Home
BEMR Contents
U.S. Map
This chapter summarizes the projected life-cycle costs for the Environmental
Management Program based on plans and capabilities as of October 1995. The
results in this chapter summarize information provided in Volumes II and III of
the 1996 Baseline Report and provide several crosscutting analyses and
perspectives.
| THE BASELINE REPORT IS NOT A BUDGET DOCUMENT
The Baseline Report is not intended to be a budget document and none of the
estimates in the report are intended as federal budget requests. Similarly, the
schedule of activities presented in the Baseline Report should not be
interpreted as establishing specific long-term priorities or as serving as a
definitive basis for planning specific projects.
|
The Base Case results reflect costs for the Environmental Management program
based on assumptions described in Chapter 3.
These results provide the foundation for many of the policy analyses and
comparisons in the Baseline Report, particularly the analyses of alternatives
in Chapter 6
.
This chapter includes five sections.
-
Section 4.1
reports overall Base Case results, including an overview of life-cycle costs
and schedules.
-
Section 4.2
describes the Base Case estimate from a geographical perspective, including the
distribution of life-cycle costs by state and site.
-
Section 4.3
focuses on costs for the major functional elements (waste management;
environmental restoration; nuclear material and facility stabilization; science
and technology development; landlord; and national program planning and
management).
-
Section 4.4
analyzes the waste types and volumes that underlie the life-cycle cost
estimate.
-
Section 4.5 examines costs for support
activities such as program management, administrative services, and security.
4.1 OVERALL RESULTS
4.1.1 The Range of the Base Case
Based on the 1996 Base Case assumptions, the life-cycle cost to complete the
Environmental Management program is projected to be between $189 billion and
$265 billion, with a mid-range estimate of $227 billion. Life-cycle cost
profiles are graphically depicted in Figure 4.1. All estimates are in constant
1996 dollars (see the box below).
Figure 4.1. Base Case Life-Cycle Cost Estimates
The mid-range estimate - $227 billion - represents the sum of life-cycle costs
for all site-specific activities and projects described in Volumes II and III
of the Baseline Report. The upper range ($265 billion) and lower range ($189
billion) bound the mid-range estimate. Personnel at sites assigned one of three
levels of confidence to their Base Case estimates (high, medium, or low). Then,
a probabilistic analysis of these estimates was conducted to establish the
range (see the "Confidence in Cost Estimates" box for more information).
| CONSTANT VS. CURRENT DOLLARS
Constant dollars
represent a dollar value adjusted for changes in prices. Dollars in the future
are adjusted by removing inflation. Unless otherwise noted, all 1996 Baseline
Report cost projections are in constant 1996 dollars as if costs were incurred
this year.
Current dollars represent the dollar value of goods or services in terms
of prices current at the time the goods or services are purchased (in other
words, inflation is factored into the estimate).
|
A number of factors contribute to the uncertainty in the life-cycle estimate.
The degree of project definition, the complexity of the project, and the
application of new technology can significantly influence the confidence in the
estimate. Other factors contributing to estimate uncertainty include errors in
estimating unit costs and labor productivity, schedule delays, and even simple
errors in arithmetic. Several of these factors, such as productivity and the
use of new technologies, are discussed later in this chapter.
| CONFIDENCE IN THE COST ESTIMATES
Cost estimators in the field assigned one of three levels of confidence to
their Base Case project estimates: low, medium, and high. A low confidence
rating means that the estimate could range from 100 percent higher to 100
percent lower than the Base Case estimate. A medium confidence rating
indicates that the estimate could be 50 percent higher to 50 percent lower. A high
confidence
rating denotes a range of 25 percent higher to 25 percent lower. Percentages of
the estimates that fall into each category are displayed below. Using these
distributions, a statistical simulation was conducted to develop the
uncertainty range in the life-cycle estimate. (Appendix C provides a more
detailed discussion of this approach).
