Home
BEMR Contents
U.S. Map
During World War II and the Cold War, the United States developed a massive
industrial complex to research, produce, and test nuclear weapons. This nuclear
weapons complex included nuclear reactors, chemical processing buildings, metal
machining plants, laboratories, and maintenance facilities that manufactured
tens of thousands of nuclear warheads, and conducted more than one thousand
nuclear explosion tests.
Weapons production stopped in the late 1980s, initially to correct widespread
environmental and safety problems, and was later ended indefinitely because of
the end of the Cold War. The work remaining, and the subject of this analysis,
is the legacy of thousands of contaminated areas and buildings, and large
volumes of "backlog" waste and special nuclear materials requiring treatment,
stabilization, and disposal. Approximately one-half million cubic meters of
radioactive high-level, mixed, and low-level waste must be stabilized,
safeguarded, and dispositioned, including a quantity of plutonium sufficient to
fabricate thousands of nuclear weapons.
In 1989, the Department of Energy established the Environmental Restoration and
Waste Management program, now called the Environmental Management program, to
consolidate ongoing activities and accelerate efforts to deal with the inactive
production facilities and sites and the accumulated waste, contamination, and
materials. Six years later, this program is responsible for the maintenance and
stabilization as well as the environmental restoration and waste management
work at virtually the entire nuclear weapons complex not being used for
continued weapons activities. The Environmental Management program is one of
the largest environmental stewardship programs in the world, with 150 sites in
over 30 states and Puerto Rico.
The 1996 Baseline Environmental Management Report provides a total life-cycle
cost estimate and anticipated schedule of the projects and activities necessary
to carry out the Environmental Management program's missions for environmental
remediation, waste management, science and technology development, the
transition of operational facilities to safe shutdown status, and the
safeguarding and securing of special nuclear materials.

This report is prepared as an analytical tool to help guide departmental
decisions and to provide an accounting of the Department's progress, spending,
and plans. In addition, federal law requires the Secretary of Energy to
regularly submit Baseline Environmental Management Reports. The 1996 Baseline
Environmental Management Report (Baseline Report) is the second of these
reports. In addition, the report serves as a benchmark or starting point
in the development of new "Ten -Year Plans" that are being prepared to
define new, near-term cleanup objectives and greatly accelerate the pace and
reduce the costs of cleanup over current plans.
The first report, prepared in 1995, estimated that the total cost of the
Environmental Management program's mission would be between $200 and $350
billion over a 75-year period. Significant decisions made over the past 12
months have changed the projected scope of the Environmental Management program
as presented in the 1995 report. The 1996 Baseline Report highlights these
changes, both at the site and national levels. These changes have resulted in a
lower total program estimate, which now is between $189 and $265 billion over a
75-year period. Guided by a new ten-year planning process, we are confident
that we can further reduce the costs and accelerate the pace of cleanup through
better coordination between sites, use of "breakthrough management" and use of
new technologies.
|
The 1996 Baseline Report IS:
-
A life-cycle cost estimate for the entire Environmental Management Program
-
A policy analysis tool that explores the potential consequences of several
policy alternatives
-
A description of environmental management activities expected to be necessary
to address the Department's legacy and projected future activities
The 1996 Baseline Report IS NOT:
-
A definitive basis for planning specific projects
-
A budget document
-
A funding request
|
The 1996 Baseline Report is based on current (as of late 1995) national and
site-level assumptions regarding the actions or activities that are most likely
to occur in the future, and it estimates the costs of these actions or
activities. It is expected that these projected activities will change in the
future. In fact, one of the principal purposes of this report is to inform a
national debate on what the best future course should be.
The Environmental Legacy: Causes and Remedies
The Environmental Management program was established to address the
environmental legacy of nuclear weapons production and other sources of waste
or contamination such as nuclear research programs. The program encompasses
remediation of the environment and facilities that have been contaminated with
radioactive materials and hazardous chemicals. The program uses safe and
practical strategies to deal with a variety of radio active and hazardous
waste. It also entails deactivating and safekeeping hundreds of facilities that
have no similar counterparts in any other government or commercial industrial
facilities. Finally, the Environmental Management program accomplishes the
stabilization and safe storage of special nuclear materials such as plutonium
and highly enriched uranium and the management and storage of spent nuclear
fuel. In addition to the legacy mission, the Environmental Management program
manages waste produced by ongoing Department missions. (e.g., national
laboratories).
