|
Home
BEMR
Contents
U.S.
Map
COLORADO UMTRA SITES
The Durango, Grand Junction, Gunnison, Maybell, Naturita, Rifle (Old and New)
and Slick Rock (Old North Continent and Union Carbide) former processing sites
are nine of 24 uranium mill processing sites designated by the Uranium Mill
Tailings Radiation Control Act for remediation by the Department of Energy.
During the 1960s private firms processed most of the uranium ore mined in the
United States for the Atomic Energy Commission, a predecessor of the Department
of Energy. Congress passed the Act in 1978 in response to public concern
regarding potential health hazards from long-term exposure to uranium mill
tailings. It authorized the Department of Energy to stabilize, dispose of, and
control uranium mill tailings and other contaminated material at 24 uranium
mill processing sites and vicinity properties. For a general discussion of the
UMTRA Program, see the overview presented in the New Mexico section of this
report.
The cost estimate model used for this report provides costs for each of the
UMTRA sites. All costs for waste management activities, program management, and
relevant landlord activities attributable to the Department are provided for
within the scope of environmental restoration. There are no Uranium Mill
Tailings Radiation Control Act sites with either current or planned nuclear
material and facility stabilization activity needs. Funding for all sites is
100 percent nondefense.
Pursuant to the Uranium Mill Tailings Radiation Control Act, the Department of
Energy entered into a Cooperative Agreement in 1982 with the State of Colorado.
The agreement outlines the roles and responsibilities of each party. It also
delineates the cost sharing arrangement that states that the Department of
Energy is responsible for 100 percent of the assessment costs and 90 percent of
the remediation costs, and the state is responsible for the remaining 10
percent of the remediation costs. In addition, the Department of Energy is
responsible for paying 90 percent of the state*s costs. The Nuclear
Regulatory Commission concurred on the original agreement and is required to
concur on all major modifications thereafter.
DURANGO, COLORADO (UMTRA SITE)
The former Durango uranium processing site is located just outside the city
limits of Durango in southwest Colorado. The site is bordered on the east by
the Animas River, on the north by Lightner Creek, and on the southwest by
Smelter Mountain. Two tailings piles were located on the 59-hectare (147-acre)
site. Prior to the cleanup, the two tailings piles contained approximately
912,000 cubic meters (1.2 million cubic yards) of contaminated material and
covered four hectares (ten acres) of the site. The mill site and ore storage
area covered about 20 hectares (eight acres). The raffinate pond area was
located nearly 0.8 kilometers (one-half mile) southeast of the millsite and
covered about six hectares (15 acres).
LOCALITY MAP
Estimated Site Total
| (Thousands of Current Year Dollars)
|
|
|
|
|
|
| Environmental Restoration
|
369
|
493
|
1,345
|
618
|
882
|
Grey shaded area reflects annual cost
estimates for the first five years of the site BEMR Base Case (as of October
1995) and includes 3% annual inflation, see Readers' Guide.
|
| 1996 Appropriation
|
537
|
|
|
These levels reflect the current estimates for
compliance with applicable statutes and agreements (as of March 1996), see
Readers' Guide.
|
| 1997 Congressional Request
|
|
24
|
|
|
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
|
|
2020
|
2025
|
2030
|
| Environmental Restoration
|
|
|
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
FACILITY MISSION
The mission of the Durango mill site was to provide uranium for the United
States Government. The source of contamination was the residual tailings that
remained after the milling process extracted the uranium. The original mill was
built on the site of an old lead smelter that operated from 1880 to 1930. The
Vanadium Corporation of America designed and built the mill in 1942 to furnish
vanadium during World War II. In 1943, Vanadium Corporation reprocessed the
vanadium tailings to recover uranium for use in the Manhattan Project. The
original mill operated until 1946 and was then shut down until 1949 when
Vanadium Corporation of America contracted to sell uranium to the Atomic Energy
Commission. Vanadium Corporation of America leased and then later purchased the
property. Plant operation continued until March 1963, when the mill was shut
down permanently. Various owners held the property until 1990, when the State
of Colorado was granted ownership of the site.
SITE MAP
The Environmental Management program is responsible for cleaning up surface-
and ground-water contamination at the UMTRA sites. The Uranium Mill Tailings
Radiation Control Act designated the residual radioactive material found at
this site for cleanup and stabilization. The Act directed the Environmental
Protection Agency to promulgate standards (Code of Federal Regulations Title
40, Part 192) and the Department of Energy to perform the cleanup. It also
assigned the Nuclear Regulatory Commission to oversee and certify the cleanup,
as well as license the completed disposal cell.
FUTURE USE
Following concurrence by the Nuclear Regulatory Commission regarding the
adequacy of the processing site cleanup, control of the site will revert to the
State, for future use as deemed appropriate by the State and local authorities,
pursuant to the Uranium Mill Tailings Radiation Control Act. This report
assumes future use of the site to be unrestricted once the ground-water project
is complete. The disposal site will remain in the control of the Federal
Government and will be monitored and maintained in accordance with the Nuclear
Regulatory Commission-approved Long-Term Surveillance Plan.
ENVIRONMENTAL RESTORATION
Surface remediation action has been completed, and the source of contamination
has been stabilized. However, residual milling-related contaminated ground
water remains.
