Home
BEMR Contents
Page 2
Back to Page 1
Comparison of Results to the 1995 Baseline Environmental Management Report
The 1996 Base Case estimate is similar to the 1995 Base Case in some respects,
and quite different in other respects. The total 1995 Base Case estimate,
including productivity estimates, was $237 (constant 1996 dollars). This total
appears quite similar to the 1996 Base Case of $227 billion. There are
important differences, however, that reflect changes in analytical methods and
in the Environmental Management program as a whole.
First, the projected cost savings due to productivity improvements greatly
affect the estimates. The 1995 total Base Case estimate was reduced from the
sum of estimates provided by field offices ($360 billion in 1996 constant
dollars) to reflect a projection of the amount of overall improvement in
productivity expected. The 1996 Base Case does not include this type of
alteration of cost projections provided by field offices, and, therefore, does
not include an explicit productivity estimate. Instead, productivity is assumed
to be included in estimates provided by field offices. The 1996 Base Case is
essentially an integrated sum of estimates provided by field offices.
To reflect efforts underway to reduce costs, the Environmental Management
headquarters office applied substantial improvements in productivity up through
the year 2000 to the 1995 Base Case cost estimates provided by field offices.
This "top down" change in cost estimates reflected a goal of achieving an
approximately 20 percent increase in productivity and efficiency. Beyond the
year 2000, the Department assumed a sustained productivity improvement rate of
one percent compounded annually. Using these assumptions for projecting costs,
the 1995 total life-cycle cost estimate was $237 billion (in constant 1996
dollars). It is worthwhile to note, however, that the site cost estimates
reported in Volume II of the 1995 Baseline Report did not include productivity
projections, and total cumulatively to $360 billion (in 1996 dollars). If
comparable "top down" changes were made to the 1996 Base Case cost estimate
provided by the sites in the 1995 Base Case estimate, then an additional one
percent compounded annually would be applied to the 1996 Base Case estimate of
$227 billion after the year 2000. Imposing this additional productivity change
to the cost estimate provided by field offices would result in a 1996 Base Case
of approximately $195 billion in constant 1996 dollars.
Another difference between the 1995 and 1996 Base Case estimates is how the
range of estimated costs was calculated. In the 1995 report, the range of
$200-$350 was developed using different productivity assumptions.
Alternatively, the 1996 cost range of $189 billion to $265 billion is based on
site confidence in the cost estimates as reported.
Because total estimates submitted by the sites in 1996 ($227 billion) are
directly comparable to the total estimates submitted by the sites in 1995 ($360
billion), the 1996 Base Case of $227 billion is compared to the 1995 cost
estimate of $360 billion. The 1996 cost estimate is thus approximately
one-third lower than the 1995 estimate.
|
Productivity Improvement
A significant portion of the difference between the 1996 and 1995 cost estimates
results from productivity improvements, or the broader concept of performing
the program in a more intelligent way.
Figure 9 shows that sites attribute approximately 10 percent of the life-cycle
cost difference from 1995 to 1996 directly to productivity improvements. In a
broader sense, many other savings from the 1995 to the 1996 Baseline Report can
be considered productivity improvements. These savings result from executing
the same scope of work in a smarter, more efficient, and less costly manner.
For example, personnel at the Oak Ridge K-25 Site have learned that a large
amount of money can be saved by using rubble from decommissioning as backfill
for the below-grade structure. The result: completing a similar scope of work
with the same risk profile at a lower cost.
Adopting explicit productivity improvements and incorporating smarter, more
efficient solutions to the problems of implementing the Environmental
Management program indicate that the sites have, in effect, assimilated last
year's productivity improvement goals, which changed the Base Case estimate
from the $350 billion provided by site personnel to $230 billion, into the
life-cycle cost estimates in the 1996 Baseline Report.
|
Figure 9. Comparison of 1995 and 1996 Baseline Report Cost Estimates
The Benefits of a New Base Case
The 1996 Base Case analysis is significantly more useful than the 1995 analysis
for several reasons, all of which result from the "bottom-up" estimating
approach. First, the data are generally more reliable at a more detailed level.
By moving the estimating process closer to the knowledge base in the field, the
Department has built the report on a better quality data base. As a result, the
analyses of state, site, and project costs are considerably more rigorous and
accurate than those in the 1995 estimate.
Second, the analysis of cost estimates principally by field personnel (by
contrast, approximately half of the 1995 cost estimates were developed by
Headquarters personnel), has had a number of collateral benefits that should
help improve program management capabilities, thereby helping to reduce costs.
As a result of this process of compiling the cost estimates, the Department now
has a cadre of experienced life-cycle cost analysts. Field personnel have been
encouraged and empowered to define meaningful long-range assump tions and
outline long-term strategies for their sites. This capability provides a better
basis for integrated site planning and facilitates better communication with
regulators and other stake holders, as well as between sites and program areas.
Sites also were encouraged to develop their Base Case estimates with input from
integrated project teams, to identify interdependencies between programs, and
to work together to resolve conflicting assumptions. The integration effort
enhanced the quality and usefulness of the final product.
Major Differences Between the 1995 and 1996 Estimates
-
The 1996 Base Case is $133 billion (36.9 percent) lower than the 1995 Base
Case.
