Home
BEMR Contents
U.S. Map
Back to Page 1
C.3 INTEGRATION ANALYSES
A variety of integration analyses was performed for the Base Case and
alternative scenarios. Section C.3.1 describes the approach used for the Base
Case; Section C.3.2 describes the approach used for the alternative scenarios.
C.3.1 Base Case Scenario
The Department used a 10-step process to develop the Base Case Scenario for the
1996 report (Figure C.1). Each step is described below.

Figure C.1. Steps in Developing the Base Case Scenario
Step 1 - Input data on cost, schedule, and waste volumes for each analytical unit
The final set of data representing the Base Case scenario was assembled and
loaded into the Baseline Environmental Management Report Integration Tool data
bases.
Step 2 - Calculate cost and waste volumes over time
The input data for the Base Case scenario included estimates of
when each activity would start and end, annual cost during that period, and
annual waste volumes generated during that period. In this step, cost and waste
volumes were summed to develop an initial schedule for the Environmental
Management program activities.
Step 3 - Compare waste volumes to treatment, storage, and disposal capacity
The initial schedule for waste generation was compared to the
schedule for waste treatment, storage, and disposal. Differences between total
volumes, annual profile of volumes, waste types, and treatability groups were
identified. Estimates of waste flows between sites made by both the sending and
receiving sites were compared and differences identified.
Step 4 - Define new treatment, storage, and disposal needs over time (if
necessary)
Differences between waste generation activities and waste treatment, storage,
and disposal schedules were resolved by working with the sites. Updates were
applied to the input data base.
Step 5 - Calculate new treatment, storage, and disposal costs over time
(if necessary)
Sites provided revised estimates of waste management costs based on the revised
treatment, storage, and disposal needs developed in Step 4. These revised
estimates were input into the Baseline Environmental Management Report
Integration Tool data bases.
Step 6 - Calculate total cost over time
Total costs and waste volumes were calculated with any changes applied in Steps
3 to 5.
Step 7 - Compare total program cost to funding levels
The initial total program cost estimate was compared to assumed annual funding
levels. Where costs exceeded assumed funding levels, rescheduling of activities
was necessary.
Step 8 - Reschedule activities as needed
Individual activities or projects were rescheduled manually to match more
closely cost and funding estimates. Rescheduling was performed jointly by
Department of Energy staff from Headquarters and sites. Steps 3 through 8 were
repeated as necessary until total program cost matched assumed funding levels
on an annual basis within a reasonable tolerance. This cost and schedule
estimate was considered the initial Base Case scenario.
Step 9 - Review Base Case scenario
Program managers at Headquarters and field sites reviewed the initial Base Case
scenario. Minor changes were made based on this review process.
Step 10 - Document final Base Case scenario
Department personnel documented the final Base Case scenario based on
programmatic review. Cost and schedule estimates, aggregated at the activity
level and shown for specific projects, are presented in the individual site
summaries presented in Volumes II and III of the 1996 report.
C.3.1.1 PERFORMING THE INTEGRATION
The integration analysis was performed jointly by Department of Energy staff
from Headquarters and the sites. The participation of site staff ensured that
the individual sites were cognizant of all changes in estimated schedule and
that all schedule changes were consistent with site-specific compliance
agreements, work sequencing, and other constraints. The integration and
scheduling analysis was aimed at smoothing projected costs and waste generation
rates to match available funding and waste management capacities. The only
"new" activities generated during this process were treatment, storage, and
disposal facilities needed to manage low-level waste, low-level mixed waste,
and transuranic waste generated from environmental restoration and nuclear
material and facility stabilization activities. Otherwise, the analysis only
moved project start dates for individual activities or projects backward or
forward in time.
Rescheduling required to meet funding or waste management capacity limitations
may result in differences between the schedule and funding profiles for
activities in the 1996 report and those in site baselines or other source
documents. Therefore, baselines and other documents in reading rooms and
elsewhere may not match up exactly with the Base Case in the 1996 report.
Certain general rules were used during the integration/scheduling process.
Projects under way in 1995 or scheduled to begin from 1995 to 2000 were not
rescheduled. Projects that are governed by existing compliance agreements were
not rescheduled regardless of starting date. No attempt was made to trade off
funding between sites. A flat funding assumption was applied to each site.
C.3.1.2 DOCUMENTATION
Department personnel developed a change control process for documenting all
changes in the input data and in scheduled starting dates for projects and
activities. This process included (1) operator procedures to be used at the
beginning and end of each session to document how the operator made changes in
the data base and (2) data manager procedures to merge changes made by multiple
operators into a single copy of the data base and to maintain appropriate
configuration control. A change control process also was used to manage revised
data submissions from the field sites.
C.3.2 Alternative Scenarios
The Base Case scenario incorporates a broad range of assumptions regarding the
eventual outcomes of various decisionmaking processes that will determine the
solutions applied to problems and the ultimate end states for Department of
Energy facilities. The final cost and schedule for the Environmental Management
program will depend considerably on decisions reached through processes
specified in the Comprehensive Environmental Response, Compensation, and
Liability Act, the Resource Conservation and Recovery Act, the National
Environmental Policy Act, and other environmental laws. It is important to
understand which decisions are likely to affect life-cycle cost and schedule
significantly as well as the potential magnitude of these effects. The
Department identified three general categories of decisions that have the
potential to affect significantly the life-cycle cost and schedule for the
Environmental Management program (Table C-12).
Table C-12. Types of Decisions Likely to Affect the Life-Cycle
Costs of the Environmental Management Program
| Land Use - What effect do future land-use decisions have on the overall
scope, cost, and schedule of cleanup for Environmental Management sites? What
factors limit consideration of land uses?
Program and Project Scheduling - What are the cost consequences of
delaying programs and projects? What is the relationship between program pace,
funding levels, and total life-cycle cost?
Minimal Action - What is the minimum funding required to prevent risks to
human health and the environment from increasing for 75 years without the
constraints of current legal requirements?
|
C.3.2.1 GENERAL APPROACH
With some modifications, the ten-step process used to develop the Base Case (see
Figure C-1) also was used to develop alternative scenarios. The modifications
generally consisted of either changing input data at the start of the process
or assumptions at specific steps during the process. The most significant
difference was that the alternative scenarios were evaluated only for the five
sites that had the highest life-cycle costs in the 1996 Baseline Report:
Hanford Site, Idaho National Engineering Laboratory, Oak Ridge Reservation
(consisting of the K-25 Site, the Y-12 Site, Oak Ridge National Laboratory and
Oak Ridge Associated Universities), Rocky Flats Environmental Technology Site,
and Savannah River Site). This limitation was imposed for several reasons.
First, the five highest-cost sites represent approximately 70 percent of the
total 1996 Baseline Environmental Management Report cost estimate; therefore,
changes from the Base Case estimates at these sites will have the greatest
influence on the total Environmental Management program cost. Second, many of
the highest-cost sites have developed tools and data sets for evaluating
programmatic alternatives; this allowed maximum use of previous analyses.
