|
Home
BEMR Contents
U.S. Map
A number of significant assumptions regarding factors affecting costs underlie
the Base Case estimate. Varying these assumptions can often influence the
overall life-cycle cost estimate. To help inform national policymaking and
local decisionmaking processes, the 1996 Baseline Report provides a more
rigorous analysis of alternative program scenarios. By changing certain key
assumptions we are able to examine the influence of each factor on the
life-cycle cost and schedule of the Environmental Management program (see box).
The analyses varied assumptions regarding the following factors expected to
influence program costs:
-
Land Use
- What effect do future land-use decisions have on the overall scope, cost, and
schedule of cleanup for Environmental Management sites? What factors limit
consideration of land uses?
-
Program and Project Scheduling
- What are the cost consequences of delaying and accelerating programs and
projects? What is the relationship between program pace, funding levels, and
life-cycle cost?
-
A "Minimal Action" Scenario - What is the minimum funding required for
preventing risks to human health and the environment from increasing for 75
years without the constraints of current legal requirements?
The approach for estimating life-cycle costs for the alternative scenarios
mirrors the basic methodology employed for the Base Case estimate. Site
estimates and assumptions provided the basis for these analyses. The land-use
analysis varies from the Base Case in that the analysis assumes different site
end states suitable for various uses, and measures the cost and waste volume
consequences of cleaning up to these alternative end states. The program and
project scheduling analysis assumes the same actions and subsequent end states
for programs and projects as described in the Base Case, but applies funding
and scheduling constraints to better analyze the cost consequences of
accelerating or delaying programs and projects. The minimal action scenario
uses methods developed by site personnel to re-scope projects and activities to
meet a set of minimal action assumptions and thus diverges dramatically from
the Base Case. Although implementation of particular scenarios may require
regulatory relief, no scenario specifically examines the impact of changing
regulatory requirements.
| SCENARIOS ARE NOT DECISIONS
Scenario analyses attempt to identify a set of possible futures,
each of which is plausible, but not assured. These analyses are intended to
foster and help inform local and national discussions regarding potential
policy strategies for the Environmental Management program. Each scenario
provides an explicit framework for further discussions and reaction. The
analyses were developed using hypothetical assumptions that do not represent
plans or decisions endorsed by the Department of Energy or the Environmental
Management program.
|
The three analyses focus on the five sites in the Environmental Management
program estimated to have the highest life-cycle costs - Hanford Site,
Washington; Idaho National Engineering Laboratory, Idaho; Oak Ridge
Reservation, Tennessee; Rocky Flats Environmental Technology Site, Colorado;
and, Savannah River Site, South Carolina. Together, these sites account for
approximately 70 percent of the Environmental Management total program cost
estimate and comprise over one million acres of federal land. By focusing on
the five highest-cost sites rather than on the other 145 sites in the program,
the analysis is able to account for the majority of program costs and
establishes a reliable basis for evaluating the impacts of alternative
assumptions. Figure 6.1 shows the distribution of costs for the five sites in
relation to the entire Environmental Management program.

Figure 6.1. Distribution of Life-Cycle Costs for the Five
Highest-Cost Sites
In developing the scenarios, the Department assumed that intersite
funding could generally not occur. That is, one site could not
accelerate work by "borrowing" funding from another site. It was assumed that intrasite
funding could take place. For example, funding for waste management activities
could be used to fund stabilization and deactivation activities within a site.
(The exception to this convention was for a single land-use case that addressed
extreme clean-up).
6.1 LAND USE
One of the primary difficulties in estimating the total cost of the
Environmental Management program is that future land use (i.e., the ultimate
disposition of lands currently managed by the Department) generally has not
been determined. The Department continues to work with local stakeholders and
regulators to determine future uses of land and facilities. This process has
identified initial future use preferences at a number of sites (Charting the
Course: The Future Use Report , April 1996), but final decisions are
still pending. Until these decisions are made, there will be considerable
uncertainty regarding the nature and extent of required environmental
restoration activities. This, in turn, adds uncertainty to estimates of total
program cost. For example, analyses presented in the 1995 Baseline
Environmental Management Report indicated that future-use decisions could
change the total cost of the Environmental Management program by hundreds of
billions of dollars. It was a broad analysis, without site-specific data. The
land-use analysis presented here provides site-specific data and is a more
limited evaluation of how a range of potential future land-use decisions could
affect environmental restoration activities, and how these changes would affect
the total cost of the Environmental Management program. A key feature of this
analysis is the consideration of site-specific constraints on future land use.
|
SIGNIFICANT FINDING OF THE LAND-USE ANALYSIS
The Department conducted a land-use analysis to examine how future
decisions will affect cost and end-state conditions. Four scenarios, preserving
infrastructure for ongoing missions and ecologically sensitive areas, were
developed ranging from Iron Fence to Modified Green Fields. An
additional scenario, Maximum Feasible Green Fields eliminated Department
missions from the end state and completed cleanup to the fullest extent of
available technologies regardless of the impact on the ecology.
-
Consideration of site-specific constraints in preserving missions and habitats
significantly restricts the range of land uses possible at sites; the resulting
variation in estimated program cost was, at most, six percent from the Base
Case.
-
Implementation of a Maximum Feasible Green Fields
scenario is expected to cost 77 percent more than the Base Case. This scenario
yields an additional 65,450 hectares (162,000 acres) clean enough for
Residential or Agricultural uses compared to the Base Case. Under this
scenario, the Department's industrial infrastructure would be largely
eliminated, and the more extensive remedial actions would result in
considerable disturbance of ecologically sensitive areas.
-
Assumptions regarding future missions did not consider long-term storage of
special nuclear materials. This storage would significantly affect the number
of acres that would be held as buffer zones to provide security and protect
offsite populations.
|
This section includes a description of the general assumptions for this
analysis; a description of the five alternative scenarios developed for the
land-use analysis; an overview of how the alternative scenarios were developed
and analyzed; the results in terms of estimated cost, the schedule of
remediation activities, and end states in acres of land attaining specific
cleanup levels; and the implications of this analysis. Appendix C provides a
more detailed discussion of the land use analysis methodology, and Appendix D
presents site-specific results for each of the alternative scenarios.
6.1.1 General Assumptions for the Land-Use Analysis
The alternative scenarios evaluated in this section are based on changes to the
Base Case assumptions for environmental management activities. The primary
assumptions and bounds for this analysis are as follows:
-
The primary focus of this analysis is the estimated cost for environmental
restoration and associated support activities. Waste management activities and
cost estimates are affected only to the extent that changes in environmental
restoration activities result in changes in the volume of waste that is treated
and/or disposed at waste management facilities. A number of Environmental
Management program activities are not
affected by this analysis, including (1) decommissioning of waste management
facilities; (2) high-level waste and spent nuclear fuel management, and (3)
nuclear material and facility transition activities.
-
The alternative scenarios incorporate land-use standards
developed for this analysis that provide a consistent basis for comparing land
use assumptions and evaluating alternatives across sites. Land-use standards
are provided for six land use categories: Disposal/Storage Areas, Open Space,
Industrial, Recreational, Residential, and Agricultural. The land-use standards
include both operational definitions as well as assumed technology strategies
for each category.
-
The alternative scenarios also incorporate site-specific constraints
on future use (i.e., real-world limitations on the future uses that can be
achieved). These constraints include ongoing program missions (including waste
disposal/storage); legal commitments (e.g., Records of Decision); the presence
of unique or sensitive ecological systems (e.g., endangered species habitat),
and the limits of current technology (e.g., the inability to remove
contaminants such as tritium from ground water).
-
All alternative scenarios assume a level of annual funding for the
Environmental Management program equal to that for the Base Case. If estimated
costs increased above this amount (e.g., because of more extensive remedial
actions), projects and activities were delayed until sufficient funding was
available. The scenarios generally assumed no transfer of funds from one site
to another.
6.1.2 Alternative Land-Use Scenarios
The Department used the underlying land-use assumptions in the Base Case as the
point of reference to evaluate the effect of the following five alternative
land-use scenarios on the estimated life-cycle costs of the Environmental
Management program: Maximum Feasible Green Fields, Modified Green Fields,
Recreational, Industrial, and Iron Fence. These five scenarios were chosen to
represent varying land use outcomes (and differing levels of environmental
restoration activity). The Maximum Feasible Green Fields and Iron Fence
scenarios represent the two endpoints of the land-use continuum attained at the
five highest-cost sites. The Recreational scenario represents an intermediate
land-use end state without access restrictions, while the Industrial scenario
represents an intermediate land-use end state with access restrictions. The
Modified Green Fields scenario illustrates how an aggressive clean up strategy
might be tempered when considering continued Departmental missions at these
five large sites.
Maximum Feasible Green Fields - To illustrate a maximum cleanup scenario,
the land-use analysis assumed that continued Department of Energy missions and
stewardship facilitated by a continued government presence would end at some
future time. This scenario removes site-specific constraints, except for
technology challenges and assumes a limited number of disposal areas. To
support the Residential or Agricultural land uses required by this scenario,
the most aggressive cleanup goals are used in removing all contaminated media
or materials at the five sites.
Modified Green Fields - This scenario, like the Maximum Feasible Green
Fields scenario, has as its goal Residential or Agricultural standards, but it
considers all applicable site-specific constraints. It represents the most
stringent remediation strategy possible while continuing Departmental missions
and presence at the site.
Recreational - Contaminated areas at each site are assumed to be
remediated to a level that supports Recreational uses, while considering
site-specific constraints. This scenario combines removal and containment
remediation strategies.
Industrial - Contaminated areas at each site are assumed to be remediated
to a level that supports Industrial uses, while considering site-specific
constraints. This scenario places more emphasis on containment strategies than
does the Recreational scenario because Industrial use encompasses more
institutional controls.
Iron Fence - Contaminated areas at each site are assumed to be remediated
to a level that supports the Disposal/Storage land uses (also termed Controlled
Access). Generally, contamination will be monitored or contained in place. The
Iron Fence scenario is intended as the alternative with the least cost.
Therefore, in a small number of instances where removal actions are less costly
than containment actions, this scenario selects the least-cost alternative.
