Home
BEMR Contents
U.S. Map
LAND-USE ANALYSIS SITE-SPECIFIC RESULTS
Chapter 6 presents the land-use sensitivity analysis for the five highest-cost
sites: Hanford Site, Idaho National Engineering Laboratory, Oak Ridge
Reservation, Rocky Flats Environmental Technology Site, and Savannah River
Site. The tables in Chapter 6 depict results that are summaries of the
individual site results. The lower-level site results that support those
summarized results are presented here for interested readers.
-
Site Maps, Acreage, and Findings Summaries - Included in this appendix are two
versions of each site's Base Case map showing end-state conditions. One map
employs land-use standards to depict how clean sites will be (Maximum Allowable
Use) and a contrasting version shows the site's assumed uses (Likely Use).
Tables provide acreage by land-use standard and cost totals for the alternative
scenarios and the Base Case. In addition, significant findings are included for
each site.
-
Site-Specific Constraints - Following the maps and summary information is a
discussion of constraints at sites which limit the Department's consideration
of future uses. A summary of contraints at sites is also included.
The methodology to conduct this analysis is detailed in Appendix C. Discussions
of complex-wide implications are discussed in Chapters 6 and 7.
FRAMING THE RESULTS
The land-use analysis was undertaken to produce information for national-level
policy discussions. Most sites have conducted extensive studies of land-use
alternatives for their individual sites, which have involved site stakeholders
and regulators. This policy-level analysis cannot substitute for the
community-level analysis needed to make decisions. The factors that affect
land-use decisions have been summarized, and the relative prioritization of
those factors, developed by site communities, has been captured here.
The site-specific results are presented only as background information to the
analysis in Chapter 6. Although care was taken to capture site-specific
conditions correctly, some inaccuracies may have resulted from summarizing and
generalizing the data necessary for the national analysis.
Those seeking information concerning individual site land-use alternatives and
analyses should consult the future-use points of contact at the individual
sites. A listing of those representatives and source documents relating to site
future use are provided at the end of this appendix. Appendix H is a listing of
site reading rooms that provide access to such reports and documents.
Hanford
LAND-USE SUMMARY
The majority of land on the Hanford Site currently meets Residential use
standards and, of the remaining land, the Department actively uses only 3,300
hectares (8,150 acres) for industrial and storage/disposal activities. The
storage of plutonium onsite is a major determinant of future land use because
of buffer area and emergency planning requirements. In addition, the disposal
and waste management activities in the 200 Area require an appropriate buffer
area. As a result, the anticipated land use at the site is different from the
maximum allowable use.
The site's Base Case cleanup strategies are aggressive in the 100 Area, assuming
the complete dismantlement of the six reactors, removal of the reactor cores,
and extensive excavation of contaminated soils. In contrast, the 200 Area
remains Controlled Access for storage/disposal and waste management activities
in all alternative cases. These two factors limit the range of variability in
alternative land- use scenarios and their cleanup costs.
Alternative Land-Use Case Acreages*
|
Land-Use
Standard
|
|
Likely Use
|
Maximum
Allowable Use
|
Maximum
Allowable Use
|
Maximum
Allowable Use
|
| Storage & Disposal
|
6,000
|
6,000
|
6,640
|
6,640
|
6,640 |
6,000
|
6,000 |
| Open Space
|
278,000
|
0
|
0
|
0
|
0
|
0
|
0
|
| Industrial
|
2,500
|
2,500
|
2,500
|
2,500
|
2,500
|
2,400
|
2,300 |
|
Recreational
|
72,000
|
0
|
16,360
|
16,360
|
16,360
|
0
|
0
|
|
Residential
|
0 |
261,000
|
244,000
|
244,000
|
244,000
|
261,100
|
261,200
|
|
Agricultural
|
0
|
89,000
|
89,000
|
89,000
|
89,000
|
89,000
|
89,000
|
| COST |
$50.2 billion
|
$47.7 billion
|
$49.1 billion
|
$49.2 billion
|
$51.0 billion
|
$51.7 billion
|
*Acre numbers have been rounded for presentation
MAXIMUM FEASIBLE GREEN FIELDS
In this most aggressive cleanup scenario, almost 101,000 hectares (250,000
acres) could meet Residential use standards. However, since the disposal
activities remain in the 200 Area, the associated buffer requirements continue
to apply. Therefore, despite a significant increase in land meeting residential
standards, the anticipated uses in this case do not vary significantly from the
Base Case. In addition, the Maximum Feasible Green Fields case results in the
loss of industrial infrastructure in the 300 and 400 areas.
