|
Home
BEMR
Contents
U.S.
Map
The former Grand Junction mill site (also known as the Climax Millsite) is a
46-hectare (114-acre) site in Mesa County, located in an industrial area of the
City of Grand Junction, Colorado on the north bank of the Colorado River. It
contained one large tailings pile and a remaining mill building.
LOCALITY MAP
Estimated Site Total
|
(Thousands of Current Year Dollars)
|
| |
|
|
|
| Environmental Restoration
|
20,713
|
19,935
|
18,946
|
6,593
|
1,512
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
15,036
|
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
11,578
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
13,060
|
992
|
611
|
|
|
|
|
73,317
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The mission of the Grand Junction mill site was to provide uranium for the
United States Government. The source of contamination was the residual tailings
remaining after the uranium was extracted during the milling process. In 1951,
Climax Uranium Company, a division of American Metals Climax (now known as
AMAX, Inc.), started milling operations at the site; the mill was shut down in
March 1970. After the mill shutdown, 34 hectares (85 acres) were developed into
an industrial park, 16 hectares (40 acres) were deeded to the State of Colorado
as a repository for tailings from vicinity property remedial action projects in
the Grand Junction area, and 4 hectares (10 acres) were sold to a private
citizen. The State of Colorado presently owns the majority of the designated
tailings site. Three hectares (seven acres) are under private ownership.
SITE MAP
The Environmental Management program is responsible for cleaning up surface-
and ground-water contamination at the UMTRA sites. The Uranium Mill Tailings
Radiation Control Act designated the residual radioactive material found at
this site for cleanup and stabilization. The Act directed the Environmental
Protection Agency to promulgate standards (Code of Federal Regulations Title
40, Part 192) and the Department of Energy to perform the cleanup. It also
assigned the Nuclear Regulatory Commission to oversee and certify the cleanup
and license the completed disposal cell.
FUTURE USE
The State of Colorado currently owns the former processing site. Following
concurrence by the Nuclear Regulatory Commission on the adequacy of the
remedial action, the State is free to retain the site or dispose of it in
accordance with the Uranium Mill Tailings Radiation Control Act. At this time,
however, the State is proposing to assign ownership to the City of Grand
Junction, with a public park as the likely projected future use. This report
anticipates that the State of Colorado will impose land-use restrictions, as
necessary, to protect the public health, safety, and the environment. The
Bureau of Land Management transferred the disposal cell to the Department of
Energy prior to remedial action. The disposal cell will be maintained in
accordance with a license issued by the Nuclear Regulatory Commission.
Therefore, the offsite disposal cell will remain under Department of Energy
Controlled Access for the life cycle of this estimate.
ENVIRONMENTAL RESTORATION
Surface remedial action has been completed and the source of contamination has
been stabilized. However, residual milling-related contaminated ground water
remains.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2015
|
2020
|
2025
|
2030
|
| UMTRA Surface
|
|
|
|
|
|
|
|
|
| Assessment
|
509
|
|
|
|
|
|
|
2,545
|
| Remedial Action
|
9,229
|
|
|
|
|
|
|
46,146
|
| UMTRA Ground water
|
|
|
|
|
|
|
|
|
| Assessment
|
264
|
102
|
63
|
|
|
|
|
2,144
|
| Remedial Action
|
6
|
112
|
42
|
|
|
|
|
801
|
| Direct Program Management/Support
|
3,053
|
778
|
505
|
|
|
|
|
21,681
|
| Total |
13,060
|
992
|
611
|
|
|
|
|
73,317
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Surface Project
The cleanup effort associated with the Grand Junction site has comprised
remediation of tailings at the former processing site as well as remediation of
over 4000 vicinity properties. All contaminated site materials were removed
from the processing site by spring 1994, with site restoration (seeding and
wetlands establishment) completed in August 1994. Approximately 3.1 million
cubic meters (4.1 million cubic yards) of contaminated materials were
transported 27 kilometers (17 miles) to the Cheney disposal cell. The capacity
of the disposal cell is 3.4 million cubic meters (4.5 million cubic yards). The
Completion Report describing these activities has been written and submitted to
the Nuclear Regulatory Commission for review.
Some ongoing vicinity property cleanup continues in Mesa County, with materials
transported to a reserved area of the Cheney disposal cell. The UMTRA Program
is currently planning to accept vicinity property tailings until February 1998,
with completion of the cell cover by September 1998. However, the Department of
Energy is working closely with the State of Colorado and the City of Grand
Junction to develop a Long-Term Radon Management program for disposition of
additional vicinity property tailings past the FY 1998 cut-off date, while
keeping within the cell capacity of 3.4 million cubic meters (4.5 million cubic
yards). If that program is not implemented, then Nuclear Regulatory Commission
site certification and licensing will occur in FY 1999, with transfer of the
Cheney disposal cell to the Grand Junction Projects Office's Long-Term
Surveillance and Maintenance program in early FY 2000.
Although all UMTRA sites require some vicinity property cleanup, no other
single site has as many vicinity properties to clean up as Grand Junction.
Additionally, the remediation of many of these vicinity properties is complex.
For this reason, there are two remedial action contractors. One remedial action
contractor is tasked with the remediation of the Grand Junction processing site
tailings and another remedial action contractor, located in the Grand Junction
Projects Office, is tasked with the remediation of the vicinity properties
associated with the Grand Junction former processing site. The site remedial
action contractors have trucked the tailings found at the vicinity properties
to the processing site for transport to the Cheney disposal cell.