6.1.3 How the Land-Use Scenarios Were Developed and Analyzed
Three variables were identified that significantly affect environmental
restoration activities: (1) level of existing contamination, (2) future-use
assumptions, and (3) site-specific constraints. Data for these variables were
collected for the Base Case. The five highest-cost sites verified the Base Case
data and defined the parameters for developing new cost and schedule data for
the alternative scenarios described above. These variables, and how they were
combined to develop the alternative land-use scenarios, are described briefly
below.
6.1.3.1 FUTURE-USE ASSUMPTIONS
The starting point for any land-use analysis is an assumed future-use goal.
These goals determine the types of activities that are assumed to occur in the
future, the likely exposure pathways, and whether contaminated media may be
remediated with in situ remediation strategies, such as capping in place.
These, in turn, determine the type and extent of environmental restoration
activities that are likely to be required. For example, containment of surface
and subsurface contamination (e.g., capping and monitoring) is sufficient for
an Industrial future-use goal because adequate controls are maintained (e.g.,
capped areas can be fenced off), the types of exposures are limited, and
assumed exposure levels are relatively low. In contrast, a Residential
future-use goal requires extensive removal of surface and subsurface
contamination because the types of activities associated with this use (e.g.,
gardening, excavating foundations, playing in dirt) can breach containment
structures, more types of exposures are possible, and assumed exposure levels
are relatively higher.
Table 6.1. Land-Use Categories Defined for this Analysis
| Disposal/Storage Area |
The Department maintains restricted access areas for secure storage
or disposal of nuclear materials or waste. Barriers and security fences prevent
access by unauthorized persons. Wildlife and plants are controlled or removed.
This category also is known as "Controlled Access". |
| Industrial
|
Active industrial facility
where ground water may be restricted.
|
| Open Space |
Posted areas are reserved generally as buffer or
wildlife management zones. Native Americans or other authorized parties may be
allowed permits for occasional surface area use. Access to or use of certain
areas may be prevented by passive barriers (e.g., where soil is capped).
Limited hunting or livestock grazing may be allowed.
|
| Recreational
|
Unfenced areas where daytime
use for recreational activities (e.g., hiking, biking, sports), hunting, and
some overnight camping is allowed. Fishing may be limited to catch-and-release.
|
| Residential |
Unfenced areas where permanent Residential use
predominates. There is no restriction on surface water, but ground-water use
may be restricted.
|
| Agricultural
|
Unfenced areas where
subsistence or commercial agriculture predominates without restriction on
surface or ground-water use.
|
This analysis required a consistent basis for comparing land-use assumptions and
evaluating alternative scenarios across the five highest-cost sites. Therefore,
a set of land-use standards was developed for six land-use categories that
includes both operational definitions and assumed technology strategies for
each category (Table 6.1).
The standards were used to describe uses and relative cleanup level of acreage
consistently. For instance, land on which grazing is permitted has been
referred to by individual sites as Agricultural use, but according to the
standards, it is categorized as an Open Space use. If the land has not been
contaminated, it would meet the cleanup levels for all uses and could be
described as suitable for Agricultural use. (Appendix D presents Base Case
application of standards for uses and cleanup levels.) These standards were
developed solely for this analysis and are not intended to replace
specific land-use definitions at any site nor usurp the authority of that site
to tailor land-use to conditions present. Using these standards, the Base Case
future-use assumptions were compared and, to the extent possible, reconciled
with the future land-use preferences identified by the Future Use Working
Groups.
6.1.3.2 SITE-SPECIFIC CONSTRAINTS
In general, any desired land-use goal is achievable with current environmental
restoration technologies. Notable exceptions include instances where there is
no effective removal technology (e.g., tritium in ground water) or where risks
to remediation workers using conventional removal technologies are unacceptably
high. These and other site-specific constraints place limits on the land-use
goals that are likely to be achieved. For example, all of the five
highest-cost sites have assumed that some Department of Energy missions (e.g.,
industrial activities, monitoring of waste disposal areas) will continue
through the end of the Environmental Management program. In addition, the
Department has entered into legal commitments that incorporate specified
land-use goals. Finally, the presence of unique or sensitive ecological systems
may limit future human uses of these areas. Because it is unrealistic to assume
certain future uses in the face of these site-specific constraints (e.g.,
Residential use within a waste disposal area), the Department incorporated
these constraints into this analysis.
6.1.3.3 LEVEL OF EXISTING CONTAMINATION
At the five highest-cost sites, the majority of the land area (approximately
400,000 hectares [one million acres] or 87 percent) is essentially
uncontaminated and already meets the requirements for the Open Space,
Residential, or Agricultural land-use categories. This includes approximately
80,000 hectares (200,000 acres) at Idaho National Engineering Laboratory that
had unexploded ordnance (removal of unexploded ordnance is essentially
complete) and approximately 60,000 hectares (150,000 acres) at the Savannah
River Site where stream beds are contaminated. Both these areas meet the
requirements of the Open Space land-use category. This analysis focuses on the
remaining 63,000 hectares (155,000 acres) (13 percent). These areas are
contaminated to varying degrees. In most cases some remedial action will be
required, even to meet Disposal/Storage Area standards. In some areas, however,
existing contamination is sufficiently low that remedial action may be required
under some future use assumptions (e.g., Residential), but not others (e.g.,
Open Space). This information is incorporated into the analysis.
6.1.3.4 DEVELOPING THE LAND-USE SCENARIOS
Using the six standard land-use categories, a nominal future-use assumption was
assigned to each land-use scenario. These uses ranged from Disposal/Storage
Area for the Iron Fence scenario to Residential/Agricultural for the two Green
Fields scenarios (Table 6.2).
For each land-use scenario, remedial strategies were assigned to all
contaminated areas at the five highest-cost sites. Cost and waste volume data
were calculated to remediate the site to the nominal land use category for that
scenario, except where site-specific constraints or level of existing
contamination indicated otherwise. For areas with no site-specific constraints,
remedial actions were used where existing contamination did not already
meet or exceed the nominal land-use standard. In the Industrial scenario, for
example, areas were remediated unless existing contamination was low enough to
meet Industrial or Recreational standards. As a consequence, the remedial
strategy for a given area of contaminated soil might be containment (capping)
under the Iron Fence, Industrial, and Recreational scenarios, but removal under
the two Green Fields scenarios.
Table 6.2. Assumed Remedial Strategies for Alternative Land-Use
Scenarios
| Iron Fence |
Disposal/Storage Area
|
If area currently meets any land use standards, no actions
required; otherwise, remediate to meet disposal/storage area standards
|
Maintain Base Case remedial strategies:
-
Do not vary areas with disposal/ storage missions
-
Remediate areas with other ongoing missions to meet Industrial standards
-
Avoid active removal for ecologically sensitive areas (remain mostly open
space)
-
Generally do not vary areas with existing Records of Decision
|
| Industrial |
Industrial
|
If area currently meets industrial or recreational standards,
no actions required; otherwise remediate to meet industrial standards
|
|
| Recreational |
Recreational
|
If area currently meets recreational standards, no actions
required; otherwise remediate to recreational standards
|
|
| Modified Green Fields |
Residential or Agricultural
|
Remediate all areas to meet residential or agricultural
standards
|
|
| Maximum Feasible Green Fields
|
|
|
Remediate most areas to meet Residential or Agricultural
standards3
|
1No actions are required for uncontaminated areas because they
already meet Residential or Agricultural standards
2For some areas, technical constraints limited remedial strategies
under some scenarios but not others (e.g., some areas can be remediated to meet
Open Space, Industrial, and Recreational standards but not Residential or
Agricultural)
3 All site-specific constraints are lifted except for technology
limitations and certain disposal areas at the Hanford Site, Idaho National
Engineering Laboratory, and Savannah River Site
For areas with site-specific constraints, the Base Case remedial strategy was
generally left unchanged across all scenarios. For example, contaminated areas
in portions of the sites with an assumed ongoing Industrial mission were
assumed to be remediated to meet Industrial standards, whether the nominal
future-use assumption was Disposal/Storage Area or Residential/Agricultural.
The only exception was the Maximum Feasible Green Fields scenario, in which all
site-specific constraints were lifted except for technology constraints and
constraints regarding certain waste disposal areas at the Hanford Site, Idaho
National Engineering Laboratory, and the Savannah River Site.
Parametric models were used to estimate environmental restoration costs and
volumes of waste generated for each contaminated area under each alternative
scenario. The Baseline Environmental Management Report Integration Tool (See
Methodology in Appendix C) was then used to estimate waste management costs
associated with the changing waste volumes, as well as changes in program
duration under each alternative scenario.
6.1.4 Results
This section presents the results of the land-use analysis in terms of cost and
schedule estimates and end-state conditions.
6.1.4.1 COST AND SCHEDULE ESTIMATES
Estimated costs for the Environmental Management program at the five
highest-cost sites range from $150 billion for the Iron Fence scenario to $284
billion for the Maximum Feasible Green Fields scenario (Figure 6.2). These
estimated costs are respectively six percent lower and 77 percent greater than
the Base Case estimate of $160 billion for these five sites. When site-specific
constraints are considered (i.e., Iron Fence through Modified Green Fields),
there is little difference in estimated cost among the alternative scenarios.
The estimate for the Modified Green Fields scenario ($166 billion) is only 10
percent greater than the estimate for the Iron Fence scenario and six percent
greater than the Base Case estimate. The Base Case estimate is between that of
the Industrial scenario ($155 billion) and the Recreational scenario ($162
billion). It is important to remember that these are generalized findings, and
that actual land use will likely vary significantly among different sites.

Figure 6.2. Costs for Environmental Restoration, Waste
Management, and Nuclear Material and Facility Stabilization By Land-Use Case
When site-specific constraints are considered, environmental restoration
activities account for most of the variation in estimated cost. Waste
management cost estimates change slightly because of variation in estimated
waste volumes, but few changes in overall waste management strategy are
required, given that most waste management and nuclear material and facility
stabilization activities were held constant across the scenarios. When
site-specific constraints are lifted (i.e., for the Maximum Feasible Green
Fields scenario), cost estimates increased more steeply for both environmental
restoration and waste management activities. These large increases are due to
the more extensive removal strategies used during environmental restoration
activities as well as the greater volumes of waste expected to be generated by
these activities. They also reflect a major change in waste management strategy
at Oak Ridge Reservation and the Rocky Flats Environmental Technology Site.