Third, plans for the final disposition of many of the other sites are well
developed (e.g., future-use plans have been made); therefore, there is less
uncertainty about the future of the Environmental Management program at these
other sites. Finally, focusing on the five highest-cost sites allowed the
Department of Energy to perform the alternatives analysis with efficiency
(i.e., obtain a high benefit with low cost).
The analysis of alternative scenarios for the 1996 report is a joint effort
between Headquarters and field personnel. This is an important improvement over
the approach used for the 1995 Baseline Environmental Management Report. For
the 1996 report, Headquarters developed the overall framework for the analyses,
provided written guidance, and developed survey instruments to assist in data
collection. Joint workshops were held at each of the five highest-cost sites to
enable field personnel to provide critical input on assumptions, determine the
data sources to use for the analyses, and determine the specific scenarios to
use for each analysis. For the Land-Use and Funding/Schedule analyses,
Headquarters assembled data provided by the field, used parametric models to
supplement missing data, and analyzed the alternative scenarios; the field
sites reviewed the results prior to publishing the 1996 report. For the Minimal
Action scenario, field personnel provided all alternative data.
A second improvement this year is the inclusion of examples illustrating how
risks may change for a project as part of the alternative scenario analyses.
This year's analyses begin to incorporate information on risk using an approach
that builds on the Risk Principles established by the Department and the
process used to develop Risk Data Sheets for the annual budget. Incorporating
these principles and processes, this year's analyses encompassed a "bottom-up"
process using site-driven methods, data sets, and assumptions.
C.3.2.2 LAND USE
The five highest-cost sites comprise over 470,000 hectares (1.16 million acres)
of federal land in a variety of environmental settings from saturated
bottomlands to high desert. While much of this land is uncontaminated, future
use of the land is driven not only by level of residual contamination but also
by its proximity to ongoing Department of Energy activities, permanent waste
disposal sites and other practical considerations. The analyses presented in
the 1995 Baseline Environmental Management Report suggested that land-use
decisions could change the total cost of the Environmental Management program
by hundreds of billions of dollars. This year's analyses focused on improving
on the 1995 analysis in three major ways (Table C-13). The first phase of the
analysis focused on two improvements: (1) verifying and quantifying the Base
Case assumptions on land use, remedial technology strategies, and problems with
no feasible solution; and (2) understanding the relationship between the Base
Case land-use assumptions and alternative land-use preferences being developed
by the Environmental Management program's Future-Use Project. The second phase
of the analysis focused on the third improvement, using each site's best
judgments on what future uses were feasible and what technology strategies
would be used to achieve those uses to evaluate costs and risks associated with
alternative land-use scenarios. Each of these two phases is described in detail
below.
Table C-13. Improved Focus of Land-Use Analyses
Verifying Base Case Assumptions - Ensuring
full understanding and quantification of Base Case assumptions on land use,
remedial technologies, and problems with no feasible solution.
Linking with Future-Use Planning - Understanding the
relationship between the Base Case land-use assumptions and stakeholder
preferred land-use alternatives.
Obtaining Field Input - Ensuring fullest use of
site-specific assumptions about what alternative land uses are feasible and
what technologies would be used to attain those alternative uses.
|
Verifying Base Case Assumptions - The Department used an eight-step
process to verify Base Case assumptions (Table C-14). Each step is described
below.
Table C-14. Steps in Verifying Base Case Assumptions
| 1. Develop land-use standards
2. Define technology strategy standards for each land-use category
3. Divide sites into geographical map units
4. Map Baseline Environmental Management Report projects and core reporting
levels into map units
5. Ensure that Base Case assumptions regarding current and future land use are
consistent with land-use standards
6. Compare Base Case technology strategies with technology strategy standards
7. Compare Baseline Environmental Management Report assumptions with Future-Use
preferences
8. Verify list of problems excluded from the Base Case because there is no
feasible solution
|
Step 1 - Develop land-use standards.
The Department developed operating definitions for six land-use categories for
this analysis (Table C-15). These standards provide a consistent basis for
quantifying and comparing land-use assumptions across the five highest-cost
sites. These standards are not intended to replace specific land-use
definitions at any site nor usurp the authority of each site to define land-use
categories.
Table C-15. Operational Definitions for Land-Use Categories
| Disposal/Storage Area
|
Restricted areas maintained by the Department for secure
storage or disposal of nuclear materials or waste. Access by unauthorized
persons is prevented via barriers and security forces. Wildlife and plants are
controlled or removed. This category also is known as "controlled access."
|
| Industrial
|
Active industrial facility where use of
ground water may be restricted depending on site conditions.
|
| Open Space
|
Posted areas reserved generally as buffer or wildlife
management zones. Native Americans or other authorized parties may be allowed
permits. Access to or use of certain areas may be prevented by passive barriers
(e.g., where soil is capped). Limited hunting or livestock grazing may be
allowed. Access to ground and surface water may be restricted.
|
| Recreational
|
Unfenced areas where daytime use for
recreational activities (e.g., hiking, biking, sports, hunting) and some
overnight camping is allowed. Fishing may be limited to catch-and-release. No
permanent residences are allowed. Access to ground water may be restricted.
|
| Residential
|
Unfenced areas where permanent residential use predominates.
There is no restriction on surface water use, but ground water use may be
restricted.
|
| Agricultural
|
Unfenced areas where subsistence or
commercial agriculture predominates without restriction on use of surface or
ground water.
|
Step 2 - Define technology strategy standards for each land-use category.
Technology strategy standards were developed for each land-use category.
Separate standards were developed for contaminated media, waste in storage, and
contaminated buildings. Table C-16 presents an example of these standards (for
contaminated media). These standards provide a consistent basis for comparing
and evaluating remedial technology strategies across the five highest-cost
sites. These standards are intended as a general description of the overall
technology strategy that would be used to meet a given land-use standard. It is
recognized that site-specific conditions may require deviations from the
overall strategy (e.g., removal of "hot spots" of soil contamination in an area
where the general strategy is containment of contamination via capping).
Table C-16. Environmental Management Technology Strategies for Contaminated
Media
|
| Storage/Disposal Area
|
contain |
contain
|
contain
|
no further action
|
contain contents, leave structure in place
|
remove or stabilize contents, leave structure in place
|
| Industrial
|
remove hot spots, otherwise contain
|
contain
|
contain
|
no further action
|
contain contents, leave structure in place
|
remove or stabilize contents, leave structure in place
|
| Open Space
|
remove hot spots, otherwise contain
|
contain
|
contain
|
no further action |
contain contents, leave structure in place
|
remove or stabilize contents, leave structure in place
|
| Recreational
|
remove hot spots, otherwise contain
|
contain
|
contain
|
dredge and remove hot spots and accessible areas
|
contain contents, leave structure in place
|
remove or stabilize contents, leave structure in place
|
| Residential
|
remove |
remove
|
remove/treat or contain
|
dredge and remove |
remove contents and structure
|
remove contents and structure
|
| Agricultural
|
remove
|
remove
|
remove/treat
|
dredge and remove
|
remove contents and structure
|
remove contents and structure
|
1 Underground tanks with petroleum products must be removed under
current law.
Step 3 - Divide sites into geographical map units.
