliance
strategies, once the site is determined by the Nuclear Regulatory Commission to
be in compliance with Subpart B of the Environmental Protection Agency
Standards and it is certified, no additional long-term surveillance or
monitoring will be conducted.
Results of ground-water monitoring in 1994 at the Lowman disposal site indicate
that there is no contamination of ground water. The UMTRA project site
characterization program conducted by the Department of Energy at the Lowman
site included extensive hydrogeological investigations involving seventeen
five-centimeter (two-inch) monitoring wells.
In May 1994, ground-water samples were collected from two background monitoring
wells upgradient of the disposal cell and four monitoring (point-of-compliance)
wells downgradient of the disposal cell. Parameters selected for analysis
included antimony, barium, chromium, lead, molybdenum, nitrate, uranium, and
radionuclides.
Direct Program Management/Support
Program management supports management efforts for the National Environmental
Policy Act process, site characterization and licensing, public
information/participation, applicable state and federal regulator costs,
quality assurance audits, program and management support for the technical
assistance contractor, special studies, document control, technical assistance
contractor site and technical management, cost and schedule controls, planning
and preparation of the federal budget, and the Environmental Management
Progress Tracking System.
FUNDING ESTIMATE
The following table presents estimated funding information for the Lowman site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2005
|
2010
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
3 |
|
|
|
|
|
|
15
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|