Home
BEMR Contents
U.S. Map
BASELINE REPORT METHODOLOGY
Table of Contents
C.0 Introduction
C.1 Defining the Study
C.1.3 Developing
Categories for Personnel Requirements
C.2 Gathering and Assembling Data
C.2.1 Gathering Data
C.2.1.1
Environmental Restoration Activities
C.2.1.2 Nuclear
Material and Facility Stabilization Activities
C.2.1.3 Waste Management
Activities
C.2.1.4 Science and
Technology Activities
C.2.1.5 Landlord Activities
C.2.1.6
National Program Planning and Management Activities
C.2.1.7 Support Activities
C.2.2 Assembling the Data
C.2.3 Verifying and
Documenting Data
C.3 Integration Analyses
C.3.1 Base Case Scenario
C.3.1.1 Performing the
Integration
C.3.1.2 Documentation
C.3.2 Alternative Scenarios
C.3.2.1 General Approach
C.3.2.2 Land Use
C.3.2.3 Program and
Project Scheduling
C.3.2.4 Minimal Action
C.3.3 Risk
C.4 Estimating Program
Improvements
C.4.1 Technology Development
C.4.2 Pollution Prevention
C.4.3 Productivity
C.5 Developing Documentation
C.6 Stakeholder Involvement
C.7 Base Case Uncertainty
Analysis
C.0 INTRODUCTION
This appendix presents the methodology used to develop the cost and schedule
estimates for the 1996 Baseline Environment Management Report. The Department
of Energy used a five-step process to build on and enhance the approaches and
tools used to develop the 1995 Baseline Environment Management Report (Table
C-1). The purpose was to improve the basis for the cost and schedule estimates,
increase the involvement of personnel at the individual field sites in data
analysis, increase stakeholder involvement, and improve the consistency between
the 1996 Baseline Environment Management Report and other program planning
initiatives. All of the Base Case data, including the final integrated cost and
schedule estimates, were either provided directly from the individual sites or
reviewed by the sites prior to inclusion in the 1996 report. This allowed the
field personnel, who know their individual sites best and have experience with
their respective regulators and stakeholders, to ensure that the cost and
schedule data are complete and reflect the most current understanding of how
the Environmental Management program is likely to unfold at each site. Each of
the steps in the general methodology is described in a separate subsection
below. This appendix concludes with the methodology for the uncertainty
analysis for the Base Case.
Table C-1. Steps in the General Methodology
| Define the Study - Establish the scope, framework, and
general assumptions for the estimates; seek input from stakeholders
Gather and Assemble Data - Collect, verify, and document cost, waste
volume, and schedule data
Perform Site-and Complex-Wide Integration - Ensure that costs remain
within assumed funding limits and account for all waste transfers
Estimate Program Improvements - Evaluate the impacts of technology
development, pollution prevention, and productivity improvements
Develop Documentation - Prepare the 1996 report
|
C.1 DEFINING THE STUDY
Assumptions are developed at three levels: general assumptions to guide the
development of the 1996 report, national assumptions to be applied uniformly
across all of the Department of Energy sites, and site-specific assumptions.
C.1.1 Setting Assumptions
General assumptions - Five overarching, general assumptions guide the
development of the 1996 report (Table C-2). These assumptions are identical to
those used to develop the 1995 Baseline Environmental Management Report. The
primary assumption is that all Department of Energy activities will be in full
compliance with all legal agreements (e.g., compliance agreements, consent
orders) and all applicable federal, state, and local laws and regulations. For
example, cost estimates must assume that remedial technologies will be designed
to meet all applicable or relevant and appropriate regulations and will comply
with all worker safety regulations.
Table C-2. General Assumptions for the Baseline Environmental Management
Report
| Legal Requirements - all Department of Energy actions will
be consistent with existing legal agreements and will comply with existing laws
and regulations.
Ongoing Decision Processes - all cost and schedule estimates will be as
consistent as possible with the status of ongoing negotiations, decisionmaking
processes, and related studies as of October 1995.
Funding Limits - all cost and schedule estimates will assume a minimum
funding level consistent with meeting the milestones in existing compliance
agreements. Assumed funding beyond the year 2000 will be "capped" at each
site's FY 2000 estimate of compliance funding unless cost increases are
dictated by existing compliance agreements.
Local Visions of the Future - all cost and schedule estimates will
reflect, to the extent possible, each site's own views of its likely future.
Estimates, not Decisions - the cost and schedule figures are only
estimates and not presumptions of future decisions the Department has yet to
make.
|
The second general assumption is that all cost and schedule estimates will be as
consistent as possible with the status of ongoing decisionmaking processes as
of October 1995. The Department currently is engaged in a number of
negotiations, discussions, and studies in support of key decisions such as:
-
Federal Facility Compliance Act negotiations to determine the locations of
future mixed low-level waste management facilities;
-
The Future Use Project aimed at determining local stakeholders' preferred
future land uses for Department of Energy sites; and
-
Studies leading to National Environmental Policy Act documentation such as the
Waste Management Programmatic Environmental Impact Statement and
site-specific environmental impact statements.
The Baseline Environmental Management Report should reflect the key policy
decisions reached through these democratic processes. However, many of these
processes will not achieve final decisions for several months or years, and
their directions are expected to change any number of times as these processes
evolve. As a consequence, the specific assumptions used to develop cost and
schedule estimates for the 1996 report (e.g., future land use and missions at
each site) reflect the state of these processes "frozen" as of October 1995.
Therefore, it is likely that the 1996 report will rapidly become out of date
with respect to the current state of these processes.
The third general assumption is that all cost and schedule estimates will assume
a minimum funding level consistent with meeting the milestones in existing
compliance agreements. Because the milestones in most compliance agreements do
not extend beyond the year 2000, assumed funding beyond that year will be
"capped" at each site's FY 2000 estimate of compliance funding. Annual site
costs beyond FY 2000 will not be permitted to exceed the funding cap unless
these cost increases are dictated by existing compliance agreements.
The fourth general assumption is that the assumptions used to develop cost and
schedule estimates for the 1996 report will reflect each site's vision of the
future. The inherent uncertainties associated with predicting activities
several decades into the future make it difficult to estimate accurately the
total life-cycle cost and schedule for the Environmental Management program.
The best current understanding of potential future developments at each site is
likely to be held by those individuals that live and work at or nearby these
facilities.
The final general assumption is that the 1996 report is not a decision document.
The Department recognized that the cost and schedule estimates in the 1996
report could be interpreted as final decisions. However, the assumptions used
to develop the 1996 report, and the cost and schedule estimates resulting from
implementing these assumptions, are developed solely to meet the Congressional
mandates for the 1996 report, except where these assumptions, costs, and
schedules reflect conditions set forth in Records of Decision, compliance
agreements, and other legal agreements. Assumptions and cost and schedule
estimates are expected to change in future reports as new information becomes
available and ongoing decisionmaking processes evolve.
