 |
Hanford Site
Richland, Benton County, Washington
|
|
Office: Richland Operations Office
Size:
359,680 acres (562 square miles)
NPL Status:
Four areas were placed on the NPL on October 4, 1989 (Areas 100, 200, 300, and
1100).
Mission:
Chosen in 1943 for the Manhattan Project, the Hanford Site was used to produce
plutonium for the world's first nuclear weapons. Today the focus of activities
is site cleanup and environmental restoration; scientific and environmental
research; development and application of radioactive waste and hazardous waste
management technology; and design, construction, and operation of major
energy-related test and development facilities.
Overview of Environmental Conditions:
Onsite soil, groundwater, and sediment contamination by various hazardous and
radioactive substances. Various levels of radionuclides are also routinely
identified in the Columbia River.
CERCLA/RCRA Remediation Funding in FY 95: $132,820,000
|
Progress in Reaching Interagency Agreement
DOE, EPA Region X, and the State of Washington negotiated and signed the
Hanford Federal Facility Agreement/Consent Order (hereafter referred to as the
Tri-Party Agreement) on May 15, 1989. This Tri-Party Agreement provides the
framework for effective investigation of waste sites and subsequent remediation
of hazardous and mixed waste contamination at Hanford. An annual update is
prepared to address additional problems and to incorporate schedules agreed to
in approved RI/FS Work Plans or other work scopes agreed to by the three
parties. Revision 2 of the Tri-Party Agreement was published in September 1992,
which included the second and third amendments to the Consent Order.
On May 23, 1993 negotiations began on significant changes to the Tri-Party
Agreement. Change for CERCLA activities included development and inclusion of
milestones related to the proposed Environmental Restoration Disposal Facility,
consolidation of the 300 Area OUs into a single CERCLA project, and accelerated
groundwater remediation projects. The Environmental Restoration Disposal
Facility incorporated NEPA values into the CERCLA process as a result of the
Environmental Restoration Disposal Facility exemption from NEPA in the 1993
Tri-Party Agreement negotiations. Moreover, under CERCLA, the Environmental
Restoration Disposal Facility is exempted from having to obtain permits. The
amended Tri-Party Agreement was signed on January 25, 1994.
In July 1994, the DOE, EPA Region X, and the Washington State Department of
Ecology agreed to negotiate on matters related to Hanford's "Refocusing
Environmental Restoration" program. The parties agreed to negotiate cleanup
schedules in order to achieve earlier remediation of sites along the Columbia
River, and to increase emphasis on protecting and remediating groundwater. In
addition, the parties agreed to consult with affected Indian Nations and other
stakeholders to seek and respond to their values and concerns. The parties
concluded formal negotiations on September 30, 1994, and the amended Tri-Party
Agreement was signed on July 28, 1995 after a 45-day public comment period.
Negotiations on Amendment 6 are expected to be completed in October 1995, and
the public comment period is expected to end in December 1995. This amendment
primarily addresses ways of becoming more efficient and cost-effective within
the framework of the Tri-Party Agreement. The proposed changes fall into these
broad categories:
|
1) |
|
Single Regulator Approach (eliminating support agency
staffing); |
| 2) |
|
Eliminating current Tri-Party Agreement Project
Manager positions and providing unit managers and their line managers with
increased responsibility and authority regarding their projects; and |
| 3) |
|
Streamlining the dispute resolution/decision-making
process. |
For detailed information regarding the Tri-Party Agreement, see the FY 91
CERCLA 120 Report to Congress.
Specific Cost Estimates and Budgetary Proposals Involved in Each Interagency
Agreement
Funds budgeted for CERCLA activities in the environmental restoration program
under the Tri-Party Agreement total $110 of appropriated funding for FY 96 and
$90.9 for FY 97 according to the request in the President's Budget.
Public Comments Regarding Interagency Agreements
Amendments and updates to the Tri-Party Agreement are subject to public comment
periods prior to signature by the three parties. The most recent Tri-Party
Agreement renegotiation package underwent 45 days of public comment during
1995. The amendment was signed by the three parties on July 28, 1995. For
detailed information regarding the Tri-Party Agreement comment process, see the
FY 91 CERCLA 120 Report to Congress. All future changes to the Tri-Party
Agreement will also be subject to public review and comment.
Progress in Conducting the Remedial Investigations/Feasibility Studies
The Hanford Site includes a broad range of waste units that contain either
radioactive, hazardous, mixed (both radioactive and hazardous), or
nonradioactive/nonhazardous solid waste. Certain hazardous substances and
hazardous wastes remain on and under the Hanford Site and have been detected in
groundwater and surface water. An estimated 5 billion cubic yards of solid and
dilute liquid waste, including hazardous substances, mixed waste, and hazardous
waste and constituents, have been disposed of at the Hanford Site.
All remediation work at the Hanford Site is included within four NPL sites (the
100, 200, 300, and 1100 Areas), 74 source OUs containing 1,249 identified
hazardous waste sites (985 past-practice sites), and 4 groundwater OUs. OUs
were prioritized by EPA and the State of Washington in 1989 for investigation
based on an initial assessment of environmental risk.