Level of Confidence and Basis of Life-Cycle Estimate (Dollar Weighted)
In addition to confidence levels, cost estimators reported the method (basis)
upon which they developed their estimates. The basis of each site's estimates
was reported as one of the following categories: based on best professional
judgement, based on historical information or past experience, modeled, or
based on unit costs. Percentages of the estimates that fall into each of these
categories are displayed above. In general, there is a correlation between the
confidence sites have in their estimates and the use of detailed or
sophisticated cost estimating models.
|
The mid-range estimate of $227 billion is the projected cost for carrying out
the currently planned tasks, including existing compliance agreement
obligations (as of October 1995), for the active sites within the scope of the
Environmental Management program. This case is used as the basis for analysis
in this chapter and the basis for comparison of the alternative cases in
Chapter 6. The mid-range case is referred to throughout this report as
the "Base Case" estimate.
4.1.2 Productivity
For any long-range program, the amount by which the program improves
productivity will have a significant effect on life-cycle cost. For example, if
productivity, defined as the ratio of outputs-to-inputs, increases at an annual
rate of one percent, the program will be approximately 50 percent more
productive in 2040 than it was in 2000. Larger productivity improvement rates
have even more dramatic effects over a longer time horizon. Therefore, any
program that has an extended timeframe should be concerned about productivity
improvement and should ask the question: How will productivity influence the
long-term costs of the program? The Environmental Management program is such a
program.
For this reason, the Environmental Management program asked site personnel to
include an estimate of projected productivity savings in their life-cycle cost
estimates. The site-derived productivity savings, which were approximately five
to ten percent across the Environmental Management program, were included in
the site estimates. Almost all of these productivity improvements are expected
before 2000. These productivity improvement initiatives include
performance-based contracting, re-engineering of operational processes,
privatization, reducing overhead activities, streamlining site characterization
processes, and introducing cost-efficient technologies.
Two additional productivity estimates were derived from the Base Case based on
different assumptions regarding productivity improvement. For the purposes of
this report, a long-term productivity goal of one percent after 2000 was
established. The one percent assumption reflects the average productivity
savings historically achieved by government agencies. The highest cost case
assumes that productivity will not increase over current levels. That is,
projected site productivity savings estimates were removed from the life-cycle
estimates.
Based on these three productivity cases, the life-cycle cost for the program
ranges from $195 billion to $241 billion. Figure 4.2 presents these three
cases, depicting three different productivity-based life-cycle cost profiles
for the Environmental Management program.
Figure 4.2. Annual Cost Estimate Based on Productivity Assumptions
Site-based productivity estimates produce a total life-cycle cost reduction of
$14 billion, resulting in a total life-cycle cost for the program of $227
billion. This case is used as the base estimate for the confidence level range
(discussed in Section 4.1.1).
It is also the basis for the results in the remainder of this chapter. With no
productivity savings, completion of the Environmental Management program is
estimated to cost $241 billion--$14 billion higher than the Base Case and $46
billion higher than the lowest case (reflecting one percent productivity
savings beyond 2000). In the 1995 Baseline Report, productivity assumptions
were incorporated in the Base Case estimate. These assumptions projected a
potential short-term productivity goal of 23 percent by the year 2000 and a
long-term goal of one percent productivity savings after 2000. This assumption
decreased the total 1995 life-cycle cost from approximately $350 billion ($360
billion in constant 1996 dollars) to $230 billion ($237 billion in constant
1996 dollars). The 1995 approach, which is explained in Section 5.3, differs
from the 1996 approach described above.
4.1.3 Reconciling the Base Case Cost Estimate with Budget Projections
The Base Case is not a budget estimate. In fact, with cost projections expected
to exceed budget availability and priorities continuing to be defined, a clear
articulation of the current baseline projection is useful. The projected budget
target (as of October 1995), based on larger federal budget realities, is that
funding for the Environmental Management program will be funded at
approximately $5.5 billion in annual funding (in current dollars) by 2000.
After accounting for expected inflation, this number equates to $4.9 billion in
constant 1996 dollars. The difference between the assumed funding for the Base
Case estimate and the funding target results in a projected budget shortfall.
Figure 4.3 indicates that this shortfall amounts to $27 billion over a 25-year
period.
This budget shortfall has been anticipated since 1993. During this period, the
Department has successfully reconciled this shortfall through a number of
management initiatives intended to deliver more results for less money.