The five highest-cost sites were divided into appropriate "map units" for this
analysis. Each map unit is comprised of a discrete geographical area based on
the types of problems, activities, and contamination present. For the most
part, the map units represented portions of the sites currently managed as one
regulatory or geographical unit (e.g., Waste Area Groups, operable units, or
other recognizable areas). The objective was to divide the sites into logical
"pieces" within which land-use standards and technology strategies would be
reasonably uniform. Thus, the process for verifying Base Case assumptions and
developing alternative land-use and technology strategies would be simplified.
Step 4 - Map Baseline Environmental Management Report activities and projects
into map units.
Crosswalks between activities and projects were developed and the geographical
map units defined above. Many activities and projects are defined
geographically (e.g., the 100 and 200 Areas at the Hanford Site); these
generally corresponded directly to the map units on a one-to-one basis. Other
activities and projects are more site-wide in nature (e.g., program management,
long-term surveillance and monitoring). These were either allocated by
percentage to the appropriate geographic areas or analyzed separately.
Step 5 - Ensure that Base Case assumptions regarding current and future land use
are consistent with standards.
Base Case assumptions were revised so that they were consistent with the
standard land-use categories and technology strategies defined above. In
many cases the Base Case assumptions were consistent with the standards, but
terminology differed. Some of the standards were modified to accommodate the
realities at each site. For example, the "open space" category was altered to
include "resource management" because some open space areas are effectively
wildlife preserves, some are used for cattle grazing, and others for controlled
hunting.
Two important distinctions were made during this verification process. The first
is the distinction between current land use at each site and the future
land-use assumptions that form the basis for the Base Case cost and schedule
estimates. The second is the distinction between residual contamination,
or how clean each area is at present or is anticipated to be after cleanup, and
the actual or anticipated use that the area can support, given both the
residual contamination as well as real world constraints. This latter
distinction is extremely important because certain lands managed by the
Environmental Management program are currently not contaminated (i.e., they
meet the residual contamination standards for any land use, including
agricultural) but are unlikely to ever be used for agricultural use. For
example, some uncontaminated land areas at the five highest-cost sites are
critical habitat for endangered or threatened species. Under current law, some
control over use of these lands to protect these species is likely, even though
the land and ground water are clean enough to support agriculture. An important
part of the verification process was to ensure identification of all
constraints on actual future use, including the presence of permanent storage
and disposal facilities and ongoing Department of Energy missions (e.g.,
Defense Programs, Energy Research).
Step 6 - Compare Base Case technology strategies with land-use standards.
Base Case technology strategies were compared with land use defined by residual
contamination and actual/anticipated use. One objective was to verify that the
technology strategy standards defined above were consistent with site-specific
technology strategies when aiming at a given residual contamination standard. A
second objective was to document instances where Base Case technology
strategies, governed by laws, regulations, and legal agreements, are aimed at
achieving residual contamination standards that are more (or less) stringent
than anticipated use.
Step 7 - Compare Baseline Environmental Management Report assumptions with
Future-Use preferences.
Headquarters and field staff worked jointly with representatives of the
Environmental Management program's Future Use Project to compare, and reconcile
where possible, Base Case anticipated use assumptions with preferred future
uses being developed in conjunction with stakeholders through the Future Use
Project. The 1996 report presents the Project assumptions and point out where
they are in conflict with Baseline Environmental Management Report Base Case
assumptions. This document provides a basis for continuing dialogue on future
land-use choices and how they will affect the Environmental Management program.
Step 8 - Verify problems excluded from Base Case because of no feasible solution.
Those problems excluded from the Base Case because they cannot feasibly be
remediated using existing technologies were identified. Reasons for such
exclusions include no suitable technology (e.g., certain contaminants cannot be
removed from ground water with current technologies), high collateral
ecological damage (e.g., draining a surface-water body to remove contaminated
sediments would severely damage the ecosystem), and excessively high cost
(e.g., remediating subsurface contamination from underground nuclear test
explosions can be accomplished with current technologies, but the cost would be
in the trillions of dollars).
Evaluating Alternative Land-Use Scenarios - A four-step process was used
to evaluate alternative land-use scenarios (Table C-17). Each step is described
below.
Table C-17. Steps in Evaluating Alternative Land-Use Scenarios
| 1. Define alternative scenarios
2. Develop site maps for each alternative scenario
3. Develop project cost and waste volume estimates for each alternative scenario
4. Develop integrated cost estimate for each alternative scenario
|
Step 1 - Define alternative land-use scenarios.
Using the verified Base Case as a point of departure, the effect of five
alternative land-use scenarios on the estimated life-cycle costs for the
Environmental Management program was evaluated: Maximum Feasible Green Fields,
Modified Green Fields, Recreational, Industrial, and Iron Fence. These five
alternative scenarios were chosen to represent varying land-use outcomes and
differing levels of cleanup. The Maximum Feasible Green Fields case and the
Iron Fence case were chosen to represent the two endpoints of the land-use
continuum. The Recreational scenario represents an intermediate land use
end-state without access restrictions, while the Industrial scenario represents
an intermediate land-use end state with access restrictions. The Modified Green
Fields represents a special scenario that illustrates how an aggressive cleanup
strategy might be tempered when considering continued Departmental missions.
Note also that the Iron Fence scenario is intended as the least-cost
alternative. Therefore, in a few instances where removal actions are less
costly than containment actions, the scenario selects the least-cost
alternative. The decision rules for developing these scenarios are described
below.
Maximum Feasible Green Fields - The decision rule requires that all
portions of the site be remediated to the Residential or Agricultural land-use
standard. All Department of Energy missions at the sites were assumed to end at
some future time. Most of the site-specific constraints noted below were
ignored, with the exceptions of technology challenges and a limited number of
disposal areas at the Hanford Site, Idaho National Engineering Laboratory, and
the Savannah River Site.
Modified Green Fields - The decision rule requires that all portions of
the site not meeting the site-specific constraints noted below be remediated to
the Residential or Agricultural land-use standard. Areas already achieving an
equivalent land-use standard need not be remediated at all. Areas that cannot
be feasibly remediated to these land-use standards should be remediated to the
greatest extent possible.
Recreational - The decision rule for this case requires that all portions
of the site not meeting the site-specific constraints noted below be remediated
to the Recreational land-use standard with water use restricted. Areas already
achieving equivalent or more stringent land-use standards (e.g., Residential)
need not be remediated at all. Areas that cannot feasibly be remediated to the
Recreational land-use standard should be remediated to the greatest extent
possible.
Industrial - The decision rule for this case requires that all portions
of the site not meeting the site-specific constraints noted below be remediated
to the Industrial land-use standard with water use restricted. Areas already
achieving an equivalent or more stringent land-use standard (e.g., Residential,
Agricultural) need not be remediated at all. Areas that cannot feasibly be
remediated to the Industrial land-use standard should be remediated to the
greatest extent possible.
Iron Fence - The decision rule for this case requires that all portions
of the site not meeting the site-specific constraints noted below be remediated
to the Disposal/Storage Area land-use standard. Areas already achieving an
equivalent or more stringent land-use standard (e.g., Agricultural) need not be
remediated at all. Areas that cannot be remediated to the Disposal/Storage Area
land-use standard should be remediated to the greatest extent possible.