The Environmental Management Program encompasses six major functional areas:
(1) environmental restoration; (2) waste management; (3) nuclear
material and facility stabilization; (4) science and technology
development; (5) landlord; and (6) national program planning and
management. Figure 1 depicts the scope of the Environmental Management program
and the key interrelationships of the six major areas.
Figure 1. The Scope of the Environmental Management Program
Primary among these is waste management, which involves safe treatment,
storage, and disposal of existing waste and waste yet to be generated.
Environmental restoration activities address remediation of contaminated soil
and water as well as decommissioning of contaminated surplus facilities.
Nuclear material and facility stabilization involves stabilizing and
consolidating special nuclear materials such as plutonium and highly enriched
uranium and deactivating surplus facilities to a safe, low-maintenance
condition while awaiting final decommissioning. Science and technology
development includes a variety of basic and applied research activities that
explore more effective and less expensive remedies to address the environmental
and safety problems of the Environmental Management program. Landlord functions
represent crosscutting, site-wide activities such as road maintenance and fire
and ambulance services necessary to keep communication, transportation, and
security systems operational at large facilities. National program planning and
management encompasses Headquarters functions.
What is the Base Case?
The Environmental Management Base Case is a long-range projection of
activities, schedules, and associated costs that fully describes the
Environmental Management program, as currently projected, from its current
state to completion (see "Why Life-Cycle Estimates" ) based upon compliance
with current laws, regulations, and agreements. The Base Case looks to the
future, but does so only with the knowledge, information, and assumptions that
are available today. Because these inputs are rapidly changing, the 1996 Base
Case is essentially a snapshot in time of a dynamic and complex program. The
Base Case is not a budget estimate or a program funding request. Nor is it
intended to provide details of specific projects.
The information in the Base Case falls into four categories:
(1) descriptions of Environmental Management activities;
(2) estimates of the annual cost of each Environmental Management
activity; (3) estimates of the annual waste volumes generated by each
activity; and, (4) initial schedule estimates for each activity, including
starting dates and duration. "Activities" are specific sets of actions taken to
disposition special nuclear material or contaminated facilities, remediate
contaminated areas, manage waste, maintain federal lands and facilities, and
manage the programs individually and collectively in an integrated manner.
|
Why Life-Cycle Estimates?
The purpose of life-cycle cost analysis is to evaluate the total direct,
indirect, recurring, nonrecurring, and related costs incurred or
estimated to be incurred for a project. The life-cycle cost estimate
encompasses all costs of a project, including those related to
characterization, design, remediation, operation, maintenance, support,
deactivation and disposition over the anticipated useful life span of that
project.
Life-cycle estimates help identify activities that have the most significant
financial impact on a project during its life span and provide information for
effective strategic planning, budgeting, execution, and control of project
activities. While near-term planning remains critical for budgeting and tasking
purposes, it is incapable of identifying the long-term implications of issues
and the strategies posed to resolve them. Life-cycle planning is also critical
to ensure that issues affecting sites throughout the complex are addressed in a
programmatically efficient manner.
|
Limitations of a Life-Cycle Cost Estimate
Projecting future activities and costs is always fraught with uncertainty. This
uncertainty is compounded when projecting the path of an unprecedented program
such as stabilizing and remediating the facilities and residues of the nuclear
weapons complex. Activities such as these are expected to last decades. They
will be affected by unpredictable factors, such as the development of new
technologies and laws, and are extremely controversial. Nonetheless, these are
also some of the reasons why good program management and good public policy
require that such an estimate be compiled. The following is a list of specific
limitations of the life-cycle Base Case for the Environmental Management
program :
-
The program has a large unknown scope for which the nature and extent of
existing problems have not been adequately characterized and an expected remedy
has not been defined.
-
The program faces challenges resulting from the production of unique
radioactive materials. The program must, therefore, develop new approaches and
technologies to address unique environmental cleanup problems.
-
The program is responsible for environmental management problems for which
there are no current effective remedies and no effective remedies on the
horizon (defined as "infeasible"). Some are infeasible for technological
reasons (no available technology); others are infeasible because addressing
them will result in unacceptable levels of ecological damage. (The Base Case
does not include the costs for undertaking infeasible projects. However, costs
for surveillance and monitoring of these problems are included.)
