End Points Management
End Points Management
The Need for End Point Specifications
The policy of the EM is that a formal project management approach be used for the
planning, managing, and conducting of its projects. A fundamental premise of project
management for facility deactivation is answering the question:
How do you know when the project is complete?
|
Just as the design specifications
are essential to a construction project, specifying "end points" is the key to answering
this question for a deactivation project. A requirement to specify end points (DOE
O 430.1A, LIFE CYCLE ASSET MANAGEMENT, Section 6.g) is used to establish
a facility's conditions when deactivation is complete. |
Definition: End-State
vs. End Points
End-state has been used to refer to the overall status and disposition of a facility
after deactivation. End Points refer to the detailed specifications for the condition
of spaces, systems, and equipment within a facility, and related documentation.
Either way, the terms refer to conditions of a facility at the completion of the
deactivation project.
|
|
Specifying and achieving end points is a systematic, engineering way of proceeding
from an existing condition to a stated desired final set of conditions in which
the facility is safe and can be economically monitored and maintained. An end point
method is a way to translate broad mission statements to explicit goals that are
readily understood by engineers and craft personnel who do the work. (It should
be recognized that while end points as addressed here are for a final set of conditions
for deactivation, they may represent an interim point for the overall EM cleanup
goal.)
The end points concepts and ideas are not original. The end point methods described
here build on original concepts and ideas of several individuals. The basic approach
was created during the cleanup of the Three Mile Island Unit 2 where it was used
to define the completion of the cleanup prior to long-term storage. That method
was modified for application at the Uranium Trioxide (UO3) and PUREX facilities
at Hanford during 1994.
EM's end points specification methods were originally developed for deactivation
project planning. They are equally applicable and usable for planning of stabilization
and decommissioning projects.
Specific end points will vary from facility to facility. The method(s) by which
facility-specific end points are defined should, however, be consistent. Therefore,
this handbook does not (and cannot) attempt to define what end points should be.
Rather, it provides methods by which each project's manager can derive their facility's
end points based on objectives and principles common to all deactivation.
Compiling end point specifications for the entire facility has the following uses
during and/or after implementation:
- As input for scheduling and estimating the project cost.
- To create detailed work plans for each space and system in the facility.
- To document bases for performance based contracting or out-sourcing of work, where
practical to do so. In effect, to become part of the performance specifications.
- To demonstrate conformance to agreements negotiated with third parties who have
a legitimate stake in the condition of the facility after deactivation.
- To show compliance with both local and federal regulations.
The Need for a Method to Derive End Points
The detailed specification and actual end points achieved will undoubtedly vary
from facility to facility. Variations are expected because of the differences among
facilities with respect to past missions, equipment and systems, containment, degree
of contamination and ability to isolate the contamination, facility environs, projected
ultimate disposition, if known, and a host of other factors. Regardless of variations
in conditions achieved, the method used to decide and specify end points are fundamentally
similar.
The methods described here can be readily adapted to a wide range of facilities;
they are intended to expedite choosing how to proceed with end point planning and
implementation. In some cases, the primary objective of a project may be to continue
or in some cases initiate the "stabilization" of material or a facility, as contrasted
with "deactivation." The basic approach in this handbook can be adapted to such
projects. However, more front-end effort to define end points method matrices and
checklists described here may be necessary.
For those facilities that will be, or are candidate for, transfer to an extended
care or decommissioning organization, two important documents that should be used
together with this handbook are DOE G 430.1-4, DECOMMISSIONING IMPLEMENTATION GUIDE,
and the Decommissioning Handbook (DOE/EM-0383, January 1999).
Deactivation work can involve a wide range of tasks, such as removal of remaining
hazardous material, elimination or shielding of radiation fields, partial decontamination
to allow access for inspection, isolation of systems, installation of monitors and
alarms, etc. It is important that the end point for each of these tasks be established
clearly and in advance, for the following reasons:
- End Points must be such that the central element of the deactivation objective -
to achieve a low risk-low cost condition - is unquestionably achieved.