Site-Specific Constraints - To ensure that the land-use analysis took
account of all site-specific constraints on future use, certain exceptions were
made for portions of the five highest-cost sites. For these circumstances, the
Base Case land-use assumptions (including cost and waste volume estimates) are
carried through each alternative scenario but are left unchanged. Criteria for
exceptions included legal decisions, contractual relationships, technical
limitations, and program plans:
-
Legal Commitments - A Record of Decision, contractual agreement or other
legally binding decision document (e.g., Corrective Measures under the Resource
Conservation and Recovery Act or specific conditions in a Consent Order) that
dictates future use has been signed, or local laws place restrictions on access
to ground water (e.g., the Snake River Plain Aquifer in Idaho).
-
Technical Constraints - Contamination problems that have no viable removal
strategies compatible with Agricultural or Residential use (e.g., ground water
contaminated with tritium) or present unacceptably high risks to workers using
conventional construction-type removal technologies.
-
Safeguarding of Natural, Historical, and Cultural Resources - The need to
maintain buffer zones supporting endangered species (e.g., the red-cockaded
woodpecker at the Savannah River Site) or ecologically unique habitats (e.g.,
the tall grass prairie at the Rocky Flats Environmental Technology Site) and
the need to preserve certain buildings as part of the nation's historical
heritage due to their role in developing nuclear weapons and energy.
-
Site Safety Considerations - The need to establish and maintain buffer zones
around ongoing or planned waste disposal areas (e.g., the 200 Areas at the
Hanford Site), storage of dangerous materials (e.g., special nuclear
materials).
-
Practical Constraints - The need to limit future use on certain areas due to
spatial relationships with other areas (e.g., clean parcels of land effectively
surrounded by industrial or waste storage/disposal areas cannot be effectively
used for many activities).
Step 2 - Develop site maps for each alternative scenario.
Once the alternative scenarios were defined, a set of maps was developed for
each site that presented final land-use assumptions under the four alternative
scenarios. As with the Base Case, these maps distinguish between the residual
contamination standards that can be achieved under each scenario and the
anticipated alternative uses. The maps also included the site's judgments about
the technology strategies that would be used to achieve the land uses specified
in each alternative scenario.
Step 3 - Develop project cost and waste volume estimates for each alternative
scenario.
Using the maps and assumptions developed above, alternative sets of cost and
waste volume data were obtained for all projects and activities under each
alternative scenario. These data were obtained using two general approaches. In
some cases, the sites provided alternative cost, waste volume, and project
duration estimates for specific projects or activities. Where sites were unable
to provide these estimates, Department personnel used the Automated Remedial
Assessment Methodology, a computer-based estimating tool (Table C-18). After
being calibrated to each site's Base Case assumptions, the methodology
estimated changes in cost, waste, and duration for environmental restoration
projects and activities. The alternative data sets were assembled and loaded
into the Baseline Environmental Management Report Integration Tool as input
data.
Table C-18. The Automated Remedial Assessment Methodology
| The Automated Remedial Assessment Methodology was developed for the Waste
Management Programmatic Environmental Impact Statement to provide relative
estimates of cost, labor requirements, and waste volumes generated from
alternative environmental restoration scenarios. Given a set of environmental
restoration goals (e.g., cleanup goals and points of compliance), the Automated
Remedial Assessment Methodology algorithms will (a) select remedial
technologies; (b) determine the effectiveness of each technology in destroying,
removing, or immobilizing contaminants; (c) determine the amount and type of
waste generated from using each technology; and (d) estimate the cost and labor
requirements for each technology. The Automated Remedial Assessment Methodology
is applicable to six types of environmental problems: contaminated soils,
buried waste, contaminated ground water, contaminated surface water, buildings,
and liquid containment structures.
The Automated Remedial Assessment Methodology is composed of four modules: (1)
Decision logic modules are used to select an applicable technology category
based on the environmental restoration goals, type of environmental problem,
contaminants of concern, and geological/climatological setting. (2) Technology
applicability rules are used to determine the constraints of applicability for
each technology category. (3) Technology effectiveness algorithms are used to
determine reductions in contaminant concentrations and waste volumes generated
from the application of technologies. (4) Cost and labor estimating factors are
used to estimate cost and labor requirements.
|
Step 4 - Develop integrated cost estimates for each alternative scenario.
Using the alternative data sets as inputs, the Baseline Environmental Management
Report Integration Tool was used to provide integrated cost and schedule
estimates for each alternative land-use scenario. Use of the Integration Tool
ensured that all estimates were fully integrated and that waste management and
support costs were adequately accounted. Costs for managing low-level,
low-level mixed, transuranic, and transuranic mixed waste were estimated using
the System Cost Model (Table C-19).
Table C-19. The System Cost Model
| The System Cost Model was developed for the Waste Management Programmatic
Environmental Impact Statement to estimate life-cycle costs for designing,
constructing, operating, and decommissioning treatment, storage, and disposal
facilities for low-level, low-level mixed, transuranic, and transuranic mixed
waste. The System Cost Model also estimates the cost of transporting waste or
resulting products from generator to treatment sites and from treatment to
storage sites. The user is required to identify the volume and nature of waste
to be managed, the time period over which the waste is to be managed, the type
and capacity of existing and planned waste management facilities, and where
waste generated at each site is to be treated, stored, and disposed. The System
Cost Model uses these input data and conceptual facility design criteria to
determine the ability of existing and planned facilities to manage the waste as
well as the type and size of new facilities that would be required. The System
Cost Model then uses documented cost equations to estimate the following
life-cycle costs associated with these activities:
Studies and bench scale tests, including manpower during research, equipment
installation, project management before Title I, and related contingency.
Demonstration, including manpower during demonstration, design, inspection,
project management, construction, construction management, management reserve,
and related contingency.
Construction, including design, inspection, project management, construction
management, management reserve, and related contingency.
Operation management, including conceptual design, safety assurance, permitting,
preparation for operations, and project management.
Operation and maintenance, including operations manpower, utilities, materials,
maintenance, and related contingency.
Decommissioning, including manpower, surveillance and maintenance, assessment
and characterization, environmental documentation review, operations, closure,
and post-closure monitoring.
|
C.3.2.3 PROGRAM AND PROJECT
SCHEDULING
The analyses presented in the 1995 Baseline Environmental Management Report
suggested that scheduling of Environmental Management activities has the
potential to affect life-cycle cost substantially. Changes in funding levels or
delays in the shipment of high-level waste and spent nuclear fuel to a geologic
repository may influence the pace and cost of the Environmental Management
program. To provide insight into the cost consequences of higher or lower
funding and project delays, the potential influence of funding and schedule on
life-cycle cost was evaluated. This year's analyses focused on improving the
1995 analysis in two major ways (Table C-20). First, the analysis focused on
developing an understanding of how the scope of work required to complete a
project would change if the starting date for that project were accelerated or
delayed. Second, the analysis focused on using each site's best judgment on the
most reasonable way to reschedule projects and activities to accommodate
funding constraints or delays.
