|
Home
BEMR
Contents
U.S.
Map
Text goes here
The Gunnison former mill site is a 25-hectare (61-acre) tract located southwest
of the City of Gunnison and adjacent to the Gunnison airport. Tailings covered
an area of approximately 16 hectares (39 acres).
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
|
|
|
|
|
| Environmental Restoration
|
2,067
|
945
|
413
|
566
|
846
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
2,592
|
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
915
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
|
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
929
|
899
|
638
|
|
|
|
|
12,325
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The mission of the Gunnison mill site was to provide uranium for the United
States national defense program. The source of contamination was the residual
tailings that remained after the milling process extracted the uranium. Various
companies owned and operated the mill over the years. The last owner was
Kermac, a subsidiary of Kerr-McGee Oil Industries. The mill was closed in 1962,
and the State of Colorado now owns the site.
SITE MAP
The Environmental Management program is responsible for cleaning up surface-
and ground-water contamination at the UMTRA sites. The Uranium Mill Tailings
Radiation Control Act designated the residual radioactive material found at
this site for cleanup and stabilization. The Act directed the Environmental
Protection Agency to promulgate standards (Code of Federal Regulations Title
40, Part 192) and the Department of Energy to perform the cleanup. It also
assigned the Nuclear Regulatory Commission to oversee and certify the cleanup
and license the completed disposal cell.
FUTURE USE
The Department of Energy acquired the Gunnison disposal site from the Bureau of
Land Management via a legislative withdrawal and jurisdictional transfer. The
disposal site will be monitored and maintained under Controlled Access in
accordance with the Nuclear Regulatory Commission-approved Long-Term
Surveillance Plan. Under the provisions of the Uranium Mill Tailings Radiation
Control Act, public access to the disposal site will be restricted. Upon
Nuclear Regulatory Commission site certification under the Surface Project, the
State may dispose of the former processing site according to the provisions of
the Uranium Mill Tailings Radiation Control Act. In this case, the State is
expecting to assign ownership of the processing site to Gunnison County, and
the proposed future use will likely be Recreational. It is anticipated that the
State of Colorado will impose such restrictions as necessary to protect the
public health, safety, and the environment.
ENVIRONMENTAL RESTORATION
Surface remedial action has been completed, and the source of contamination has
been stabilized. However, residual milling-related contaminated ground water
remains.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
|
|
2015
|
2020
|
2025
|
2030
|
| UMTRA Surface
|
|
|
|
|
|
|
|
|
| Assessment
|
118
|
|
|
|
|
|
|
588
|
| Remedial Action
|
36
|
|
|
|
|
|
|
181
|
| UMTRA Ground water
|
|
|
|
|
|
|
|
|
| Assessment
|
190
|
90
|
65
|
|
|
|
|
1,724
|
| Remedial Action
|
3
|
103
|
42
|
|
|
|
|
741
|
| Direct Program Management/Support
|
582
|
706
|
531
|
|
|
|
|
9,091
|
| Total |
929
|
899
|
638
|
|
|
|
|
12,325
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Surface Project
Remedial action began in 1991. All contaminated materials have been removed
from the site and are stabilized in the landfill disposal cell six miles east
of Gunnison. The surface remedial action was completed in December 1995. The
Nuclear Regulatory Commission and the State of Colorado concurred upon the
remedial action. The Completion Report describing these activities is currently
being written. Nuclear Regulatory Commission certification and licensing will
occur in FY 1997, with transfer of the disposal cell to the Grand Junction
Projects Office's Long-Term Surveillance and Maintenance program in early FY
1998.