-
The estimate must project how long short-term interim measures will be used to
address problems for which no long-term solutions are available.
The Base Case estimates must also address uncertainties that stem from legal
and institutional issues. Department of Energy policy requires management of
its facilities in compliance with applicable federal, state, and local
regulations. Many of these laws, including the Comprehensive Environmental
Response, Compensation, and Liability Act, the Clean Water Act, and the Clean
Air Act, have been targeted by Congress for reauthorization. Changes to these
laws will likely affect the Environmental Management program, although the
timing, substance, and extent of the changes are unclear.
|
Site-Based Cost Estimates: "Bottom Up" Approach
The 1996 Base Case cost estimates were developed through a "bottom up"
estimating approach. Detailed cost estimates developed for specific projects
were aggregated into sequentially larger groupings. This resulted in estimates
for entire sites, installations, and programs. This approach, in which project
and site managers take responsibility for estimating costs, offers several
advantages: increased reliability (due to involvement of staff that best
understands the work); traceability of summary estimates to detailed data;
availability of detailed estimates for Headquarters to analyze issues at a
national level; and development of analytical tools that can be used for
improved site and program management. This method is in contrast to a "top down
" method that uses field data in a centralized cost estimation model. Because
of a lack of adequately developed life-cycle cost estimates from the field,
this "top down" method was used for roughly half of the cost data in the 1995
Baseline Report.
|
Site-specific cleanup and compliance agreements, developed with the U.S.
Environmental Protection Agency and states that host Department of Energy
facilities, are a primary means for the Department to implement the provisions
of federal, state, and local regulations. However, because regulators make
final decisions about the choice of remedial action and the satisfactory
completion of each action, the decisionmaking process adds complexity and
uncertainty to the Department's planning processes. In some cases, final
agreements are not yet concluded. In other cases, agreements are signed, but
subsequent information and events may require that these agreements be
renegotiated.
In other instances, site objectives are not fully defined because the
Department cannot define them alone. For example, decisions related to the
future configuration of the nuclear weapons complex are dependent on
international factors such as arms control treaties. These decisions may
dramatically affect continued operations and associated environmental
management costs at some installations.
Base Case Methodology
The Department used a five-step process to develop the cost and schedule
estimates for the 1996 Baseline Report.
-
Define the study:
Establish the scope, framework, and general assumptions for the estimates; seek
input from stakeholders.
-
Gather and Assemble Data:
Collect, verify, and document cost, waste volume, and schedule data.
-
Perform Site-and Complex-Wide Integration:
Ensure that costs remain within assumed funding limits and that all waste
transfers are accounted for.
-
Estimate Program Improvements:
Evaluate the impacts of technology development, pollution prevention, and
productivity improvements.
-
Develop Documentation: Prepare the 1996 report.
In developing the Base Case estimate, every effort was made to ensure that
personnel at individual sites were fully involved with the data collection and
analysis. The overall scope of the Base Case and the national assumptions
underlying the estimates were consistent across the program, but each site
developed its own, fully integrated, cost and schedule estimates using the most
current data. Once these estimates were complete, the Department conducted a
complex-wide integration process to ensure that the interdependencies across
sites (for example, waste transfers) were fully understood. Volumes II and III
of this report present the Base Case for each site.
The Department maintained an active stakeholder involvement process throughout
the development of this report. Particular objectives were to ensure public
input to the overall scope and framework for the 1996 estimate and the
site-specific assumptions and estimating methods. Stakeholder input was also
sought to ensure that the Base Case assumptions were consistent with other
Departmental initiatives (for example, future land use planning).
Base Case Assumptions
A variety of factors significantly affects the estimated scope, schedule, and
total cost of the Environmental Management program. Site personnel developed
detailed, site-specific assumptions for each factor to estimate costs.
Site-specific assumptions are described in Volumes II and III of the 1996
Baseline Report. Table 1 lists the major assumptions from which the Base Case
was developed. The Base Case assumptions reflect program plans and conditions
as of October 1995. Any changes since that time are not necessarily reflected
in this report.