Specific priorities for the Environmental Management program include:
From 1993-1996
-
Improved Contractor Efficiency
- Reduced contractor employment by 17,000 individuals or 33 percent; initiated
performance-based contracting systems at most of the large sites in the
complex.
-
Renegotiated Compliance Agreements
- To date, renegotiated agreements have resulted in more than $1 billion in
potential savings for the Hanford Site and Savannah River Site.
-
Involved Stakeholders and Workers - At Fernald, Ohio, recommendations
from the Citizen Task Force on disposal options and future land use at the site
are expected to result in over $2 billion in savings.
From 1997-2000
-
Privatizing Operations
- Improving public sector efficiency with more private sector incentives.
-
Conducting Management 'Work Outs'
- Department of Energy, contractors, and regulators come together to develop
common sense reforms.
-
Investing in Science - Bridging basic science and applied research needs
on our most intractable environmental problems.
We believe that these efforts will greatly assist in reconciling estimated Base
Case costs to budget realities. Additional changes such as legislative
amendments to Superfund will also contribute to helping the program operate
more cost effectively. Clearly, however, it is critical to good management to
anticipate budget problems through effective life-cycle analysis.
Figure 4.3. Long-Term Budget Shortfall
4.1.4 A Look at the Life-Cycle Base Case
The life-cycle activities for the Base Case will cost $227 billion and span a
75-year period (1996 to 2070), although most sites will be completed
considerably sooner. By 2070, all environmental management sites requiring
remediation will be completed (i.e., only long-term surveillance and monitoring
activities and ongoing waste management activities at active sites will
remain). Figure 4.4 presents the Base Case schedule for the completion of
environmental remediation and decommissioning activities at the sites. As noted
in Section 3.3.2, 102 sites require remediation. This figure illustrates that
80 percent of these sites will be remediated by 2021.
Annual costs at the program's completion in the year 2070 do not reach zero
because of 'post-closure' expenditures, referred to as post-closure long-term
surveillance and monitoring activities. These activities focus on sampling,
analyzing monitoring well data, maintaining protective covering or barriers,
and providing for active institutional controls at near-surface and deep
geologic disposal sites where long-lived radioactive wastes were left in place.
Preliminary estimates indicate these long-term costs would range from $45-$65
million annually for several decades.
Figure 4.4. Base Case Schedule for Remediating Sites
The distribution of estimated Environmental Management program costs for major
functional elements changes as the program (and the cleanup effort) moves
closer to completion (see Figure 4.5). Given these estimates, the mix of
activities comprising the Environmental Management program will change
significantly over time. In the near term, the program is focusing on
stabilizing nuclear materials and facilities. In 2000, for example, nuclear
material and facility stabilization activities represent approximately 18
percent of the estimated site costs for waste management, environmental
restoration, and nuclear material and facility stabilization. By 2020, these
activities drop to six percent and by 2040 they are less than one percent of
estimated cost because these activities are essentially complete. Also, during
the next 40 years, the majority of environmental restoration activities are
expected to be completed. Although environmental restoration costs as a percent
of total costs actually increase from 2000 to 2020 when many large facilities
are scheduled for decommissioning, they shrink to less than six percent of
total estimated program costs by 2060. By this point, the environmental cleanup
is essentially complete and all waste currently in inventory and generated by
the Environmental Management program will have been disposed. By 2060, the
primary responsibility of the program is expected to be managing waste
generated by other Department of Energy programs (for example, the Energy
Research Program and Defense Programs).
Figure 4.5. Cost Estimate for Major Functional Elements
At the program "end state" (in 2070), all mission-related activities are
expected to be completed and most sites are available for alternative land
uses. The expectation is that buildings are decommissioned, waste planned for
offsite disposal is treated and will have been shipped to a permanent disposal
site or commercial facility, and waste being disposed of onsite is capped in
pits or trenches or securely enclosed in disposal cells. In 2070, Environmental
Management program activities are focused on long-term surveillance and
monitoring and waste management for Department of Energy programs still active
at the sites. In other words, sites with ongoing missions outside
of the Environmental Management program (for example, National Laboratories)
will continue to incur ongoing waste management costs.
