About DOE Button Organization Button News Button Contact Us Button
US Department of Energy Seal and Header Photo
Science and Technology Button Energy Sources Button Energy Efficiency Button The Environment Button Prices and Trends Button National Security Button Safety and Health Button
Office of Environmental Management
  You are here: Skip Navigation LinksEM Home > Resources > Related Publications > Fiscal Year 1995 Progress in Implementing Section 120 of the CERCLA, September 1996 (Historical) > IV. Site Summaries for Facilities on the NPL (By State) > Weldon Spring Site Remedial Action Project, St. Charles County, Missouri

Office of Environmental Management

Missouri State Map

Weldon Spring Site Remedial Action Project

St. Charles County, Missouri

Office: Oak Ridge Operations Office

Size: 226 acres (0.4 square mile)

NPL Status: Quarry placed on the NPL on July 22, 1987 and Chemical Plant and Raffinate Pits placed on the NPL on March 13, 1989.

Mission: The Weldon Spring Site was developed by the U.S. Army for explosives production during World War II, and was operated by the Atomic Energy Commission from 1955 to 1966 as a uranium processing plant.

Overview of Environmental Conditions: Soil, surface water, groundwater, and building rubble contamination resulting from the handling and disposal of uranium ore concentrates and scrap.

CERCLA/RCRA Remediation Funding in FY 95: $41,403,000

Progress in Reaching Interagency Agreement

DOE and EPA Region VII entered into an FFA, signed on August 12, 1986. An amended FFA was signed on June 30, 1992.

Specific Cost Estimates and Budgetary Proposals Involved in Each Interagency Agreement

Funds budgeted for environmental restoration under the FFA at the site total $58.5 million of appropriated funding for FY 96 and $67.5 million for FY 97 according to the request in the President's Budget.

Public Comments Regarding Interagency Agreements

The public comment period for the FFA began on March 22, 1992 and remained open for 45 days. No comments were received during this period.

Progress in Conducting Remedial Investigations/Feasibility Studies

Initial work was started under a CERCLA/NEPA FFCA executed in 1986. Subsequently, the site was placed on the NPL in July 1987. The Weldon Spring Site project issued a work plan in August 1988 which presented the overall strategy for accomplishing remedial actions. That strategy included the development of an umbrella RI/FS for the Chemical Plant Area, an RI/FS for Quarry bulk wastes, an RI/FS for Quarry residuals, and several interim response actions. A need was subsequently identified to specifically address groundwater at the Chemical Plant Area through an additional RI/FS.

Major accomplishments in FY 95 include:

  • Completed the joint RA Work Plan for the Site Groundwater Operable Unit with the Department of the Army in May 1995.

  • Completed the Site Groundwater Sampling Plan in August 1995.

Progress in Conducting Remedial Actions

Remedial actions accomplished during FY 95 include:

  • Completed construction and initiated testing of the Pilot Sludge Processing Facility in December 1994.

  • Completed acquisition of 2 million cubic yards of soil in the Soil Borrow Area from the State of Missouri in July 1995. This Area will be utilized during disposal facility construction.

  • Demolished the last 4 buildings in the demolition packages in December 1994. To date, 43 of the 44 buildings have been demolished.

  • As of September 1995, treated a total of 100 million gallons of water at the Quarry Water Treatment Plant and Site Water Treatment Plant.

  • Completed excavation of 72,883 cubic yards in the Quarry bulk waste removal effort in September 1995, for a cumulative excavated volume of 116,000 cubic yards (approximately 96 percent of the total anticipated volume).

  • Expect to complete construction of the Site Water Treatment Plant-Train 2 facilities in October1995.

The White House FirstGov.gov E-gov IQ FOIA
U.S. Department of Energy | 1000 Independence Ave., SW | Washington, DC 20585
1-800-dial-DOE | f/202-586-4403

Web Policies | No Fear Act | Site Map | Privacy | Phone Book | Employment