Table 1. Major Base Case Assumptions
|
Factor Affecting Estimate
|
Base Case Assumption
|
| Land Use
|
Explicit assumptions for future use at each site
All Environmental Management activities are consistent with assumed site
end-states
|
| Schedule
|
National permanent geologic repository available in 2016
Waste Isolation Pilot Plant available in 1998
|
| Site Completion
|
Work assumed complete when that site has been remediated to the extent
specified in land use plans, when all facilities have been properly stabilized
and dispositioned and when all waste has been safely disposed
Annual surveillance and monitoring costs will be incurred at sites where
restricted areas remain (e.g., waste disposal sites or nuclear materials
storage)
|
| Transportation
|
Site roadways and railways will be upgraded or replaced as necessary to
accommodate higher shipping frequencies and larger/heavier items
No major regulatory changes to further restrict the offsite shipments of
hazardous and radioactive materials
New waste shipment packaging will be designed. Department of Transportation and
Nuclear Regulatory Commission certification will require 3 years following
design
|
| Funding Limitation
|
Annual funding sufficient to meet the requirements and milestones of all
existing and applicable laws, permits, regulations, DOE, and agreements
Funding by site capped at the FY2000 compliance funding levels and held constant
thereafter (unless compliance agreements by site extend beyond FY2000
|
Environmental Activities Generally Excluded from the Base Case
Although the 1996 Base Case addresses a large number of activities required to
clean up and manage newly generated and legacy waste associated with the
nuclear weapons complex, there are several exclusions from the 1996 Base Case
cost estimate. These exclusions are:
-
Cost estimates for remediation activities that are either not technically
possible or not planned. Examples of these activities are further described in
Table 2.
-
Cost estimates for sites and/or facilities with ongoing missions (i.e., Defense
Programs, Nuclear Energy, Energy Research). These exclusions include
stabilization, deactivation, and decommissioning of facilities and treatment,
storage, and disposal of chemical and radioactive substances associated with
ongoing mission activities.
-
Cost estimates for annual, long-term, post -closure surveillance and
monitoring.
-
Costs for the first six years of the Environmental Management program ($28.5
billion).
-
Cost estimates for potential liabilities due to natural resources damages
claims.
-
Cost estimates for disposition of special nuclear materials (e.g., plutonium)
or other materials in inventory (e.g., depleted uranium or lithium).
Table 2. Examples of Contaminated Sites
Not Included in the Base Case
|
Installation
|
Project |
Reason Excluded
|
| Hanford Site |
Columbia River, Hanford Reach
Ground Water
|
No feasible remediation approach available
Limited pump-and-treat followed by natural attenuation and monitoring
|
| Oak Ridge Reservation (Y-12, K-25, Associated Universities)
|
Clinch River
Watts Bar Reservoir
Poplar Creek Embayment
White Oak Creek
|
No feasible remediation approach available
|
| Oak Ridge National Laboratory
|
Deep Hydrofracture Grout Sheet
|
No feasible remediation approach available
|
| Savannah River Site |
L Lake
Savannah River Swamp
Par Pond
|
No feasible remedy without causing collateral ecological damage
|
| Fernald Plant |
Great Miami River
|
No feasible remediation approach available
|
| Idaho National Engineering Laboratory
|
Snake River Plain Aquifer
|
Limited pump-and-treat followed by natural attenuation and monitoring
|
| Rocky Flats Environmental Technology Site
|
Walnut Creek
Woman Creek
Great Western Reservoir
|
No feasible remedy without causing collateral ecological damage
|
| Nevada Test Site |
Underground Test Areas
|
No feasible remediation approach available
|
| Sandia National Laboratory/New Mexico
|
Chemical Waste Landfill Ground Water
|
Natural attenuation and monitoring assumed
|
Environmental Restoration Assumptions
Environmental restoration costs comprise approximately one-third of the current
FY 1996 annual program costs. The Base Case for environmental restoration
encompasses environmental remediation or containment activities at nearly all
150 sites included in this Baseline Report. The report addresses 10,500
potential release sites that have been grouped into 295 geographically based
units.
Virtually all of the 10,500 potential release sites have been at least
partially characterized. Approximately 46 percent have been fully
characterized. However, final remedial action and/or regulatory decisions have
been made for substantially fewer sites. For this reason, the environmental
restoration cost estimate is based largely on two site-specific assumptions:
program scope (that is, the amount and type of contamination); and the
remediation technologies that will be selected. Table 3 describes the general
Base Case Environmental Restoration assumptions for remedial actions and
decommissioning.