Table C-20. Improved Focus of Program and Project Scheduling
Analyses
| Understanding Scope Growth - Obtaining a better understanding of how the
scope of work required to complete a project would change if that project were
accelerated or delayed.
Obtaining Field Input - Ensuring that site-specific understanding of
urgent risks, best management practices, and the inter-relationships between
projects is used to the fullest in determining which projects would be
accelerated or delayed under various funding assumptions.
|
Understanding Scope Growth
The Department used a two-step process to obtain a better understanding of scope
growth: (1) Defining scope growth for this analysis, and (2) Determining scope
growth factors for high-cost environmental management projects. Each of these
steps is described below.
Step 1 - Defining scope growth.
The Base Case cost and schedule estimate is based on numerous assumptions about
when activities and projects are expected to begin and end. Changes to that
schedule could affect the amount of work required to complete the activity for
many reasons. For example, a delay in starting a project could increase the
scope because of the spread of contamination in the environment or the
deterioration of a building or structure. Delays also may reduce the scope of a
project if, for example, significant radioactive decay occurs. Note that project
delays may result in missed compliance milestones, and the Department would be
liable for fines and penalties if such milestones were missed. This analysis
does not include the impacts of fines and penalties on total program cost.
The methodology used for the scheduling analyses in the 1995 Baseline
Environmental Management Report did not allow consideration of scope growth (or
decline). Three elements of scope growth were defined for this analysis:
Duration scope growth - Some activities are necessary to keep a waste, an
area, or a facility in a safe, secure state until a final cleanup action is
implemented. These activities (e.g., surveillance and maintenance, waste
storage) must be performed for safety and health reasons. Accelerating or
delaying cleanup actions will not affect these costs on an annual basis but
will affect how long these costs will be incurred. Thus, accelerating cleanup
actions will shorten these activities and reduce life-cycle costs, and delaying
cleanup actions will lengthen these activities and increase life-cycle costs.
Physical scope growth - Many environmental problems worsen over time. For
example, contaminant plumes may spread over a larger area; buildings, waste
storage containers, and tanks may deteriorate. A small number of problems
actually improve over time (e.g., short-lived radionuclides such as tritium
decay rapidly). Costs for Environmental Management activities will increase or
decrease as the physical nature of the problem changes. Where delaying a
project results in physical scope growth, project costs will increase.
Conversely, accelerating a project that has physical scope growth potential
will likely decrease project cost.
Fixed nature of support costs - A large portion of Environmental
Management program costs are not incurred for specific projects. Site- or
program-wide support activities include things such as information services,
general infrastructure support, and program management. The 1995 Baseline
Environmental Management Report analyses suggested that the costs for these
support activities are relatively fixed with respect to the level of "direct
mission" activities at the site. In other words, a site or program's support
costs would be similar whether two, four, or ten projects are in progress at
the site. Accelerating the completion of Environmental Management program
activities would reduce the number of years for which support costs would be
incurred and thus reduce the life-cycle cost for that site. Conversely,
delaying the completion of the Environmental Management program would increase
the number of years for which support costs are paid and increase life-cycle
cost.
Step 2 - Determining scope growth factors for highest-cost projects.
Headquarters and field staff worked jointly to identify the highest-cost
projects at each of the five highest-cost sites and estimate scope growth
factors for these projects. The analysis focused on the highest-cost projects
(those that represented 80 or 90 percent of total program costs) to gather the
greatest amount of data at least cost. Additional types of projects were
included in the analysis to obtain representative examples of all types of
environmental management activities.
For environmental restoration and nuclear material and facility stabilization
activities, Headquarters personnel developed a survey instrument to estimate
scope growth factors associated with delays of 5, 10, 25, and 50 years or
acceleration of 5 or 10 years. Field personnel completed the surveys. Scope
growth factors for each project were based on total project cost (i.e., a scope
growth factor of 2 indicated that the project would be twice as expensive). The
field personnel also estimated increases or decreases in waste volumes
associated with acceleration or delays. Headquarters and field personnel
reviewed the surveys at joint site workshops to finalize the scope growth
estimates. The scope growth factors were used to modify Base Case cost
estimates for each project during the analysis phase described below.
The approach for determining scope growth for waste management activities
depended on the type of waste. For high-level waste and spent nuclear fuel,
sites provided alternative life-cycle cost estimates for each of the funding
and schedule scenarios. In some cases, more than one estimate was provided for
each scenario (e.g., two or three separate estimates were prepared for the
reduction in funding scenario to reflect several levels of reduced annual
funding). Scope growth for low-level, low-level mixed, transuranic, and
transuranic mixed waste was estimated using the calibrated System Cost Model
(see Table C-19). The model calculates duration scope growth associated with
prolonged periods of waste storage. Costs for hazardous and sanitary waste are
sufficiently low that these waste streams were not included in this analysis.
Evaluating Alternative Program and Project Scheduling Scenarios
The Department used a three-step process to evaluate alternative program and
project scheduling scenarios: (1) Define alternative scenarios; (2) Develop
scheduling priorities based on scope growth factors, and (3) Develop an
integrated cost estimate for each alternative scenario. Each step is described
below.
Step 1 - Define alternative program and project scheduling scenarios.
Using the Base Case schedule as a point of departure, the effect of three
program and project scheduling scenarios on the estimated life-cycle costs for
the Environmental Management program was evaluated: Accelerating Stabilization
and Deactivation, Funding Reduction, and Delaying Waste Disposal. The
rationale, assumptions, and decision rules for these scenarios are described
below. All scenarios assume that existing compliance agreements may not be met
and that no fines or penalties will be assessed as a consequence.
Accelerating Stabilization and Deactivation - Surveillance and
maintenance activities are required to maintain nuclear material and
contaminated facilities in a safe condition prior to stabilization and
deactivation. These costs decrease, often dramatically, after nuclear material
stabilization and facility deactivation actions are completed. This case
examines how the total cost of the Environmental Management program could be
reduced by accelerating stabilization and deactivation and how much additional
funding would be necessary for this acceleration. Also examined in this case
are the cost savings achievable from the reduced support costs associated with
more rapid completion of stabilization and deactivation activities. This
analysis assumes:
-
Funding for environmental restoration and waste management activities is the
same as in the Base Case, but otherwise funding will increase sufficiently to
stabilize all nuclear materials by FY 2002 and deactivate all facilities by FY
2010.
-
Only nuclear material and facility stabilization projects will be accelerated.
-
A geologic repository for high-level waste and spent nuclear fuel will open as
scheduled in the Base Case.
Funding Reduction - This scenario evaluates the impacts of
across-the-board reductions in the Environmental Management program budget.
This analysis assumes:
-
Funding is reduced for the duration of the Environmental Management program to
$4.9 billion (in constant 1996 dollars).
-
Projects with high scope growth will be accelerated and projects with little or
no scope growth will be delayed.
-
There are no constraints on funding allocation/reallocation, so that funds can
be shifted from one type of activity to another (e.g., from environmental
restoration to waste management).
-
Shipments of high-level waste and spent nuclear fuel to a geologic repository
may not occur as scheduled in the Base Case.