Environmental Restoration Activities Cost Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
|
|
| UMTRA Surface
|
|
|
|
|
|
|
|
|
| Remedial Action
|
28
|
|
|
|
|
|
|
140
|
| UMTRA Ground water
|
|
|
|
|
|
|
|
|
| Assessment
|
214
|
96
|
33
|
35
|
|
|
|
1,891 |
| Remedial Action
|
4
|
89
|
54
|
|
|
|
|
734
|
| Direct Program Management/Support
|
448
|
736
|
435
|
251
|
|
|
|
9,349
|
| Total
|
693
|
922
|
522
|
286
|
|
|
|
12,114 |
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
Surface Project
Remedial action was completed in May 1991 at the Durango former processing
site. All contaminated materials were relocated to an isolated disposal site in
Bodo Canyon, Colorado. Approximately 1.9 million cubic meters (2.5 million
cubic yards) of residual radioactive materials were remediated, including
remediation of 129 vicinity properties. The disturbed areas of the site were
backfilled with uncontaminated soil to a level compatible with the surrounding
terrain, recontoured to promote surface drainage, and revegetated. Site
certification by the Nuclear Regulatory Commission is scheduled for March 1996,
and Bodo Cell Nuclear Regulatory Commission licensing is expected in June 1996.
Major Surface Project Milestones
| Nuclear Regulatory Commission Issues Bodo Cell
General License
|
1996
|
|
Transfer Disposal Cell to Grand Junction Projects Office Long-Term Surveillance
and Maintenance Program
|
1996
|
The Durango Remedial Action Plan, which was concurred upon by the Nuclear
Regulatory Commission in December 1994, outlines the contaminant distribution
and remediation needed. The UMTRA Surface Project will conduct surveillance and
maintenance of the disposal cell after the completion of remedial action and
prior to its transfer to the Grand Junction Projects Office's Long-Term
Surveillance and Maintenance program in FY 1996.
Ground-Water Compliance Project
The Department is developing a Programmatic Environmental Impact Statement
pertaining to all 24 UMTRA sites. For a discussion of the Programmatic
Environmental Impact Statement, see the UMTRA program narrative in the New
Mexico section of this report. Site-specific National Environmental Policy Act
documentation will be developed to propose an appropriate ground-water
compliance strategy and reasonable alternatives for the Durango site once the
Programmatic Environmental Impact Statement is complete.
This report assumes a natural flushing ground-water compliance strategy. With
this approach, contamination concentrations can be reduced naturally to
maximum, background, or alternate concentration limits within 100 years, as
established in the Environmental Protection Agency standards. For all types of
ground-water compliance strategies, once the Nuclear Regulatory Commission
determines the site to be in compliance with Subpart B of the Environmental
Protection Agency Standards and the site is certified, no additional long-term
surveillance or monitoring will be conducted.
The total volume of contaminated ground water is estimated to be 984 million
liters (260 million gallons), and the contaminant plume extends offsite. The
ground-water contaminants of potential concern are antimony, cadmium, lead,
manganese, molybdenum, selenium, sodium, sulfate, uranium, vanadium, chloride,
arsenic, and thallium.
The following milestone dates have been established for planning purposes.
Major Ground-Water Compliance Project Milestones
| Site Observational Work Plan
|
2002
|
|
Publish Environmental Assessment/Finding of No Significant Impact
|
2003
|
|
Publish Remedial Action Plan
|
2005
|
|
Compliance Strategy
|
2011
|
|
Licensing
|
2011
|
Ground water at the former mill tailings area moves toward the Animas River.
The Animas River does not recharge the local aquifer. Ground-water samples
collected in previous years from the wells downgradient of the processing site
show the ground water is contaminated as a result of former uranium milling
activities. Hydrogeologic information on the aquifer characteristics, however,
indicates that the amount of ground water discharging to the Animas River is
small relative to the flow in the river.
During the first ten years of remediation, verification monitoring will be
performed to ensure that natural flushing is working as predicted. The data
collected during this phase will be provided to the Nuclear Regulatory
Commission in a confirmation report. Upon acceptance of the confirmation
report, the site will be turned over to the Grand Junction Projects Office's
Long-Term Surveillance and Maintenance program. This program will conduct
"compliance monitoring" for up to 90 years. When maximum concentration limits
or background or alternate concentration limits have been achieved, a
certification report will be prepared to close out all Department of Energy
involvement at this site.
Direct Program Management/Support
Program management supports management efforts for the National Environmental
Policy Act process, site characterization and licensing, public
information/participation, applicable state and federal regulator costs,
quality assurance audits, program and management support for the technical
assistance contractor, special studies, document control, technical assistance
contractor site and technical management, cost and schedule controls, planning
and preparation of the federal budget, and the Environmental Management
Progress Tracking System.
FUNDING ESTIMATE
The following table presents estimated funding information for the Durango
site.
Nondefense Funding Estimate
| (Five-Year Averages, Thousands of Constant 1996
Dollars)
|
|
|
| Environmental Restoration
|
693
|
922
|
522
|
286
|
|
|
|
12,114
|
| * Total Life Cycle is the sum of the annual costs in
constant FY 1996 dollars.
|
|
 |