Table 3. Base Case Assumptions for Environmental Restoration Activities
|
Activity |
Media |
Base Case Assumption |
| Remedial Actions |
Ground Water |
Sources of contamination addressed by removal or containment as high-priority
Pump and treat technologies utilized if technology is effective
Containment and monitoring emphasized in absence of effective removal
technologies
All groundwater contained on site
|
| Remedial Actions |
Surface Water |
Small ponds and streams remediated by removal of sediments
Large bodies of water (e.g., Clinch River, Columbia River) monitored due to lack
of effective technology or potential ecological damage
|
| Remedial Actions |
Soil/Buried Waste |
Contained in place, unless significant contaminant releases are expected |
| Decommissioning |
Large Buildings (e.g., Reactors, Processing Buildings) |
Generally contained by entombment |
| Decommissioning |
Small Buildings (e.g., Laboratories) |
Decontaminated and demolished |
Waste Management Assumptions
The Base Case estimate for waste management includes costs for: (1) existing
inventories of waste, (2) waste streams from environmental restoration
activities, (3) waste streams from nuclear material and facility stabilization
activities, (4) additional waste generated by waste management activities, and
(5) newly generated waste from non-Environmental Management sources. Activities
for waste management are defined as treatment, storage (and handling), and
disposal of waste. Waste management also includes treatment, storage, and
disposal of spent nuclear fuel, which the Department does not consider a waste.
Table 4 highlights the Base Case treatment, storage, and disposal assumptions
detailed by waste type
Table 4. Base Case Waste Management Assumptions
|
Waste Type |
Activity
|
|
Storage
|
Treatment |
Disposal
|
| High-Level Waste |
Continued storage in tanks at Hanford, Savannah River Site, West Valley
Demonstration Project, & Idaho National Engineering Laboratory
Continued storage of calcine in bins at Idaho National Engineering Laboratory
|
Vitrify at Hanford, Savannah River Site, and West Valley Demonstration Project
|
Geologic repository assumed
|
| Transuranic Waste |
Onsite storage
|
Treatment to Waste Isolation Pilot Plant waste acceptance criteria
|
Waste Isolation Pilot Plant (beginning in 1998)
|
| Low-Level Waste |
Onsite storage at generator sites while awaiting treatment and disposal at six
Department of Energy sites
|
Treatment to meet transport and disposal criteria
|
Disposal at seven sites: Hanford, Oak Ridge, Idaho National Engineering
Laboratory, Los Alamos National Laboratory, Nevada Test Site, Savannah River,
and Rocky Flats Environmental Technology Site and also at commercial facilities
|
| Low-Level Mixed Waste |
Storage at 30 generator sites
|
Treatment to meet land disposal restrictions
Treatment performed in accordance with the Federal Facility Compliance Act
|
Disposal at seven sites: Hanford, Oak Ridge, Idaho National Engineering
Laboratory, Los Alamos National Laboratory, Nevada Test Site, & Savannah
River, Rocky Flats Environmental Technology Site and also at commercial
facilities
|
| Hazardous Waste |
Onsite storage for accumulation prior to treatment
|
Treatment mostly at commercial facilities
|
Commercial facilities
|
| Sanitary Waste |
No storage
|
Treatment at point of generation as needed
|
Commercial or onsite disposal depending on the site
|
| Special Case Waste |
Onsite storage
|
Treatment as required
|
Disposal in a national geologic repository
|
Table 5 provides these assumptions for spent nuclear fuel.
Table 5. Base Case Assumptions for Spent Nuclear Fuel
| Spent Nuclear Fuel Activity |
|
Storage |
Treatment |
Disposal |
| Consolidation of storage at the Savannah River Site and Idaho National
Engineering Laboratory; continued storage at the Hanford Site
Cost of building new storage facilities included
All spent nuclear fuel assumptions are compatible with the Record of Decision
for the Spent Nuclear Fuel Final Environmental Impact Statement
|
No reprocessing |
Availability of a Geologic repository assumed |
Nuclear Material and Facility Stabilization Assumptions
The Base Case estimates for nuclear materials and facility stabilization
activities are based upon a defined "universe" of materials and facilities that
have been, or will be, declared surplus by the Department. The Base Case
development process involved validating a list of facilities scheduled to
undergo stabilization and deactivation in the 1995 Baseline Report. This list
was based on the Surplus Facility Inventory and Assessment Project conducted in
1994. The assessment identified those facilities that are declared surplus now
or expected to be surplus prior to October 1998.