Delaying Waste Disposal - The final case analyzes the effect of a delay
in shipments of high-level waste and spent nuclear fuel to a geologic
repository. Delays in shipments to a repository will force the Environmental
Management program to store these materials for a longer period of time. For
this analysis:
-
Funding for environmental restoration and nuclear material and facility
stabilization activities are the same as in the Base Case, but funding for
waste management activities will increase to cover the increased storage costs.
-
Disposal of high-level waste and spent nuclear fuel is delayed. Treatment
activities will be completed using the Base Case schedule, but post-treatment
storage will continue until shipments to a repository are completed.
-
Acceptance of Department of Energy high-level waste and spent nuclear fuel at a
geologic repository is delayed for 30 years.
Step 2 - Determine scheduling priorities based on scope growth factors.
Using the scope growth factors defined above, and site-specific understanding of
urgent risks and project inter-dependencies, priorities for rescheduling
projects to meet the parameters of the three funding and schedule scenarios
were developed. Where funding constraints are critical (e.g., in the funding
reduction scenario), efforts ensured that delays were assigned to a
sufficiently large number of projects to meet the reduced funding limits. These
priorities were used to accelerate and delay projects in the integration
analysis described in Step 3.
Step 3 - Develop integrated cost estimate for each alternative scenario.
The first part of this process was to revise the Baseline Environmental
Management Report Integration Tool to apply scope growth factors as projects
are rescheduled (i.e., annual costs for each activity were inflated or deflated
based on the scope growth/decrease factors). Using the assumptions and
scheduling priorities developed in the first two steps, Headquarters staff
rescheduled projects in a manner that attempted to minimize the cost for each
case. Using the revised schedules, the Integration Tool recalculated project
costs and associated support costs. Waste management costs for low-level,
low-level mixed, transuranic, and transuranic mixed waste were recalculated
using the calibrated System Cost Model. All annual costs were summed and
compared to funding limit assumptions. Projects were rescheduled as necessary
to meet funding limits. Final alternative life-cycle costs were aggregated and
reported for each scenario.
C.3.2.4 MINIMAL ACTION
The assumed strategies in the Base Case reflect actions required by regulations
or compliance agreements and/or likely to be acceptable to internal and
external stakeholders. These actions are likely to go beyond those required to
safeguard waste and surplus materials in an efficient, cost-effective manner.
For example, regulations or agreements may require complete treatment and
disposal of a volume of radioactive waste when safe, long-term storage of all
or a portion of that volume would be feasible and cost-effective. Similarly,
program plans may call for complete decontamination and dismantlement of a
surplus facility when entombment would be feasible and cost-effective.
The analyses presented in the 1995 Baseline Environmental Management Report
suggested that adopting a "minimal action" strategy could reduce the annual
costs of the Environmental Management program in the near term, but long-term
surveillance and monitoring costs would increase. The methodology used for that
report did not allow the Department to determine how low the annual costs could
go by pursuing this type of strategy. The objective of this year's analysis has
been to develop a scenario which will minimize the total cost of the
Environmental Management program over the next 75 years without increasing
risks to offsite populations, onsite workers, or ecological receptors (except
where such increases are a necessary component of actions taken to reduce other
risks). The first phase of this analysis focused on defining the general
principles and guidelines for this analysis and site-specific assumptions for
the five highest-cost sites. The second phase focused on using each site's best
judgments on how the program would change to estimate the costs and risks
associated with this scenario. Each of these phases is described in detail
below.
Defining General Principles and Guidelines - The minimal action scenario
combines elements of urgent risk reduction, mortgage reduction, minimum action,
regulatory relief, prudent management practices, and institutional controls
into an overall strategy aimed at (1) minimizing risks to public health,
workers, and the environment, and (2) minimizing cost during the minimal action
period (75 years). Increased risks and costs after the end of the
minimal action are permitted. The following general principles guided
development of this scenario:
-
Use institutional controls. The Federal Government will maintain
control of federal lands.
-
Assume regulatory relief. All actions must meet minimum onsite
worker safety standards, but are not necessarily in compliance with current
environmental, safety, and health laws and regulations unless needed to meet
the above-stated goals.
-
Address urgent risks. All urgent risks must be reduced through
actions such as stabilizing unstable materials as needed to meet the
above-stated goal; moving waste from unsafe storage into safe storage as needed
to meet the above-stated goal; intercepting plumes at the installation
boundary; stabilizing high-risk nuclear materials; deactivating high-risk
facilities; and removing and vitrifying unstable high-level waste.
-
Pursue mortgage reduction. High mortgages must be reduced through
actions such as stabilizing nuclear materials and deactivating facilities with
high surveillance and maintenance costs and completing technology development
to support the above actions and the above-stated goals.
-
Minimize waste treatment. Waste treatment should be minimized to the
extent necessary to meet the above-stated goal through actions such as
stabilizing or continuing to monitor high-level waste in place (except urgent
risk tanks), maintaining spent nuclear fuel in safe (dry) storage, placing
other radioactive or mixed waste in permanent storage, minimizing shipments of
high-level waste and spent nuclear fuel to a geologic repository, and
completing technology development to support the above actions and the
above-stated goal. In each case, the 75-year costs associated with the "treat
and store/dispose" versus "store only" strategy were compared to identify the
minimum cost option that is consistent with the above-stated goals.
-
Minimize remediation and facility decommissioning. Remedial actions
and decontamination and decommissioning should be minimized to those necessary
to meet the above-stated goal through actions such as maximizing No Further
Action sites, maximizing containment and entombment strategies, and completing
technology development to support the above actions and the above-stated goals.
In each case, the 75-year costs associated with the "removal" versus
"containment" strategy were compared to identify the minimum cost option that
is consistent with the above-stated goals.
-
Minimize stabilization and deactivation. Stabilization and
deactivation efforts should be minimized to those necessary to meet the
above-stated goal through actions such as minimizing removal of contaminated
equipment, minimizing removal of materials in pipelines and ducts, and
completing technology development to support the above actions and the
above-stated goals. In each case, the 75-year costs associated with the
"complete" versus "partial" stabilization/deactivation strategy were compared
to identify the minimum cost/effort option that is consistent with the
above-stated goals.
-
Minimize support and technology development costs. Support and
technology development costs should be minimized to those necessary to support
the above actions and the above-stated goals through actions such as minimizing
support costs and identifying where emerging and new technologies can enable
cost savings or changes in program/project priorities.
-
Pursue prudent management practices. More "complete" actions (e.g., full
stabilization, complete decontamination and decommissioning, waste treatment
and disposal) should be pursued if the 75-year costs for these actions are
lower than the above actions.
Using the above general principles, field personnel developed site-specific
assumptions for Environmental Management activities at their sites. Although
specific assumptions varied somewhat among the five highest-cost sites, there
was considerable convergence in these assumptions.
-
Contaminated environmental media. No further action will be taken
for the majority of problems unless they pose urgent environmental of human
health risk within the next 75 years. A limited amount of removal and
containment strategies will be used for problems where contaminants are
spreading rapidly onsite or offsite.