-
The duration of the 1996 Base Case is shorter than the duration of the 1995
case. Remediation at eighty percent of sites is expected to be complete by 2021
in the 1996 estimate as opposed to 2035 in the 1995 estimate.
-
1996 Base Case waste volume projections are lower than the comparable 1995
projections.
-
The 1996 Base Case reflects less costly environmental management strategies (to
achieve essentially the same risk reduction goal), particularly for facility
decommissioning and waste management, than the 1995 Base Case.
|
1995 Versus 1996 Estimate - Reasons for Differences
Two major factors underlie the differences between the 1995 and 1996 estimates.
For the 1996 report, the Environmental Management program has better knowledge
of the scope of the program and a better understanding of how to achieve this
scope cost-effectively. A detailed analysis indicates that more accurate
information results in a different 1996 life-cycle cost estimate for four
reasons: change in scope of the estimate, change in technical assumptions for
addressing environmental problems, change in anticipated productivity
improvements, and change in the analytical model used to estimate costs. Table
7 provides definitions and examples for each reason.
Table 7. Example of Differences in the Estimates
|
Reason |
Definition |
Representative Example |
| Change in Scope |
Change in the nature or magnitude of environmental problems being addressed. |
Since preparing cost estimates for the 1995 report, Hanford Site waste
management personnel have gained a clearer understanding of the volume of waste
that will be generated by the Environmental Restoration program. This
understanding translated into lower volumes in the 1996 estimate than the 1995
projections. |
| Change in Technical Assumptions for Addressing Environmental Problems |
Change in technical approach, strategy, or schedule for addressing an
environmental problem. |
In late 1995, the Department of Energy signed an agreement with the State of
Idaho that accelerates the cleanup of the Idaho National Engineering
Laboratory. The acceleration reduces storage and surveillance and maintenance
costs that depend on the pace of the cleanup.
At Oak Ridge Reservation, the 1996 report reflects commercial management of
waste. By contrast, Oak Ridge Reservation assumed government management of this
waste in 1995. Oak Ridge Reservation personnel anticipate that commercial waste
management will be less costly than government waste management.
|
| Change in Anticipated Productivity Improvements |
Change in amount of work that can be performed by a given input. |
The Savannah River Site is undergoing several restructuring efforts including
business re-engineering, consolidation, and fixed-price subcontracting, that
are leading to productivity increases.
The Pantex Plant is increasing productivity through waste minimization efforts.
|
| Change in Estimating Models |
Use of different unit cost estimates, cost estimating algorithms, or models. |
For the 1995 report, Headquarters modeled all nuclear material and facility
stabilization direct mission costs using a standard scheduling scenario. In
1996, large sites estimated these costs based upon realistic scenarios. |
Although Table 7 presents four main categories for changes in cost estimates,
there is not always a clear delineation between the categories. Some cost
differences are caused solely by one factor. For example, a decrease in spent
nuclear fuel disposal costs from the 1995 estimate to the 1996 estimate is due
to a change in the cost estimating model site models were used in 1996
rather than the national model used in 1995. Other cost differences cannot be
classified so simply. For example, success in waste minimization can be
described as both a reduction in scope and an improvement in productivity.
The scope of the estimate is smaller (i.e., fewer activities to be estimated)
in the 1996 estimate than in 1995. Technical assumptions for addressing
environmental problems have changed from 1995 to 1996. In general, the 1996
estimate reflects less costly technical approaches to facility decommissioning
and waste management.
The majority of the cost reduction in the 1996 report occurs in five major
Environmental Management activities (Table 8):
-
Facility decommissioning cost estimates dropped primarily due to a change in
technical approach. In the 1996 report, site plans reflect a better
understanding of the scope of decontamination activities required prior to
facility demolition.
-
To treat and store low-level, low-level mixed, and transuranic waste, sites
assume the use of less costly commercial waste management facilities rather
than more costly government facilities. Sites also plan to reuse existing
government facilities instead of building new ones. Other cost reduction
factors include better estimates of waste volume and more aggressive waste
minimization and recycling efforts.
-
Sites plan to accelerate spent nuclear fuel disposal at a national geologic
repository. A reduction in cost also stems from the use of better methods to
estimate disposal costs.
-
Some sites have reduced the required scope of remedial activities based on the
results of recent negotiations with regulators. These estimates also reflect
more insight to the potential results of future agreements.
-
Program management and other support cost estimates are lower because the
estimates for direct mission activities are lower.
Table 8. Overview of Activities with Large Reduction in Cost Estimates from 1995
to 1996
|
Activity Area |
1995 Estimate |
1996 Estimate |
Difference |
Primary Driver |
| Facility Decommissioning |
$47.2 Billion |
$18.2 Billion |
$29.0 billion
(63 percent) |
Sites plan to perform less decontamination before demolition because of a
better understanding of the scope of decontamination that is necessary before
facility demolition. |
| Low-Level Waste, Low-Level Mixed Waste, and Transuranic Waste Treatment and
Disposal |
$54.9 Billion |
$32.0 Billion |
$22.9 billion
(42 percent) |
Sites plan to use less costly commercial waste management facilities rather
than more costly government facilities. Sites also plan to reuse existing
government facilities instead of building new ones.