National assumptions - Certain assumptions were applied uniformly across
all of the Department of Energy sites. These assumptions dealt with issues such
as projected funding levels; where treatment, storage, and disposal of
low-level mixed waste, low-level waste, and transuranic waste would occur; and
when a geologic repository and the Waste Isolation Pilot Plant are expected to
accept waste for disposal. Most of the national assumptions were developed at
Headquarters based on the current status of ongoing decision processes (e.g.,
negotiations with states under the Federal Facility Compliance Act), current
Environmental Management program plans, and discussions with the Office of
Management and Budget. Each site reviewed the national assumptions and applied
them as appropriate to their sites.
Site-specific assumptions - Personnel at each site provided specific
assumptions regarding how the Environmental Management program is likely to
unfold at the site. These assumptions dealt with issues such as expected future
land use and the likely types of remedial technologies to be used for
particular problems. Headquarters personnel reviewed the site-specific
assumptions and modified them as necessary. Site-specific assumptions are
listed in the individual site summaries presented in Volumes II and III of the
1996 report.
C.1.2 Defining Activities
and Projects for Environmental Management Program Functional Elements
The FY 1995 National Defense Authorization Act requires the Department to
provide a description of each project and activity to be performed by the
Environmental Management program. The format used this year is similar to that
used for the 1995 Baseline Environmental Management Report. Information is
organized according to activities and projects for each Environmental
Management program element. In this year's report, some terminology and
categories differ and greater emphasis was placed on linking cost and schedule
estimates to specific, discrete projects at each site.
C.1.2.1 GENERAL
DEFINITIONS AND CRITERIA
Activities - Activities represent the general sets of actions required to
remediate contaminated areas, disposition special nuclear material and
contaminated facilities, manage waste, maintain federal lands and facilities,
and manage the Environmental Management program. Table C-3 lists the general
types of activities being conducted by the six functional elements of the
Environmental Management program. The following subsections define and describe
each of these activities. Each individual site has provided an estimate of the
cost and schedule for, and a written description of the scope of work included
in each activity. The individual site summaries presented in Volumes II and III
of the 1996 report provide these estimates and descriptions.
Table C-3. Program Elements and Activities
Environmental Restoration
Assessment
Remedial Actions
Facility Decommissioning
Long-Term Surveillance and Monitoring
Nuclear Material and Facility Stabilization
Surveillance and Maintenance
Pre-Stabilization
Post-Stabilization
Post-Deactivation
Nuclear Material Stabilization
Facility Deactivation
|
Waste Management
Waste Treatment
Waste Storage
Waste Disposal
Science and Technology Development
Landlord
National Program Planning and Management
|
Projects - A primary goal for the 1996 Baseline Environmental Management
Report is to provide more complete information about how the costs estimated
for each activity are linked to specific projects. The Department used four
general criteria for defining projects associated with environmental
restoration, nuclear material and facility stabilization, and waste management
activities (Table C-4). Projects had to be tangible entities linked to
geographically identifiable problems or sites and large enough to address real
problems and represent significant cost. To facilitate schedule estimates,
projects had to have a definable beginning and end. To improve linkages with
other program planning efforts, individual sites had to be able to crosswalk
projects with existing budget breakdowns and planning tools.
Table C-4. Criteria for Defining Projects
-
Tangible entities linked to geographically identifiable problems or sites
-
Large enough to address real problems and represent significant cost
-
Definable beginning and end
-
Able to be linked to existing budget breakdowns and planning tools
|
Using the above criteria, each site identified its major projects, using those
identified in the 1995 Baseline Environmental Management Report as a starting
point. Environmental restoration projects generally represent discrete,
identifiable geographical portions of sites (or entire small sites). For
nuclear material and facility stabilization activities, large facilities are
listed as discrete projects, while smaller facilities are grouped together by
facility category and geography. Waste management projects are specific
facilities used to treat, store, and/or dispose of high-level waste, spent
nuclear fuel, low-level waste, low-level mixed waste, and transuranic waste at
each site where the waste type is present.
Personnel at individual sites have provided an estimate of the cost and schedule
for each major project. The individual site summaries presented in Volumes II
and III of the 1996 report provide these estimates.
C.1.2.2 ENVIRONMENTAL
RESTORATION ACTIVITIES
Environmental restoration is carried out to ensure that potential exposures to
radionuclides and other contaminants in environmental media and surplus
facilities are eliminated or reduced to levels prescribed through formal
agreement with regulators. The major environmental restoration activities are
assessment, remedial actions, facility decommissioning, and long-term
surveillance and monitoring. To support these activities, related actions may
be undertaken including treatment of contaminated soils or ground water onsite,
packaging waste for commercial treatment and/or disposal, and disposing of
consolidated contaminated materials such as soils or building rubble onsite.
Assessment involves all activities required to identify and characterize
release sites or facilities and reach a formal agreement with regulators
regarding appropriate further actions (e.g., Superfund Records of Decision).
Specific tasks include reviewing historical records; physically assessing
current conditions at the release site or facility; collecting and evaluating
media samples to identify the nature and extent of contamination; assessing
current and future risks to human health and the environment; developing and
evaluating the feasibility of potential decommissioning or remedial options
(including no action); conducting appropriate public involvement activities;
and preparing, reviewing, and revising all reports and documents required by
applicable regulations.
Remedial actions follow assessment and involve all activities required to
implement further actions determined through formal agreement with regulators.
There are three general types of remedial actions: active removal, containment,
and "No Further Action" Active removal of most contaminants, including
radionuclides, involves excavating or extracting contaminated media and one or
more of the following: treatment to remove contaminants from the medium,
placing the contaminated medium or byproducts in appropriate containers for
shipment to treatment or disposal sites, and/or directly disposing of the
contaminated medium or byproducts in an appropriate disposal facility. In-place
destruction (e.g., bioremediation) may be possible for some organic
contaminants. Containment involves leaving contaminants in place and
constructing physical barriers (e.g., caps, slurry walls) or implementing
interception strategies (e.g., pumping ground water) to prevent further
migration of contaminants. No Further Action is taken where contaminants have
been eliminated or are present in such low concentrations as to have no
significant health consequences. This situation may result when contamination
upon investigation is lower than suspected or limited expedited response
actions were sufficient to address long-term risk concerns.
Facility decommissioning activities involve the safe decontamination
and/or dismantlement of surplus facilities that have been deactivated. The
contents of these facilities are primarily reactors, hot cells, processing
plants, storage tanks, research equipment, and other structures. Related tasks
include surveillance and maintenance, characterization, environmental
documentation review, waste disposal, and closeout. There are three general
types of facility decommissioning actions: full decontamination and
dismantlement, decontamination and containment, and entombment. Full
decontamination and dismantlement involves complete decontamination of facility
contents, demolition of structural materials, and removal of demolition
materials. Decontamination and containment involves decontamination and
demolition, with capping demolition materials in place. Entombment involves
partial decontamination, limited or no demolition, and encasing remaining
materials in concrete.