Idaho National Engineering Laboratory
LAND-USE SUMMARY
The Idaho National Engineering Laboratory is the largest and most remote of the
five sites included in the analysis. Under the Base Case, 99 percent of the
land area meets the land-use standard for Residential use, as only small areas
of the site were used for production or storage/disposal activities. The
contaminated areas and facilities present only limited opportunities for
alternative land uses. In addition, the site's Base Case decommissioning
assumptions are aggressive, assuming "clean closure" and removal of all
contaminated material. As a result, the Base Case costs approximate the
Modified and Maximum Feasible Green Fields costs. The only major change in land
use occurs in the Iron Fence Case, in which a large area of approximately
77,600 hectares (192,000 acres) containing unexploded ordnance is not fully
remediated.
Alternative Land-Use Case Acreages*
|
Land-Use
Standard
|
|
Likely Use
|
Maximum
Allowable Use
|
Maximum
Allowable Use
|
Maximum
Allowable Use
|
| Storage & Disposal
|
184
|
184
|
184 |
184
|
156 |
156
|
156 |
| Open Space
|
524,816
|
0
|
192,000
|
0
|
0
|
0
|
0
|
| Industrial
|
45,000
|
540
|
540 |
540
|
540 |
485
|
171 |
|
Recreational
|
0
|
0
|
0
|
0
|
28
|
28
|
0
|
|
Residential
|
0 |
569,276
|
377,276
|
569,276
|
569,276
|
569,331
|
569,673
|
|
Agricultural
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
| COST
|
$18.5 billion
|
$17.2 billion
|
$17.3 billion
|
$17.3 billion
|
$18.5 billion
|
$19.0 billion
|
* Acre numbers have been rounded for presentation.
MAXIMUM FEASIBLE GREEN FIELDS
This most aggressive case for the Idaho National Engineering Laboratory results
in only a small increase in cost from the Base Case. Some of the highest cost
projects at the site (Idaho Chemical Processing Plant Tanks, Radioactive Waste
Management Complex) have no other reasonable end state, and their costs remain
constant across the alternative cases. Under this scenario, only an additional
160 hectares (400 acres) of land are added to the Residential use category.
While the site is essentially clean, its remote location and environmental
setting limit any interest in reuse or redevelopment. In addition, State laws
prohibiting new wells in the Snake River Plain Aquifer preclude any possibility
of Residential or Agricultural use.
Oak Ridge Reservation
LAND-USE SUMMARY
The Oak Ridge Reservation is the smaller of the two sites located in
environmental settings with high water tables. While the majority of the site
is uncontaminated, the compact nature of the site and the three major
production areas limit use of that land to Open Space. In addition, the Oak
Ridge National Laboratory and the Y-12 Plant have established continuing
missions that limit their variability in all cases except Maximum Feasible
Green Fields. A significant portion of cost at the site is allocated to
monitoring and addressing the migration of contamination from numerous areas of
buried waste. These costs remain constant for all cases except for Maximum
Feasible Green Fields.
Alternative Land-Use Case Acreages*
|
Land-Use
Standard
|
|
Likely Use
|
Maximum
Allowable Use
|
Maximum
Allowable Use
|
Maximum
Allowable Use
|
| Storage & Disposal
|
2,541
|
2,541
|
2,541
|
2,541
|
2,541 |
2,541
|
0 |
| Open Space
|
28,932
|
0
|
1,735
|
0
|
0
|
0
|
0
|
|
Industrial
|
3,527
|
3,527
|
3,527
|
3,527
|
1,979
|
1,969
|
0 |
|
Recreational
|
0
|
1,735
|
0
|
1,735
|
3,283
|
1,735
|
0
|
|
Residential
|
0 |
27,197
|
27,197
|
27,197
|
27,197
|
28,755
|
35,000
|
|
Agricultural
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
| COST
|
$25.1 billion
|
$22.9 billion
|
$24.3 billion
|
$28.5 billion
|
$29.1 billion
|
$132.0 billion
|
* Acre numbers have been rounded for presentation.
MAXIMUM FEASIBLE GREEN FIELDS
The Oak Ridge Maximum Feasible Green Fields scenario is the most aggressive
cleanup proposed in the analysis. While the additional acreage meeting
Residential land-use standards is not large, the task of excavating, treating
and disposing large areas of buried waste at Oak Ridge National Laboratory,
Y-12 Plant, and K-25 Plant, and large volumes of contaminated sediment from
White Oak Lake result in a 520 percent increase in life-cycle cost. The
majority of this cost increase is from treatment and disposal of previously
buried waste. As in the other Maximum Feasible Green Fields scenarios, the
existing industrial infrastructure is removed, and potentially sensitive
habitat is disturbed.