Under the other land-use scenarios (including the Base Case), the waste
management strategy included onsite disposal of some waste at these sites.
Under the Maximum Feasible Green Fields scenario, however, all waste was
assumed to be shipped offsite for disposal.
The average duration of the Environmental Management program at the five
highest-cost sites is estimated to change as the scope of environmental
restoration activities changes under the alternative scenarios (Table 6.3). The
reduced scope of activities under the Industrial and Iron Fence scenarios
reduced the average program duration estimate from 75 years (Base Case) to 73
years (Industrial) and 72 years (Iron Fence). When site-specific constraints
were considered, the small increase in the scope of environmental restoration
activities under the Recreational and Modified Green Fields scenarios did not
increase estimated program duration. Under the Maximum Feasible Green Fields
scenario, however, average program duration increased to 78 years.
These program duration estimates do not include long-term surveillance
and monitoring required to safeguard residual contamination at sites that is
expected to decay naturally or is contained within engineered structures. Such
activities may be required for decades. Although it was not possible to
quantify the duration of surveillance and monitoring, it is likely that it
would be longer for scenarios that emphasized containment over removal
strategies (i.e., Iron Fence and Industrial) than for the Green Fields
scenarios.
6.1.4.2 END STATE CONDITIONS
Table 6.4 illustrates the differences in end-state conditions among the Base
Case and each alternative land-use scenario. Using the land-use standards
discussed above, the acreage of the five highest-cost sites has been depicted
according to the most stringent standard met by the assumed end-state
condition, yielding a measure of cleanup level and referred to as maximum
allowable use.
As noted earlier, the majority of the land area at the five highest-cost sites
(approximately 400,000 hectares [one million acres]) is relatively
uncontaminated and currently meets the requirements for Open Space, Residential
or Agricultural land-use categories. Of these, the smaller number of acres
meeting the Agricultural land-use standard is due to the large number of acres
for which use of ground water is prohibited (in this analysis, ground water use
is required to meet the Agricultural land use standard but not the Residential
land-use standard). In addition, a relatively limited number of acres meet the
standards for Storage/Disposal or Industrial uses across all cases. For the
currently contaminated land areas, most of the variation in land use
assumptions involves shifting from an emphasis on open space in the Iron Fence
scenario to residential in the Modified Green Fields. Recreational use,
although a small percentage of overall use, is most frequent in the
Recreational and Modified Green Fields scenarios. When site-specific
constraints are lifted (i.e., in the Maximum Green Fields scenario), all land
areas except Storage/Disposal Areas are assumed to be remediated to meet a
Residential or Agricultural standard.
Table 6.4. Acreages of Maximum Allowable Use*
| Agricultural |
132,500 |
132,500
|
132,500 |
132,500
|
132,500 |
133,000
|
| Residential
|
653,000
|
844,000
|
861,000
|
844,000
|
863,000
|
1,022,500
|
| Recreational |
17,500 |
19,500
|
3,000 |
67,500
|
153,000 |
0
|
| Open Space
|
341,000
|
147,500
|
147,500
|
103,500
|
0 |
0
|
| Industrial |
10,000
|
14,000 |
14,000
|
10,000 |
9,500
|
5,000 |
| Disposal/ Storage
|
13,500
|
10,000
|
9,500
|
10,000
|
9,500
|
7,000
|
| Total |
1,167,500
|
1,167,500 |
1,167,500
|
1,167,500 |
1,167,500
|
1,167,500 |
* Acre numbers have been rounded for presentation
The Maximum Feasible Green Fields scenario yields an additional 65,500 hectares
(162,000 acres) of Residential and Agricultural use over that achieved in the
Base Case, at an increased cost of approximately $124 billion.
6.1.5 Implications of the Results
The land-use analysis demonstrates that when site-specific constraints are
considered, land-use options are limited, and thus land-use decisions are
likely to have only a small effect on environmental restoration costs. In the
absence of such constraints, however, a greater range of land-use options is
available, and therefore land-use decisions may have a greater effect on costs.
This result is vividly illustrated by comparing the Maximum Feasible Green
Fields and Modified Green Fields scenarios. Both assume the same aggressive
clean up strategies but yet yield dramatically different results. The reason is
that when site-specific constraints other than technology limits are lifted,
cost estimates increase by $124 billion. This additional cost highlights the
critical importance of site-specific constraints in land-use planning.
Many of the site-specific constraints examined in this analysis are
manifestations of federal and local policies or priorities. For example, legal
commitments and local laws limit future-use options for approximately 295,000
hectares (730,000 acres) (63 percent) of the uncontaminated land at the five
highest-cost sites. In addition, the presence of endangered species and
ecologically unique habitats may limit future use for approximately 57,000
hectares (140,000 acres) (12 percent) of uncontaminated land and some
contaminated land at these sites. It will be necessary to consider these
constraints, along with stakeholder and regulator preferences, to make ultimate
decisions regarding future use. Near-term resolution of these issues is
important, because the decisionmaking processes that govern environmental
restoration activities will continue in the absence of coherent integrated site
planning. Land-use options may become limited after deployment of certain
remedial strategies, or remedies designed to meet Residential standards may be
applied inappropriately, resulting in higher than necessary costs.
The siting of Disposal/Storage Areas and continuing Department missions have
implications beyond the acres directly around these structures. The
implications of these future missions on land-use alternatives underscores the
importance clarifying overall goals and developing an integrated, complex-wide,
multimission facilities plan. In fact, the site missions considered in this
analysis did not include long-term storage of plutonium and other nuclear
materials at any of these large sites. Such storage could preclude releasing
any land because of security and public safety concerns. Other missions will
require safety analyses to determine their specific buffer requirements.
Technology challenges relating to ground water and surface water will continue
to limit land use alternatives in the near term. Information relating to
technology limits and costs of aggressive remediation strategies should be
integral to all decisionmaking activities regarding land use and remedial
strategies.
EFFECTS OF LAND-USE DECISIONS ON RISK
Future land-use decisions will have implications beyond the cost and duration of
the Environmental Management program. Future land-use decisions can also
influence the risks incurred by members of the public, workers involved in
remediation, site personnel (not involved in remediation), and the environment.
Because land-use decisions affect the remedial strategy and, hence, the
remedial technologies selected to accomplish remediation, the choice of land
use will affect the type of work performed by remedial workers, the volume of
waste requiring subsequent management, and the types of accidents that could
injure workers, expose them to radioactive or hazardous materials, or release
such materials into the environment. All of these factors influence the risks
to the public, remedial workers, and the environment.
A comprehensive evaluation of risks associated with the five land-use scenarios
discussed above was beyond the scope of this analysis. However, to provide some
indication of these effects, several sites evaluated how risks to human health
and the environment might change with land-use goals. The sites used their own
methods to assess changes in risk for selected projects. An example of these
analyses is presented in the box on the following page. This evaluation is not
based on an engineering study, but is a qualitative examination of potential
risk consequences.
|
EFFECT OF LAND USE ON RISK - AN EXAMPLE FROM THE OAK RIDGE RESERVATION
The Oak Ridge Reservation evaluated the risk impacts of land-use decisions using
five environmental restoration projects for which it was feasible to achieve
alternative future uses ranging from Iron Fence to Green Fields. This
evaluation assumed that protection of public health and onsite personnel is
maintained during the activities required to achieve each of the alternative
land-use scenarios, and the only potential risk implications evaluated that
could be significant would be those to the involved remedial worker. Risks to
waste management workers from waste generated during remediation were not
evaluated.
The evaluation indicated that moving from a highly restrictive future land-use
scenario (Iron Fence) to an unrestrictive future land-use scenario (Green
Fields) would significantly increase risks to remedial workers. This potential
increase in risk is primarily due to the greater number of worker-hours
required to reach a less restrictive land use.M
Typically, the longer the duration of the remediation, construction, or
operation and maintenance activities, the greater the chance of injury from
physical hazards (e.g., construction accidents) and the greater the exposure to
radiological and chemical hazards. General construction accidents also are more
likely as strategies move toward more removal activities because some tasks
such as earth moving or demolition activities have greater inherent physical
risks based upon the nature of the work and the equipment involved.
|
6.2 PROGRAM AND PROJECT SCHEDULING
Many observers have speculated that the pacing of the Environmental Management
program has a significant impact on life-cycle cost. The 1995 Baseline Report
confirmed the premise that life-cycle costs will increase if the program is
extended and decrease if direct mission activities are completed more rapidly.
Given the scale of the projects undertaken in the Environmental Management
program, their cost, and the long-term commitment required, the relationship
between cost and schedule is important. A clear understanding of how scheduling
may influence cost will provide the basis for effective long-term planning and
greater integration of the various components of the program. This section
provides an analysis of the likely impact of changes in the schedule of direct
mission activities on the life-cycle cost of the Environmental Management
program in a series of alternative scheduling cases.
The following discussion on program and project scheduling is divided into six
sections: General Assumptions; Description of the Alternative Cases; Analytical
Approach; Results; Overall Implications of the Analysis; and Limitations of the
Analysis. As with the other alternative scenarios, this analysis focuses on the
five highest-cost sites in the Environmental Management program: Hanford Site,
Idaho National Engineering Laboratory, Oak Ridge Reservation, Rocky Flats
Environmental Technology Site, and Savannah River Site.
|
SIGNIFICANT FINDINGS OF THE PROGRAM AND PROJECT SCHEDULING ANALYSIS
Key assumptions in the area of program and project scheduling were modified to
develop three scenarios. These scenarios examined the life-cycle cost effects
of reducing program funding, delaying high-level waste and spent nuclear fuel
disposal, and accelerating facility stabilization and deactivation activities.
Significant findings are:
-
A $49 billion increase in life-cycle cost for the Funding Reduction Scenario
is largely due to increased pre-treatment storage for high-level waste,
increased surveillance and maintenance for plutonium-holding buildings and
chemical separations facilities, and support costs. Support costs account for
approximately forty-five percent of the life-cycle cost increase. Due to the
fixed nature of support costs, as Environmental Management funding is reduced,
there are fewer resources available to address direct mission activities. In
the Funding Reduction scenario, direct mission activities are delayed, thereby
postponing program completion and increasing support costs.