Treatment, storage, and disposal are a small part (less than 10 percent)
of environmental restoration activities. These activities are required at some
sites (i.e., the Oak Ridge K-25 Site, the Paducah Gaseous Diffusion Plant, the
Pinellas Plant, and the Portsmouth Gaseous Diffusion Plant) with large facility
decommissioning projects and few or no established waste management facilities.
At two other sites (the Hanford Site and the Savannah River Site),
environmental restoration activities include construction and operation of
large disposal cells for waste generated from remedial actions and facility
decommissioning.
Long-term surveillance and monitoring is conducted to ensure that the
selected remedies continue to provide the level of protection for human health
and the environment that is specified in formal agreements with regulators.
These activities are required for all remedies involving containment or No
Further Action and may be required for long-term remediation strategies (e.g.,
ground-water pump-and-treat operations) and following completion of facility
decommissioning actions. Specific tasks may include compliance monitoring to
ensure that the remedial technologies remain effective as well as surveillance
to ensure that physical access to restricted areas is prevented.
C.1.2.3 NUCLEAR MATERIAL
AND FACILITY STABILIZATION ACTIVITIES
Nuclear material and facility stabilization involves stabilizing and storing
special nuclear materials prior to their final disposition and deactivating
facilities that the Department has declared surplus because they no longer are
needed to meet mission objectives (e.g., research, waste management, nuclear
weapons production or dismantlement). The major activities are nuclear material
stabilization, facility deactivation, and surveillance and maintenance.
Surveillance and maintenance is an integral component of both stabilization and
deactivation.
Nuclear material stabilization activities are carried out to reduce the
near-term risks associated with current storage configurations for special
nuclear materials by placing these materials in a condition suitable for
long-term storage. These activities include repackaging and consolidation of
these materials.
Facility deactivation activities are carried out to ensure that surplus
facilities are secure and in a safe shutdown condition pending their ultimate
disposition, which could range from demolition to further cleanup and
commercial reuse. These activities involve eliminating immediate safety and
environmental hazards as well as removing most contaminants within the
facility. Specific tasks include removing equipment and stock chemicals;
cleaning out pipelines, holding tanks, and process vessels; and removing
reactor cores.
Surveillance and maintenance activities involve all actions required to
ensure adequate security of nuclear materials and surplus facilities, pending
their ultimate disposition. Specific tasks include maintaining fences and other
access barriers and providing onsite surveillance, environmental monitoring,
repairs, and other routine maintenance. Surveillance and maintenance continues
before, during, and after stabilization and deactivation until the final
disposition has been completed. At some sites (e.g., the Rocky Flats
Environmental Technology Site), surveillance and maintenance also includes
storage of special nuclear materials after stabilization has been completed.
The scope of work associated with surveillance and maintenance differs markedly
before stabilization, between stabilization and deactivation, and after
deactivation. Consequently, at sites where data are available, separate
estimates are provided for pre-stabilization, post-stabilization,
and post-deactivation surveillance and maintenance. Surplus facilities
may go directly to stabilization or deactivation, or they may go directly from
stabilization to deactivation. Therefore, not all phases of surveillance and
maintenance may occur. At the Hanford Site and Savannah River Site, data are
reported by projects and phase. At the Idaho National Engineering Laboratory,
Oak Ridge Reservation, and Rocky Flats Environmental Technology Site, data are
reported by phase. At the remaining sites, data are reported as a single
nuclear material and facility stabilization estimate.
C.1.2.4 WASTE MANAGEMENT
ACTIVITIES
Waste management involves the safe and efficient treatment, storage, and
disposal of waste and spent nuclear fuel. Most of this effort involves the
design, permitting, construction, operation, maintenance, stabilization, and
clean closure of treatment, storage, and disposal facilities. The waste comes
from three primary sources: existing inventories; waste derived from
environmental restoration activities; waste derived from nuclear material and
facility stabilization activities; additonal wastes generated by waste
management activities; and new waste generated by ongoing Departmental
missions. The Environmental Management program manages eight types of waste:
high-level, transuranic mixed, transuranic, low-level mixed, low-level, special
case, hazardous, and sanitary. The program also manages the Department's
inventory of spent nuclear fuel, which the Departments does not consider a
waste material.
Treatment activities involve applying a wide variety of technologies such
as incineration, vitrification, and grouting to transform waste into material
suitable for disposal. In addition to constructing, operating, maintaining, and
closing waste treatment facilities, specific tasks include characterizing waste
to determine appropriate handling procedures and packaging and transporting
waste to appropriate treatment or disposal facilities. The Department will use
commercial vendors for high-level and transuranic waste at some sites. For
purposes of this report, treatment also includes conditioning of spent nuclear
fuel prior to disposal.
Storage activities are undertaken if no appropriate treatment or disposal
facility is available for a given volume of waste. In addition to constructing,
operating, maintaining, and closing storage facilities, specific tasks include
characterizing waste to determine appropriate handling procedures, and
packaging and transporting waste to appropriate treatment or disposal
facilities.
Disposal activities involve placing post-treatment materials into
appropriate landfills, repositories, or other engineered structures and
providing adequate security, surveillance, and maintenance to ensure that
contaminants are not released from these facilities into the environment. In
addition to construction, operation, and maintenance of disposal facilities,
specific tasks include providing onsite surveillance, environmental monitoring,
repairs, and other routine maintenance.
C.1.2.5 SCIENCE AND
TECHNOLOGY DEVELOPMENT ACTIVITIES
Science and technology development activities include managing and directing
focused, problem/solution-oriented technology development programs to support
environmental restoration, nuclear material and facility stabilization, and
waste management activities. These activities include basic as well as applied
science research. Technologies are designed to reduce risks, facilitate
compliance, minimize waste generation, and decrease site cleanup costs. A major
goal is to enhance the commercialization and implementation of new technologies
to reduce costs and provide a world-wide leadership role for the United States
in environmental remediation. Costs for technology development activities are
shown in the 1996 report in two ways. In Volume I, costs are presented as part
of National Program Planning and Management (see Chapter 4). In Volume II,
costs are presented in the Maryland/Washington, D.C. site summary. Although
costs for these activities are appropriated at Headquarters, approximately 91
percent of this funding is transferred to field operations.
C.1.2.6 LANDLORD ACTIVITIES
Landlord activities involve the physical operation and maintenance of Department
of Energy sites. Specific tasks vary but generally include providing utilities,
maintenance, and general infrastructure for the entire site.
C.1.2.7 NATIONAL PROGRAM
PLANNING AND MANAGEMENT ACTIVITIES
National Program Planning and Management activities include planning,
monitoring, and reporting ongoing activities, cost/schedule tracking, clerical,
and other administrative support. Also included are grants to states and
locations as well as Department-wide development and implementation of
effective strategies, techniques, methods, and policy guidance for the safe,
secure, efficient, and cost-effective transportation of Department of Energy
materials. Costs for national program planning and management fall into two
categories. Program management includes program support, which involves general
technical contractor support services for all Environmental Management
Headquarters elements, special projects of immediate concern, and other
projects that arise during the fiscal year. Program direction includes salaries
and benefits for all federal Full-Time Equivalent personnel at Headquarters.