Under this scenario, the entire site is clean enough for Residential use and
there is local interest in residential development of the site, especially
along the banks of the Clinch River. Private sector interest in industrial
development on the site may be limited by the removal of existing
infrastructure.
Rocky Flats
LAND-USE SUMMARY
The Rocky Flats Environmental Technology Site represents the smallest 2,500
hectares (6,216 acres) of the five sites discussed in this analysis. The
majority of land is uncontaminated and meets Residential land-use standards,
but is currently limited to use as a buffer area for the plutonium stored at
the site. This buffer area contains large areas of sensitive tall grass prairie
habitat as well as Preble's jumping field mouse habitat. The core area of the
site is the focus of cleanup efforts and measures only 155 hectares (384
acres). Under all cases, except for Maximum Feasible Green Fields, this core
area attains Industrial land-use standards to allow for potential environmental
technology development activities.
Alternative Land-Use Case Acreages*
|
Land-Use
Standard
|
|
Likely Use
|
Maximum
Allowable Use
|
Maximum
Allowable Use
|
Maximum
Allowable Use
|
| Storage & Disposal
|
68 |
68 |
68 |
68
|
68 |
68 |
0 |
| Open Space
|
5,688
|
0
|
0
|
0
|
0
|
0
|
0
|
| Industrial
|
460
|
460
|
460 |
460
|
460 |
460
|
0 |
|
Recreational
|
0
|
1,227
|
1,227
|
1,227
|
1,227
|
1,227
|
0
|
|
Residential
|
0 |
4,461
|
4,461
|
4,461
|
4,461
|
4,461 |
6,216 |
|
Agricultural
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
| COST
|
$17.3 billion
|
$15.8 billion
|
$17.3 billion
|
$17.3 billion
|
$17.4 billion
|
$26.0 billion
|
* Acre numbers have been rounded for presentation.
MAXIMUM FEASIBLE GREEN FIELDS
The Maximum Feasible Green Fields scenario for this site envisions the complete
removal of all contaminated soil, building materials, and previously buried
waste. Under this scenario, the entire site meets Residential use standards.
The excavation of buried waste and the disposal of all remediation waste at an
offsite location results in a significant (50 percent) increase in life-cycle
cost. In addition, cleanup activities remove all existing industrial
infrastructure and disturb/damage tall grass prairie and jumping mouse habitat.
While land at the site would be clean enough to support Residential uses, the
extensive private ownership of mineral rights may preclude full residential
development. Some of the land might eventually be dedicated to residences,
wildlife management areas, and mining activities.
Savannah River Site
LAND-USE SUMMARY
The Savannah River Site is the larger of the two sites (the other being Oak
Ridge Reservation) located in humid environmental settings. The majority of the
surface area at the site is uncontaminated. However, contaminated surface
waters and sediment (streams south of production areas, L Lake, Par Pond) limit
most of the remainder of the site to Open Space use. The area of the site north
of the production areas is not affected by surface or ground-water
contamination and therefore meets the land-use standard for Agricultural use.
The Base Case remediation strategy assumptions at this site are quite aggressive
and, as a result, the Base Case costs at Savannah River Site approach those for
the Recreational scenario. In addition, the end state of the five reactors and
two chemical processing buildings is held constant, thereby limiting the
variability of costs associated with alternative land-use cases.
Alternative Land-Use Case Acreages*
|
Land-Use
Standard
|
|
Likely Use
|
Maximum
Allowable Use
|
Maximum
Allowable Use
|
Maximum
Allowable Use
|
|
Likely Use
|
Maximum Allowable Use
|
Maximum Allowable Use
|
Maximum Allowable Use
|
Maximum Allowable Use
|
Maximum Allowable Use
|
Maximum Allowable Use
|
| Storage & Disposal
|
645
|
645
|
4,145
|
645 |
645
|
645 |
645
|
| Open Space
|
190,755
|
147,255
|
147,255
|
147,255
|
103,255
|
0
|
0
|
| Industrial
|
6,600
|
6,600
|
3,100
|
6,600 |
4,300
|
4,300 |
2,400 |
|
Recreational
|
0
|
0
|
0
|
0
|
46,300
|
149,555
|
0
|
|
Residential
|
0 |
0
|
0 |
0
|
0 |
0
|
150,955 |
|
Agricultural
|
0
|
43,500
|
43,500
|
43,500
|
43,500
|
43,500
|
44,000
|
| COST
|
$48.8 billion
|
$46.8 billion
|
$46.9 billion
|
$49.4 billion
|
$49.7 billion
|
$54.8 billion
|
* Acre numbers have been rounded for presentation.