-
Vitrified high-level waste and spent nuclear fuel will be stored for an
additional 30 years in the Delayed Waste Disposal Scenario
until shipments to a national geologic repository begin. Additional storage
costs will increase life-cycle cost by less than one percent.
-
The Accelerating Stabilization and Deactivation Scenario reduces the
amount of annual surveillance and maintenance required to keep facilities in a
safe, secure, and stable condition until final disposition is determined.
Accelerating these activities reduces life-cycle cost by less than one percent.
|
6.2.1 General Assumptions for the Scheduling Analysis
The alternative schedules in this section are based on changes to the Base Case
assumptions. The primary assumption driving schedules in the Base Case is that
funding is available to fulfill negotiated compliance agreements and to meet
legal requirements. The scheduling analysis does not assume that funding will
be available to meet all of these requirements. End states, however, are
assumed to be the same as in the Base Case. The assumptions varied in this
analysis include:
-
the level of funding available;
-
commencement of shipments of Department of Energy high-level waste and spent
nuclear fuel to a geologic depository; and
-
the priority of programs and projects to be completed.
While continuing to address urgent risks and minimize costs, this analysis
varies these assumptions in a series of scheduling scenarios. Each scenario
changes one or more of the assumptions and demonstrates the likely impact on
life-cycle cost. (Note: all scenarios were developed independent of compliance
agreements and potential fines and penalties.)
6.2.2 Alternative Scheduling Scenarios
The Department developed three alternative scheduling scenarios for the
analysis.
-
Funding Reduction
- The current Base Case projects annual funding requirements of $7.5 billion in
FY 2000. This assumption complies with the FY 1995 National Defense
Authorization Act mandate that requires the Department to provide cost
estimates associated with complying with existing compliance agreements
regardless of budget targets. Because this Base Case estimate clearly exceeds
expected funding availability, it is prudent to analyze the long-term impacts
of reduced funding using a scenario that constrains the overall program
spending. This is exactly what is analyzed through the funding reduction case
that constrains the Environmental Management program's annual budget to $4.9
billion ($5.5 billion in current dollars).
-
Accelerating Stabilization and Deactivation
- The Environmental Management program performs surveillance and maintenance on
all of its facilities to maintain them in a safe, secure condition until final
disposition has been achieved. Stabilization and deactivation of facilities can
help to lower these non-discretionary costs through the removal of fissile and
other dangerous materials. However, because of the additional cost required to
perform stabilization or deactivation, sites are often forced to limit the pace
at which these activities are performed and incur high-cost surveillance and
maintenance activities. This case examines how life-cycle cost is affected if
stabilization and deactivation of facilities was accelerated to reduce the
amount of costly surveillance and maintenance required.
-
Delaying Waste Disposal - Base Case costs are based on the availability,
beginning in 2016, of a geologic repository for the disposal of Department of
Energy high-level waste and spent nuclear fuel. This scenario analyzes the
impact of a 30-year delay in waste shipments on the life-cycle cost of the
Environmental Management program.
Projects were rescheduled and life-cycle costs were recalculated for each
alternative scenario using a general analytical approach.
6.2.3 Analytical Approach
The program and project scheduling analysis relies upon data collected in the
Base Case. Additional information was gathered from the sites to assist in the
analysis.
Three scheduling variables, duration scope growth, physical scope growth, and
support costs, were identified as posing a probable impact on life-cycle cost.
The Department evaluated the impact of these variables on projects accounting
for approximately 80 percent of the costs at each of the five highest-cost
sites. This provided a manageable and representative sample of the activities
in the Environmental Management program.
6.2.3.1 DURATION SCOPE GROWTH
Scope growth refers to the increase or decrease in the cost of a project due to
a delay or acceleration in the current Base Case schedule. Duration scope
growth refers to increases in cost due to additional years of nondiscretionary
activities performed at the site, including surveillance, monitoring, and
maintaining contaminated areas and facilities, and the storage of waste
awaiting treatment or disposal. These activities must be performed each year
that a project is in operation or awaiting clean up to keep a waste, an area,
or a facility in a safe, secure state until a final action is implemented.
6.2.3.2 PHYSICAL SCOPE GROWTH
Typically, contaminated facilities deteriorate and contaminated land areas
increase over time. Aging production and processing buildings, decaying storage
facilities, and migrating contaminants in the soil contribute to the change in
physical scope of the project. These changes are referred to as physical scope
growth. Where delaying a project results in physical scope growth, project
costs may increase. Conversely, accelerating a project that has physical scope
growth potential may decrease project cost.
Projects were assessed by the sites according to how the scope of a project
would change over time if that project were delayed, and conversely, how the
scope might change if the project were accelerated. For environmental
restoration and nuclear materials and facility stabilization activities,
estimates of physical scope growth were provided for 5, 10, 20, and 50 year
delays.
The Department used a different approach to determine physical scope growth for
waste management activities. Using models, the Department estimated the change
in costs under different treatment scenarios and then compared these costs to
the Base Case. Each treatment scenario required a different strategy for the
construction of storage and treatment facilities to house and treat waste. (See
Appendix C for further details on this methodology.)
6.2.3.3 SUPPORT COSTS
As discussed in previous chapters, a portion of the Environmental Management
program costs are not incurred for specific projects. Instead, they are
incurred for activities that are not directly related to direct mission
activities, but are essential to the safe and effective management of these
activities. Accelerating the completion of the Environmental Management program
activities should reduce the number of years for which these support costs are
incurred and therefore reduce life-cycle costs. Conversely, delaying the
completion of the Environmental Management program should increase the number
of years for which support costs are paid and increase life-cycle cost.
For the scheduling analysis, models were used to estimate annual support costs.
Based on the statistical relationship between support and direct mission costs
in the Base Case at each site, new support costs were estimated for each
alternative scenario.
6.2.4 Scheduling Results
Section 6.2.2 briefly described the three scheduling scenarios. The results of
the analysis are presented below.
6.2.4.1 FUNDING REDUCTION
For this scenario, a reduced annual funding level of $4.9 billion (in 1996
constant dollars) was assumed, consistent with the Administration's outyear
target of $5.5 billion (in current dollars) for FY 2000.
To meet the funding constraint, each site's funding limit was reduced
proportionally in FY 1998, FY 1999, and FY 2000 and then held constant
thereafter at the FY 2000 level. For the five large sites, this amounts to $3.5
billion in 2000. All activities and end states in this case were consistent
with those assumed in the Base Case, since this analysis focuses on
rescheduling, and not on re-scoping. Therefore, compliance agreements are met
in substance, but not according to schedule.

Figure 6.3. Annual Comparison of the Funding Reduction Case and
the Base Case
Projects were rescheduled based on comparisons of the likely impact of scope
growth on life-cycle cost. To stay beneath the funding level, projects assumed
to have little or no scope growth were delayed, and projects assumed to have
significant scope growth were accomplished as soon as possible. Because of
technical constraints, relationships between large, interconnected projects,
including those where changes in scope could cascade from one project to
another, were maintained.
A reduction in near-term spending results in a 31 percent increase in life-cycle
costs. Delayed treatment and disposal of waste results in increased
storage costs, ground-water and surface-water contamination migrates as
remediation is delayed, facilities decay, requiring maintenance and repairs,
and sites have to pay additional support costs as the program end date
stretches past the Base Case. As discussed in earlier chapters, support costs
are relatively fixed. As funding levels are reduced, fewer dollars are
available to conduct direct mission activities. Figure 6.3 provides an annual
cost profile comparison between the Funding Reduction Case and the Base Case.
|
A $4.0 BILLION FUNDING REDUCTION CASE
The $4.9 billion Funding Reduction case described in this chapter estimates the
expected life-cycle cost for the five largest sites under a currently targeted
funding scenario. In reality, however, many different funding levels could be
set, each of which would have a different impact on the total life-cycle cost
of the Program. This sidebar describes additional analyses performed to better
estimate the relationship between different funding levels and total life-cycle
cost of the Environmental Management program.
Using simplified modeling techniques, the likely change in total life-cycle
cost was estimated if the funding level were reduced to $4 billion annually. As
in the $4.9 billion case, certain assumptions were made about the cost drivers
in the program: support costs were assumed to be relatively fixed, and direct
mission costs were expected to increase over time as a result of scope growth.
Because of the fixed nature of support costs and the impact of scope growth as
projects are delayed, an annual budget of $4 billion not only extends the
program into the twenty-second century, but also significantly increases
life-cycle cost. Under the $4 billion case, the total life-cycle cost for the
five sites is $297 billion, an increase of 87 percent above the Base Case.
Direct mission activities would be completed in approximately 2172, more than
100 years after the end date of the Base Case. The increase in life-cycle cost
is largely due to support costs incurred during the additional years of
operation.
As the funding level is reduced, support costs become a larger proportion of
the total budget. Thus, direct mission activities will take significantly
longer to complete, incurring additional support costs, nondiscretionary
surveillance and maintenance costs, and a significant amount of scope growth as
facilities deteriorate and contaminants spread. In many ways, this is a
conservative estimate. In addition to the support costs required to maintain
sites in a safe working state, other nondiscretionary costs are also incurred
irrespective of the level of clean-up activity. If funding falls to a level
where resources are only available to pay for support costs and
nondiscretionary requirements, direct mission activities cannot be performed.
|
6.2.4.2 ACCELERATING STABILIZATION AND DEACTIVATION
Surveillance and maintenance activities ensure that adequate material and
facility safety and security requirements are met. These costs represent a
"mortgage" associated with managing potential hazards resulting from the
presence of radioactive and hazardous materials in the facility. Stabilization
and deactivation activities are conducted to mitigate these hazards. Once these
hazards have been mitigated, surveillance and maintenance costs for maintaining
the facilities are reduced significantly.

Figure 6.4. Annual Comparison of the Accelerating Stabilization and Deactivation
Case and The Base Case
Further acceleration of stabilization and deactivation has minimal life-cycle
cost impact. By completing projects earlier in the life cycle, total
costs decrease because fewer surveillance and maintenance activities are
required.
This scenario was analyzed to determine if total life-cycle cost reductions
could be achieved by accelerating stabilization and deactivation activities.