Major Surface Project Milestones
| Site Remedial Action
|
1996
|
|
Nuclear Regulatory Commission Issues General License
|
1997
|
|
Transfer Disposal Cell to Grand Junction Projects Office Long-Term Surveillance
and Maintenance Program
|
1998
|
The Gunnison Remedial Action Plan outlined contaminant distribution and the
remediation needed. The Remedial Action Plan, which requires concurrence by the
Nuclear Regulatory Commission, was published in July 1989. Fifteen hectares (39
acres) of the 25-hectare (61-acre) site were covered by tailings that have been
relocated to the landfill disposal cell. A total of approximately 646,000 cubic
meters (850,000 cubic yards) of materials, including building demolition
debris, were transported. Remediation of 12 vicinity properties is occurring
concurrently with site remediation activities. Completion of the disposal cell
cover and restoration of the processing site are expected to occur by early FY
1996. The UMTRA Surface Project will conduct surveillance and maintenance of
the disposal cell after the completion of the remedial action and prior to its
transfer to the Grand Junction Projects Office's Long-Term Surveillance and
Maintenance program in FY 1998.
The site has been fully characterized; however, semi-annual monitoring of the
site is performed to ensure that surface remedial action construction does not
impact the ground water.
Ground-Water Compliance Project
The Department is developing a Programmatic Environmental Impact Statement
pertaining to all 24 UMTRA sites. For a discussion of the Programmatic
Environmental Impact Statement, see the UMTRA program narrative in the New
Mexico section of this report. Site-specific National Environmental Policy Act
documentation will be developed to propose an appropriate ground-water
compliance strategy and reasonable alternatives for the Gunnison site once the
Programmatic Environmental Impact Statement is completed.
This report assumes a natural flushing ground-water compliance strategy at the
Gunnison site. With this approach, contamination concentrations are expected to
be reduced naturally to maximum, background, or alternate concentration limits
within 100 years, as established in the Environmental Protection Agency
standards. For all types of ground-water compliance strategies, once the
Nuclear Regulatory Commission determines the site to be in compliance with
Subpart B of the Environmental Protection Agency Standards and it is certified,
no additional long-term surveillance or monitoring will be conducted.
The total volume of contaminated ground water is estimated to be 371 million
liters (98 million gallons), and the contaminant plume extends offsite. The
ground-water contaminants of potential concern are cadmium, lead-210, iron,
cobalt, manganese, sulfate, uranium, thorium-230, and polonium-210. An
alternate water system was built during the UMTRA Surface Project. Residences
that had domestic wells in the aquifer downgradient of the processing site,
which were or could be affected by contamination, now use this system.
The following milestone dates have been established for planning purposes.
Major Ground-Water Compliance Project Milestones
| Site Observational Work Plan
|
2001
|
|
Publish Environmental Assessment/Finding of No Significant Impact
|
2002
|
|
Publish Remedial Action Plan
|
2004
|
|
Compliance Strategy
|
2009
|
|
Licensing
|
2010
|
Ground-water samples are being collected at the former Gunnison processing site
and private locations to monitor water quality during surface remediation and
to assess the extent of ground-water contamination from former processing
activities.
Samples collected during 1994 from wells downgradient of the former processing
site were similar to samples collected in past years, indicating that former
uranium milling activities have impacted ground water in the alluvial aquifer.
Uranium concentrations continue to exceed maximum concentration limits in
monitoring wells approximately 1,829 meters (6,000 feet) downgradient of the
former processing site. Uranium concentrations in a downgradient monitoring
well show a minor upward trend, indicating that the contaminants may be moving.
However, a domestic well near the monitoring well does not show any indications
of contamination from the former processing site.
Direct Program Management/Support
Program management supports management efforts for the National Environmental
Policy Act process, site characterization and licensing, public
information/participation, applicable state and federal regulator costs,
quality assurance audits, program and management support for the technical
assistance contractor, special studies, document control, technical assistance
contractor site and technical management, cost and schedule controls, planning
and preparation of the federal budget, and the Environmental Management
Progress Tracking System.
FUNDING ESTIMATE
The following table presents estimated funding information for the Gunnison
site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
|
|
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
929
|
899
|
638
|
|
|
|
|
12,325
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|
 |