Other facilities are still operating and currently have no scheduled date for
shutdown or transfer. These facilities are considered outside the program's
planning horizon and are not reflected in the 1996 Base Case. Typically these
facilities are associated with ongoing nuclear weapons activities.
Nuclear material and facility stabilization activities include material
stabilization, facility deactivation, and surveillance and maintenance.
Stabilization entails placing nuclear materials into a condition suitable for
long-term storage. In some instances, Base Case stabilization costs include
storage costs for nuclear material. For example, at the Rocky Flats
Environmental Technology Site, storage costs constitute a significant portion
of the stabilization estimate. Deactivation, which usually occurs after
completion of stabilization, focuses on removal of material, shutting down
facility systems, and removal or de-energizing equipment to reduce potential
facility hazards.
Surveillance and maintenance activities encompass all actions required to
ensure adequate material and facility requirements for safety and security.
Surveillance and maintenance activities are assumed to continue during the
stabilization and deactivation phases (as well as before and between these
phases). The Base Case captures surveillance and maintenance costs that are
incurred before and after stabilization and after deactivation activities.
Post-deactivation surveillance and maintenance is assumed to continue for two
years. After that, facilities are assumed to be decommissioned. These costs are
included as part of environmental restoration activities.
The Base Case estimates were developed by personnel at four sites (Hanford
Site, Idaho National Engineering Laboratory, Rocky Flats Environmental
Technology Site, and Savannah River Site). Estimates for nuclear material and
facility stabilization costs at other sites were generated by Headquarters
personnel using parametric cost-estimating techniques and site-specific data.
In instances where parametric cost estimating techniques were used, the
following hypothetical scheduling scenario was assumed (in this sequence):
seven years of surveillance and maintenance after transfer of a facility to the
Environmental Management program, three years of stabilization activities,
three years of post-stabilization surveillance and maintenance, three years of
deactivation activities, and two years of post-deactivation surveillance and
maintenance.
Surplus facilities already in the Environmental Management program were
scheduled according to this hypothetical scenario. Surplus facilities not yet
in the program were assigned arbitrary transfer dates, typically selected to
fit funding constraints assumed in the Base Case. Insufficient data was
available to guide scheduling of these facilities according to risk or other
priorities.
Science and Technology Development Assumptions
The Environmental Management program's science and technology development
activities represent an aggressive national program of basic and applied
research, development, demonstration, testing, and evaluation for innovative
environmental cleanup solutions. The program seeks to develop technologies that
facilitate compliance with applicable laws, regulations, and agreements;
minimize generation of waste; and clean up Environmental Management sites in a
manner that is safer, faster, and less expensive than baseline technologies. In
many cases, the development of new technologies is critical for providing a
method of significantly reducing long-term risks to the environment and
improving worker/public safety within realistic financial constraints.
The major science and technology assumptions included in the Base Case are as
follows:
-
Current Base Case cost estimates for Environmental Management activities are
based upon the use of existing technologies. This assumption allows one to
calculate future savings resulting from the development of emerging
technologies against this baseline.
-
Funding for science and technology development is currently 6 percent of the
Environmental Management Base Case and is assumed to remain at this level until
the year 2030.
Landlord Assumptions
Landlord activities support the performance of direct mission activities. In
developing landlord cost estimates, site personnel determined FY 1996 costs for
landlord activities, then assessed how these levels might change over time as
several factors change: maturity of the program, level of annual direct mission
activities being performed, cleanup completeness, and other factors relevant to
the site.
National Program Planning and Management Assumptions
Headquarters personnel used a simple model to estimate the costs for national
program planning and management. As part of this process, independent cost
estimates were developed for program direction and program management. Program
direction costs include salaries, benefits, travel, and training for federal
employees. For the purposes of this report, the Department assumed that program
direction costs will remain a constant percentage of total cost over the
life-cycle of the program. Hence, as program funding decreases over time,
program direction will decrease proportionally. Program management costs fund
contractors that support federal employees. The Department assumed that program
management costs will also decrease as a percentage of total cost over time as
the program matures and becomes better defined. These costs have already
dropped 55 percent from FY 1994 to FY 1996.