For the analysis, stabilization and deactivation activities in the Base Case
were accelerated to begin in the near-term, ultimately reducing costly
surveillance and maintenance activities by one or two years. The results of the
analysis demonstrate that approximately $500 million in life-cycle cost can be
saved by accelerating stabilization and deactivation activities. The results
imply that most stabilization and deactivation activities have already been
scheduled prudently in the Base Case to realize cost savings in the out-year
costs for facilities. Figure 6.4 provides an annual cost profile comparison
between the Accelerating Stabilization and Deactivation Case and the Base Case.
6.2.4.3 DELAYING WASTE DISPOSAL
The Environmental Management program currently assumes that it will permanently
dispose of high-level waste and spent nuclear fuel at a national geologic
repository. In the Base Case, sites assume that shipments from the
Environmental Management program to a national geologic repository begin in
2016. For this analysis, the Department assumes that sites send waste to a
geologic repository beginning in the year 2046, a 30-year delay.
Only three of the five sites currently have high-level waste and spent nuclear
fuel assumed to be disposed of at a national geologic repository: the Hanford
Site; the Idaho National Engineering Laboratory; and the Savannah River Site. (Note:
The Department of Energy's Office of Civilian Radioactive Waste Management
manages and funds the development of a national geologic repository. The costs
incurred by a 30-year delay in this analysis represent only those direct costs
to the Environmental Management program and reflect Department of Energy
defense and nondefense waste only. This analysis does not account for any costs
incurred by the Civilian Radioactive Waste Management program. Furthermore, the
results are not intended to be extrapolated or applied to the commercial
nuclear industry or to costs associated with the disposal of commercial nuclear
waste.)
For this scenario, high-level waste and spent fuel are still being treated to
the same end state assumed in the Base Case. High-level waste vitrification
will continue as scheduled in the Base Case. However, the vitrified glass logs
will be stored for an extended period until the repository can accept them.
Increases in life-cycle cost are due to additional years of waste storage, and
in some cases, the construction of new storage facilities.

Figure 6.5. Annual Comparison of the Delaying Waste Disposal
Case and the Base Case
The results of this case reveal that delaying waste disposal shipments to a
national geologic repository has an impact of less than $1 billion (about a one
percent increase) on the life-cycle cost of the Environmental Management
program. Figure 6.5 provides an annual cost profile comparison between
the Delay Waste Disposal Case and the Base Case.
Delaying shipments to a national geologic repository increases life-cycle cost by
approximately one percent. Delaying the disposal of high-level waste
and spent nuclear fuel increases life-cycle cost because storage facilities
must accommodate the waste for a longer period of time. In some cases, if
onsite storage is inadequate, sites must construct new storage facilities.
6.2.5 Overall Implications of Program and Project Scheduling Analysis
The scheduling analysis indicates that there will be a significant increase in
total life-cycle cost of the Environmental Management program if annual funding
levels are reduced to $4.9 billion. The increase is due not only to support
costs that must be paid as long as there are mission activities at the site but
also to scope growth of direct mission activities. Stabilization and
deactivation activities would have to be postponed and additional years of
costly surveillance and maintenance would be realized. In addition, treatment
of high-level waste would have to be performed at a much slower rate, thereby
increasing pre-treatment storage costs (i.e., single-shell tanks that currently
are storing high-level waste would have to be replaced). Any near-term savings
from a reduced Environmental Management program budget are offset by large
increases in life-cycle cost.

Figure 6.6. Comparison of Alternative Scheduling Scenarios
(Cumulative Costs)
The results demonstrate that the Accelerating Stabilization and Deactivation and
Delaying Waste Disposal cases have a minimal impact on the total life-cycle
cost of the program. By accelerating stabilization and deactivation activities,
more funds are spent earlier in the life-cycle, but less is spent in later
years, resulting in only $300 million savings in direct mission cost. Delaying
disposal activities increases direct mission life-cycle cost by only $600
million because of additional storage costs. Because neither case extends the
life-cycle of the program, support costs do not vary significantly from the
Base Case. Both cases support evidence that these activities are prudently
scheduled in the Base Case. Figures 6.6 and 6.7 provide life-cycle cost
comparisons of the Base Case and the three alternative scheduling scenarios.
Figure 6.7 provides a summary comparison of the scheduling cases, broken-out by
direct mission and support costs. Support costs increase approximately $20
billion in the Funding Reduction Case, a 15 percent increase above the Base
Case.

Figure 6.7. Comparison of Alternative Scheduling Scenarios
(Direct Mission and Support Cost Totals)
EFFECTS OF PROJECT DELAYS ON RISK
Scope growth associated with project delays may have implications beyond the
cost of the Environmental Management program. Scope growth also has the
potential to affect risks to public health, workers, onsite personnel, and the
environment. Additional years of nondiscretionary activities such as
surveillance and maintenance or waste storage will increase the period of time
that workers are exposed to the types of accidents that could injure them,
expose them to radioactive or hazardous materials, or release such materials
into the environment. Physical deterioration of facilities or storage units, or
the spread of contamination in the environment, could increase both the
likelihood of accidents and the amount and type of work required to complete
direct mission activities.
A comprehensive evaluation of risks associated with project delays is beyond the
scope of this analysis. However, to provide some indication of how risks to
human health and the environment might change with project delays, several
sites evaluated how risks to human health and the environment might change if
selected projects were delayed for 5, 10, 20, or 50 years. An example of these
analyses is presented in the box below. This evaluation is not based on an
engineering study, but is a qualitative examination of potential risk
consequences.
|
EFFECT OF PROJECT DELAY ON RISK - AN EXAMPLE FROM THE OAK RIDGE RESERVATION
The Oak Ridge Reservation considered the possible risk implications of delaying
the decontamination and decommissioning of the K-25 Gaseous Diffusion Plant and
associated process buildings. The process buildings are contaminated by uranium
hexafluoride, technetium-99, asbestos, PCB's, inorganic acids, organic acids,
metal fluorides, hexafluorides, oxyfluorides, and other chemicals. A
qualitative evaluation of the risks associated with the workers, onsite
personnel, offsite receptors, and ecological receptors was performed.*
Because of the location of the buildings, the Department predicts that delays
of up to 50 years will not affect risks to onsite personnel, the public, or the
environment. However, the current conditions of these facilities pose risks to
the workers performing general surveillance and maintenance activities in the
buildings and risks to the workers during the decommissioning activities. The
results indicate that worker risk is mainly dominated by physical hazards
(e.g., the roofs in some buildings are currently in need of repair).
Based on the conditions of the buildings, even a five-year delay in starting
decontamination could increase the risk to workers. Risk would likely increase
as a result of continuing building decay, which may cause washout events (due
to damage in the steam lines or water lines), air exposures (due to breakdown
in the air handling system), and roof collapse. A roof failure has already
occurred at a facility awaiting decommissioning at K-25 and it is expected that
a failure could occur in other buildings. A 50-year delay could result in an
even greater increase in risk to workers both before and during the
decommissioning is initiated since the gaseous diffusion plant and associated
facilities would show even further signs of decay.
* This analysis assumed that techniques would remain the same, and the
decontamination and decomissioning strategy in the Base Case would be the same
strategy employed for each of the delay cases.
|
6.2.6 Limitations of the Analysis
This scheduling analysis is intended to be used for policy analysis purposes.
Thus, it is meant to show at a policy level how and why aggregate life-cycle
costs change as Base Case scheduling assumptions change. It is not meant to
show how these changes affect costs at individual sites or to help sites
schedule projects.
First, not all projects were rescheduled. Only those projects accounting for 80
percent of the costs in each program at each site were examined. By focusing on
only a portion of the activities at a given site, the analysis potentially
understates both savings from an acceleration case and cost increases from the
funding reduction and delay disposal cases.
Second, support costs were modeled at each site to reflect changes in the annual
cost due to rescheduling. Support costs were estimated using a statistical
analysis of the relationship between Base Case annual direct and support costs.
Third, the scope growth factors provided by the sites are subject to
uncertainty. Specific activities were rescheduled based on theoretical scope
changes. How the costs for activities change over time is difficult to
estimate, and an analysis based on those estimated scope changes would have the
same level of uncertainty.
6.3 A "MINIMAL ACTION" SCENARIO
The current budget deficit and the growing need to reassess national priorities
have led to a controversial yet pragmatic question: What is the minimum funding
required for maintaining the Environmental Management program without
increasing risk to human health or the environment, but without the
constraints of current environmental regulations and compliance agreements? The
interest in this "minimal action" scenario is driven by a number of diverse
perspectives on the program. Some observers, especially supporters of the
program, have speculated that the cost of a minimal action scenario is not
significantly different from current program expenditures (especially in the
short term). This view is based on the fact that a large amount of funding
currently is required simply for the program to serve as the landlord at
Environmental Management sites and to monitor the storage of highly radioactive
waste and special nuclear materials.
Other observers, especially critics of the current regulatory system, believe
that current requirements can be relaxed, generating a substantial cost savings
without negative human health and environmental consequences. Finally,
policymakers express interest in this minimal action case because it provides a
lower boundary for the range of alternatives available to the program. With
this information in hand, policymakers and stakeholders can better understand
what tasks are truly necessary for short- and long-term risk and cost
reduction.
|
SIGNIFICANT FINDINGS OF THE MINIMAL ACTION ANALYSIS
This analysis examines the consequences of re-structuring the Environmental
Management Program to focus on two objectives: preventing human health and
environmental risks from increasing and otherwise minimizing costs for 75
years. Meeting compliance agreements and regulatory requirements was not
necessary as long as activities were consistent with these objectives.
-
Major changes in the program would occur under this scenario. Remedial actions
would be limited to problems with urgent risk implications, and most facility
decommissioning would cease. Waste treatment would be minimized, with onsite
storage or disposal replacing offsite shipments for disposal. Waste storage
facilities would not be required to meet national waste regulations. All
high-level waste, spent nuclear fuel, and special nuclear materials would
remain onsite.
-
Estimated costs during the 75-year period would decrease by more than 40
percent, with major declines in environmental restoration costs (70 percent
lower) and waste management costs (40 percent lower). On the other hand,
estimated annual costs for long-term surveillance and monitoring activities after
the 75-year period would be nearly four times higher than in the Base Case.