Many sites complete their Environmental Management mission-related activities
before 2070. A closer examination of the estimated life-cycle cost profile in
Figure 4.1 reveals a downward trend in annual costs. The estimate after 2050 is
relatively level. Ninety percent of the total life-cycle cost is expected to be
incurred by 2037 (see box).
| A 75-YEAR LIFE-CYCLE PROGRAM?
While the life-cycle data indicate that Environmental Management
mission-related activities are complete at all sites by 2070, many of the sites
complete a substantial amount of work long before 2070. For example, 90 percent
of the projected life-cycle costs for environmental management activities
occurs by 2037. After this date, most of the costs are for managing wastes from
on-going mission activities and for long-term surveillance and monitoring of
remediated sites. These costs would extend far into the future, but are assumed
to be complete in 2070 for the Baseline Report.
|
Despite the general downward
cost trend described above, estimated costs suddenly increase or decrease for
brief periods at several points. These upswings and downswings appear as
anomalies to the overall trend, but reflect the progression of the program. For
example, in 2020, completion of remediation and decommissioning activities at
the Energy Technology Engineering Center, Fernald, Los Alamos National
Laboratory, and Sandia National Laboratory-New Mexico contribute to a drop in
estimated environmental restoration costs of more than $300 million. At the
same time, treatment of high-level waste decreases (primarily at the Hanford
Site), resulting in an additional cost decrease of almost $200 million. In
2025, a sudden increase in estimated cost occurs. It results from an upswing in
high-level waste disposal costs following vitrification activities at the
Savannah River Site. Estimated costs for high-level waste disposal are $200
million higher in 2025 than in 2024 and remain at the higher level until 2035
when high-level waste disposal costs increase again by an additional $400
million per year because of the expected beginning of shipments of vitrified
high-level waste from the Hanford Site to a geologic repository for disposal.
| PROJECTED LIFE-CYCLE COSTS BY CONGRESSIONAL APPROPRIATION
The Congressional Appropriations Subcommittee on Energy and Water appropriates
funds for the Environmental Management program. These discretionary
appropriations are divided into two accounts: defense and nondefense. Environmental
Management defense funding represents $207 billion (or 91 percent) of
total costs. Environmental management activities with a past defense mission
(such as producing plutonium for nuclear warheads in production reactors at
Savannah River Site) are appropriated under the defense account. On a
life-cycle basis, nondefense activities represent $19 billion (or 9 percent) of
the total projected life-cycle program cost. Environmental management activities
with a former nondefense mission (such as the Fast Flux Test Facility
at Hanford Site in Washington) are funded through nondefense appropriations.
|
4.2 A GEOGRAPHICAL VIEW OF THE ENVIRONMENTAL MANAGEMENT PROGRAM
Figure 4.6. Annual Estimated Costs by State
The Department's Environmental Management program currently is operating in
approximately 30 states and territories. By 2020, this number is expected to
drop to 21 states. (See Figure 4.6 for the estimated annual spending level for
environmental management activities in each state and a depiction of cleanup
progress over time.) In 2060, the total is expected to drop to 15 states, with
almost all of the costs for long-term surveillance and monitoring and
management of waste generated by programs with ongoing missions. Remediation is
complete at all these sites by 2070.
Table 4.1 shows the Base Case cost estimate by state and site. These estimates
reveal that the majority of costs will be spent at a small number of states and
sites. Approximately three-quarters of the program's costs are concentrated in
six states (Washington, Idaho, South Carolina, Tennessee, New Mexico, and
Colorado), primarily at the five highest-cost sites (Hanford Site, Idaho
National Engineering Laboratory, Oak Ridge Reservation, Rocky Flats
Environmental Technology Site, and Savannah River Site). For the purposes of
this report, a site with life-cycle costs greater than $15 billion is defined
as a high-cost site. Historically, the five highest-cost sites played the
largest roles in nuclear weapons production and, therefore, require the largest
amount of cleanup and waste management (see Table 4.2). Because these sites
represent such a large portion of the program, the analysis of alternatives in
Chapter 6
focuses solely on them.