Better waste volume estimates and aggressive waste minimization and recycling
efforts.
|
| Spent Nuclear Fuel Disposal |
$11.8 Billion |
$4.1 Billion |
$7.7 billion
(65 percent) |
Acceleration of spent nuclear fuel disposal at a national geologic repository
and use of better estimation models. |
| Remedial Activities |
$24.4 Billion |
$17.5 Billion |
$6.9 billion
(28 percent) |
New agreements with regulators and more accurate predictions of the results of
future agreements. |
| Program Management and Other Support Activities |
$87.2 Billion |
$57.2 Billion |
$30.0 billion
(34 percent) |
Support and program management cost estimates are lower because less management
and support is necessary for mission activities. |
Although cost estimates generally are lower in 1996 than in 1995, life-cycle
estimates for several Environmental Management activities did not change
significantly. These include high-level waste management, surveillance and
maintenance of facilities, and support/landlord activities for the nuclear
material and facility stabilization program. Note that the 1995 estimates have
been inflated to constant 1996 dollars for this comparison.
Differences By Site
Almost all of the $133 billion reduction in estimated costs from the 1995
Baseline Report occurs at the five highest-cost sites (Figure 10).
-
At the Hanford site, the estimate for waste management support costs dropped
from $15 billion in the 1995 report to $7 billion in 1996. This reflects the
overall lower estimates for direct mission costs in the 1996 estimate. Also,
low-level and low-level mixed waste management cost estimates dropped from $10
billion in the 1995 report to $3 billion in 1996 due to lower expected waste
volumes.
-
At the Idaho National Engineering Laboratory, a change in schedule accounts for
the major difference between the 1995 and 1996 estimates. An agreement signed
by the Department of Energy and the State of Idaho requires the Department to
remove all spent nuclear fuel from the state by 2035 (15 years earlier than
previously planned); to prepare all high-level waste for disposal by 2035 (15
years earlier than previous estimates); and to begin transuranic waste
shipments to the Waste Isolation Pilot Plant in 1999.
-
At the Oak Ridge Reservation, the majority of the cost difference ($14 billion)
is due to changes in the technical approach for waste management and
decommissioning. The 1996 report emphasizes commercial rather than government
treatment and disposal, a less costly strategy. The decrease in decommissioning
estimates reflects a change in decommissioning strategies for the gaseous
diffusion plants.
-
At the Rocky Flats Environmental Technology Site, facility decommissioning cost
estimates dropped from $11 billion in 1995 to $4 billion in 1996 due to a
decrease in the amount of decontamination activities anticipated to be
performed prior to demolition. Low-level and low-level mixed waste management
cost estimates decreased from $5.5 billion to $1.2 billion reflecting a
reduction in expected waste volumes and a shift from offsite disposal strategy
to a mixture of onsite and offsite disposal.
-
At the Savannah River Site, the facility decommissioning cost estimate dropped
from $12 billion in 1995 to $7 billion in 1996 primarily due to the assumption
of a less costly technical approach to decommissioning reactors and canyons. In
addition, support cost estimates for waste management and nuclear material and
facility stabilization activities dropped from $20 billion in 1995 to $10
billion in 1996 because the 1996 estimate reflects a smaller program and fewer
direct mission costs.
Figure 10. Comparison of the 1995 and 1996 Cost Estimates for the Five
Highest-Cost Sites
Alternative Scenarios
A number of significant assumptions underlie the Base Case estimate. Varying
these assumptions can often influence the overall life-cycle cost estimate. To
help inform national policymaking and local decisionmaking processes, the 1996
Baseline Report provides a more rigorous analysis of alternative program
scenarios. By changing certain key assumptions we are able to examine the
influence of each factor on the life-cycle cost and schedule of the
Environmental Management program. The analyses varied assumptions regarding the
following three factors expected to influence program costs:
-
Land Use
What effect do future land-use decisions have on the overall scope, cost,
and schedule of cleanup for Environmental Management sites? What factors limit
consideration of land uses?
-
Program and Project Scheduling
What are the cost consequences of delaying and accelerating programs and
projects? What is the relationship between program pace, schedule, funding
levels, and total life-cycle cost?
-
A "Minimal Action" Scenario What is the minimum funding required
for preventing risks to human health and the environment from increasing for 75
years without the constraints of current legal requirements?
The approach for estimating life-cycle costs for the alternative scenarios
mirrors the basic methodology employed for the Base Case estimate. Site
estimates and assumptions provided the basis for these analyses. The land-use
analysis varies from the Base Case in that the analysis assumes different end
states suitable for various uses, and measures the cost and waste volume
consequences of cleaning up to these alternative end states. The program and
project scheduling analysis assumes the same actions and subsequent end states
for programs and projects as described in the Base Case, but applies funding
and scheduling constraints to better analyze the cost consequences of
accelerating or delaying programs and projects. The minimal action scenario
uses methods developed by site personnel to re-scope projects and activities to
meet a set of minimal action assumptions. Therefore, the minimal action case
diverges dramatically from the Base Case. No scenario examines the impact of
changing existing regulatory requirements.