-
A minimal action strategy would leave waste inventories onsite and many
buildings standing. These would require significant surveillance and monitoring
efforts to continue far into the future. As waste management facilities and
buildings deteriorate over time, risks to workers will increase, and additional
costs for upgrades or repairs would be incurred. There also would be a greater
chance that contamination could spread offsite to threaten public health and
the environment.
|
The minimal action scenario differs substantially from the other alternate
program cases in this chapter: it requires a complete re-examination of the
mission of every activity in the program. An initial analysis of a minimal
action case was conducted for the 1995 Baseline Report (see box). The 1996
Baseline Report expands on this analysis by: (1) focusing in more detail on the
life-cycle cost implications of a minimal action scenario at the five
highest-cost sites, (2) examining in more depth the site end-states and
long-term risks associated with the case, and (3) making a more explicit
comparison between the Base Case and the minimal action case.
Like many of the other analyses in this report, this case is a policy-level
examination of the consequences of modifying key program assumptions. However,
this analysis provides a broad perspective on the implications of a minimal
action analysis. The information in this section is not based on a
detailed engineering analysis. Each site developed its own methods of
addressing this scenario; in many cases this involved a complete rescoping of
projects and activities. The next steps for a more complete minimal action
scenario is to extend the analysis to all Environmental Management sites and
base the results on a more detailed engineering evaluation of the minimal
action alternatives.
This section begins with a presentation on how the minimal action case was
developed, highlighting the guiding principles and strategies used by the sites
to develop their minimal action approach. This is followed by an overview of
the assumptions used by the sites in developing their minimal action scenario.
The results of the analysis are presented in three areas: 1) Minimal action
75-year cost estimate by site, functional area, and over time; 2) End states at
each site (final physical condition), focusing on post-2070 land use, onsite
waste inventories, and surveillance and monitoring activities; and, 3) Onsite
and offsite risks (both human and environmental) during and beyond the minimal
action case period. The section concludes with a discussion of the overall
implications and limitations of the minimal action analysis.
|
1995 MINIMAL ACTION CASE
The 1995 Baseline Environmental Management Report Minimal Action case projected
program costs through 2070 with the premise that available annual funding would
be dramatically reduced beyond the year 2000.
Assumptions
-
Treatment and disposal of all high-level waste and spent nuclear fuel
-
Stabilization and surveillance and monitoring of surplus facilities
-
"Safe" storage of all low-level, low-level mixed, and transuranic waste
Excluded from Scope of Analysis
-
Environmental Restoration
-
Deactivation and decontamination activities
-
Treatment and disposal activities for low-level, low-level mixed, and
transuranic waste
-
Long-term risk information
Findings
-
Twenty-seven percent reduction in 75-year cost estimates from 1995 Base Case
|
6.3.1 How the Minimal Action Case Was Developed and Analyzed
|
MINIMAL ACTION SCENARIO PERIOD OF ANALYSIS
Unlike the Base Case, Environmental Management activities in this minimal action
scenario are not completed by the year 2070. For purposes of analysis, however,
the period of 1996 through 2070 was chosen to provide a snapshot of the minimal
action case. Use of this time period provided an easy comparison of activities,
cost estimates, and end states between the Base Case and the minimal action
case. Throughout this section, the 75-year period of analysis refers
specifically to the time period of 1996 through 2070 and should not be
interpreted as the complete life-cycle period of the minimal action case.
|
The objectives of this case are to develop an alternate scenario that does not
increase life-cycle risks from current levels to humans and the environment
while still reducing costs through 2070. The minimal action case examines
75-year costs and activities at the five largest sites within the Environmental
Management program (Hanford Site, Idaho National Engineering Laboratory, Oak
Ridge Reservation, Rocky Flats Environmental Technology Site, and Savannah
River Site). The sites used the following broad guiding principles to create
their minimal action scenario:
-
All activities should reflect the lowest possible cost options.
-
Activities must not
increase the public health, worker, or ecological risks associated with the
Base Case through 2070.
-
Activities must be consistent with safety goals but do not need to address
compliance agreements or regulatory requirements.
These principles differ from the Base Case in that the Base Case is a compliance
case, whereby costs, end states, and risks reflect activities that address all
current environmental regulations and compliance agreements.
In developing their minimal action scenario, the sites used the following
strategies to develop a case that stabilizes and safely contains waste and
surplus materials onsite and minimizes the costs of safeguarding these
materials throughout the 75-year minimal action case time period (1996 through
2070):
-
Urgent risk reduction - Eliminate immediate human health and environmental
risks.
-
Mortgage reduction - Minimize costs during the minimal action analysis period.
-
Minimum action - Eliminate projects that do not pose risks during the minimal
action analysis period.
-
Regulatory relief - Activities do not need to meet compliance agreements or
environmental regulations unless they affect urgent risks.
-
Prudent management practices - Pursue more "complete" actions if
cost-effective.
-
Institutional controls - The Federal Government will maintain all control of
federal lands.
Each of the five sites used the 1996 Base Case data as a foundation for
developing site-specific assumptions and 75-year costs. From the Base Case,
sites modified their project and activity schedules and scopes of work based on
minimal action assumptions. After developing a set of minimal action projects
and activities, each site evaluated cost differences, site "end states," and
pre-2070/post-2070 onsite and offsite risks.
6.3.2 Cross-Site Assumptions
Based on the approach discussed above (address urgent risks while reducing costs
and overall effort), each site developed its own site-specific minimal action
scenario. In general, the sites adopted similar approaches when addressing
specific activities (Table 6.5). The only exception was the treatment and
stabilization of high-level waste.
For high-level waste, each site found a different minimal action approach to
addressing onsite high-level waste inventories. Savannah River Site found that
the best minimal action strategy is to stabilize high-level waste and store it
onsite. The site recently completed construction of the Defense Waste
Processing Facility (a facility used to stabilize high-level waste into glass
through a process called "vitrification"). Under the Base Case, Savannah River
Site plans to use the Defense Waste Processing Facility to vitrify the
high-level waste and then ship the glass to an offsite geologic repository.
Because the construction of this facility is already complete, the Savannah
River Site plans to use the facility in the minimal action scenario, but at an
accelerated rate. The Savannah River Site also will keep the vitrified
high-level waste onsite, saving the expenses involved in preparing and shipping
the waste to offsite disposal.
Table 6.5. Cross-Site Assumptions
| High-Level Waste |
To be disposed of in a geologic repository.
|
Onsite storage. Differing treatment and stabilization
practices across sites. |
| Spent Nuclear Fuel
|
To be disposed of in a geologic repository.
|
Onsite storage in concrete or stainless
steel "dry storage" casks.
|
| Low-Level, Low-Level Mixed, and Transuranic Waste
|
Some treatment of low-level and low-level mixed waste;
dispose of offsite. Treat transuranic waste and ship to Waste Isolation Pilot
Plant.
|
Storage and disposal onsite with minimal treatment.
|
| Environmental Restoration
|
Remediate (cleanup) all areas required by
environmental regulations/compliance agreements. Buildings will be demolished.
|
Remediate only areas with urgent
environmental or human risk implications. Buildings will be remain in place.
|
| Nuclear Material and Facility Stabilization
|
Nuclear material stabilized. Deactivation activities to
minimize surveillance and maintenance.
|
Same as Base Case. |
| Support
|
All costs to support mission activities.
|
Re-estimation based on minimal action
activities. Landlord and support activities extended through 2070 at all sites.
|
The Hanford Site stores high-level waste in 149 single-shell tanks and 28
double-shell tanks. Approximately 200 million liters (53 million gallons) of
high-level, low-level, and transuranic waste have been stored in these
underground storage tanks since 1944. While no waste has leaked from the
double-shell tanks, 67 of the older single-shell tanks have leaked
approximately four million liters (1.1 million gallons) of this waste into the
surrounding soil.
The Hanford Site found that the best minimal action approach is consolidating
the high-level waste from the double-shell tanks, and leaving single-shell tank
high-level waste in existing tanks. All high-level waste from the double-shell
tanks will be separated from low-level liquid waste and consolidated into two
tanks. The emptied double-shelled tanks will be capped. To avoid increasing
risk for the 75-year period of analysis, the Hanford Site will begin replacing
double-shell tanks around 2030. The high-level waste in the single-shell tanks
will be stabilized and remain in the tanks. Throughout the minimal action
period, the domes (roofs) of the single-shell tanks will be protected from
structural collapse. The waste in the single-shell tanks will remain in these
tanks indefinitely at some increased risk due to continued tank deterioration
and leakage.
|
HANFORD SITE - EVALUATING STRATEGIES FOR HIGH-LEVEL WASTE
The Hanford Site has 149 single-shell tanks and 28 double-shell tanks. These
tanks contain both solid and liquid high-level waste, primarily from spent fuel
reprocessing plants. Under the Base Case, all waste will be removed from these
tanks, treated so that it can be separated into two fractions (high-level waste
and low-level waste), and then vitrified. The low-level waste will then be
disposed of onsite and the high-level waste canisters will be stored onsite
until they can be shipped to a geological repository for disposal.
In developing their minimal action case, Hanford planned to stabilize and leave
single-shell tanks in place. At first, Hanford considered also leaving the
double-shell tank waste in storage and replacing these tanks every 50 years.
However, it was determined to be lower cost to process the double-shell tank
waste into two fractions so that the low-level waste fraction could be disposed
onsite and the remaining smaller high-level waste fraction could be stored in
two double-shell tanks. This would require only two double-shell tanks to be
replaced every 50 years versus 28 double-shell tanks, resulting in a lower
75-year cost estimate. Continued storage of the waste in the 149 single-shell
tanks would include adding structural support to prevent dome collapse. The
waste in the single-shell tanks would continue to be stored through the minimal
action case period at some increased risk due to continued tank deterioration
and leakage. The increased risk to the public of future leakage from the
stabilized single-shell tanks is reduced in the minimal action case by the
continued maintenance of existing site boundaries and restricted access to the
ground water under the site.
|
Idaho National Engineering Laboratory stores its high-level waste in aboveground
storage tanks. For high-level waste stabilization, however, Idaho found the
lowest risk, least-cost option in calcining the waste at the New Waste
Calcining Facility. (Calcining converts liquid high-level waste into a granular
solid. This process makes the waste less corrosive and dramatically reduces
volume.) Under the Base Case, Idaho plans to further stabilize the calcined
high-level waste through vitrification and ship it to an offsite geologic
repository. Because the high-level waste is already in a sufficiently stable
form to minimize risks over the 75-year period, Idaho's minimal action approach
is to store the calcined waste in onsite bins.