The following activities were accomplished during FY 95:
100 Area
-
Eight CERCLA PPs were submitted to the regulators for the 100-BC-1, 100-BC-2,
100-BC-5, 100-DR-2, 100-FR-1, 100-KR-1, 100-KR-4, and 100-HR-2 OUs;
-
The burial ground excavation treatability test at 118-B-1 was completed;
-
A CERCLA ROD was issued for the 100-BC-1, 100-DR-1, and 100-HR-1 OUs; and
-
Nine Focused FS Reports were submitted to the regulators for the 100-BC-1,
100-BC-2, 100-BC-5, 100-DR-2, 100-FR-1, 100-KR-1, 100-KR-4, and 100-HR-2 OUs.
200 Area
-
One CERCLA PP was submitted for the 200-UP-1 OU;
-
The 200-BP-5, 200-ZP-1, and 200-UP-1 pump and treat treatability tests were
completed. Pump and treat will continue at 200-ZP-1 and 200-UP-1 as part of the
remediation. It was determined that extraction rates were insufficient to be
effective at 200-BP-5, and this pump and treat operation was terminated;
-
The Environmental Restoration Disposal Facility CERCLA ROD was issued and
construction started;
-
A CERCLA ROD was issued for remediation at the 200-ZP-1 OU to address
groundwater contamination;
-
A Focused FS Report for the construction of Engineered Barriers to isolate
underground waste was submitted; and
-
A Limited Field Investigation Report for the 200-UP-2 OU was submitted.
300 Area
-
A Phase 3 FS Report was submitted for the 300-FF-5 OU;
-
A Phase 2 RI Report was submitted for the 300-FF-5 OU; and
-
A Limited Field Investigation Report was submitted for the 300-FF-2 OU.
1100 Area
-
Assessment activities in the 1100 Area were completed before FY 95 began.
Progress in Conducting Remedial Actions
Under the Hanford Site Past Practice Strategy, sites that pose a threat to
human health and the environment are identified. These sites are considered for
Expedited Response Actions (ERAs).
The following ERA activities were accomplished in FY 95:
100 Area
-
The N-Springs ERA is located near the N-Reactor. Past liquid effluent
discharges have led to strontium-90 radionuclide releases along the southern
bank of the Columbia River, known as N-Springs. In August 1995 operations of a
groundwater treatment system at N-Springs began. DOE plans to decide on the
technical feasibility of installing an underground barrier wall in FY 96 to
further inhibit contaminant movement.
200 Area
-
The 200 West Area carbon tetrachloride treatment site (located in the 200-ZP-2
OU) vapor extraction continues. The system is now automated. Through September
1995, more than 140,000 pounds of carbon tetrachloride have been removed.
There were no ERAs done during FY 95 in either the 300 or 1100 Areas.
Other accomplishments include:
100 Area
-
6,800,000 gallons of groundwater have been pumped and treated at the 100-HR-3
OU.
200 Area
-
Pump and treat is continuing as remediation in the 200-ZP-1 and 200-UP-1 OUs;
4,200,000 gallons and 4,900,000 gallons respectively have been treated through
FY 95 at these OUs.
300 Area
-
The PP for the 300-FF-1 and 300-FF-5 OUs is currently out for public review.
Remediation will begin after issuance of a PP and ROD.
1100 Area
-
Cleanup of the 1100 area was completed in FY 95. The 1100 area cleanup
consisted of excavation of PCB-contaminated soil from the Horn Rapids Landfill
and Ephemeral Pool and construction of a cap. In addition, smaller stained soil
sites were cleaned up by excavating and disposing of the materials offsite. The
1100 Area is primarily used as a vehicle garage and maintenance area for the
Hanford Site.
Enforcement Activities
In October 1990, DOE stopped construction of the low-level mixed waste
laboratory (Milestone M-14-00) in order to review options for obtaining
analytical services from commercial laboratories. DOE subsequently resumed
construction of a smaller laboratory. In October 1991, DOE submitted a request
to change Milestone M-14-00 from construction of a laboratory to assurance of
adequate laboratory capacity for mixed waste samples under the IAG. This
request was denied by EPA and the State of Washington in November 1991, and DOE
initiated dispute resolution under the IAG. In April 1992, the Senior Executive
Committee agreed on a proposal to resolve the issue. As a result of the delay
in schedule, and based on public comment, the state required further changes to
the agreement to mandate that analytical laboratory services be acquired in the
vicinity of Hanford. In addition, the state required DOE to pay a $100,000
penalty, to perform an ERA of the N-Springs, and to establish IAG milestones
for completion. DOE is committed to complete existing (approved) ERAs and the
N-Springs response action.
DOE has completed an EE/CA for the N-Springs ERA. DOE has also received an
Action Memorandum from the Washington State Department of Ecology directing it
to proceed with the selected alternative of barrier wall construction and
emplacement of a groundwater pump and treat operation. During February 1995,
initial tests to drive a barrier wall into the ground at the N-Springs were
unsuccessful. DOE and the regulators plan to make a decision on the technical
feasibility of the barrier wall in February 1996.
|