Policy on Decommissioning of Department of Energy
Facilities Under the Comprehensive Environmental Response, Compensation, and
Liability Act (CERCLA)
May 22, 1995
Purpose
This Policy establishes the approach agreed upon by the Department of Energy
(DOE) and Environmental Protection Agency (EPA) for the conduct of
decommissioning projects [1]
consistent with CERCLA requirements. This Policy creates a framework for the
conduct of decommissioning of DOE facilities and provides guidance to EPA
Regions and DOE Operations Offices on the use of CERCLA response authority to
decommission such facilities. The principal objectives of this Policy are to
ensure that decommissioning activities are protective of worker and public
health and the environment, consistent with CERCLA and, where applicable, the
Resource Conservation and Recovery Act (RCRA), ensure stakeholder involvement,
and achieve risk reduction without unnecessary delay.
This Policy builds on the foundation established in the recent EPA/DOE/DOD
"Guidance on Accelerating CERCLA Environmental Restoration at Federal
Facilities" (August 22, 1994). Specifically, this Policy represents the next
step in realizing the goal of that guidance to "develop decisions that
appropriately address the reduction of risk to human health and the environment
as expeditiously as the law allows." To achieve that end, this Policy endorses
the use of removal action authority to conduct decommissioning, although DOE
and EPA recognize that removal action will not necessarily be the final
response action needed at a facility subject to decommissioning.
The DOE Office of Environmental Management (EM), and EPA Federal Facilities
Restoration and Reuse Office (FFRRO) and Federal Facilities Enforcement Office
(FFEO) have developed this approach for applying CERCLA authority to
decommissioning activities to encourage streamlined decisionmaking in
decommissioning activities.
Background
Executive Order 12580 "Superfund Implementation" delegates from the President
to the Secretary of Energy certain CERCLA response authorities for facilities
under DOE jurisdiction, custody, or control. The EPA/DOE/DOD "Guidance on
Accelerating CERCLA Environmental Restoration at Federal Facilities" (August
22, 1994) reaffirms this point, stating that "federal agencies, other than EPA,
have jurisdiction for carrying out most response actions at federal facility
sites. As EPA is not the lead agency at such sites, its role is different from
that at other Superfund sites." Consistent with Executive Order 12580, the
National Contingency Plan (NCP) designates DOE as the lead agency for
responding to releases on, or where the sole source of the release is from, a
facility under DOE's jurisdiction, custody, or control. As lead agency, DOE is
authorized to conduct removal action, remedial action, and any other response
measures consistent with the NCP. The exercise of such response authority must
be in accordance with the requirements of section 120 of CERCLA. For facilities
that are listed on the National Priorities List (NPL), section 120 of CERCLA
requires DOE and EPA to enter into an Interagency Agreement (IAG), which
establishes requirements for remedial action at the facility. Therefore, the
roles and authority of DOE and EPA will be defined, in part, by the terms of
such agreement. For non-NPL facilities, DOE may take response action subject to
CERCLA, the NCP, and other applicable requirements.
DOE will utilize CERCLA response authority whenever a hazardous substance is
released, or there is a substantial threat of release, into the environment,
and response is necessary to protect public health, welfare, or the
environment. DOE Order 5400.4 requires DOE to respond to any release or
substantial threat of a release of a hazardous substance into the environment
in a manner consistent with CERCLA and the NCP, regardless of whether or not
the release or threatened release is from a site listed on the NPL.
The definition of "environment" includes all natural media under U.S.
jurisdiction. CERCLA does not generally address releases which are entirely
within buildings because the presence of hazardous substances within a building
does not constitute a release of such substances into the environment.
Hazardous substances within a building, however, may pose a substantial threat
of a release that may require a CERCLA response. Determining whether a threat
of a release is substantial will depend on the specific circumstances present
at a facility.
Under the authority delegated by Executive Order 12580, DOE is responsible for
evaluating site conditions to determine if conditions or anticipated activities
at facilities subject to decommissioning pose a substantial threat of release.
So that EPA can fulfill its responsibilities to ensure compliance with CERCLA
requirements, including remedy selection, [2]
at NPL facilities, DOE Operations Offices will consult with EPA Regions and
share information as determined by the DOE Operations Office and affected EPA
Region. In the event EPA disagrees with DOE's determination as to the presence
of a release or substantial threat of release, EPA and DOE should make every
effort to resolve the dispute in a manner satisfactory to both parties. If
resolution is not possible and EPA determines that a threat of release is
substantial, then under section 106 of CERCLA, with the concurrence of the
Attorney General, EPA may order DOE to take appropriate action. EPA may also
issue a CERCLA section 106 order to any other party, including past or present
DOE contractors, that is liable under CERCLA section 107. EPA may further
exercise any authority that is provided under an applicable IAG to "stop work"
until EPA concerns are satisfactorily addressed. RCRA authorities may also be
available to EPA. Specifically, these authorities may address waste management,
corrective action, and closure requirements that may be established or enforced
through regulations, permits, orders, or agreements.