Activities in two states, Washington (Hanford Site) and South Carolina
(Savannah River Site), dominate the life-cycle cost estimates. They account for
approximately $100 billion (or 44 percent) of projected life-cycle costs. The
concentration of costs at the Hanford and Savannah River sites is particularly
evident in Figure 4.7, which presents the total life-cycle cost by site and
major crosscutting functions. In this figure, the highest-cost sites and
crosscutting functions are presented separately while the smaller sites are
grouped into an "Other Sites" category.
The expected end dates for the five highest-cost environmental management sites
are listed in Table 4.3. Surveillance and monitoring activities will continue
beyond these dates. All sites will be complete by 2070. These dates are
expected to change based on variables such as project resequencing, program
acceleration or delay (for example, to reduce long-term overhead costs or to
wait for new technologies), regulatory changes, or significant budget
reductions. However, these milestones are useful starting points for analyzing
time lines, priorities, and the potential for program acceleration. (See the
scheduling alternative case analysis in Chapter 6
.)
Many of the other sites will be completed much sooner. Remediation is already
under way at most Environmental Management sites. As described earlier, 80
percent of sites requiring remediation will be completely remediated by 2021.
Only surveillance and monitoring and waste management at sites for programs
with research or production missions remain after that point.
Table 4.1. Base Case Estimate by State and Site
| Alaska
|
6
|
<1%
|
|
Amchitka Island
|
6
|
<.01%
|
| Arizona
|
212
|
<1%
|
|
Monument Valley
|
113
|
0.05%
|
|
Tuba City
|
99
|
0.04%
|
| California
|
4,574
|
2.02%
|
|
Lawrence Livermore National Laboratory
|
2,408
|
1.06%
|
|
Oakland Operations Office
|
948
|
0.42%
|
|
Lawrence Berkeley Laboratory
|
533
|
0.23%
|
|
Energy Technology Engineering Center
|
351
|
0.15%
|
|
Stanford Linear Accelerator Center
|
161
|
0.07%
|
|
Sandia National Laboratories - Livermore
|
105
|
0.05%
|
|
General Electric Vallecitos Nuclear Center
|
23
|
0.01%
|
|
Laboratory for Energy-Related Health Research
|
22
|
0.01%
|
|
General Atomics
|
17
|
0.01%
|
|
Geothermal Test Facility
|
5
|
<.01%
|
|
Oxnard Facility
|
<1
|
<.01%
|
| Colorado
|
18,203
|
8.02%
|
|
Rocky Flats Environmental Technology Site
|
17,319
|
7.63%
|
|
Grand Junction Projects Office
|
662
|
0.29%
|
| Grand Junction
|
73
|
0.03%
|
|
Naturita Site
|
43
|
0.02%
|
|
Slick Rock
|
33
|
0.01%
|
|
Maybell Mill Site
|
22
|
0.01%
|
|
Rifle Sites
|
20
|
0.01%
|
|
Durango
|
12
|
8.02%
|
|
Gunnison Mill Site
|
12
|
0.01%
|
|
Rio Blanco/Rulison
|
7
|
<.01%
|
| Connecticut
|
22
|
<1%
|
|
CE
|
22
|
0.01%
|
| Florida
|
437
|
<1%
|
|
Pinellas Plant
|
437
|
0.19%
|
| Idaho