Individual site summaries in Volumes II and III of the 1996 report also include
separate cost estimates for program management/support activities. These
represent program management, program direction, and other support activities
associated with the site and/or particular functional elements (e.g.,
environmental restoration, waste management) at the site. Examples of support
activities include furnishing government equipment, upgrading laboratories, and
performing treatability and prevention of contamination dispersion studies.
C.1.3 Developing
Categories for Personnel Requirements
The National Defense Authorization Act of 1995 required, for the first time,
that the Baseline Environmental Management Report provide an estimate of the
personnel required to perform the mission activities of the Environmental
Management program. The Department selected the nine labor categories defined
by the Common Occupational Classification System used for earlier work force
planning projects (Table C-5). Using these categories, each site provided
counts of their human resource needs for the years FY 1996 through FY 1998.
These counts included both federal and contractor (direct and indirect)
personnel. All data are presented in the site summaries in Volumes II and III
of this report.
Table C-5. Labor Categories Used to Estimate Personnel Requirements
| General Managers, Executives, First Line Supervisors, and
Program/Project Managers - Persons who engage in activities related to
planning, scheduling, monitoring, coaching, overseeing, and evaluating the work
of others, and who control and distribute resources within their organizational
units, programs, or projects.
General Administrative, Secretarial, and Clerical Support Staff - Persons
who provide office support services to managerial, scientific, engineering, and
professional staff through activities such as typing, word processing, making
appointments, and answering telephones.
Administrative and Other Professional Occupations - Persons who provide
services and professional advice, inspect operations and facilities, and/or
maintain computer, communications, and financial systems.
Engineers - Persons who apply physical laws and principles for the
development and use machines, materials, instruments, processes, and services
and engage in activities such as research, design, construction, testing,
procurement, production, operations, and sales.
Scientists - Persons who apply scientific methods to investigate the laws
of natural, physical, and social phenomena and their application to problems in
fields such as engineering, medicine, production, and the environment.
Technicians - Persons who apply scientific, technical, or engineering
principles to solve basic problems; who repair, maintain, or provide basic
operation of tools or equipment; or who collect and analyze data via field
sampling and laboratory analysis.
Operators - Persons who control and operate vehicles, machines, systems,
equipment, and plants to produce, destroy, move, and store materials and
supplies.
Craftsmen - Persons who construct, destruct, alter, and/or maintain
buildings, bridges, pipelines, and other structures and/or who fabricate
materials and machinery.
Laborers and General Service Workers - Persons who engage in manual labor
or general infrastructure support activities.
|
C.2 GATHERING AND ASSEMBLING
DATA
The magnitude of the environmental problems associated with the nuclear weapons
complex, the length and complexity of the cleanup effort, and the uncertain and
changeable nature of the Environmental Management program make it difficult for
site personnel to develop precise long-range cost and schedule estimates. The
need to meet the Congressional mandate for a program baseline, coupled with the
need to provide a basis for evaluating program alternatives (e.g., how total
cost would change if annual funding went up or down), required the ability to
isolate direct project costs from various indirect costs, including landlord
activities. Numerous differences in cost estimating methodologies, planning
methodologies, and accounting practices across the complex made this a
difficult task.
Given the uncertainties and needs, the Department developed life-cycle cost
estimates for two types of scenarios. The first is the Base Case scenario,
which represents current views (as of October 1995) of the most likely set of
activities and costs that will occur during the life cycle of the Environmental
Management program. The second type is alternative scenarios, which
examine the potential impacts of various policy decisions on total program cost
and schedule. The 1996 report examines alternative scenarios for land use,
program funding and schedule, and minimal action. The alternative scenarios
were limited to the five Environmental Management sites with the highest
life-cycle cost estimates: Hanford Site, Idaho National Engineering Laboratory,
Oak Ridge Reservation, Rocky Flats Environmental Technology Site, and Savannah
River Site. These five sites represent the majority (70 percent) of the total
cost estimate in the 1996 report.
For the Base Case scenario, cost and schedule estimates are based primarily on
site-specific (field) data, supplemented with parametric modeling by
Headquarters only when necessary to fill data gaps. Headquarters developed the
overall scope and the general assumptions to be used, as well as a framework
and software application for reporting data. Personnel at each individual site
developed their own, fully integrated cost and schedule estimates using their
most current baselines and planning documents. Headquarters personnel provided
assistance in cost estimation and data integration as needed, and worked
closely with sites to ensure that support costs were included fully. Personnel
at the individual sites verified all changes proposed by Headquarters prior to
inclusion in the 1996 report.
For the alternative scenarios for land use and program funding and schedule, the
personnel at individual field sites provided critical assumptions that would
affect projects and described how these projects would change, and Headquarters
used parametric modeling to estimate the cost consequences of these changes.
For the minimal action scenario, site personnel provided both critical
assumptions and alternative cost and schedule estimates for their individual
site.
C.2.1 Gathering Data
Obtaining an integrated cost and schedule estimate required the following basic
types of data for each Environmental Management activity:
-
Identity and location
are used to identify the activity, track it through the Baseline Environmental
Management Report data bases and analyses, and ensure that costs were accounted
for at the appropriate site.
-
Annual cost, start date (year), and duration
(years) are used to develop cost profiles over time for each site.
-
Data on waste type and annual volumes generated
are used to coordinate planned waste management facilities with estimated waste
generation and to estimate waste management costs.
-
Data on assumed technologies are used to evaluate the impact of
technology development on cost and schedule estimates.
Because of the potential need to reschedule Environmental Management projects to
accommodate funding and waste management constraints, it also was critical to
understand which projects were governed by existing compliance agreements (to
avoid creating a Base Case that was not in compliance with these agreements).
Specific methods used to collect data for each of these types of projects are
described in separate sections below.
To develop cost and schedule estimates for specific projects, it also was
necessary to determine which activities were associated with each project and
the sequence in which these activities would be performed. Environmental
restoration projects generally consisted of three activities: assessment (e.g.,
remedial investigations, feasibility studies), remediation or decommissioning,
and post-remediation surveillance and monitoring (e.g., ground-water
monitoring, inspecting containment barriers such as caps). Nuclear material and
facility stabilization projects could consist of as many as five activities:
pre-stabilization surveillance and maintenance, nuclear material stabilization,
post-stabilization surveillance and maintenance, deactivation, and
post-deactivation surveillance and maintenance. Waste management projects could
consist of four activities: pre-treatment storage, treatment, post-treatment
storage, and disposal.