Support Cost Assumptions
In addition to direct mission activities, the Environmental Management program,
like private firms and other public agencies, also must perform "support"
activities. These activities fall into six main categories:
-
Management;
-
Finance and Administrative Services;
-
Environment, Safety, and Health;
-
Infrastructure;
-
Safeguards and Security; and
-
Stakeholder and Regulatory Interactions, and Other.
Support activities are not extraneous; they are vital to maintaining site
safety and ensuring environmental cleanup progress. For example, it is
necessary to conduct environment, safety, and health activities and to provide
safeguards and security at all sites, particularly those storing uranium,
plutonium, and other nuclear materials.
The benefits of support activities are shared across projects within a
functional area. Therefore, the Baseline Report does not identify support costs
as a separate category (except for cost estimating purposes). Rather, support
costs in this report are spread across the direct mission activities within
each appropriate functional area.
To develop support cost estimates, site personnel first developed a time
profile for their direct mission activities. Then, based upon this profile,
site personnel estimated the level of support activities that they would need
on an annual basis and their costs. Specifically, site personnel determined FY
1996 costs for support activities, then assessed how these levels might change
over time based on changes to several factors: maturity of the program, level
of annual cleanup activity being performed, completeness of cleanup, and any
other factors relevant to the site.
Results
The 1996 Base Case life-cycle cost estimate for completing the Environmental
Management program is projected to be between $189 billion and $265 billion,
with a mid-range estimate of $227 billion. All estimates are in constant 1996
dollars. The life-cycle cost profiles are graphically depicted in Figure 2.

Figure 2. Base Case Life-Cycle Cost Estimate
The mid-range estimate $227 billion represents the sum of
life-cycle costs for all site-specific activities and projects described in
Volumes II and III of the Baseline Report. The upper range ($265 billion) and
lower range ($189 billion) are estimated using a probabilistic analysis of each
site's evaluation of levels of confidence in their Base Case estimates.
The mid-range estimate of $227 billion is the projected cost for carrying out
the currently planned tasks, including existing compliance agreement
obligations (as of October 1995), facility maintenance, and general operating
requirements using available technology.
The life-cycle activities for the Base Case are estimated to span a 75-year
period (1996 to 2070), although most sites will be completed considerably
sooner. By 2070, all environmental management sites requiring remediation are
assumed to be remediated; only post-closure long-term surveillance and
monitoring activities and ongoing waste management activities at active sites
will remain. Preliminary estimates indicate these long -term costs would range
from $45-$65 million annually for several decades. Figure 3 shows the Base Case
schedule for remediating sites.
Figure 3. Base Case Schedule for Remediating Sites
Reconciling the Base Case Cost Estimate with Budget Projections
The Base Case is not a budget estimate. In fact, with cost projections expected
to exceed budget availability and priorities continuing to be defined, a clear
articulation of the current baseline projection is useful. The projected budget
target (as of October 1995), based on larger federal budget realities,
indicates that the Environmental Management program will be funded at
approximately $5.5 billion in annual funding (in current dollars) by 2000.
After accounting for expected inflation, this number equates to $4.9 billion in
constant 1996 dollars. The difference between the assumed funding for the Base
Case estimate and the funding target results in a projected budget shortfall.
Figure 4 indicates that this shortfall amounts to $27 billion over a 25-year
period.
Figure 4. Long-Term Budget Shortfall
This budget shortfall has been anticipated since 1993. During this period, the
Department has successfully reconciled this shortfall through a number of
management initiatives intended to deliver more results for less money.
Specific priorities for the Environmental Management program include: From
1993-1996
-
Improved Contractor Efficiency
Reduced contractor employment by 17,000 individuals or 33 percent;
initiated performance-based contracting systems at most of the large sites in
the complex.
-
Renegotiated Compliance Agreements
To date, renegotiated agreements have resulted in more than $1 billion in
potential savings for the Hanford Site and Savannah River Site.
-
Involved Stakeholders and Workers At Fernald, Ohio,
recommendations from the Citizen Task Force on disposal options and future land
use at the site are expected to result in over $2 billion in savings.