|
18,980
|
8.36%
|
|
Idaho National Engineering Laboratory
|
18,622
|
8.21%
|
|
Argonne National Laboratory - West
|
357
|
0.16%
|
|
Lowman
|
<1
|
<.01%
|
| Illinois
|
1,427
|
<1%
|
|
Argonne National Laboratory - East
|
847
|
0.37%
|
|
Chicago Operations Office
|
406
|
0.18%
|
|
Fermi National Accelerator Laboratory
|
165
|
0.07%
|
|
Site A/Plot M, Palos Forest Preservation
|
6
|
<.01%
|
|
Madison
|
2
|
<.01%
|
| Iowa
|
26
|
8.04%
|
|
Ames
|
26
|
0.01%
|
| Kentucky
|
4,857
|
2.14%
|
|
Paducah Gaseous Diffusion Plant
|
4,831
|
2.13%
|
|
Maxey Flats Disposal Site
|
26
|
0.01%
|
| Maryland/District of Columbia
|
18,240
|
8.04%
|
|
Environmental Management Program Headquarters
|
18,218
|
8.03%
|
|
W.R. Grace & Company
|
22
|
0.01%
|
| Massachusetts
|
13
|
<1%
|
|
Ventron
|
12
|
0.01%
|
|
Shpack Landfill/Ventron
|
<1
|
<.01%
|
| Mississippi
|
8
|
<1%
|
|
Salmon Test Site
|
8
|
<.01%
|
| Missouri
|
1,578
|
<1%
|
|
Weldon Spring Site Remedial Action Project
|
448
|
0.20%
|
|
Kansas City Plant
|
447
|
0.20%
|
|
St. Louis Downtown Site
|
266
|
0.12%
|
|
St. Louis Airport Site
|
244
|
0.11%
|
|
St. Louis Airport Site Vicinity Properties
|
97
|
0.04%
|
|
Latty Avenue Properties
|
76
|
0.03%
|
| Nebraska
|
1
|
<1%
|
|
Hallam Nuclear Power Facility
|
1
|
<.01%
|
| Nevada
|
3,652
|
1.61%
|
|
Nevada Test Site
|
3,644
|
1.61%
|
|
Central Nevada Test Area and Project Shoal Site
|
8
|
<.01%
|
| New Jersey
|
713
|
<1%
|
|
Princeton Plasma Physics Lab
|
321
|
0.14%
|
|
Maywood Chemical Works
|
255
|
0.11%
|
|
Wayne Interim Storage Site
|
99
|
0.04%
|
|
Middlesex Sampling Plant
|
25
|
0.01%
|
|
DuPont & Company
|
8
|
<.01%
|
|
New Brunswick Site
|
6
|
<.01%
|
| New Mexico
|
14,942
|
6.58%
|
|
Waste Isolation Pilot Project
|
8,391
|
3.70%
|
|
Los Alamos National Laboratory
|
4,081
|
1.80%
|
| Sandia National Laboratories - Albuquerque
|
1,591
|
0.70%
|
|
Albuquerque Operations Office
|
802
|
0.35%
|
|
Inhalation Toxicology Research Institute
|
42
|
0.02%
|
|
Project Gasbuggy
|
15
|
0.01%
|
|
South Valley Site
|
12
|
0.01%
|
|
Shiprock
|
8
|
<.01%
|
|
Ambrosia Lake
|
1
|
<.01%
|
| New York
|
4,927
|
2.17%
|
|
West Valley Demonstration Project
|
3,744
|
1.65%
|
|
Brookhaven National Laboratory
|
867
|
0.38%
|
|
Separations Process Research Unit
|
145
|
0.06%
|
|
Colonie Site
|
52
|
0.02%
|
|
Niagara Falls Storage Site
|
33
|
0.01%
|
|
Seaway Industrial Park
|
28
|
0.01%
|
|
Linde Air Products
|
28
|
0.01%
|
|
Ashland Oil #1
|
21
|
0.01%
|
|
Ashland Oil #2
|
8
|
<.01%
|
|
Bliss and Laughlin Steel
|
1
|
<.01%
|
| North Dakota
|
24
|
<1%
|
|
Belfield
|
19
|
0.01%
|
|
Bowman
|
5
|
<.01%
|
| Ohio
|
9,158
|
4.04%
|
|
Portsmouth Gaseous Diffusion Plant
|
3,960
|
1.74%
|
|
Fernald Environmental Management Project
|
3,017
|
1.33%
|
|
Mound Plant
|
1,357
|
0.60%
|
|
Ohio Operations Office
|
428
|
0.19%
|
|
Reactive Metals, Inc. (RMI Titanium Co.)