The three alternative scenario analyses focus on the five sites in the
Environmental Management program estimated to have the highest life-cycle costs
- Hanford Site, Washington; Idaho National Engineering Laboratory, Idaho; Oak
Ridge Reservation, Tennessee; Rocky Flats Environmental Technology Site,
Colorado; and, Savannah River Site, South Carolina. Together, these sites
account for approximately 70 percent of the Environmental Management total
program cost estimate.
Land Use
One of the primary difficulties in estimating the total cost of the
Environmental Management program is that future land use (e.g., the ultimate
disposition of lands currently managed by the Department) generally has not
been determined. Until the future land uses are decided there is a considerable
amount of uncertainty regarding the degree of cleanup required and the
resulting program cost.
The land-use analysis in the 1995 Baseline Report indicated that decisions
affecting future land use could affect total program cost by billions of
dollars. It was a broad analysis, without site-specific data. The analysis in
the 1996 report provides site-specific data and focuses more narrowly on how
land-use decisions may affect environmental restoration activities and
associated waste management costs. The analysis also quantifies the amount of
land achieving various uses under a set of alternative assumptions. The 1996
analysis also considers real-world constraints on the future uses that can be
achieved. Such constraints include ongoing program missions, legal commitments,
the presence of unique or sensitive ecological systems, and the limits of
current technology.
Using the underlying land-use assumptions in the Base Case as the point of
reference, this analysis examines the effect of the following five alternative
land-use scenarios on the estimated life-cycle costs of the Environmental
Management program: Maximum Feasible Green Fields, Modified Green Fields,
Recreational, Industrial, and Iron Fence.
These five scenarios were chosen to represent varying land-use outcomes (and
differing levels of cleanup). The "Maximum Feasible Green Fields" and "Iron
Fence" scenarios were chosen to represent the two endpoints of the land-use
continuum reasonably attained at the five highest-cost sites. The
"Recreational" scenario represents an inter mediate land-use end state without
access restrictions, while the "Industrial" scenario represents an intermediate
land-use end state with access restrictions. The "Modified Green Fields"
represents a special scenario that illustrates how an aggressive clean up
strategy might be tempered when considering continued Department of Energy
missions at these five large sites.
|
Scenarios Are Not Decisions
Scenario analyses attempt to identify a set of possible futures, each of which
is plausible, but not assured. These analyses are intended to foster and help
inform local and national debate regarding potential policy strategies for the
Environmental Management program. Each scenario provides an explicit framework
for further discussion and reaction. The analyses were developed using
assumptions that are hypothetical in nature, assumptions that do not reflect
plans or proposals by the Department of Energy or the Environmental Management
program.
|
Each of the three scenarios is a combination of three variables that
significantly impact environmental restoration activities: (1) level of
existing contamination, (2) future use assumption, and (3) site-specific
constraints. Future use assumptions (goals) determine the types of activities
that are assumed to occur in the future, the possible pathways of exposure, and
the type and extent of environmental restoration activities that may be
required. Site-specific constraints place limits on the land-use goals such as:
technology limitations, unacceptable risks to remediation workers, ongoing
Department of Energy activities, legal commitments, and ecological sensitivity.
The level of existing contamination and the remedial action required to meet a
specific land-use goal further affects environmental restoration activities. In
most cases some remedial action will be required, even to meet disposal
/storage area standards. In some areas, however, existing contamination is
sufficiently low that remedial action may be required under some future use
assumptions (e.g. Residential) but not others (e.g. Open Space). The estimated
cost is based on performing enough clean up to allow for the intended land use,
but no more. As a consequence, the postulated remedy for a plot of contaminated
soil might be containment (capping) under the Iron Fence, Industrial,
and Recreational scenarios, but removal under the two Green Fields
scenarios. For areas with site-specific constraints, the Base Case remedial
strategy was generally left unchanged across all scenarios. The only exception
was the Maximum Feasible Green Fields scenario, in which all site-specific
constraints were lifted except for technology constraints, and certain waste
disposal areas at the Hanford Site, Idaho National Engineering Laboratory, and
the Savannah River Site. Table 9 summarizes the assumptions and life-cycle cost
estimates for each of the land-use scenarios.
Table 9. Land-Use Case Assumptions
|
Land-Use Scenario |
Land-Use Category |
Assumption |
Life-Cycle Cost Estimate (Constant 1996 Dollars in Billions) |
Change from Base Case |
| Maximum Feasible Green Fields |
Residential or Agricultural/td>
| Aggressive cleanup goals to support residential and agricultural uses
Ignore most site-specific constraints
Removal of all contaminated media or materials
|
$284 |
77% |
| Modified Green Fields |
Residential or Agricultural |
Aggressive cleanup goals to support residential and agricultural uses
Consider all site-specific constraints
Combine removal and containment strategies
|
$166 |
6% |
| Recreational |
Recreational |
Contaminated areas remediated to support recreational uses
Consider all site-specific constraints
Combine removal and containment remediation strategies
|
$162 |
1% |
| Industrial |
Industrial |
Contaminated areas remediated to support industrial uses
Consider all site-specific constraints
Emphasize containment rather than removal strategies
|
$155 |
3% |
| Iron Fence |
Disposal/Storage Area |
Contaminated areas remediated to support disposal/storage land uses (i.e.,
controlled access)
Consider all site-specific constraints
Containment and monitoring of all contaminated media or material (unless remove
was less expensive)
|
$150 |
6% |
Estimated costs for the Environmental Management program at the five
highest-cost sites range from $150 billion for the Iron Fence scenario to $284
billion for the Maximum Feasible Green Fields scenario (Figure 11). These
estimated costs are respectively 6 percent lower and 77 percent greater than
the Base Case estimate of $160 billion for these five sites. When site-specific
constraints are considered (i.e., Iron Fence through Modified Green Fields),
there is little difference in estimated cost among the alternative scenarios.