C.2.1.1 ENVIRONMENTAL
RESTORATION ACTIVITIES
Data for environmental restoration activities were obtained by updating
information in a core data base. To facilitate the updating of this
information, the software application used to collect data was seeded with each
site's 1995 Baseline Environmental Management Report data where possible. Field
staff employed the software application for the entry of data at each site,
aggregated the data at the Department of Energy Operations Office level, and
transmitted the data to Headquarters. Headquarters staff performed an initial
screening of the data to ensure that all needed data fields were
completed in the correct format and that the data were referenced adequately.
Headquarters staff then performed a detailed content review to determine
whether all data elements required for Baseline Environmental Management Report
analyses were provided. Examples of specific reviews included determining that:
-
All significant areas of contamination (or waste streams) were listed;
-
Waste type and volume were provided;
-
Each waste stream had at a minimum basic characterization of its radiological
and hazardous chemical properties;
-
Remedial or decommissioning strategy was included; and
-
Contingency costs were provided for all relevant records.
Headquarters staff also coordinated the use of a parametric model (the Automated
Remedial Assessment Methodology) in the few instances where sites could not
estimate the cost of and waste volumes from decommissioning of surplus
facilities.
C.2.1.2 NUCLEAR MATERIAL
AND FACILITY STABILIZATION ACTIVITIES
The cost estimates for nuclear material and facility stabilization are, for the
most part, order-of-magnitude estimates. Base Case estimates were
field-developed at four sites: Hanford Site, Idaho National Engineering
Laboratory, Rocky Flats Environmental Technology Site, and Savannah River Site.
The remainder were developed using parametric cost-estimating techniques at
Headquarters. In instances where parametric cost estimating techniques were
used, the Department assumed a hypothetical "7-3-3-2-2" scheduling scenario (in
this sequence): seven years of pre-stabilization surveillance and maintenance;
three years of stabilization; three years of post-stabilization surveillance
and maintenance; two years of deactivation; and two years of post-deactivation
surveillance and maintenance. This represents a change in assumptions from the
1995 Baseline Environmental Management Report, which used a hypothetical
"10-5-2" scheduling scenario: ten years of pre-stabilization surveillance and
maintenance; five years of stabilization/deactivation; and two years of
post-deactivation surveillance and maintenance. Facility decommissioning
activities are assumed to begin after two years of post-deactivation
surveillance and maintenance. Therefore, any surveillance and maintenance costs
beyond that period are considered part of environmental restoration activities.
Table C-6 presents the assumptions used to develop nuclear material and
facility stabilization cost estimates.
Table C-6. Assumptions for Nuclear Material and Facility Stabilization
Estimates
| The "7-3-3-2-2" hypothetical scheduling scenario assumes seven years of
pre-stabilization surveillance and maintenance, three years for nuclear
material stabilization, three years of post-stabilization surveillance and
maintenance, two years of facility deactivation, and two years of
post-deactivation surveillance and maintenance. This scenario does not
necessarily represent the way that current and future surplus facilities will
be addressed.
Data for each facility represent the best information available from the Surplus
Facility Inventory Assessment data base as of December 1994, as modified by the
individual field sites during the 1996 data collection process.
Only surveillance and maintenance, nuclear material stabilization, and facility
deactivation activities are included in this estimate.
Surveillance and maintenance are occurring during stabilization and deactivation
activities and in some cases include storage costs for special nuclear
material.
|
Data for nuclear material and facility stabilization activities were obtained by
translating data from the 1995 Baseline Environmental Management Report format
to the 1996 Baseline Environmental Management Report format and seeding the
software application used to collect data with this information. The software
application allowed the sites to define scheduling/transfer units (Table
C-7), update specific facility data, add or remove facilities, modify the 1995
Baseline Environmental Management Report cost and waste volume estimates,
and/or provide their own cost and waste volume estimates. Sites used the
software application for data entry, aggregated the data at the Department of
Energy Operations Office level, and transmitted the data to Headquarters.
Table C-7. Scheduling/Transfer Units
| Each scheduling/transfer unit includes a site-specific grouping of
facilities based on similarities such as geographical location and/or
historical use. They typically consist of more than one separate building
(e.g., a large chemical processing building and dozens of ancillary buildings
may be included in a single unit). Scheduling/transfer units are used to define
nuclear material and facility stabilization costs as well as to schedule
projects moving from stabilization to decommissioning. |
Two sites - the Hanford Site and Savannah River Site - provided cost and
schedule estimates by phase for individual scheduling/transfer units. Three
sites - the Idaho National Engineering Laboratory, Oak Ridge Reservation, and
Rocky Flats Environmental Technology Site - provided cost and schedule
estimates by phase for a single, site-wide scheduling/transfer unit. At the
remainder of the sites, a single estimate was provided for all nuclear material
and facility stabilization activities combined. In cases where a site was
unable to provide any cost and schedule estimates, the 1996 Baseline
Environmental Management Report used a modification of the four-step process
originally defined for the 1995 report:
Modify List of Surplus Facilities Expected to Require Stabilization - For
the 1995 report, the Department produced a unified list of approximately 3,500
facilities (as of December 1994) likely to require stabilization in the future.
This list was based on a comparison of the Surplus Facilities and Inventory
Assessment data base and a list of surplus facilities developed for the Waste
Management Programmatic Environmental Impact Statement. Each site reviewed and
updated this list for the 1996 report.
Define Cost Estimating Categories and Classify Facilities - For the 1996
report, the Department used the same 22 facility categories developed for the
1995 report based on physical characteristics and types of historical activity
(Table C-8).
Modify and Execute Algorithms for Estimating Cost and Waste Volume - For
the 1996 report, the Department modified the algorithms for estimating cost and
waste volumes for each of the 22 facility categories. The 1995 algorithms,
developed using a "10-5-2" scenario, were modified to reflect the "7-3-3-2-2"
scenario used for the 1996 report. These algorithms are based on multiplying
the facility's physical characteristics (square feet, linear feet, gallons of
facility size) by a unit cost (per square foot, linear foot, or gallon).
Provide List of Facilities and Cost and Waste Estimates to Field for Review and
Verification - Numerous discussions have taken place between
Headquarters and site personnel regarding what facilities are on the list; how
these have been classified for cost estimation purposes, size and other key
physical characteristics; types of waste expected to be present; and waste
volumes expected to be generated during stabilization. The lists and resulting
cost estimates were modified based on the updated information provided by the
field.