|
141
|
0.08%
|
|
Battelle - Columbus Laboratories
|
101
|
0.04%
|
|
Painesville
|
88
|
0.04%
|
|
Luckey
|
63
|
0.03%
|
|
B&T Metals
|
3
|
<.01%
|
|
Baker Brothers
|
<1
|
<.01%
|
|
Piqua Nuclear Power Facility
|
<1
|
<.01%
|
| Oregon
|
6
|
<1%
|
|
Lakeview
|
6
|
<.01%
|
| Pennsylvania
|
3
|
<1%
|
|
Canonsburg
|
3
|
<.01%
|
| South Carolina
|
48,769
|
21.49%
|
|
Savannah River Site
|
48,769
|
21.49%
|
| Tennessee
|
25,137
|
11.06%
|
|
Oak Ridge National Laboratory
|
9,352
|
4.12%
|
|
Oak Ridge K-25 Site
|
7,286
|
3.21%
|
|
Oak Ridge Y-12 Plant
|
6,168
|
2.72%
|
|
Oak Ridge Operations Office
|
2,038
|
0.90%
|
|
Oak Ridge Reservation Off-Site
|
267
|
0.12%
|
| TeOak Ridge Associated Universities
|
26
|
0.01%
|
| Texas
|
689
|
<1%
|
|
Pantex Plant
|
683
|
0.30%
|
|
Falls City
|
6
|
<.01%
|
| Utah
|
129
|
<1%
|
|
Monticello Mill Site & Vicinity
|
110
|
0.05%
|
|
Green River
|
8
|
<.01%
|
|
Salt Lake City
|
7
|
<.01%
|
|
Mexican Hat
|
3
|
<.01%
|
| Washington
|
50,208
|
22.12%
|
|
Hanford Site
|
50,208
|
22.12%
|
| Wyoming
|
11
|
<1%
|
|
Riverton
|
10
|
<.01%
|
|
Spook
|
1
|
<.01%
|
| TOTAL
|
226,950
|
100.00%
|
Table 4.2. Historical Mission of the Five Highest-Cost Sites Drives
Environmental Management Costs
Hanford Site
145,000 Hectares
(358,500 Acres)
|
$50.2 billion
|
-
Uranium fuel fabrication and irradiation
-
High-level waste management
|
Idaho National Engineering Laboratory
230,000 Hectares
(570,000 Acres)
|
$18.6 billion
|
-
Reprocessing of spent nuclear fuel
-
High-level waste management
|
Oak Ridge Reservation
14,140 Hectares
(35,000 Acres)
|
$25.1 billion
|
-
Uranium enrichment / energy research
-
Weapons component production
-
Remediation activities
|
Rocky Flats Environmental Technology Site
2,510 Hectares
(6,216 Acres)
|
$17.3 billion
|
-
Plutonium weapons trigger fabrication
-
Stabilization of nuclear materials and facilities
|
Savannah River Site
80,000 Hectares
(198,000 Acres)
|
$48.8 billion
|
-
Uranium fuel fabrication and irradiation
-
High-level waste management
|
Figure 4.7. Distribution of Environmental Management Life-Cycle Estimate
Table 4.3. Estimated End Dates for the Five Highest-Cost Sites
| Hanford Site
|
2052
|
2039
|
| Idaho National Engineering Laboratory
|
2045
|
2035
|
| Oak Ridge Reservation
|
2045
|
2044
|
| Rocky Flats Environmental Technology Site
|
2055
|
2034
|
| Savannah River Site
|
2040
|
2031
|
*See definition of site completion in Section 3.3.2.
Figure 4.8 focuses only on the highest-cost sites, providing total site cost
estimates broken out by the functional elements of the Environmental Management
program. At the Hanford Site, Idaho National Engineering Laboratory, and
Savannah River Site, waste management consumes the largest portion of estimated
program costs. At the Oak Ridge Reservation, environmental restoration
activities are the highest proportion of estimated cost. At the Rocky Flats
Environmental Technology Site, nuclear material and facility stabilization
activities represent the largest proportion of estimated cost.
Figure 4.8. Costs by Major Functional Element for the Five Highest-Cost
Sites
Click Here for Page 2
Chapter -1- / -2-
/ -3- / -4- /
-5- / -6- / -7- /
-8-
Appendix -A2- / -B-
/ -C- / -D- /
-E1- / -E2- / -F-
/ -G- / -H- / Glossary
|
 |