The estimate for the Modified Green Fields scenario ($166 billion) is only 10
percent greater than the estimate for the Iron Fence scenario and 6 percent
greater than the Base Case estimate. The Base Case estimate falls between that
of the Industrial scenario ($155 billion) and the Recreational scenario ($162
billion). It is important to remember that these are generalized findings, and
that actual land use will likely vary significantly among different sites.
Figure 11. Cost by Land-Use Scenario
The land-use analysis shows that the effect of land-use decisions, after
considering site-specific constraints, is relatively narrow. This result is
vividly illustrated when one compares the Maximum Feasible Green Fields to the
Modified Green Fields scenario. Both scenarios employ the same aggressive clean
up standards, but yet yield dramatically different results. The reason is that
consideration of the constraints outside of technological limitations yields an
additional 141,000 hectares (350,000 acres) of Residential and Agricultural use
at an increased cost of approximately $118 billion. This difference in results
leads to the conclusion that site-specific considerations are of critical
importance in land-use planning.
Many of the site-specific constraints examined in this analysis stem from
federal and local policies or priorities. For example, legal commitments and
local regulations limit future use options for approximately 295,000 hectares
(730,000 acres) (63 percent) of the uncontaminated land at the five
highest-cost sites. In addition, the presence of endangered species and
ecologically unique habitats may limit future use of approximately 57,000
hectares (140,000 acres) (12 percent) of uncontaminated land and some
contaminated land at these sites. It will be necessary to consider these
constraints, along with stakeholder and regulator preferences, in order to make
ultimate decisions regarding future use. Near-term resolution of these issues
is important, because the decisionmaking processes that govern environmental
restoration activities will continue in the absence of coherent integrated site
planning. Land-use options may become limited after deployment of certain
remedial strategies, or remedies designed to meet residential standards may be
applied inappropriately, resulting in higher than necessary costs.
The siting of disposal/storage areas and continuing Department missions have
implications beyond the land directly around these structures. The implications
of these future missions on land-use alternatives underscores the importance of
clarifying overall Department goals and developing integrated, complex-wide,
multimission facilities plans.
Technological challenges relating to ground water and surface water will
continue to limit land-use alternatives in the near term. Information relating
to technological limits and costs of aggressive remediation strategies should
be integral to all decisionmaking activities regarding land use and remedial
strategies.
Program and Project Scheduling
Many observers have speculated that the pacing of the Environmental Management
program has a significant impact on life-cycle cost. In very simple terms,
there is an expectation that costs will increase if the program is extended and
decrease if cleanup activities are completed more rapidly. Given the scale of
Environmental Management projects, their cost, and the long-term commitment
required, it is important to fully understand the relationship between cost and
schedule. A clear understanding of how these two factors interact provides a
basis for effective long-term planning and greater integration of the component
activities of the program.
The Department developed three alternative scheduling scenarios for the
analysis. (Note: all scenarios were developed independent of compliance
agreements and potential fines and penalties.) Two of these scenarios are
highlighted.
Funding Reduction The current Base Case projects that annual
funding requirements will increase to $7.5 billion in FY 2000. The National
Defense Authorization Act, which mandates the Baseline Report, requires the
Department to provide a cost estimate associated with complying with existing
compliance agreements regardless of budget targets. Because the Base Case cost
estimate clearly exceeds expected funding availability, it is prudent to
analyze the long-term impacts of reduced funding using a scenario that
constrains the overall program spending. This is exactly what is analyzed
through the Funding Reduction case, which constrains the Environmental
Management program's annual budget to $4.9 billion ($5.5 billion for FY 2000
when converted into constant 1996 dollars). The results of this analysis are
shown in Figure 12 and indicate:
-
There is a $49 billion increase in life-cycle cost largely due to increased
pretreatment storage for high-level waste, increased surveillance and
maintenance for plutonium storage buildings and chemical separations
facilities, and support costs. Support costs account for roughly half of the
life-cycle cost increase.
-
Support costs do not decrease proportionately as the Environmental Management
budget is reduced. Many support activities such as safeguards and security
cannot be reduced below a certain minimum as long as any amount of special
nuclear material is present at a facility. Consequently, reduced funding,
combined with relatively constant support costs, result in fewer resources
available for cleanup activities. In the Funding Reduction scenario, cleanup
activities are delayed, thereby stretching out the duration of the
Environmental Management program about 20 years.
Figure 12. Annual Comparisons of the Funding Reduction for the Five Highest
Cost Sites
Delaying Waste Disposal Base Case costs are based on the
availability, begin ning in 2016, of a national geologic repository for
high-level waste. This scenario analyzes the impact of a 30-year delay in
disposal at this repository on the life-cycle costs of the Environmental
Management program. The results of this scenario:
-
A 30-year delay increases total life-cycle costs by about one percent ($1
billion).