From 1997-2000
-
Privatizing Operations
Improving public sector efficiency with more private sector incentives.
-
Conducting Management "Work Outs"
Department of Energy, contractors, and regulators coming together to
develop common sense reforms.
-
Investing in Science Bridging basic science and applied research
needs on our most intractable environmental problems.
We believe that these efforts will continue to assist in reconciling estimated
Base Case costs to budget realities. Additional changes such as legislative
amendments to Superfund will also contribute to helping the program operate
more cost effectively. Clearly, however, it is critical to good management to
anticipate budget problems through effective life-cycle analysis.
A Closer Look at the Base Case
At the program "end state" (in 2070), all mission-related activities have been
completed and most sites have been made available for alternative land uses.
Buildings are decommissioned, waste planned for offsite disposal is treated and
will have been shipped to a permanent disposal site or commercial facility, and
waste being disposed of onsite is capped in pits or trenches or securely
enclosed in disposal cells. In 2070, Environmental Management program
activities are focused on long-term surveillance and monitoring and waste
management for active Department of Energy programs. In other words, sites with
ongoing missions outside of the Environmental Management program (for example,
national laboratories) will continue to incur ongoing waste management costs.
Many sites complete their Environmental Management mission-related activities
before 2070. A closer examination of the life-cycle cost profile in Figure 3
reveals a relatively level estimate after 2050. In fact, 90 percent of the
total life-cycle cost is expected to be expended by 2037.
The Base Case includes site-based productivity estimates that produce a total
life-cycle cost reduction of $14 billion, resulting in a total life -cycle cost
estimate of $227 billion. With no productivity savings, completion of the
Environmental Management program is estimated to cost $241 billion.
A Geographical View of the Environmental Management Program
The Department's Environmental Management program currently is operating in
approximately 30 states and territories. By 2020, this number is expected to
drop to 21 states. (See Figure 5 for the estimated annual spending level for
environ mental management activities in each state and a depiction of cleanup
progress over time.)
Figure 5. Annual Estimated Cost by State
In 2060, this number drops to 15 states, with almost all of the expenditures
for long-term surveillance and monitoring and management of waste generated by
programs with ongoing missions. Significant findings include:
-
Activities in two states, Washington (Hanford Site) and South Carolina
(Savannah River Site), dominate the life-cycle cost estimate. They account for
approximately $100 billion (or 44 percent) of projected life-cycle costs.
Figure 6 shows life-cycle cost percentage by site.
-
The expected end dates for the five highest -cost sites are as follows: Hanford
Site (2070), Idaho National Engineering Laboratory (2045), Oak Ridge
Reservation (2070), Rocky Flats Environmental Technology Site (2055), and
Savannah River Site (2050). Surveillance and monitoring activities will
continue beyond these dates. All sites will be complete by 2070.
-
At Hanford, Idaho National Engineering Laboratory, and the Savannah River Site,
waste management constitutes the largest portion of program costs.
-
At the Oak Ridge Reservation, environmental restoration activities are the
highest proportion of the total cost estimate; and at the Rocky Flats
Environmental Technology Site, nuclear material and facility stabilization
activities represent the largest percentage of total estimated cost.
Figure 6. Distribution of Environmental Management Life-Cycle Estimate
Base Case Results for Major Functional Elements of the Environmental Management
Program
The program is divided into six major functional elements: waste management,
environmental restoration, nuclear material and facility stabilization, science
and technology development, landlord, and national program planning and
management. Figure 7 shows the life-cycle cost estimate by major functional
element.
Figure 7. Estimated Life-Cycle Cost by Major Functional Element
Table 6 lists the highest life-cycle cost projects in the Environmental
Management program.
Table 6. Activities with Highest Projected Costs in the Environmental Management
Program
|
Program |
Site |
Project |
Millions |
| Waste Management |
Hanford Site |
High-Level & Low-Level Vitrification |
$15,500 |
| Waste Management |
>Waste Isolation Pilot Plant |
Waste Isolation Pilot Plant |
$8,300 |
| Waste Management |
Idaho National Engineering Laboratory |
Chemical Processing Plant |
$4,800 |
| Waste Management |
Savannah River Site |
Defense Waste Processing Facility |
$3,800 |
| Waste Management |
Hanford Site |
Single- and Double-Shell Tanks
|
|