In comparing the Base Case and minimal action case assumptions, the scope of
activities in terms of nuclear material and facility stabilization does not
change. The specific goal of the nuclear material and facility stabilization
program-to ready these materials and facilities for a "cheap to keep"
mode-leads to relatively inexpensive long-term surveillance and monitoring.
This goal is consistent with the guiding principles of the minimal action
approach. Therefore, the activities involved in nuclear material and facility
stabilization will continue in the minimal action case.
6.3.3 Minimal Action Case Results
The results of minimal action analysis are presented in the following four
categories: 75-year cost estimates by function area and over time, end states,
and risk implications. Figure 6.8 compares the 75-year cost estimate for the
Base Case and minimal action case for each of the five highest-cost sites. As a
result of the minimal action case analysis, the 75 - year cost estimate for all
five sites was reduced to approximately 56 percent of the Base Case cost
estimate for the same period.

Figure 6.8. Minimal Action Results for the Five Highest-Cost Sites
6.3.3.1 75-YEAR COST ESTIMATE ACROSS FUNCTIONAL AREAS
As mentioned above, the assumptions used in the minimal action case were strong
drivers of the results of this case. Specifically, the shift in assumptions
between the Base Case and the minimal action case is clearly apparent when
75-year costs are compared at the functional level (Figure 6.9). The minimal
action case life-cycle cost estimate represents a 44 percent reduction from the
total Base Case 75-year cost estimate. The elimination of offsite shipping and
disposal activities at the Idaho, Hanford, and Savannah River Sites reduced the
high-level waste cost estimate by 45 percent from the Base Case, matching the
overall cost estimate reduction. This decrease, however, is not as equally
distributed across the remaining functional areas.
The change in strategy regarding the treatment and disposal of low-level,
low-level mixed, and transuranic waste affects the 75-year cost estimate, with
a 61 percent reduction from the Base Case. The treatment and storage of
low-level and low-level mixed waste are controlled by numerous environmental
regulations and compliance agreements. These regulations/agreements control the
type of treatment, storage, and disposal method for each waste type. In the
minimal action approach, however, the sites are not required to comply with
these specific regulations or agreements. Hence, the sites found that they
could still minimize onsite and offsite human and environmental risks for 75
years with the use of less expensive treatment activities and onsite storage
and disposal facilities.

Figure 6.9. 75-Year Cost Estimate by Functional Area for Five
Highest-Cost Sites
Under the Base Case, transuranic waste is destined for the Waste Isolation Pilot
Plant, a geologic repository. For a site to ship to the plant, all transuranic
waste must undergo extensive characterization and packaging efforts. Under the
minimal action approach, each site found that it could keep 75-year risks at
the same level as the Base Case and lower costs by storing the transuranic
waste onsite with periodical repacking.
The greatest decrease between the two cases is represented in the 75-year cost
estimate for environmental restoration activities - a 70 percent reduction in
minimal action costs from the Base Case. This dramatic cost reduction clearly
illustrates the impact of reduced compliance-driven remediation activities. It
also highlights how most Base Case environmental remediation and
decommissioning activ
|
SAVANNAH RIVER SITE - ADDRESSING THE HIGH MORTGAGE
The nuclear material and facility stabilization activities at the Savannah River
Site are focused on reducing all nuclear material hazards and preparing former
production facilities for shutdown mode. Both aspects of this program highlight
the guiding principles of the minimal action scenario: not increasing risk for
the 75-year period above Base Case levels while minimizing effort.
NUCLEAR MATERIAL AND FACILITY STABILIZATION
75-year Cost Estimate
Base Case: $3.6 billion
Minimal Action: $3.9 billion
The Savannah River Site was established in 1950 to produce special radioactive
isotopes to support national weapons programs. Upon completion of the
production activities, a large inventory of nuclear material in various stages
of the production cycle remained onsite. These materials include acidic
solutions in stainless steel tanks, radioactive isotopes packaged in storage
cans and drums, and nuclear reactor components stored in both dry and
water-filled basins. To address the potential onsite and offsite risks and
reduce the costs of managing these nuclear materials, the Savannah River Site
will convert these materials into stable forms at their separations facilities.
Upon completion of the removal of these nuclear materials, the site also is
responsible for stabilizing and deactivating more than 1,000 buildings by
coating or removing contaminated areas, removing all utility systems, and
preparing these buildings and facilities for low-cost surveillance and
monitoring activities. This aspect of nuclear material and facility
stabilization activities reduces all life-cycle period onsite and offsite risks
posed by surplus nuclear production buildings while minimizing the long-term
costs of building maintenance.
The small increase in costs for nuclear material and facility stabilization
activities at the Savannah River Site reflects the cost increase for long-term
onsite storage of special nuclear material.
|
6.3.3.2 LIFE-CYCLE COST ESTIMATE OVER TIME
When presented over time, the minimal action case clearly illustrates the change
in scope of activities at each site (Figure 6.10). In contrast to the Base
Case, funding level estimates in the minimal action case are higher in the
early years and then drop quickly, but are maintained at a fairly constant
level after approximately 2030.
One of the 75-year schedule drivers is the different approach to waste
management between the two cases. In the Base Case, the sites assume that
high-level waste, spent nuclear fuel, and transuranic waste will be shipped to
offsite disposal facilities by 2045. In the minimal action case, however, sites
found that the least-cost strategy is to retain high-level waste, spent nuclear
fuel, and transuranic waste in onsite storage facilities. This change in
strategy refocuses cost efforts away from a short-term, high investment
treatment and disposal strategy towards a strategy of long-term storage and
continual surveillance and monitoring.

Figure 6.10. Base Case and Minimal Action Case Annual Costs
Another driver in the shift in the cost estimate over time between the two cases
is the comparison of building deactivation and demolition activities. In the
Base Case, most sites stabilize, decontaminate, and demolish all major
buildings onsite and release a large amount of land for unrestricted use. Under
the minimal action case, buildings are stabilized and left standing. Long-term
surveillance and monitoring activities are required thereafter.
The shift in activity scope between the Base Case and the minimal action case is
especially apparent in the area of support cost estimates. These cost estimates
represent activities that are necessary for the continuation of each site's
mission, but they are not mission-related activities. (See Chapter 3 for a more
detailed description of Base Case support costs.) During the early stages of
the 75-year period of analysis (1996-2025), minimal action support cost
estimates range from 45 to 55 percent of Base Case cost. Between 2025 and 2050,
however, the minimal action support cost estimates approach the same levels as
the Base Case. By 2070, the minimal action support costs are actually three and
a half times higher than the Base Case costs.
While the minimal action scenarios developed by each site decrease overall cost
over the 75-year period, the minimal action scope of activities requires sites
to continue operation beyond 2070. This is specifically apparent with Savannah
River Site and Rocky Flats Environmental Technology Site, two sites that have
nearly completed all activities by 2055 under the Base Case. These changes in
minimal action and Base Case cost estimates reflect the minimal action case's
shift to long-term surveillance and monitoring activities (and corresponding
support activities) at the sites.
|
ROCKY FLATS ENVIRONMENTAL TECHNOLOGY SITE - SHIFTS IN SPENDING OVER TIME
To minimize urgent risks and reduce the cost of activities over the long term,
Rocky Flats found that a minimal action approach at their site involved a
fundamental shift in activity scheduling.
Much like Savannah River, Rocky Flats is seeking a "cheap to keep" mode for all
of its buildings and facilities. For their minimal action approach, Rocky Flats
found that accelerating the process of stabilizing facilities will allow the
site to shift more quickly to a lower-cost surveillance and monitoring phase.
Because of this acceleration, site costs are actually higher between 1996 and
2000. The increased stabilization activities increase the minimal action case
by $188 million over the Base Case for 1996 to 2000. These activities lead to a
shift to lower-cost surveillance and monitoring activities by 2015.
Although this initial minimal action investment is higher than the Base Case,
Rocky Flats manages to decrease overall 75-year costs from $17.3 billion (Base
Case) to $11.8 billion (minimal action case).
|
6.3.3.3 END STATES
As a result of storing waste onsite and eliminating most building demolition
activities, each site's minimal action end state is quite different from the
Base Case. These differences can be found in three major areas: land use,
onsite waste inventories, and surveillance and monitoring activities.
Land Use: A large portion of land controlled by each site can be
considered a buffer area used for both security and environmental safety
reasons. As a result, a large portion of the land in both the Base Case and the
minimal action case does not require any cleanup or remedial activities. Future
land use in the minimal action scenario reveals little difference from the Base
Case. For example, under the Base Case, Rocky Flats Environmental Technology
Site plans to release 2,300 hectares (5,680 acres) as unrestricted Open
Space and 40 hectares (100 acres) as restricted Open Space. The minimal
action approach decreases the unrestricted Open Space land by only 235 hectares
(580 acres). The difference: in the minimal action case, approximately 175
buildings and facilities remain standing and monitored by Rocky Flats.
Onsite Waste Inventories : As discussed above, all high-level waste,
spent nuclear fuel, and transuranic waste remain onsite in the minimal action
case. During the period of this analysis (1996-2070), in accordance with the
minimal action principles, each site must perform activities aimed at
maintaining onsite and offsite risks at the same level as the Base Case.
However, after 2070 in the minimal action case, this waste remains onsite and
will require continual storage and repacking activities that are not included
in the Base Case or minimal action case 75-year cost estimations. To understand
the magnitude of these waste inventories, the Hanford Site, for example, will
have an estimated total of 165,000 metric tons (182,000 tons) of waste
(high-level and transuranic) stored onsite at the end of the minimal action
period. In the Base Case, all of this waste is shipped to offsite disposal
facilities.