-
Special nuclear material. All nuclear material stabilization
activities will be completed as planned in the Base Case to reduce urgent risks
and high mortgages. Materials will be consolidated into central long-term
storage facilities at each site.
-
Contaminated buildings. For large, heavily contaminated buildings,
nearly all facility deactivation activities will be completed as planned in the
Base Case to reduce urgent risks and high mortgages. In some cases, less
stringent deactivation strategies will be followed (i.e., more contamination is
left in place). Facility decommissioning activities will be reduced
significantly. Most large structures will be entombed. Most smaller buildings
will be deactivated and decommissioned consistent with prudent management
practices.
-
Spent nuclear fuel. Spent nuclear fuel will be placed in dry storage
and left onsite for the 75-year period. No fuel will be shipped to a geologic
repository.
-
Low-level, low-level mixed, transuranic, transuranic mixed, and special case
waste.
Most waste will be placed in long-term storage and left onsite for the 75-year
period. Storage facilities will meet safety requirements but generally will not
meet Resource Conservation and Recovery Act requirements.
-
Hazardous and sanitary waste. This waste will be managed in
accordance with Base Case assumptions.
-
High-level waste. Strategies for this waste differ among sites. At the
Savannah River Site, all high-level waste will be vitrified and placed in
onsite storage because the vitrification facility is operational and the tanks
pose high risks due to their age and proximity to ground and surface waters. At
the Idaho National Engineering Laboratory, all high-level waste will be
calcined and placed in above-ground storage. At the Hanford Site, single-shell
tanks containing high-level waste will be stabilized and the waste will remain
in these tanks with continuous surveillance and maintenance. High-level waste
in double-shell tanks will be consolidated into two tanks that will be replaced
every 50 years.
Evaluating the Minimal Action Scenario - The Department used a two-step
process to evaluate the cost and risk implications of the minimal action
scenario. The first step was to develop alternative cost estimates; the second
was to evaluate the long-term cost and risk implications. Each step is
described below.
Step 1 - Developing alternative cost estimates.
Headquarters personnel developed a survey instrument to assist the field staff
in developing alternative cost estimates. The survey instrument identified the
highest-cost projects at each site (generally in the top 80 or 90 percent). For
each project, the survey instrument contained the Base Case cost estimates by
activity and time (in five-year increments). Using these data as a guide, site
personnel provided alternative cost and schedule estimates using available
site-specific sources (e.g., Environmental Impact Statements, other planning
initiatives and best professional judgment). Site personnel also provided
estimates of how support costs would change under the minimal action scenario,
largely based on best professional judgment. Headquarters collected the survey
instruments and aggregated the data for the 1996 report. No changes to the data
were made at Headquarters.
Step 2 - Evaluating the long-term cost and risk implications.
Each site submission described the end states resulting at the end of the
Minimal Action period in terms of the physical conditions at the site (e.g.,
number of buildings still standing and amount and form of waste onsite). Site
submissions identified problems that posed a significant liability (a) during
the first 100 years following the Minimal Action period and (b) over the longer
term (that is, 1,000 years following the Minimal Action period). The
submissions by each site also identified the types of hazards associated with
these liabilities, the types of receptors (that is, public, worker, or
ecological) that might be exposed to these hazards, and the types of exposure
scenarios that might result in risks.
C.3.3 Risk
One of the responsibilities of the Environmental Management program is to safely
manage the risks and hazards associated with cleaning up radioactive waste and
materials left from more than 50 years of research, development, testing,
production of nuclear weapons, and other defense and nondefense activities.
This responsibility makes it important to consider risks and hazards when
developing and evaluating programmatic alternatives. Because the Baseline
Report is not a planning or decisionmaking document, a vigorous assessment of
all the risk consequences associated with each alternative scenario was not
performed. However, since it is important to demonstrate that risk to human
health and the environment can be affected when changing program cleanup
strategies, specific project case studies were provided by the sites as input
to the alternatives analyses. These case studies illustrate the importance of a
comprehensive evaluation of risk before implementing any changes in
Environmental Management program strategies.
The primary objective of evaluating risk in the Baseline Report is to identify
areas where land use designations or rescheduling of projects may have the
potential to significantly affect human health and safety or drastically impact
environmental conditions. The Department used a field-driven approach for the
case study examples to ensure that the data and methodology used to develop
risk estimates are consistent with those used in the annual budget process
(i.e., Risk Data Sheets) and familiar to site-specific stakeholders.
Personnel at each of the five highest-cost sites were requested to use the
methodologies and approaches currently employed in the field to estimate the
differences in risk on selected projects between the Base Case and alternative
scenarios evaluated for the 1996 report. A new risk evaluation methodology was
not developed. Site personnel were also requested to be consistent with the
risk information they are providing for the 1998 budget formulation process,
where such information is appropriate. Headquarters staff developed the overall
framework and guidelines for the analysis, but personnel at the sites developed
all assumptions and methods used to evaluate risks associated with the Base
Case and alternative scenarios.
Site personnel were specifically requested to assess risk before, during, and
after an activity was complete. The before evaluation is defined as the
risks or hazards posed by the conditions at the site prior to initiating
activities. The during evaluation is defined as the risks or hazards
posed by the conditions at the site while the actual activity (i.e.,
remediation) is occurring. These risks and hazards are typically those risks to
workers involved in the activity. The after evaluation is defined as the
risks or hazards posed by the conditions that remain at the site after the
activity has been completed and no further work is planned.
The case study examples provided by the sites include an evaluation of potential
impacts to onsite personnel, workers, the public, and the environment. Site
personnel were encouraged to focus on a few key projects or activities where
risk information is critical to the decisionmaking process.
C.4 ESTIMATING PROGRAM IMPROVEMENTS
The Department evaluated potential impacts of two types of program improvements
on the estimated total life-cycle cost of the Environmental Management program:
technology development and pollution prevention. Each of these potential
improvements is discussed in a separate section below.
C.4.1 Technology Development
The Base Case cost and schedule estimates are based on the use of existing
technologies (e.g., no cost savings from the use of emerging technologies has
been assumed). The Department used a three-step process to estimate potential
cost savings from the successful application of 37 emerging technology systems
and subsystems: (1) Develop an implementation scenario for each alternative
technology; (2) Calculate raw cost savings for substituting an alternative
technology for a Base Case technology on a unit cost basis; and (3) Develop
"success coefficients" to adjust the raw cost savings estimates to reflect
uncertainties in how widely applicable the alternative technologies may be and
real-world constraints in substituting technologies, such as regulatory
acceptance. Appendix F presents a detailed description of the methods and
results of the technology development analysis.
C.4.2 Pollution Prevention
The Environmental Management program has initiated an aggressive pollution
prevention/waste minimization program to reduce costs and waste generation. For
the 1996 report, the Department evaluated potential life-cycle savings from 24
past pollution prevention projects, 26 ongoing field projects, 13 more recent
pilot demonstrations, and 40 new projects approved for funding in FY 1996.
Actual savings achieved from past projects were extrapolated for a period of 10
years (the useful life of most pollution prevention efforts) to obtain a total
program cost estimate. Appendix G presents a detailed description of the
methods and results of the pollution prevention analysis.