-
The increase in total life-cycle cost above the Base Case is due to longer
durations in waste storage and support cost durations.
Figure 13 provides life-cycle cost comparisons of the Base Case and two
alternative scheduling scenarios.
Figure 13. Comparison of Alternative Scheduling Scenarios Life-Cycle Cost
Estimates for the Five Highest-Cost Sites
Note: The costs incurred by a delay in waste shipments to a repository for this
analysis represent only those direct costs to the Environmental Management
program. This analysis does not account for any costs incurred by the
Department's Civilian Radioactive Waste Management program. The results of this
analysis are not to be applied to the commercial nuclear industry or to costs
associated with the disposal of commercial nuclear waste.
A "Minimal Action" Scenario
The current budget deficit and the growing need to reassess national priorities
lead to a controversial yet pragmatic question: What is the minimum funding
required for maintaining the Environmental Management program without
jeopardizing human health or the environment and without the constraints of
current environmental regulations and compliance agreements? The interest in
this "minimal action" scenario is driven by a number of diverse perspectives on
the program. Some observers, especially supporters of the current program, have
speculated that the cost of a minimal action scenario is not significantly
different from current program expenditures (especially in the short term).
This view is based on the fact that a large amount of funding currently is
required simply for the program to serve as the landlord at Environmental
Management sites and to monitor the storage of highly radioactive waste and
special nuclear materials.
Other observers, especially critics of the current regulatory system, believe
that current requirements can be relaxed, generating a substantial cost savings
without negative human health and environmental consequences. Finally, policy
-makers express interest in this minimal action case because it provides a
lower boundary for the range of alternatives available to the program. With
this information in hand, policymakers and stakeholders can better understand
what tasks are truly necessary for short- and long-term risk and cost
reduction.
The Minimal Action scenario examines the costs necessary for preventing human
health and environmental risks from increasing from current levels to workers
and offsite individuals, and minimizing costs during a period comparable to the
Base Case period (i.e., 75 years). Costs devoted solely to meeting compliance
agreements and regulatory requirements were not included.
Personnel at each site developed a site-specific minimal action scenario. Using
the 1996 Base Case data as a foundation, each site developed site-specific
assumptions and 75-year cost estimates. From the Base Case, site personnel
modified their project and activity schedules and assumed scopes of work based
on minimal action assumptions. Table 10 depicts these minimal action
assumptions.
Table 10. Cross-Site Assumptions for Minimal Action Scenario
Waste Type/
Project Area |
Base Case Assumption |
Minimal Action Case Assumption/th>
|
| High-Level Waste |
To be disposed of in a geologic repository. |
Onsite storage. Differing treatment and stabilization practices across sites. |
| Spent Nuclear Fuel |
To be disposed of in a geologic repository. |
Onsite storage in concrete or stainless steel "dry storage" casks. |
| Low-Level, Low-Level Mixed, and Transuranic Waste |
Some treatment of low-level and low-level mixed waste; dispose of offsite.
Treat transuranic waste and ship to Waste Isolation Pilot Plant. |
Storage and disposal onsite with minimal treatment. |
| Environmental Restoration |
Remediate (cleanup) all areas required by environmental regulations/compliance
agreements. Buildings will be demolished. |
Remediate only areas with urgent environmental or human risk implications.
Buildings will be remain in place. |
| Nuclear Material and Facility Stabilization |
Nuclear materials stabilized. Deactivation activities to minimize surveillance
and maintenance. |
Same as Base Case. |
| Support |
All costs to support mission activities. |
Re-estimation based on minimal action activities. Support activities extended
through 2070 at all sites. |
After identifying the projects and activities that would fulfill this minimal
action case, each site evaluated cost differences through 2070, described the
resulting situation in 2070, and analyzed what additional costs and risks might
be incurred beyond 2070. The results of this analysis indicate that:
-
Costs during the 75-year Minimal Action period would be more than 40 percent
less than the Base Case.
-
Eliminating most environmental restoration activities reduces estimated
environmental restoration costs by 70 percent.
-
Minimum onsite treatment and disposal of low-level, low-level mixed, and
transuranic waste reduces the cost estimate by 54 percent for those waste
types.
-
Eliminating offsite shipping and disposal activities at the Hanford Site, Idaho
National Engineering Laboratory, and the Savannah River Site reduce high-level
waste cost estimates by 43 percent.
-
Although estimated costs during the 75-year period decrease by more than
40 percent, estimated costs for these activities after the 75-year
period are significantly higher than the Base Case.
The general cost differences under this scenario analysis compared to the
75-year Base Case cost estimate are presented in Figure 14 (total costs) and
Figure 15 (cost by functional area).
Figure 14. Base Case Cost Estimates for the Five Highest-Cost Sites
Figure 15. 75 Year Estimates for the Five Highest-Cost Sites
The difference in the estimated costs between the Base Case and the Minimal
Action case reflects the costs of buying very different "end states" at the end
of the 75-year period. Unlike most situations in the Base Case, the Minimal
Action case leaves waste inventories onsite. This requires not only continual
surveillance and monitoring activities, but also increases long-term risk of
contamination to onsite and offsite receptors. Under the Minimal Action case,
buildings left standing require long-term surveillance and monitoring, which
may pose a potential risk to workers as these facilities continue to
deteriorate. Therefore, reducing costs during the Minimal Action period may
actually produce greater costs beyond 2070.