Scope and Applicability
This Policy applies to all decommissioning projects to be conducted by DOE.
Decommissioning projects that have selected the removal alternative as of the
date this Policy is adopted are not subject to this Policy. Such projects are
encouraged, however, to proceed in a manner consistent with this Policy to the
maximum extent practicable.
Decommissioning of facilities that are subject to the requirements of an
interagency agreement (IAG) in effect on the date this Policy is adopted will
be conducted in accordance with such requirements. When existing IAGs are
renegotiated or amended, or new agreements are adopted, any requirements
applicable to decommissioning activities should be in accordance with this
Policy.
CERCLA Response Action to Decommission Facilities
The NCP recognizes DOE as lead agency for the purpose of determining whether
response action is necessary to protect health, welfare, or the environment,
and what type of response is most appropriate under the circumstances presented
by the site. Response action may be taken when DOE determines that the action
will prevent, minimize, stabilize, or eliminate a risk to health or the
environment. When DOE determines that CERCLA removal action is necessary, DOE
is authorized to evaluate, select, and implement the removal action that DOE
determines is most appropriate to address potential risks posed by the release
or threat of release. The selection and implementation of such response should
comply with the requirements of CERCLA, the NCP, and other applicable
authorities. EPA has responsibility to oversee compliance with these
requirements.
Although the full range of CERCLA response actions may be applicable to
decommissioning activities, non-time critical removal actions should be used
for decommissioning, consistent with this Policy. The alternative approaches
available to conduct decommissioning projects typically are clear and very
limited. This often will eliminate the need for the more thorough analysis of
alternatives required for remedial actions. Non-time critical removal action
requirements provide greater flexibility to develop decommissioning plans that
are appropriate for the circumstances presented. Statutory time and dollar
limits on removal action do not apply to removal action conducted by DOE, which
increases the scope of projects that may be addressed by DOE removal action.
Most importantly, non-time critical removal actions usually will provide
benefits to worker safety, public health, and the environment more rapidly and
cost-effectively than remedial actions. For these reasons, DOE may exercise
removal action authority to conduct decommissioning whenever such action is
authorized by CERCLA, the NCP, and Executive Order 12580. To ensure an adequate
regulatory role in the removal planning and decision process, EPA Regions are
encouraged to communicate with DOE Operations Offices concerning the level of
consultation EPA believes is appropriate for specific decommissioning projects.
Such an approach will provide greater assurances that the removal action will
be consistent with CERCLA requirements and any subsequent remedial action that
may be necessary.
DOE Operations Offices will determine that removal action is appropriate for a
particular project before proceeding. The scope of activities that qualify as
removal actions under CERCLA includes site security or control precautions to
reduce access or migration, stabilization of structures or buildings,
consolidation or removal of substances or structures, and any other actions
deemed necessary by the lead agency. Any activity that reduces risks or
potential risks in a relatively short time-frame and can be identified as
appropriate with a relatively limited amount of analysis of alternatives may be
taken under removal action authority. CERCLA requires that removal actions
should, to the extent practicable, contribute to the efficient performance of
any long term remedial action conducted at the site.
DOE Decommissioning Program
The DOE Decommissioning Program will conduct decommissioning activities in
compliance with applicable requirements of CERCLA and the NCP. The decision to
conduct decommissioning may be based on any change in the facility's condition
that may trigger a need to respond to protect health or the environment, or any
other factor that leads DOE to determine that decommissioning of the facility
is appropriate. DOE will conduct a removal site evaluation as directed by the
NCP to assess site conditions and determine whether a release or substantial
threat of release exists at the facility. At any facility for which DOE
conducts a removal site evaluation, DOE will consult with EPA and will provide,
as requested, EPA with such information necessary for EPA to review such
evaluation. At any facility where DOE determines that a release or substantial
threat of release has not occurred, DOE will consult with EPA and provide any
information necessary for EPA to evaluate such determination.
Both DOE Operations Offices and EPA Regions must take a good faith approach to
assessing potential decommissioning projects. Unless the circumstances at the
facility make it inappropriate, decommissioning activities will be conducted as
non-time critical removal actions. Non-time critical removal actions generally
will provide the most appropriate level of analysis, oversight, public
participation, and flexibility to conduct decommissioning in a cost-effective
manner that fully protects health and the environment. Using non-time critical
removal action authority will enable DOE to exercise the flexibility provided
in the NCP to reduce risks and achieve results without unnecessary expenditure
or delay.