Table C-8. Categories for Nuclear Material and Facility Stabilization Cost
Estimates
| A. Large Production Reactors
|
14 large reactors used to generate uranium,
plutonium, and tritium for nuclear weapons
|
| B. Chemical Processing Buildings
|
Eight large plants ("canyons") used to
chemically separate uranium and plutonium from other fission products
|
| C. Diffusion Cascade Buildings
|
Three large facilities ("gaseous diffusion
plants") used to remove and separate uranium-235 from uranium-238
|
| D. Research Reactors
|
Smaller reactors used for research and
development
|
| E. Radiologically Contaminated Facilities
E1 - size less than 1,000 ft2
E2 - size greater than 1,000 ft2 and less than 15,000 ft2
E3 - size greater than 15,000 ft2
|
Other facilities contaminated with
radioactive materials but not hazardous substances
|
| F. Radiologically Mixed Contaminated
Facilities
F1 - size less than 1,000 ft2
F2 - size greater than 1,000 ft2 and less than 15,000 ft2
F3 - size greater than 15,000 ft2
|
Other facilities contaminated with radioactive
materials and hazardous substances
|
| G. Hazardous Materials Contaminated
Facilities
G1 - size less than 1,000 ft2
G2 - size greater than 1,000 ft2 and less than 15,000 ft2
G3 - size greater than 15,000 ft2
|
Other facilities contaminated with
hazardous materials but not radioactive materials substances
|
| H. Radiologically Mixed Contaminated
Facilities
H1 - size less than 1,000 ft2
H2 - size greater than 1,000 ft2 and less than 15,000 ft2
H3 - size greater than 15,000 ft2
|
Other facilities contaminated with special
nuclear materials
|
| I. Storage Tanks
I1 - tanks contaminated with radioactive materials
I2 - tanks contaminated with hazardous materials
|
Above-ground and underground tanks used to
store waste and other materials
|
| J. Stacks
|
Facilities used as exhaust stacks for
boilers and similar structures
|
| K. Electrical Switchyards
|
Facilities used to house temporary
generators, transformers, and other electrical service components
|
| L. Pipelines
|
Pipelines used to transfer materials
between facilities
|
| M. Ponds/Retention Basins
|
Earthen structures used to hold effluent
liquids
|
C.2.1.3 WASTE MANAGEMENT
ACTIVITIES
The Environmental Management program is responsible for managing eight types of
waste and spent nuclear fuel, which the Department does not consider as a waste
material. The approach for estimating life-cycle waste management costs
depended considerably on the type of waste being managed. Life-cycle costs and
schedules for managing high-level waste and spent nuclear fuel are fairly well
defined. The Department currently has accurate estimates of the total volume of
high-level waste and spent nuclear fuel for which the Environmental Management
program is responsible. Plans for managing high-level waste are reasonably well
advanced, and options for managing spent nuclear fuel were evaluated in
accordance with the National Environmental Policy Act process, with a Record of
Decision published in May 1995.
Most of the hazardous and sanitary waste being managed by Environmental
Management is generated by ongoing Department of Energy operations. Life-cycle
costs and schedules for managing these two waste types are based primarily on
estimated generation rates from these ongoing operations.
Low-level, low-level mixed, transuranic, and transuranic mixed waste present a
different challenge. A significant fraction of the volumes of these waste types
requiring treatment, storage, and disposal will be generated by environmental
restoration and nuclear material and facility stabilization activities.
However, since numerous environmental restoration decisions have not yet been
made, there are considerable uncertainties in the waste volumes that will
eventually be generated, the types of facilities that will be required to
manage them, and cost estimates. Site personnel estimated the volumes of these
waste types to be generated by these activities and whether they required
treatment prior to disposal.
Many of the waste management cost and schedule estimates for the 1995 Baseline
Environmental Management Report were developed at Headquarters using program
planning documents. To improve the estimates for the 1996 report, the
Department focused on obtaining "bottom-up" data from the field. This allowed
the field personnel, who are most familiar with their individual sites and have
experience with their respective regulators and stakeholders, to ensure that
the cost and schedule data are complete and reflect the most current
understanding of how the Environmental Management program is likely to unfold
at their sites. Program management costs for waste management activities are
included in the treatment, storage, and disposal costs.
High-Level Waste - Site personnel provided all cost and schedule
estimates for managing high-level waste. Planning estimates are available for
the four sites with nearly all of this waste: the Hanford Site (including the
Tank Waste Remediation System), the Savannah River Site (including the Defense
Waste Processing Facility), the West Valley Demonstration Project, and the
Idaho National Engineering Laboratory. Cost estimates for high-level waste
include the treatment and disposal of low-level waste resulting from treatment
processes such as the saltstone facility at the Savannah River Site and a
vitrification facility at the Hanford Site. Decommissioning costs for
high-level waste facilities are included in the site estimates.
Spent Nuclear Fuel - Site personnel provided all cost and schedule
estimates for managing spent nuclear fuel. A Record of Decision (May 1995) for
the "Spent Nuclear Fuel Management and Idaho National Engineering Laboratory
Environmental Restoration and Waste Management Programs Environmental Impact
Statement" supports the preferred alternative of interim storage consolidation
at three sites: the Hanford Site, the Savannah River Site, and the Idaho
National Engineering Laboratory. Spent fuel clad with aluminum will be sent to
the Savannah River Site for interim storage, and spent fuel clad with stainless
steel will be sent to the Idaho National Engineering Laboratory. The Base Case
estimate assumes consolidated storage, shipment to a geologic repository, and
decommissioning of interim storage facilities.
Hazardous and Sanitary Waste - Site personnel provided all cost and
schedule estimates for hazardous waste and sanitary waste generated and/or
managed by the Environmental Management program. These estimates are based on
current and estimated future generation rates from sources both within the
Environmental Management program (e.g., environmental restoration activities)
as well as other Department of Energy sources (e.g., facilities operated by
Defense Programs). All hazardous and sanitary waste is assumed to be handled by
the Environmental Management program. Sanitary waste is either disposed of
onsite or in municipal landfills. Hazardous waste is sent to commercial vendors
for treatment and disposal.
Low-Level, Low-Level Mixed, Transuranic, and Transuranic Mixed Waste -
Site personnel provided all cost and schedule estimates for these waste types.
This entailed a significant effort to integrate data on current waste
inventories; the estimated volume and schedule for generating waste from
environmental restoration, nuclear material and facility stabilization, and
other Department of Energy activities; existing treatment, storage, and
disposal capacity; and estimates of future capacity. Some waste will be shipped
from one site to another for treatment and/or disposal; this required an
additional effort to integrate information on waste generation at the source
site and treatment or disposal capacity at the receiving site. The Baseline
Environmental Management Report Integration Tool, developed for the 1995
report, was used to assist in this integration effort. Current Department of
Energy plans call for disposal of transuranic waste at the Waste Isolation
Pilot Plant in New Mexico. Generating sites will treat and package transuranic
waste to meet the Waste Isolation Pilot Plant waste acceptance criteria. The
life-cycle estimate for this facility includes the costs for transporting the
packaged material, disposing it, and operations.
C.2.1.4 SCIENCE AND
TECHNOLOGY ACTIVITIES
Current funding for science and technology activities is approximately six
percent of the total Environmental Management program budget. The Department
assumed that science and technology funding would continue at this percentage
until 2030, when between 70 and 80 percent of the Environmental Management
program is expected to be completed.