In addition to analyzing a lower cost end state, the Minimal Action case
suggests a third alternative scenario: any savings gained from a minimal action
case approach could be used to develop and use new technologies to address any
post-life cycle remediation activities or other end-state risks. Under this
strategy, a comparable end state might be achieved with new technologies
developed using savings that result from initially focusing activities on risks
to workers, offsite populations, and mortgage cost reduction. In creased
funding of new technologies also could be directed at long-term waste storage
and disposal strategies, which could alleviate the need for sites to continue
repackaging stored waste.
Comparison of Alternative Cases
Because the Environmental Management program is only seven years into a
projected life cycle period that could span over 75 years, decisions yet to be
made may dramatically change the direction of the program. The results of the
alternative cases provide an understanding of how changes in scope and schedule
can influence program costs and end states a first step toward assessing
program options.
To accurately compare these alternative cases to the Base Case, all cost
estimates are presented for the 75-year Base Case life-cycle period
(1996-2070). In three of the alternative cases (Maximum Feasible Green Fields,
Funding Reduction, and Minimal Action), the change in scope and schedule
require the program to extend beyond 2070. Both the Maximum Feasible Green
Fields case and the Funding Reduction case estimate the program to complete
around 2080. In the Minimal Action case, the length of time required to
complete the program was not determined but is assumed to continue past 2070
for purposes of comparison to the Base Case.
The 75-year cost estimates of the Base Case and alternative cases for the five
highest-cost sites range from less than $90 billion (Minimal Action) to more
than $272 billion (Modified Feasible Green Fields). Figure 16 shows the range
of 75-year cost estimates for each of the nine alternative cases and the Base
Case.
Figure 16. 75-Year Cost Estimates for the Five Highest-Cost Sites
Each alternative scenario has cost and benefit implications, as Table 11
illustrates.
Table 11. Benefits and Losses of the Alternative Cases
Alternative
(75-Year Cost Difference from Base Case) |
Benefits |
Losses |
| Land Use |
Iron Fence
(-$10 billion) |
Less cost over period of analysis
Maintains minimum protection of public and site workers
|
More land retained as controlled access for waste disposal |
| Land Use |
Industrial
(-$5 billion) |
Similar cost over period of analysis |
Reduces potential Recreational and Residential use of land outside controlled
areas |
| Land Use |
Recreational
(+$2 billion) |
Similar cost over period of analysis
Increase in land clean enough for Recreational uses
|
Reduces potential Residential use of land outside controlled areas |
| Land Use |
Modified Feasible Green Fields
(+$6 billion) |
Land clean enough to support Residential and Agricultural uses
Maintain potential for continued federal activities with reuse of site
facilities
|
More expensive over period of analysis |
| Land Use |
Maximum Feasible Green Fields
(+$112 billion) |
Land clean enough to support Residential and Agricultural uses
All land at Rocky Flats and Oak Ridge is cleaned to residential use standards
Minimal long-term surveillance and monitoring
Activities exceed compliance and regulatory requirements
|
Significantly more expensive over period of analysis
Extensive cleanup activities may damage sensitive habitat
Reduces potential for reuse of site facilities
Program duration exceeds Base Case
|
| Scheduling |
Accelerating Stabilization & Deactivation
(-$1 billion) |
Similar cost over period of analysis
Complete high mortgage projects faster
|
Requires additional resources for Nuclear Material and Facility Stabilization
program in early years. |
| Scheduling |
Delaying Waste Disposal
(+$1 billion) |
Similar cost over period of analysis
Little future risk as cleanup is complete
|
Additional funding required for Waste Management program
Violates compliance agreements
|
| Scheduling |
Funding Reduction
(+$39 billion) |
Less cost in early years |
More expensive over period of analysis
Program duration exceeds Base Case
Violates compliance agreements
Limits flexibility to accomplish efficient scheduling
|
Minimal Action
(-$70 billion) |
Less cost over period of analysis |
Program duration exceeds Base Case
Violates compliance agreements and regulatory requirements
Increase risk after period of analysis
Delays cleanup problems and includes the scope of contamination
|
Through an evaluation of these alternative cases, Department of Energy
personnel, regulators, and other stake holders can better understand the
potential implications of various policy options and thus participate more
effectively in the policymaking and decisionmaking processes.
Conclusion
Like all recently formed organizations, the Environmental Management program
spent the first several years of its life building a foundation: defining its
mission, gauging its scope, identifying key issues and priorities, and
assembling an infrastructure to support successful planning and management.
Since 1989, the program has introduced many planning initiatives focused on
gathering programmatic data and providing a basis for strategic planning and
program analysis. However, most of these initiatives failed to evaluate the
Environmental Management program from a life-cycle perspective.
The program has matured in seven years. The Department has now identified the
program's basic scope and where the greatest risks lie. In addition, the
baseline process has established a capability for projecting future costs and
schedules, analyzing changes in assumptions and potential scenarios, and
accounting for the interconnections between distinct sites and programs. This
analytical foundation for sound program management is summarized in the 1996
Baseline Report. Using the foundation provided by the Baseline Report, program
managers and policy makers can make more informed decisions regarding the
direction of the Environmental Management program and of the programs that
affect the Environmental Management program.