Surveillance and Monitoring Activities : Two factors - the long-term
storage of high-level waste, spent nuclear fuel, and transuranic waste and the
elimination of building demolition - require continuing surveillance and
monitoring activities not addressed in the Base Case. In the minimal action
case, the annual cost of surveillance and monitoring costs after 2070 is
estimated at $135 million (for all five sites). Under the Base Case, these five
sites estimate between $35-$50 million per year of surveillance and monitoring
costs beyond 2070.
|
OAK RIDGE RESERVATION - FOCUS ON THE MINIMAL ACTION END STATE
For its minimal action approach, Oak Ridge Reservation employs a strategy of
stabilizing existing buildings with continual surveillance and monitoring
activities to maintain them in a safe, shutdown condition. Its minimal action
strategy also includes maintaining waste inventories onsite and minimizing
remediation of non-urgent contamination. The impact of these activities on the
end state of the Reservation differs greatly from the Base Case.
In the Base Case, few buildings remain onsite; most are demolished prior to
2070. Waste will be treated and shipped to offsite disposal facilities by 2070
and there will be no existing waste inventories requiring repackaging or
surveillance activities.
The minimal action scenario presents a very different picture for Oak Ridge
Reservation. With no demolition activities planned in the minimal action case,
150 buildings remain onsite at the end of 2070. Some of these buildings contain
the waste volumes not shipped offsite, while others are vacant structures. All
land containing waste and vacant buildings requires constant surveillance and
monitoring activities to minimize structural or contamination risks. Waste
remaining onsite also requires periodic repacking to eliminate any risks of
deteriorating storage tanks and drums.
|
RISK IMPLICATIONS OF THE MINIMAL ACTION CASE
|
IDAHO NATIONAL ENGINEERING LABORATORY REMEDIATION AND RISK
The overriding objective of the minimal action scenario is to prevent the
increase in risk to onsite and offsite populations (beyond Base Case levels)
while attempting to reduce cost and effort. Nowhere is this more apparent than
in the minimal action remediation strategies developed by Idaho National
Engineering Laboratory.
Urgent Need
Test Area North is the site of a former nuclear research reactor that was
designed to perform experiments simulating reactor accidents. Since 1975, both
hazardous and radioactive contaminants have been migrating into the surrounding
area ground water. Through three removal activities, 34 million cubic meters
(44.5 million cubic yards) of contaminated ground water is being removed from
the Test Area North (completion in 2001). Upon removal, the ground water will
be treated; the resulting waste will be disposed at onsite (low-level waste)
and offsite (hazardous waste) facilities.
The remediation activities for Test Area North are exactly the same in the
minimal action and Base Cases. In developing their minimal action scenario,
Idaho determined that the remediation of the Test Area North is necessary to
address urgent environmental and human risks. If the contaminated ground water
is not extracted, offsite populations will be at risk prior to 2070.
No Increased Risk During Minimal Action Period
In developing their minimal action approach, Idaho identified a Base Case
project that does not affect risk during the minimal action case period: the
environmental restoration activities at the Radioactive Waste Management
Complex. The Complex was established in 1952 as a controlled area for the
disposal of solid radioactive waste. Monitoring of the site has shown
contamination in the soil below the Complex. The current Base Case strategy is
to remove and treat the contaminated soil and ship any remaining waste to an
offsite disposal facility. Estimated cost: $1.4 billion for the 75-year period
of analysis.
To prevent an increase in risk to offsite populations during the minimal action
case period, it is not necessary to undergo the removal, treatment, and
disposal of soil beneath the Radioactive Waste Management Complex. In
developing their minimal action approach, Idaho determined that risk during the
minimal action case period will not increase if the remedy involves capping the
contaminated area and installing monitoring equipment. The risk level continues
to be low throughout the minimal action case period, as a system of long-term
surveillance and monitoring is employed at the capped site. In doing so, the
cost of addressing risk at the Radioactive Waste Management Complex under a
minimal action scenario is only $152 million.
|
Estimating future risks involves a great deal of uncertainty. Even over the time
period of the minimal action analysis, it is difficult to predict accurately
any potential risks to humans and/or the environment. However, to obtain a
better understanding of the consequences of performing minimal actions, each
site was asked to estimate the potential risks to onsite and offsite
populations from the minimal action scenario. Given the uncertainty of
estimating risk, each site attempted to highlight potential areas of concern in
both the near term (the time immediately following the end of the minimal
action case period) and the long term (more than 100 years after the end of the
minimal action case period). The risks identified are those affecting onsite
workers and offsite populations.
During the minimal action period, as outlined in the guiding principles, each
site must address all urgent risks. In doing so, each site has included
urgently needed remediation and treatment projects in the development of its
minimal action scenario. Because of these actions, there is no expected
increase in risk to humans or the environment above Base Case levels in the
minimal action case through the end of 2070.
Risk issues become different from the Base Case at the end of the minimal action
case period. During the minimal action case period (1996-2070), buildings are
not demolished, waste remains onsite, and only urgently needed remediation
activities are carried out. In the near term, there is the possibility that
these buildings will begin to deteriorate, posing an occupational risk to
onsite workers. The waste inventories that remain in onsite storage and
disposal facilities may experience corrosion and structural deterioration. The
deterioration of these facilities poses a potential environmental risk to the
surrounding soils and ground water and a health risk to workers in the
immediate areas. Finally, the elimination of most remediation activities during
the minimal action case period creates the potential for the spread of soil and
ground-water contamination, affecting risk to both onsite and offsite
populations.
Over the long term (from roughly 100 years after the end of the minimal action
case period), the risks identified in the near term are expected to intensify.
If buildings have not already collapsed during the near term, there is an
increased risk of collapse in the long term. Contaminated soils and ground
water from both deteriorating waste storage areas and nonremediated sites may
continue to spread, posing greater risk to offsite populations. Over the long
term in the minimal action scenario, there is an increased chance that a
catastrophic event could occur, dramatically affecting risk to both onsite and
offsite populations. Investments such as replacing storage facilities and
remediating high-risk areas dramatically reduce the risk of such an accident.
6.3.4 Overall Implications of a Minimal Action Case
The minimal action case reduces Base Case life-cycle costs by 44 percent over
the 75-year period. This savings is accomplished through the elimination of
compliance-driven remediation activities, minimization of building demolition,
and change in waste disposal strategies. The question posed by this cost
reduction is: What are the benefits from additional Base Case expenditures that
are not addressed in the minimal action case scenario?
The greatest benefit of the higher Base Case costs can be found in a comparison
of end states. Unlike the Base Case, a minimal action case leaves waste
inventories onsite. This not only requires continual surveillance and
monitoring activities, but also increases long-term risk to onsite and offsite
receptors from the remaining contamination. Under a minimal action case,
buildings left standing require long-term surveillance and monitoring, which
may pose a potential risk to workers as these facilities continue to
deteriorate. While reducing costs during the 75-year period (1996-2070), a
minimal action case may actually produce greater costs beyond 2070.
These costs would be incurred through continual surveillance and monitoring
activities and the need to address potential onsite and offsite risks.
The reduced-cost minimal action case provides benefits in the potential uses of
saved funds. Specifically, any savings gained from a minimal action case
approach could be used to develop new technologies to address any post-2070
remediation activities or other end-state risks. Increased funding of new
technologies also could be directed at long-term waste storage and disposal
strategies, which could alleviate the need for sites to continue repacking
stored waste.
6.3.5 Limitations of the Analysis
When it is applied to a "real world" situation, the minimal action case has
several limitations, the greatest of which are the elimination of regulatory
and compliance requirements and the impacts on stakeholder expectations.
Specifically, the assumptions used for the minimal action analysis allow the
sites to bypass regulations and stakeholder requirements. Under current
compliance agreements, many sites have established guidelines and regulations
governing waste management, environmental restoration, and facility
deactivation and decommissioning activities. Federal environmental regulations
(such as the Resource Conservation and Recovery Act) include specific
requirements on the types of storage facilities that must be built and used at
each site. The actual costs and scope of work found in a minimal-action-like
scenario would be dramatically different.
Another limitation in a "real world" atmosphere is that, although the minimal
action period cost estimate is only 56 percent of the Base Case, sites still
require 68 percent of the Base Case cost estimate to meet minimal action goals
in the immediate period of 1996 through 2000. In the case of Rocky Flats
Environmental Technology Site, the minimal action case actually requires a 10
percent increase above the Base Case costs for the first five years. The
increase is needed to address immediate remediation activities and long-term
storage facility construction costs. For Rocky Flats Environmental Technology
Site, specifically, a long-term cost-reducing minimal action strategy requires
an increase in near-term funding.
Under this analysis, however, the following is true: there are limitations to
the "minimal cost" aspect of the minimal action case when costs are assessed
beyond the 75-year period. The minimal action case leaves waste onsite and
eliminates most building demolition. Both of these situations prolong the
requirement for long-term surveillance and monitoring activities and,
therefore, extend the long-term site costs. Without addressing onsite waste
inventories (either through onsite or offsite permanent disposal methods) and
completely demolishing all facilities, the total costs and human
health/environmental risks of a minimal action case will be greater than
the Base Case at a point beyond 2070.
Future Site of the Portsmouth Gaseous Diffusion Plant,
Portsmouth, Ohio, 1953. Decisions concerning future land uses at Department of
Energy sites, and the costs and other consequences of those decisions, will
determine whether a site is partially or fully cleaned up to its
pre-construction state. These decisions have an immense impact on life-cycle
analyses.
|
Pronghorn Antelope at the Idaho National Engineering Laboratory,
1993. The paradox at many former nuclear weapons facilities is that, although
localized, and sometimes hazardous, radioactive contamination exists, most of
the land area is very rich ecologically because the habitat has been protected
for safety and security reasons. As a result of decades of restrictions on most
human activities, such as construction, mining, logging, fishing, or hunting,
most of the land is already suitable for use as wildlife habitat, although it
may pose unacceptable risks for residential use because of unexploded ordnance
or other contamination. Life-cycle planning requires that long-term land use be
considered in developing cleanup plans, so that funding is focussed on
achieving an agreed-to end state.
|
Chapter -1- / -2- /
-3- / -4- / -5-
/ -6- / -7- /
-8-
Appendix -A2- / -B- /
-C- / -D- / -E1-
/ -E2- / -F- /
-G- / -H- / Glossary
|
 |