C.2.1.5 LANDLORD ACTIVITIES
The Environmental Management program has landlord responsibilities at nine
Department of Energy sites (Table C-9). Personnel at these sites provided
estimates of annual landlord costs for the life of the Environmental Management
program at their site.
Table C-9. Sites at Which the Environmental Management Program Has Landlord
Responsibilities
| Energy Technology Engineering Center
Fernald Site
Grand Junction Projects Office
Hanford Site
Idaho National Engineering Laboratory
|
Oak Ridge K-25 Site
Pinellas Plant
Rocky Flats Environmental Technology Site
Savannah River Site
|
C.2.1.6 NATIONAL PROGRAM
PLANNING AND MANAGEMENT ACTIVITIES
Current funding for national program planning and management activities is
approximately four percent of the total Environmental Management program
budget. The Department assumed that the program management component of this
program element will be three percent of the total budget until FY 2000, two
percent from FY 2001 to FY 2020, and one percent thereafter. The program
direction component is assumed to be one percent throughout the life of the
Environmental Management program.
C.2.1.7 SUPPORT ACTIVITIES
The Environmental Management program performs many activities to accomplish its
varied missions, including remedial actions, decommissioning, constructing, and
operating waste management facilities. However, these "direct mission"
activities do not represent all of the Environmental Management program
activities and costs. The Environmental Management program must conduct
numerous "support" activities such as program management, infrastructure
support, and human resources, which are necessary to manage the ongoing work
associated with the program and maintain and operate the lands, facilities, and
other resources for which the program is responsible.
Environmental management support activities are classified into six general
categories and 29 specific categories for this analysis (Table C-10). To ensure
that support costs are accounted for completely in the 1996 Baseline
Environmental Management Report, the Department asked site personnel to
estimate support costs based upon two factors: (1) current levels of support
costs, and (2) how support costs are likely to change in the future as the
Environment Management program matures.
Table C-10. Environmental Management Support Activity Categories
| Management - Overall management activities, including
executive direction, contractor oversight, management/award fees, program
management, and quality assurance.
Finance and Administrative Services - General administrative activities,
including administrative support, chief financial officer, human resources,
information services, legal services, and training.
Environment, Safety, and Health - Activities associated with operating
facilities and lands safely. Includes traditional activities such as emergency
preparedness, fire protection, industrial safety, and occupational medicine
services as well as environmental monitoring, analytical laboratory support,
and pollution prevention.
Infrastructure - Activities associated with providing utilities,
maintenance, and general infrastructure for a site. Includes facilities
management/engineering and maintenance, logistics support, procurement, and
utilities.
Safeguards and Security - Activities associated with protection of
nuclear materials, nuclear weapons, classified information, and government
property from acts such as theft, sabotage, and espionage.
Stakeholders and Regulatory Interactions, and Other - Other types of
activities related to operating facilities and sites. Includes negotiating and
implementing agreements with stakeholders, economic development,
laboratory-directed research and development, media/communications, regulatory
compliance, stakeholder-related outreach, taxes, technology development, and
all other support activities.
|
Estimating current support costs - Most sites were asked to estimate
their total FY 1996 support costs by general functional category. The five
highest-cost sites were asked to provide rough estimates of funding levels for
each of the 29 specific support cost categories identified above. This required
examining all accounts and estimating what portion of those accounts are for
each support cost activity, using allocations and best professional judgment as
necessary. The objective was to understand the magnitude of support costs
relative to "direct mission" activities in a base year.
Estimating changes in support costs - To estimate future support costs,
and to support the alternate scenario analyses discussed below (Section C.3.2),
most sites were asked to estimate how costs for each of the six general support
cost categories would change in response to changes in "direct mission"
activities. The five highest-cost sites were asked to make these evaluations
for all 29 specific cost categories. Site personnel had the option of
forecasting support costs directly or completing a survey instrument to provide
input on these factors to a parametric model for estimating outyear support
costs. The survey responses were used to develop algorithms specific to each
site relating estimated costs for support activities to estimated costs for
"direct mission" activities. The Baseline Environmental Management Report
Integration Tool was modified to use these algorithms to project outyear costs.
Site personnel reviewed these forecasts to ensure their quality.
The survey instrument contained three sets of questions to elicit input factors
for the support cost algorithms:
(1) How would the costs for each support activity vary in response to a change
in environmental restoration, nuclear material and facility stabilization, or
waste management activities? Site personnel were asked to circle the
appropriate response in each row of the following matrix:
| Change in "Direct Mission" Cost
|
Change in Support Activity Cost
|
| + 100%
|
0%
|
+10%
|
+20%
|
+30%
|
+40%
|
+50%
|
+60%
|
+70%
|
+80%
|
+90%
|
+100%
|
| + 75%
|
0%
|
+10%
|
+20%
|
+30%
|
+40%
|
+50%
|
+60%
|
+70%
|
+80%
|
+90%
|
+100%
|
| + 50%
|
0%
|
+5%
|
+10%
|
+15%
|
+20%
|
+25%
|
+30%
|
+35%
|
+40%
|
+45%
|
+50%
|
| + 25%
|
0%
|
+2%
|
+4%
|
+6%
|
+8%
|
+10%
|
+12%
|
+15%
|
+18%
|
+20%
|
+25%
|
| - 25%
|
0%
|
-2%
|
-4%
|
-6%
|
-8%
|
-10%
|
-12%
|
-15%
|
-18%
|
-20%
|
-25%
|
| - 50%
|
0%
|
-5%
|
-10%
|
-15%
|
-20%
|
-25%
|
-30%
|
-35%
|
-40%
|
-45%
|
-50%
|
| - 75%
|
0%
|
-10%
|
-20%
|
-30%
|
-40%
|
-50%
|
-60%
|
-70%
|
-80%
|
-90%
|
-100%
|
| - 100%
|
0%
|
-10%
|
-20%
|
-30%
|
-40%
|
-50%
|
-60%
|
-70%
|
-80%
|
-90%
|
-100%
|
(2) How would the costs for each support activity vary as the Environmental
Management program matures? Site personnel were asked to circle the appropriate
response in each row of the following matrix:
| Maturity
|
Change in Support Activity Cost
|
| + 5 years
|
+100%
|
+75%
|
+50%
|
+25%
|
+10%
|
+5%
|
0%
|
-5%
|
-10%
|
-25%
|
-50%
|
-75%
|
-100%
|
| + 10 years
|
+100%
|
+75%
|
+50%
|
+25%
|
+10%
|
+5%
|
0%
|
-5%
|
-10%
|
-25%
|
-50%
|
-75%
|
-100%
|
| + 20 years
|
+100%
|
+75%
|
+50%
|
+25%
|
+10%
|
+5%
|
0%
|
-5%
|
-10%
|
-25%
|
-50%
|
-75%
|
-100%
|
| + 30 years
|
+100%
|
+75%
|
+50%
|
+25%
|
+10%
|
+5%
|
0%
|
-5%
|
-10%
|
-25%
|
-50%
|
-75%
|
-100%
|
| + 40 years
|
+100%
|
+75%
|
+50%
|
+25%
|
+10%
|
+5%
|
0%
|
-5%
|
-10%
|
-25%
|
-50%
|
-75%
|
-100%
|
(3) How would the costs for each support activity vary in response to changes in
any other factors? Site personnel were asked to provide a quantitative and
narrative discussion of these effects.