The purpose of the Baseline Report is to articulate clearly two elements of the
Department of Energy's Environmental Management program: projected life-cycle
costs and schedules. The report describes the program, with Base Case results,
from a variety of perspectives. Because of the uncertainties inherent in
estimating environmental management costs and schedules, the overall results
are presented with a cost range rather than a single figure. The program's
overall life-cycle cost is based on Base Case estimates developed by site
personnel for the mid-range estimate, with upper and lower bounds. This range
spans from $189 to $265 billion.
The Environmental Management program now has improved information available to
analyze policy decisions and set a future course. The program is in a critical
transition period; it faces near- and midterm decisions that will have
important long-term ramifications. Some of these decisions can be made now and
adjusted later (if new information calls for a different course); others will
require long-term commitment to a specific path.
An important conclusion of the Baseline Report is that changes to the scope and
schedule of the program can significantly affect Base Case costs. By
understanding the impacts of various policy decisions, decisionmakers and
stakeholders can direct the program in a manner that minimizes life-cycle
costs, reduces program schedules, optimizes program end states, and achieves
maximum reduction of risks. However, a great deal remains to be done to ensure
that issues highlighted in this Baseline Report are framed effectively; data
and methodologies supporting subsequent analyses are continually improved; and
interested stakeholders have a voice in the debate. Specific steps include the
following:
-
Improve Life-Cycle Cost and Schedule Estimates:
The 1996 Baseline Report is the program's second attempt to develop a
comprehensive life-cycle cost estimate. This report improves upon the estimates
and analyses developed last year based on a better methodology (that is, a
bottom-up approach that emphasizes estimates developed by field personnel);
better information in areas such as program scope and outyear costs; and
improved integration across programs and sites. Because the program is
constantly changing, however, these estimates will need to be adjusted and
improved. In addition, the program must continue to address uncertainties and
information gaps with ongoing data gathering and refined methodologies.
-
Use the Baseline Report to Address Ongoing Issues, Analyze Program Options,
Provide Input to Strategic Decisions, and Develop Ties to Program Budgets:
The analyses included in the 1996 Baseline Report are examples of what can be
done with baseline information and site input. Other alternative scenario
analyses would also benefit the program (for example, impacts of various
regulatory changes, effects of increased privatization, effects of greater
waste minimization). These analyses can be used to help inform strategic
planning decisions, better focus the program's near-term planning and
budgeting, and support legislative and regulatory reform.
-
Promote Informed, Broad-based Citizen Involvement in the Debate on the Program's
Future: One of the "next steps" included in the 1995 Baseline Report
was to include more stakeholders in the debate and actively seek citizen's
views (in subsequent Baseline Report cost estimates). The 1996 Baseline Report
achieved the goal of greater stakeholder participation. However, the task of
using the information to cultivate more informed debate on the program's future
still lies ahead.
Contents
The 1996 Baseline Report consists of three volumes: Volume I The 1996
Baseline Environmental Management Report , and Volumes II and III Site
Summaries for the 1996 Baseline Environmental Management Report.
Volume I
Introduction (Chapter 1) outlines the
framework of the report by providing a background on the scope and technical
complexity of the environmental management program, a description of
alternative analyses performed, and an overview of the contents of the Baseline
Report.
The Environmental Management Program (Chapter 2)
describes the mission and scope for each of the six major functional elements
that are encompassed in the Environmental Management program: Environmental
Restoration; Waste Management, Nuclear Material and Facility Stabilization;
Science and Technology Development; Landlord; and National Program Planning and
Management.
What is the Base Case? (Chapter 3) outlines
the methodology and key assumptions used to develop the Base Case long-range
projections of activities, schedules, and associated costs.
Results (Chapter 4) summarizes the projected
life -cycle costs for the Environmental Management program including discussion
on the range of estimates, distribution of cost estimates by geographical area,
and distribution of cost estimates by functional area.
Comparison of Results to the 1995 Baseline Environmental Management Report
(Chapter 5) describes the differences between the
1996 Base line Report and the 1995 Baseline Report in terms of methodology and
assumptions, including highlights of changes at the five highest-cost sites.
Alternative Scenarios (Chapter 6) and Comparison
of Alternative Cases (Chapter 7) present and
evaluate the findings of nine alternative approaches (five land-use cases,
three program and project scheduling cases, and one minimal action case) to the
Environmental Management program.
Conclusion (Chapter 8) discusses how the
Base line Report can serve as a tool for program decisions and how the report
can continue to be improved in the future.
Volumes II and III: Site Summaries
Volumes II and III present the site data and assumptions used to develop the
1996 Baseline Environmental Management Report. Each site summary provides a
brief discussion of the site's past, current, and future missions and is
followed by discussions of the projects and activities necessary to manage and
remediate the site. Volume II covers Alaska through New Jersey and Volume III
covers New Mexico through Wyoming.
This executive summary provides a brief, nontechnical overview of the report,
which is available in Department of Energy reading rooms and the Center for
Environmental Management Information (1-800-736-3282).
Back to Page 1
|
 |