MAXIMUM FEASIBLE GREEN FIELDS
The Maximum Feasible Green Fields Case for the Savannah River Site is limited by
the possible end state for the five reactors, the chemical processing buildings
and the Storage/Disposal Areas in the E, F, and H Areas. All these areas remain
Controlled Access for storage and disposal because more aggressive remediation
or decommissioning strategies pose the possibility of spreading more
contamination to ground and surface water. Excavation, treatment, and removal
of contaminated sediments in streambeds and Carolina Bay wetlands brings the
majority of the site to Residential standards, with the corresponding
disturbance of those sensitive habitats. Industrial infrastructure is removed
and the potential for private sector reuse is reduced. The interest for
residential development is limited, and given the environmental setting, it is
likely that most of land would be used for resource or wildlife management
areas.
SITE-SPECIFIC CONSTRAINTS ON FUTURE LAND USE
The site-specific summaries presented above discussed land use primarily in
terms of "maximum allowable use" (i.e., the standards that exist currently or
could be achieved). While such uses can be achieved in theory, other factors
such as legal commitments and ongoing mission needs may affect whether such
uses are likely to be achieved. To illustrate how site-specific
constraints may affect future use, the following table compares, for the Base
Case, maximum allowable future land use with the most likely future land use at
the five highest-cost sites.
Comparison of Maximum Allowable and Anticipated Land Use
|
Land-Use Category
|
Maximum Allowable Use
(Acres*)
|
Likely Use
(Acres*)
|
| Agricultural
|
132,500 |
0 |
| Residential
|
861,000
|
0
|
| Recreational
|
3,000 |
72,000 |
| Industrial
|
13,500
|
58,000
|
| Open Space
|
147,500 |
1,028,000 |
| Storage and Disposal
|
10,000
|
9,500
|
| Total Acres
|
1,167,500
|
1,167,500
|
| *Acre numbers have been rounded for presentation
|
This comparison indicates that nearly 400,000 hectares (1 million acres) (85
percent of the total land area) at these sites currently meet or could be
remediated to meet Residential or Agricultural use standards. However, none of
these acres are likely to be used for agriculture or residences, given
site-specific constraints. Instead, these areas are likely to be used for Open
Space, Recreational, or Industrial purposes. At the Idaho National Engineering
Laboratory, for example, all of the land with maximum allowable use designated
as Residential is most likely to be used for Open Space or Industrial purposes.
The following paragraphs provide examples of how several key types of
site-specfic constraints may affect future land use.
Legal Commitments - At some sites, future land-use and technology
strategy has been determined through the regulatory process (e.g., a signed
Record of Decision). A host of other legal commitments exist. Local laws can
place restrictions on access to ground water (e.g., the Snake River Plain
Aquifer in Idaho). All these legal mechanisms limit land uses considered for
federally controlled sites or place land-use decisionmaking in the hands of
other parties. Legal commitments limit future-use options for approximately
292,000 hectares (720,000 acres) (77 percent) of the uncontaminated land at the
five highest-cost Environmental Management sites.
Technical Constraints - Some contamination problems (e.g., ground water
contaminated with tritium) have no viable removal strategies compatible with
Agricultural or Residential land uses. Containment technologies and
restrictions on ground-water use are the only means to manage such problems.
Other contamination problems present unacceptably high risks to workers using
conventional construction-type removal technologies and must be remediated by
use of remote or robotic technologies. Technical constraints restrict
future-use options for approximately 38,300 hectares (95,000 acres) (10
percent) of the uncontaminated land and 17,400 hectares (43,000 acres) (20
percent) of the contaminated land at the five highest-cost Environmental
Management sites.
Safeguarding of Natural, Historical and Cultural Resources - The buffer
areas at several Environmental Management sites support endangered species
(e.g., red-cockaded woodpeckers at the Savannah River Site) or ecologically
unique habitats (e.g., the tall grass prairie at the Rocky Flats Environmental
Technology Site). Certain buildings are part of the nation's historical
heritage due to their role in developing nuclear weapons and energy and have
been designated National Historic Landmarks. These resources limit future use
for approximately 56,500 hectares (140,000 acres) of uncontaminated land and
some contaminated land at the five highest-cost sites.