- End Points are a means by which the deactivation and receiving organizations can
achieve agreement on the conditions of transfer of facility management upon completion
of deactivation.
- Much of the deactivation work involves worker exposure to radiation or dangerous
materials. Avoiding unnecessary work can minimize this.
- Each task is, in effect, competing for resources with other deactivation tasks and
other facilities. By assuring that each task is appropriately bounded, DOE's overall
resources can be used most fully and effectively.
- An end point method is the mechanism to begin detailed planning, leading to a schedule
and budget. It is strongly emphasized that this will help avoid excess contingency
(conservatism) in establishing the deactivation project budget and schedule.
- Deactivation end points where possible should be in concert with, or at a minimum
not preclude, longer-term disposition options.
End Points focus on explicitly measurable or identifiable objectives such as, but
not limited to, configuration of systems and equipment, removal of materials, residual
contamination levels, and preservation of records for future need.
An end point method leads to work orders to deactivate a facility and achieve stable
conditions for radioactive or hazardous conditions and materials. A method must
provide a consistent, systematic way of defining, planning, and executing work.
It should represent a straightforward, common sense engineering approach, which
can be readily carried out by workers.
The methods presented here have been evolved in the field and have worked well in
the form presented. As such, they should work for any facility with appropriate
adaptation to its characteristics.
Guiding Principles for Specifying End Points
There are several guiding principles (ground rules) that form the foundation of
the end point process. They are:
- Driven by Objectives - The decision to specify an end point should be driven
by, and clearly linked to, top-tier program objectives. This is the central principle
of the logic-based approach. End Point determinations, along with allocation of
resources and selection of methods, should all stem directly and clearly from program
goals and top-tier objectives.
- Cost for Reduced Risk Achieved - End Point decisions are integrally linked
to decisions (and constraints) on resources and methods. Cost effectiveness is important.
DOE needs to achieve maximum safety improvement (and optimum risk reduction) for
every deactivation dollar spent.
That is, there is a point at which expending further resources to reduce risk will
not achieve commensurate reduction in S&M costs. If a proposed end point is
not economically feasible, it should only be specified if mandated by law.
- Decoupling from Decommissioning Decisions - In many cases, it is not known
when or how the ultimate decommissioning will be done. Therefore, end point decisions
may consider , but should not be driven by decommissioning presumptions.
- Defense-in-Depth - The end-state condition of the deactivated facility should
employ defense-in-depth as a fundamental safety approach. As applied here, defense-in-depth
involves three layers of protection: elimination or stabilization of hazards, effective
facility containment, and facility monitoring and control. In this context, the
concept of reducing risk to acceptable levels can be applied.
- Need for Ownership - Successful end point development requires "ownership"
by all affected organizations including the planners, the deactivation work force,
and the receiving organization (the "customer").
- Need for Clarity - Work teams in the field need clear, quantitative completion
criteria. They can't work effectively with vague or functional objectives. To be
workable, end points must be:
|
- |
established up front |
|
- |
clear, quantitative |
|
- |
practical and achievable |
- Need for Flexibility - End Point development is an iterative process. Most
end point decisions can be made during the planning stages early in the project,
however, some will have to be revisited as deactivation proceeds.
- Research to be Avoided - A deactivation project is intended to be done in
the short term. Therefore, it must be possible to achieve the objective with what
is then known. That is, a reasonable schedule would probably not allow for primary
research as a prerequisite for activities to achieve an end point. Similarly, development,
where considered, should probably be limited to applying existing technology to
the situation at hand unless very unusual conditions exist.
These guidelines should be used when selecting an end point method to use, setting
up criteria, and specifying detailed end points.
Tailored Approach
Two methods for developing a project's end point specifications are the "Hierarchical" method, and the
"Checklist" method . The hierarchical method is appropriate for a complex
facility with process systems and/or substantial hazards. The checklist method is
more appropriate for relatively simple buildings that are not very contaminated
and do not have complex equipment or systems. Deactivation project managers should
start with these as examples, choose one method appropriate to their project, and
adapt what is in this handbook to their project. The following table lists some
considerations for choosing one over the other.