C.4.3 Productivity
Productivity initiatives in the Environmental Management program were initiated
in 1993. Because these initiatives are recent, there are little historic data
regarding Environmental Management program productivity. In preparing cost
estimates for the 1996 report, site personnel were requested to estimate the
productivity savings they expect to achieve in comparison to the 1995 Baseline
Environmental Management Report. These productivity savings are incorporated
into the mid-range Base Case estimate of $227 billion. The Department also
estimated the magnitude of potential cost reductions if additional productivity
can be achieved in the outyears. For this estimate, the Department assumed a
one percent annual productivity improvement from FY 2001 through FY 2070 (the
historical annual productivity gains for public sector agencies). The
Department also evaluated the total cost estimate if the field-based
productivity estimates were ignored by adding the field site's estimated
productivity savings to the mid-range Base Case estimate.
C.5 DEVELOPING DOCUMENTATION
The Department prepared the 1996 report to summarize the background for this
effort, methods used to develop life-cycle estimates for the Base Case and
alternative scenarios, and results of the analyses. The report was prepared by
Headquarters staff and reviewed throughout Headquarters.
The Department also prepared individual reports for each site (see Volumes II
and III). These include background information about the site, description of
the problems being addressed by the Environmental Management program, and
descriptions of the types of remedies assumed to be used for each problem.
Results of the Base Case analysis are reported by Environmental Management
program element and activity level, and for major projects. Headquarters
activities are reported in a separate site summary. Site summaries were
reviewed throughout Headquarters and the field.
C.6 STAKEHOLDER INVOLVEMENT
The 1995 National Defense Authorization Act directed the Secretary of Energy to
consult with appropriate stakeholders in developing the 1996 Baseline
Environmental Management Report. The Department's efforts are summarized in
Table C-21 and described below.
Table C-21. Stakeholder Participation Activities Related to the
1996 Baseline Environmental Management Report
| May 1995 - Public Participation Plan and Guidance issued
May 1995 - Site-level interactions initiated to discuss 1995 Baseline
Environmental Management Report, assumptions, and exclusions
July 1995 - National stakeholder meeting in Denver, Colorado
September 1995 - Briefing to the Environmental Management Advisory Board
September 1995 - Site-specific interactions concerning the initial 1996 results
initiated (ongoing)
June/July 1996 - The 1996 report will be available on the Internet (planned)
|
The Department developed and issued in May 1995 a comprehensive public
participation plan to guide stakeholder involvement efforts for the 1996
report. Opportunities for stakeholder involvement throughout the planning and
development stages of the 1996 report were provided by many sites and are
detailed in Volumes II and III. Public participation efforts had three goals:
-
Obtain feedback on the 1995 Baseline Environmental Management Report,
site-specific assumptions for the 1996 Baseline Environmental Management
Report, and the proposed lists of activities and projects for the 1996 Baseline
Environmental Management Report.
-
Engage stakeholders in evaluating alternative scenarios for the 1996 Baseline
Environmental Management Report.
-
Seek stakeholder input on the analytical process used to develop the 1996
Baseline Environmental Management Report.
Headquarters staff were responsible for stakeholder involvement at a national
level, presenting information and taking comments at a number of national fora
that addressed program-wide issues. The goal of the July 1995 meeting, for
example, was to integrate a broad set of stakeholder perspectives early in the
1996 Baseline Environmental Management Report development process. The agenda
included discussion of the results of the 1995 Baseline Environmental
Management Report, new requirements for the 1996 Baseline Environmental
Management Report, and the proposed technical approach and methodology. Both
site leads and Headquarters staff were assigned to ensure that comments
received at these fora formed the basis for action items to incorporate changes
in assumptions and other aspects of the methodology into the 1996 report.
Personnel at each site were responsible for site-level stakeholder involvement.
The general strategy was for sites to use existing fora to inform the public
and solicit input on both national and site-specific levels. Specific
activities varied among sites but included the following:
-
Distributing brochures, fact sheets, and newsletters at related forums.
-
Publishing notices of availability of the 1995 Baseline Environmental
Management Report.
-
Placing the 1995 Baseline Environmental Management Report in Department of
Energy reading rooms.
-
Mailing information to local stakeholders.
-
Issuing articles and press releases.
-
Holding stakeholder meetings and workshops.
-
Making presentations to advisory boards.
-
Taking and responding to public comments.
Both Headquarters and site personnel completed Public Comment Records that
tracked activities, comments, and the status of action items. This record was
available to all Headquarters staff involved in production of the 1996 Baseline
Environmental Management Report and to designated coordinators at the sites. It
also will be available to stakeholders upon request.
C.7 BASE CASE UNCERTAINTY ANALYSIS
The objective of the uncertainty analysis is to establish a reasonable range
around the Base Case life-cycle cost estimate. The analysis is based on
information provided by the sites on the level of confidence in their project
life-cycle cost estimates. In general, the data were provided at the project
level for over 1,300 estimates. Site personnel rated the estimates in three
categories: high confidence, medium confidence, and low confidence. An example
of the question used to rate the level of confidence in environmental
restoration projects is shown in Table C-22.
Table C-22. Sample Data Collection Question for Level of
Confidence Analysis
| Rate the level of confidence in the cost data and estimating
techniques used for this true subproject. Valid responses are:
Low (e.g., given the projected scope, cost estimates are extremely uncertain and
could be + or 100% or more)
Medium (e.g., given the projected scope, cost estimates are somewhat uncertain
and could be + or 50%)
High (e.g., given the projected scope, cost estimates are likely to be accurate
within + or 25%)
|
Using the confidence ratings, a low, most likely, and high estimate were
established for each project. For example, a $10 million project estimate with
a medium confidence rating would yield a $5 million low cost estimate, a $10
million most likely estimate, and a $15 million high estimate. All projects
that did not have an assigned confidence rating (approximately 6 percent of the
project estimates) assumed a value of medium confidence. Using the three
estimates for each project (low, most likely, and high), a mean and standard
deviation were calculated to establish a normal distribution. A Monte Carlo
simulation was conducted across all of the estimates to generate a range of
possible total life-cycle cost estimates. The simulation was run for 1,000
trials. To account for outliers, the range produced by the simulation was
adjusted to three standard deviations around the mean estimate.
The use of Monte Carlo simulation has a number of important limitations. First,
the simulation assumes independence among all of the projects. Certainly, many
projects are related and the availability of funds for one project could
greatly influence other projects. Second, the use of a normal distribution may
not reflect the true distribution of uncertainty in this class of projects. Two
other distributions (triangular and log-normal) may be more representative, but
the normal distribution was selected. Finally, the level of confidence ratings
were collected at the project level and did not take into account the effects
of time. Consequently, the level of confidence is the same whether it is the
first year or the last year of the project. Since the uncertainty surrounding
the estimate is likely to increase over time, the simulation may have
underestimated the uncertainty range.
Back to Page 1
Chapter -1- / -2- /
-3- / -4- / -5-
/ -6- / -7- /
-8-
Appendix -A2- / -B- /
-C- / -D- / -E1-
/ -E2- / -F- /
-G- / -H- / Glossary
|
 |