Major Surface Project Milestones
| Vicinity Property Remedial Action
|
1998
|
|
Nuclear Regulatory Commission Issues General License
|
1999
|
|
Transfer Disposal Cell to Grand Junction Projects Office Long-Term Surveillance
and Maintenance Program
|
2000
|
The Grand Junction Remedial Action Plan outlined the necessary contaminant
distribution and remediation. The Remedial Action Plan, which requires
concurrence by the Nuclear Regulatory Commission, was published in December
1994.
The processing site has been fully characterized, and no further monitoring
under the Surface Project is occurring. However, radiological monitoring is
still being performed at the Cheney disposal cell to ensure that no
contaminants are being released into the air during the vicinity property
remediation efforts. In addition, several wells were placed adjacent to the
disposal cell to monitor water quality.
The Long-Term Surveillance Plan, which describes how the disposal cell will be
managed, will be written concurrently with the Cheney disposal cell Completion
Report and final Audit Report. The latter two documents will be included as
part of the Department of Energy's site Certification Report, which explains
that the processing site has been cleaned up according to the provisions of the
Remedial Action Plan. The site Certification Report and the Long-Term
Surveillance Plan will be submitted to the Nuclear Regulatory Commission for
concurrence as the first step towards licensing the Cheney disposal cell.
The UMTRA Surface Project will conduct surveillance and maintenance of the
disposal cell after the completion of the remedial action and prior to its
transfer to the Grand Junction Projects Office's Long-Term Surveillance and
Maintenance program in FY 2000.
Ground-Water Compliance Project
The Department is developing a Programmatic Environmental Impact Statement
pertaining to all 24 UMTRA sites. (For a discussion of the Programmatic
Environmental Impact Statement, see the UMTRA Program narrative in the New
Mexico section of this report.) Site-specific National Environmental Policy Act
documentation will be developed to propose an appropriate ground-water
compliance strategy and reasonable alternatives for the Grand Junction site,
once the Programmatic Environmental Impact Statement is complete.
Cost estimates for this report assume a natural flushing ground-water
compliance strategy at the Grand Junction site, based on currently available
site characterization information. With this approach, contamination
concentrations can be reduced naturally to maximum, background, or alternate
concentration limits within 100 years, as established in the Environmental
Protection Agency standards. For all types of ground-water compliance
strategies, once the Nuclear Regulatory Commission determines this site to be
in compliance with Subpart B of the Environmental Protection Agency Standards
and it is certified, no additional long-term surveillance or monitoring will be
conducted.
The total volume of contaminated ground water is estimated to be 2.3 billion
liters (600 million gallons), and the contaminant plume extends offsite. The
ground-water contaminants of potential concern are cadmium, manganese,
molybdenum, sulfate, uranium, vanadium, arsenic, cobalt, fluoride, iron,
nickel, radium-226, and zinc. Background ground-water quality in the alluvium
shows uranium, molybdenum, and selenium concentrations, and net gross alpha
activities are above the maximum concentration limits.
The following milestone dates have been established for planning purposes.
Major Ground-Water Compliance Project Milestones
| Site Observational Work Plan
|
1995
|
|
Publish Environmental Assessment/Finding of No Significant Impact
|
2002
|
|
Publish Remedial Action Plan
|
2004
|
|
Compliance Strategy
|
2009
|
|
Licensing
|
2011
|
At the Grand Junction processing site, ground water occurs in alluvial sand and
gravel associated with the Colorado River. Uranium processing activities have
affected ground water in the alluvium (uppermost aquifer). The contamination
extends approximately 1,006 meters (3,300 feet) downgradient from the
site. The alluvial aquifer is not currently used in the vicinity of the
processing site for any known purpose. The current risk to human health or the
environment is limited because water used for domestic and most other purposes
is taken from the Grand Mesa Reservoir, approximately 40 kilometers (25 miles)
upgradient from the processing site.
Sampling of an onsite well that is downgradient indicates a slight increase in
uranium concentration since 1989. Contaminants within ground water near the
former Grand Junction processing site are moving downgradient toward the
Colorado River, which may be the ultimate point of discharge for local ground
water.
During the first ten years of remediation, verification monitoring will be
performed to ensure that natural flushing is working as predicted. The data
collected during this phase will be provided to the Nuclear Regulatory
Commission in a confirmation report. Upon acceptance of the confirmation
report, the site will be turned over to the Grand Junction Projects Office's
Long-Term Surveillance and Maintenance program. This program will conduct
Acompliance monitoring@ for up to 90 years. When maximum concentration limits
or background or alternate concentration limits have been achieved, a
certification report will be prepared to close out all Department of Energy
involvement at this site.
Direct Program Management/Support
Program management supports management efforts for the National Environmental
Policy Act process, site characterization and licensing, public
information/participation, applicable state and federal regulator costs,
quality assurance audits, program and management support for the technical
assistance contractor, special studies, document control, technical assistance
contractor site and technical management, cost and schedule controls, planning
and preparation of the federal budget, and the Environmental Management
Progress Tracking System.
FUNDING ESTIMATE
The following table presents estimated funding information for the Grand
Junction site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
| |
2015
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
13,060
|
992
|
611
|
|
|
|
|
73,317
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|
 |