About DOE Button Organization Button News Button Contact Us Button
Go Button
US Department of Energy Seal and Header Photo
Science and Technology Button Energy Sources Button Energy Efficiency Button The Environment Button Prices and Trends Button National Security Button Safety and Health Button
Office of Environmental Management
EMPDC

CONTACT EM
Content suggestions or technical issues regarding this site should be sent to

Office of Environmental Management

Nevada State Map

Nevada Test Site

Nye County, Nevada

Office: Nevada Operations Office

Size: 864,000 acres (1,350 square miles)

Mission: The Nevada Test Site, created in the early 1950s, is used as a detonation and testing range for both nuclear and non-nuclear weapons.

Overview of Environmental Conditions: Contamination of onsite groundwater and soil resulting from both nuclear and non-nuclear weapons testing activities.

CERCLA/RCRA Remediation Funding in FY 95: $31,502,000

The environmental restoration activities at the Nevada Test Site are being conducted under DOE authorities. Negotiation of an FFA with the State of Nevada was initiated in FY 93 under RCRA and the Atomic Energy Act. Negotiations are expected to be completed during the second quarter of FY 96. A Draft Sitewide Environmental Impact Statement has been prepared and is expected to be distributed for public comment in February 1996.

Specific Cost Estimates and Budgetary Proposals

Funds budgeted for environmental restoration for Nevada Test Site total $45.4 million of appropriated funding for FY 96 and $51.1 million for FY 97 according to the request in the President's Budget.

Progress in Conducting Remedial Actions

DOE submitted a PA and draft Hazard Ranking System scores for the Nevada Test Site and eight offsite locations to EPA Region IX on April 15, 1988. DOE has since rescored the Nevada Test Site, using the revised Hazard Ranking System. The Hazard Ranking System package was resubmitted to EPA Region IX in December 1991. The Nevada Test Site is being evaluated for potential listing on the NPL by EPA. Although EPA Region IX recommended that the site be listed, EPA has made no final decision.

Remediation activity undertaken thus far has centered on continued research into the development of a process to remediate large areas of soils contaminated with plutonium from past activities. Five bench-scale technologies have been tested. A preliminary risk assessment and a draft cost benefit analysis for these contaminated soil sites were completed. Technology development of radiation detection systems for plutonium also continued. In addition, an effort to identify, verify, and document all potential release sites, known as the Environmental Restoration Sites Inventory, was initiated. Progress on the Underground Test Area Operable Unit also continued.

The Nevada Test Site continues remediation of inactive underground storage tanks.

There were several RCRA closure activities initiated during FY 95. Decommissioning of the Junior Hot Cell and SAFER closure of the 5 Point Landfill at the Tonopah Test Range were completed. The Interim Actions completed during FY 95 included removal of 12 underground storage tanks and 10 abandoned septic tanks. Four assessments were also completed in FY 95.

Work performed during 1995 for the Groundwater Characterization Project, renamed the Underground Test Area RI/FS Project, includes drilling of several new and reconfigured wells, development of a subproject work plan, and data analysis and modeling studies. The Underground Test Area RI/FS project regional groundwater model and risk assessment are scheduled for completion in late 1996.


Last Updated 3/24/2009
The White House Link: Energy.Gov/RECOVERY FirstGov.gov Link: Privacy Program E-gov IQ FOIA
U.S. Department of Energy | 1000 Independence Ave., SW | Washington, DC 20585
1-800-dial-DOE | f/202-586-4403