Home
BEMR Contents
U.S. Map
POLLUTION PREVENTION
Section 3170 of Public Law 103-337, The National Defense Authorization Act for
FY 1995, requires the Department of Energy to include a discussion on pollution
prevention in the 1996 Baseline Environmental Management Report. This section
of the Baseline Report responds to that legislative mandate by: (1) summarizing
the Department of Energy's pollution prevention program, and (2) discussing the
program's potential impact on reducing life-cycle costs of the Department of
Energy's environmental management efforts.
POLLUTION PREVENTION PROGRAM OVERVIEW
The Office of Environmental Management established a Pollution Prevention
program in 1991. The Department of Energy defines pollution prevention as the
use of materials, processes, and practices, including recycling activities,
that reduce or eliminate the generation and release of pollutants,
contaminants, hazardous substances, and waste into land, water, and air. This
section describes the Pollution Prevention program's objectives, goals, status,
and future directions.
Program Objectives and Goals
The overall program objective is to minimize pollutant generation and release by
implementing cost-effective technologies, practices, and policies. Partnerships
among government agencies and private industry are used to achieve this
objective. The Department of Energy has committed to meeting the following
waste reduction goals by 2000:
-
Reduce the generation of radioactive, low-level mixed, and hazardous waste from
routine operations by 50 percent.
-
Reduce the generation of sanitary waste from routine operations by 33 percent.
-
Divert 33 percent of sanitary waste from all operations for recycling.
Achieving these goals will result in significantly decreased waste-related
expense that could represent an accumulated savings of over $1 billion by 2010
and of $5 billion over the environmental management life cycle. These goals
should be attainable based on benchmarks from similar organizations involved
with radioactive waste management. For example, the commercial nuclear power
industry and the United States Navy reduced generation of low-level waste by 75
percent in six years following passage of the Low-Level Waste Policy Amendments
Act of 1985. Part of this reduction occurred as a result of improved volume
reduction treatment processes; however, the principal reduction resulted from
limitations on waste quantities allowed for disposal and from surcharges on
waste generators. The Department of Energy is currently applying this industry
approach by holding its waste generators accountable for both the quantity of
newly generated waste and the direct cost(s) of managing the waste until final
disposition. Beginning in FY 1996, selected Department of Energy sites will
participate in a pilot program that will charge waste generators for the cost
of disposing of their waste.
The United States Navy has documented a series of case studies in which
hazardous waste generation rates were reduced significantly, sometimes up to 80
to 90 percent. Based on these results, the Department of Energy's goal of a 50
percent reduction should be achievable.
Program Status and Direction
The Department's commitment to pollution prevention is described in its 1996
Pollution Prevention Program Plan. The Department has institutionalized the
program by establishing a Pollution Prevention Executive Board, an Office of
Pollution Prevention within the Environmental Management program, and pollution
prevention coordinators at its field sites. An important element of the program
is the "high return on investment" program that funds specific pollution
prevention projects that have the largest "payback" potential.
Cost Reductions from Specific Pollution Prevention Projects
The Department has sufficient information for three specific categories of
pollution prevention projects to report waste volume reductions and
corresponding cost savings. These are: (1) high return on investment projects,
(2) waste minimization/pollution prevention projects, and (3) past pollution
prevention projects.
In 1994, the Department sponsored pilot demonstrations of 13 high return on
investment projects. Based on the success of these projects, an increase in
funding was approved in FY 1996 for 22 projects in the high return on
investment program. The Department is currently considering supplemental
funding of nine additional projects.
Cost savings, total project costs, and various other data are kept for each high
return on investment project. These data are used to forecast life-cycle
savings through 2010, which is the useful life of most high return on
investment projects. In addition, the Office of Pollution Prevention funded 26
projects (referred to in the table below as field projects) that did not meet
the criteria for the high return on investment program but provided significant
payback over a longer time period. Past pollution prevention projects have also
resulted in cost savings. Table G.1 summarizes projected life-cycle savings
over ten years through 2005 for high return on investment projects (assuming
the Board approves supplemental funding), field projects, and selected past
pollution prevention projects for which cost savings data are available.
Because the high return on investment program is still in the early stages,
most of the savings illustrated are projected rather than actual savings.
Table G.1. Projected Life-Cycle Savings
| High Return on Investment Pilot Demonstration
|
13
|
$2,700,000
|
$36,700,000
|
| High Return on Investment FY962
|
31
|
8,300,000
|
143,500,000
|
| High Return on Investment FY 1996 Supplemental
|
9
|
2,100,000
|
101,000,000
|
| Field Projects
|
26
|
2,700,000
|
256,000,000
|
| Selected Past Projects
|
24
|
Implementation Costs Not Available
|
1,077,000,000
|
| TOTAL
|
103
|
|
$1,614,200,000
|
Pollution Prevention Examples
Current return on investment projects focus primarily on routine waste from
Department operations. They include a wide range of simple and complicated
projects and are applicable at many Department facilities. For example, a
$5,000 investment in laundering rags can avoid nearly $14,000 in yearly
disposal costs. Dry-ice abrasion equipment is used in a more
technology-intensive project that will clean surface radiation from
lead-shielding bricks. A $500,000 investment yields a one-time savings of $1.2
million by avoiding disposal of a mixed radioactive waste.
Historically, the Environmental Management program has overseen pollution
prevention projects implemented throughout the Department. Although pollution
prevention data were not required for reporting purposes, many sites kept track
of their accomplishments. Some of these projects involved waste streams other
than routine waste such as environmental restoration waste. For example, in
1994, modified procedures for soil borings avoided 150 metric tons (165 tons)
of contaminated soil drill cuttings, saving $4.5 million in waste disposal
costs. At Weldon Springs, the use of slightly contaminated soil as capping and
stabilization materials in remediation projects elsewhere on the site prevented
the soil from becoming a waste and saved about $15 million. At the Hanford
Site, two liquid effluents that had been discharged to evaporation ponds were
eliminated by changing equipment and modifying existing systems to save over
$26 million.
Summary of Pollution Prevention Results
Currently, the projected savings from specific projects for which data are
available exceeds $1.6 billion. Other specific projects for which life-cycle
data are not available would increase this figure. Many of these projects can
be replicated or adapted at multiple sites throughout the Department. Although
there are insufficient data to extrapolate total projected pollution prevention
savings in a meaningful, quantitative way, it is not unlikely that complex-wide
savings could be in the tens of billions of dollars. In addition, the
Department has established goals for reducing the volume of radioactive,
low-level mixed, sanitary, and hazardous waste from routine operations by 50
percent by the year 2000. Achieving these goals will reduce waste management
costs by an estimated $5 billion over the environmental management life cycle.
Regardless of total savings, actual results and projections from specific
projects are unequivocal in demonstrating that pollution prevention activities
save far more than they cost. Therefore, the Department will continue to pursue
pollution prevention activities aggressively because they are consistent with
the Department's core values for respecting the environment, and they result in
a more efficient use of limited resources by reducing site operating costs.
Chapter -1- / -2- /
-3- / -4- / -5-
/ -6- / -7- /
-8-
Appendix -A2- / -B- /
-C- / -D- / -E1-
/ -E2- / -F- /
-G- / -H- / Glossary
|
 |