Site Safety Considerations - Site safety considerations require that
activities be limited to land for ongoing missions including research and
storage/disposal of waste. In addition to land for housing these activities, in
the past large areas of land have been set aside to provide buffer zones for
those activities involving dangerous materials and weapons production. Future
site missions, including long-term storage of nuclear weapons material, will
determine whether those buffer zones can be contracted or must be maintained.
Current projected land uses include only minimal buffers around disposal areas
and do not include buffers for future research or storage missions.
Approximately 2,600 hectares (6,500 acres) (3 percent) of contaminated land are
restricted for storage, disposal and buffer purposes at the five highest-cost
Environmental Management sites.
Practical Constraints - Given that permanent disposal of waste and
continued research missions are planned for portions of four of the five sites
analyzed, there are practical limitations to the future use of land adjacent to
storage/disposal or research facilities. Spatial relationships are also
significant. Parcels of clean land effectively surrounded by industrial or
waste storage/disposal areas cannot be effectively used for many activities.
Spatial and other practical constraints limit future-use options for
approximately 20,000 hectares (50,000 acres) (5 percent) of uncontaminated land
at the five sites analyzed.
Although a comprehensive listing would be too extensive here, a summary of the
key factors constraining land use at the five highest-cost sites is included in
the following table to provide a greater understanding of individual site
constraints.
Key Constraints at Five Highest-Cost Sites
Future Use Points of Contact and Reference List
Argonne National Laboratory - East
Tim Crawford (708) 252-2436
Argonne National Laboratory - East, Laboratory Integrated Facilities Plan,
FY 94.
Document No. JOSTD-106-G-T006
FY 1993 - Site Development Plan.
Brookhaven National Laboratory
Joseph Eng (516) 334-7982
Brookhaven National Laboratory, Future Land Use Plan. August 31, 1995
The Impact of Brookhaven National Laboratory on the Long Island Economy.
June 1995.
1992 Site Development Plan, Brookhaven National Laboratory
Fermi National Accelerator Laboratory
John Kasprowicz (708) 252-2691
FY 1993 Site Development Plan, Fermi National Accelerator Laboratory.
Fernald Environmental Management Project
Sue Peterman (513) 648-3179
Gary Stegner (513) 648-3153
Fernald Citizens Task Force, Recommendations on Remediation Levels, Waste
Disposition, Priorities and Future Use. July 1995
Fernald Citizens Task Force Tool Box. October 1994.
Hanford Site
Paul Krupin (509) 372-1112
The Future for Hanford: Uses and Cleanup, the Final Report of the Hanford Future
Site Uses Working Group. December 1992.
Comprehensive Land Use Plan For the Hanford Site, DRAFT. (to be released
June 1996)
Hanford Remedial Action Environmental Impact Statement, DRAFT. (To be
released June 1996)
Hanford Site Development Plan. May 1993. DOE/RL-93-19
The Hanford Strategic Plan, DRAFT, 1996.
Idaho National Engineering Laboratory
Dan Shirley (208) 526-9905
Long-Term Land Use Future Scenarios for the Idaho National Engineering
Laboratory. August 1995.
Idaho National Engineering Laboratory, Site Development Plan, 1994.
DOE/ID-10390.
DRAFT, 1995, Idaho National Engineering Laboratory Comprehensive Facility and
Land Use Plan.
Kansas City Plant
Phil Keary (816) 997-7288
FY 1994, Kansas City Plant, Site Development Plan.
Kansas City Area Operations Plan. January 1996.
Lawrence Livermore National Laboratory
Rick D'Arienzo (510) 422-9247
Shaun Kesterson (510) 637-1702
FY 1995 Site Development Plan. UCRL-LR-110253-95.
FY 1995 Technical Site Information. AR-1183655-94
Los Alamos National Laboratory
Pete Crowley (505) 665-8764
Juan Griego (505) 665-6439
Bill Pelzer (505) 667-7756
Site Development Plan, Annual Update 1993, Los Alamos National Laboratory.
LALP-93-27.
Mound Plant
Tim Sullivan (513) 865-3220
Mound Plant, Site Development Plan, FY 1996.
Nevada Test Site
Tim Killen (702) 295-1288
Nevada Site Development Plan, September 21, 1994.
Nevada Test Site, DRAFT, Environmental Impact Statement. January 1996.