Compliance with Applicable Requirements, Permits, Agreements, and Orders
Decommissioning activities must comply with all applicable requirements
established by any existing IAGs, Federal Facility Agreements (FFAs), Site
Treatment Plans required under the Federal Facility Compliance Act, permits and
orders issued pursuant to authorized State or Federal programs, and other
applicable requirements. Decommissioning activities should comply with relevant
and appropriate standards to the extent practicable, as provided by the NCP,
and as necessary to contribute to the efficient performance of any long term
remedial action.
- In particular, States authorized by EPA to implement and enforce State
hazardous waste programs in lieu of RCRA may have authority under such programs
to enforce requirements applicable to decommissioning activities. These
requirements include waste management, corrective action, and closure
requirements which may be established or enforced through regulations, permits,
orders, or agreements. The degree to which State hazardous waste and other
requirements may affect decommissioning projects will depend on a number of
site-specific factors including the scope of State authorization, and whether
the facility to be decommissioned is included within a RCRA-permitted facility
or is otherwise subject to RCRA requirements. EPA and DOE intend to work with
authorized States to coordinate RCRA and CERCLA authorities to the maximum
extent practicable in order to prevent unnecessary duplication or delay in
decommissioning projects subject to both authorities.
EPA Involvement
DOE lead agency responsibilities for determining whether response action is
warranted, and what type of response is appropriate, must be coordinated with
EPA oversight and remedy selection authority [3]
for facilities included in sites listed on the NPL. Clarifying the integration
of DOE and EPA responsibilities at facilities included within a site listed on
the NPL and subject to decommissioning is essential to achieving streamlined,
effective response action that fully protects human health and the environment.
To achieve coordinated integration with respect to decommissioning, this Policy
establishes guidelines for defining the appropriate level of EPA consultation
and stakeholder participation.
EPA involvement with DOE decommissioning activities on NPL sites will depend on
the complexity and potential risk to health and the environment posed by the
facility to be decommissioned. EPA involvement should focus on key documents
and decision points in the removal action process. The NCP requires EPA
approval of sampling and analysis plans developed in accordance with section
300.415(b)(4) of the NCP. EPA involvement may be appropriate with respect to
other steps in the removal process.
The extent of EPA involvement will be determined by the EPA Region and DOE
Operations Office responsible for the facility, based on the circumstances
presented by each facility. Factors to be considered in determining EPA
involvement in decommissioning projects include complexity, severity of
potential risks, duration, cost, and appropriateness of applying EPA resources
to the project. Where no IAG exists for the site, or where an existing IAG does
not address decommissioning in general, or specific facilities appropriate for
decommissioning in particular, the DOE Operations Office and EPA Region should
identify the steps in the removal action process where EPA involvement can be
most effective. In particular, EPA involvement should ensure that
decommissioning activities comply with applicable requirements, that protection
of health and the environment is achieved, and that decommissioning is
consistent with ongoing or subsequent remedial actions at the site.
Stakeholder Involvement
Decommissioning activities will be conducted in full compliance with the
community relations and public participation requirements established by
CERCLA, the NCP, and DOE policies. The nature and scope of these stakeholder
involvement requirements will depend on the type of removal action taken. All
non-time critical removal actions will comply with the public participation
requirements applicable to such actions outlined in the NCP. Where applicable,
a formal community relations plan (CRP) will be prepared, specifying the
community relations activities to be conducted during the removal. The CRP will
be prepared prior to completion of the analysis of removal alternatives. In
addition, stakeholders will be provided notice and an opportunity to submit
comments on the analysis of removal alternatives. Written responses to public
comments will be prepared.
DOE will establish an Administrative Record as provided by CERCLA section 113
and the NCP for non-time critical removals. The Administrative Record will
include the results of the removal site evaluation and other factual
information and analyses upon which the decision to conduct response action was
based. As additional information is developed that forms the basis for
selection of the response action, such information will be included in the
Administrative Record. The Administrative Record will be accessible to the
public, consistent with the requirements of the NCP. Public comments, and DOE's
response, will be included in the Administrative Record.
Conclusion
Use of non-time critical removals for conducting decommissioning activities
effectively integrates DOE lead agency responsibility, EPA oversight
responsibility, and stakeholder participation. The DOE Decommissioning Program
will utilize DOE expertise in devising and implementing appropriate solutions
to decommissioning projects. Effective EPA oversight and stakeholder
participation will be provided in compliance with applicable requirements.
Decommissioning projects will retain sufficient flexibility to tailor
activities to meet specific site needs, and achieve risk reduction and
restoration expeditiously.
* * * * *
This policy and any internal procedures adopted for its implementation are
intended exclusively for employees of the U.S. Environmental Protection Agency,
for employees of the U.S. Department of Energy, and for DOE contractors. This
guidance does not constitute rulemaking by the Agency and may not be relied
upon to create a right or benefit, substantive or procedural, enforceable at
law or in equity, by any person. The Agency may take action at variance with
this guidance or its internal implementing procedures.
|