All support cost estimates were incorporated into estimates of Adirect mission@
activities to ensure that all costs were accounted for in the total program
cost estimate. Thus, support costs are not reported separately in the 1996
Baseline Environmental Management Report.
C.2.2 Assembling the Data
The Department used a nine-step process to assemble cost and schedule data prior
to the integration analyses (Table C-11). Each step is described below.
Table C-11. Steps in Gathering and Assembling Data
| 1. Develop analytical units for integration analyses
2. Define linkages between analytical units and to external data sources
3. Develop data collection software
4. Modify data dictionary and data formats and develop software for input to
Baseline Environmental Management Report Integration Tool
5. Perform initial quality assurance/quality control of data and identify
missing data
6. Modify data and fill in missing data using parametric models
7. Assemble preliminary data set for input into Baseline Environmental
Management Report Integration Tool
8. Perform final quality assurance/quality control on input data
9. Assemble final data set for input to Baseline Environmental Management Report
Integration Tool
|
Step 1- Develop analytical units for integration analyses
Information obtained for Environmental Management program activities included
anticipated starting dates and duration. The integration analyses for the Base
Case and alternative scenarios required the ability to revise starting dates
and durations in order to meet anticipated funding restrictions, allow for
capital costs of new waste management facilities, and ensure that remediation
and nuclear material and facility stabilization projects that would generate
waste would be coordinated with waste management capacity. The Department
therefore compiled information for each activity into analytical units for
purposes of integration and scheduling.
With two exceptions, the analytical units corresponded directly to the
Environmental Management activities defined earlier (see Section C.1.2).
Analytical units for environmental restoration activities were defined at a
lower level (the project level) to provide more flexibility in the integration
and scheduling analysis. The 295 environmental restoration activities were
subdivided into 936 projects. For waste management activities, the
uncertainties associated with future generation of low-level, low-level mixed,
transuranic, and transuranic mixed waste made it necessary during integration
to define "new" (hypothetical) facilities to manage this waste, particularly
later in the time period covered by this analysis.
Step 2 - Define linkages between analytical units and to external data sources
Building an integrated Base Case estimate requires an understanding of the
interdependencies between Environmental Management activities or projects
within, and in some cases, between sites. For example, the costs for managing
waste generated by an environmental restoration activity may be reported in a
waste management activity. In cases where this waste is generated at one site
and managed at another, the two interrelated activities will be at different
sites. In addition, some activities are sequentially related to one another.
For example, facility deactivation precedes facility decommissioning. Cross
linking efforts for the Base Case focused in two areas. (1) For all activities
expected to generate waste volumes, an attempt was made to identify the
specific waste management facility (project) at which that waste would be
managed. (2) Facility decommissioning projects were linked to specific
scheduling transfer units to ensure that deactivation and decommissioning
activities were fully linked.
Providing data sets for the alternative scenarios examined in the 1996 report
requires an understanding of the linkages between Baseline Environmental
Management Report activities and data bases in two key parametric models.
Environmental restoration core reporting levels were linked to a data base of
release sites (source areas) used by the Automated Remedial Assessment
Methodology to provide estimates of environmental restoration costs for
alternative land-use scenarios (see Section C.3.2.2). Data on existing and
planned waste management facilities (obtained from the field) were placed and
updated in the System Cost Model data bases to estimate waste management costs
for alternative scheduling analyses (see Section C.3.2.3).
Step 3 - Develop data collection software
To streamline the data collection and review process, the Department developed
software to collect and report Base Case data. These software applications were
seeded with data from the 1995 Baseline Environmental Management Report. Site
personnel modified and updated these data and provided missing data as
necessary and submitted the completed data packages. Key data included
duration, annual cost, annual waste volumes by type, anticipated start date,
and whether any portion of the element was included in a compliance agreement.
To improve overall efficiency, the software applications also were used to
collect other Environmental Management programmatic data not required
specifically for the 1996 Baseline Environmental Management Report but needed
for other analytical requirements.
Step 4 - Modify data dictionary and data formats and develop software for input
to Baseline Environmental Management Report Integration Tool
A set of specifications was developed for loading the Base Case data into the
Baseline Environmental Management Report Integration Tool for performing the
integration analyses (see Section C.3.1.1). The Department also developed
software to translate data from the data collection applications to the
Baseline Environmental Management Report Integration Tool. This software
application also assisted in quality assurance/quality control efforts.
Step 5 - Perform initial quality assurance/quality control of data and identify
missing data
Initial data submissions from the field were reviewed and evaluated.
Headquarters staff performed an initial screening of the data to ensure that
all needed data fields were completed in the correct format and that the data
were referenced adequately. Headquarters staff then performed a detailed
content review to determine whether all data elements required for the 1996
Baseline Environmental Management Report were provided and consistent with
overall program plans. Missing and problematic data were identified.
Step 6 - Modify data and fill in missing data using parametric models
Based on the above data reviews, site personnel corrected data errors and
omissions and re-submitted the completed data packages. Additional rounds of
review and quality assurance/quality control were performed as necessary.
Step 7 - Assemble preliminary data set for input into Baseline Environmental
Management Report Integration Tool
The Department translated data from the completed data packages into the
Baseline Environmental Management Report Integration Tool data formats.
Step 8 - Perform final quality assurance/quality control on input data
The translated data were loaded into the Baseline Environmental Management
Report Integration Tool. These data were used to provide a final quality
assurance/quality control check on the input data. Missing or problematic data
were provided or modified accordingly.
Step 9 -Assemble final data set for input to Baseline Environmental Management
Report Integration Tool
Following extensive review and quality assurance/quality control checks, the
final set of data representing the Base Case was assembled and loaded into the
Integration Tool data bases.
C.2.3 Verifying and
Documenting Data
Throughout the data assembly process, quality assurance reviews were performed
to ensure that the data used for the integration and scheduling analysis were
the most accurate and complete representation of the Environmental Management
program that could be provided to date. Data from all available sources were
checked to ensure completeness, avoid double-counting, and ensure smooth
integration of data from all sources. Internal consistency checks included a
mass balance accounting to ensure that all waste that the report assumed will
be generated is also assumed to be treated, stored, and/or disposed,
particularly when transfer from one site to another is anticipated.
Click Here for Page 2
Chapter -1- / -2- /
-3- / -4- / -5-
/ -6- / -7- /
-8-
Appendix -A2- / -B- /
-C- / -D- / -E1-
/ -E2- / -F- /
-G- / -H- / Glossary
|
 |