Oak Ridge Reservation
Gary Bodenstein (423) 576-9429
Dave Kendal (423) 576-9359
Future Land Use Process for Oak Ridge Operations, A Report to the U.S. Department
of Energy on the Recommended Future Use of the Oak Ridge Reservation, Paducah
Gaseous Diffusion Plant, and the Portsmouth Gaseous Diffusion Plant. December
1995.
Oak Ridge Reservation, Site Development Plan. June 1994. ES/EN/SFP-22.
Paducah Gaseous Diffusion Plant
Carlos Alvarado (502) 441-6804
John Morgan (502) 441-5069
Future Land Use Process for Oak Ridge Operations, A Report to the U.S. Department
of Energy on the Recommended Future Uses of the Oak Ridge Reservation, Paducah
Gaseous Diffusion Plant, and the Portsmouth Gaseous Diffusion Plant. December
1995.
DRAFT, Site Management Plan (to be released mid-1996)
Pantex Plant
Gordon Gabert (806) 477-3163
Sharon Buell (806) 477-4041
Pantex Plant, FY 1994, Site Development Plan, PLN14.
Pantex Plant Future Use Recommendations. December 1995.
FY 1997 Pantex Plant Capital Asset Management Process (CAMP) Report.
Pinellas Plant
David Ingle (813) 514-8943
FY 1996 Community Transition Plan, Pinellas Plant Community Reuse Organization.
October 1995.
FY 1994, Pinellas Plant Construction Plan and Site Development Plan. March
1994. MMSC-FAC-94110,UC-700
Portsmouth Gaseous Diffusion Plant
Bob Barnett (616) 897-2700
Sandy Childers (614) 897-2336
John Sheppard (614) 897-5510
Future Land Use Process for Oak Ridge Operations, A Report to the U.S. Department
of Energy on the Recommended Future Uses of the Oak Ridge Reservation, Paducah
Gaseous Diffusion Plant, and the Portsmouth Gaseous Diffusion Plant. December
1995.
Site Development Plan - Portsmouth Uranium Enrichment Plant. July 1992.
POEF-3001.
Rocky Flats Environmental Technology Site
Laura Johnston (303) 966-4755
Frazer Lockhart (303) 966-7846
Future Site Use Recommendations, Future Site Use Working Group. July
1995.
Site Development Plan, FY 1993, Rocky Flats Plant.
Rocky Flats Environmental Technology Site, Accelerated Site Action Plan, DRAFT,
1995.
Rocky Flats Environmental Technology Site "Vision," DRAFT. November 1995.
Sandia National Laboratories - Albuquerque
Deborah Garcia (505) 845-5460
Karen Talbot-Rohde (505) 881-7180
Handbook: Baseline For Future Use Options. June 1995.
Sandia National Laboratory Site Development Plan FY 1995, Sites Planning
Department, 1995.
1993 Environmental Report. SAND94-1293 UC-630. 1994.
Workbook: Future Use Management Area 1, Sector P, The Withdrawn Area. October
1995.
Workbook: Future Use Management Area 2, Sectors 2E and 2G, Areas 1 - V. September
1995.
Workbook: Future Use Management Area 3,4,5, and 6, Sector 3B Ross Aviation, Inc.;
Sector 4C, Allied Signal Federal Management and Technology, New Mexico; Sector
5M, Mazano Administrative Storage Area; Sector 6A Tijeras Arroyo and Arroyo Del
Coyote. January 1996.
Workbook: Future Use Management Area 7, Sector D Igloo Area and Test Sites;
Sector F DOE Buffer Zone; Sector H Training Areas; Sector I
Test Sites; Sector K Thunder Range; Sector L Pendulum Site Area; Sector N Coyote
Test Area; Sector Q Inhalation Toxicology Research Institute. March 1996.
Sandia National Laboratories - California
Deborah Garcia (505) 845-5460
FY 1995 Site Development Plan.
Savannah River Site
Virginia Gardner (803) 725-5752
Gail Jernigan (803) 725-4535
Cris Van Horn (803) 725-5313
Stakeholder-Preferred Options for SRS Land and Facilities. January 1996.
Land-Use Baseline Report, Savannah River Site. June 1995.
WSRC-TR-95-0276.
Savannah River Site, 1993, Predecisional Draft, Site Development Plan. WSRC-RP-93-477.
DRAFT - FY95 Site Development Plan for the Savannah River Site.
Chapter -1- / -2- /
-3- / -4- / -5-
/ -6- / -7- /
-8-
Appendix -A2- / -B- /
-C- / -D- / -E1-
/ -E2- / -F- /
-G- / -H- / Glossary
|