Considerations for Choosing an End Point Method
|
Consideration |
Favors the
Hierarchical
Method |
Favors the
Checklist
Method |
|
There is clear need for end points
to be systematically derived and defensible. |
X |
|
|
A long-term post-deactivation S&M
period is anticipated. |
X |
|
|
Facility is to be dismantled immediately
after deactivation. |
|
X |
|
Facility is a single building or room. |
|
X |
|
Facility has many rooms, some of which
are inaccessible or heavy contaminated. |
X |
|
|
Facility has one or more complex process
systems. |
X |
|
|
Facility contains substantial radioactive
or chemical hazards. |
X |
|
|
Facility contains several RCRA units. |
X |
|
|
There is no fixed radioactive contamination
and it is relatively straightforward to remove all hazardous materials. |
|
X |
|
Facility has no radioactive or hazardous
materials. |
|
X |
|
There is very little budget or resource
for deactivation work. |
|
X |
|
Very little resources are available
for end point coordination. |
|
X |
Headquarters, Field Office, and Contractor Roles
This describes the relative roles of the three primary organizations involved in
deactivation end point decisions that have a project-level focus .
Clearly the defined lines of authority and responsibility flow from the government
to the contractor. Once DOE direction has been established, the contractor proposes
how to get there. Within this context, for efficient project management and expediting
the path forward, an approach has worked well in which all three organizations participate
essentially simultaneously in significant decisions. This is in lieu of a several
step sequential process, with iterations at each step, in which each level of authority
must agree before the next becomes involved.
Headquarters Role
Specifying detailed end points is predominantly a field activity. DOE Headquarters
involvement is important early when decisions may substantially affect budgets,
when a decision requires unique interaction with other DOE sites, or when a national
or international policy or program might be affected. The DOE Headquarters program
manager's participation in the development and approval of the project plan or project
management plan indicates acceptance of the project baseline that is derived from
the overall facility end-state decision. Such approval is also tantamount to approving
the final configuration, which directly affects future budget requirements or general
budget levels for future S&M.
Headquarters responsibilities specific to detailed end point specifications are
to:
- Assist in deciding and achieving end points that require interaction at a national
level.
- Stimulate experience transfer among the various sites regarding deactivation end
points.
Field Office Role
DOE provides the programmatic direction for the overall end-state as a prelude to
proceeding at the working level. The Field Office is responsible for determining
what the facility's condition will be after deactivation. This is done in coordination
with appropriate headquarters organizations that deal with budgets and national
priorities.
The Field Offices' primary responsibility with respect to achieving detailed end
points are then to ensure that the deactivation contractor is performing to a set
of measurable objectives. The field office project manager should have approval
authority over the project plan. This signature should indicate agreement with the
level of planning and that the baseline can be achieved with the identified resources
and within the baseline schedule.
In the course of deciding on implementing end points, there may be occasions when
the field office will become involved in the more-routine aspects of achieving end
points. Such involvement could include, for example:
- Concurring with the method proposed for end points and the top-level setup for applying
the method.
- Resolving disputes between the deactivation contractor and the organization that
will receive the facility for post-deactivation S&M.
- Providing an interface with stakeholders (including Federal and State regulators)
where field office agreements are likely to result in requirements that will directly
affect end point planning.
- Providing an interface for other field office support activities and functions.
- Providing an interface with Headquarters for resolving issues beyond the scope of
the Field Office.
Deactivation Contractor Role
Within the larger responsibility of preparing a detailed project plan, specifying
and achieving detailed end points rests with the facility deactivation contractor.
In general, this is the maintenance and operations (M&O) or integrating contractor,
but not necessarily in all cases. The contractor should:
- Define the method to be used for specifying end points.
- Conduct detailed end point planning, including coordination with the receiving organization.
- Incorporate this planning into the detailed project planning, including WBS, estimating,
and scheduling.
- Create work plans as needed.
- Conduct the work.
- Obtain concurrence from the Field Office and the receiving organization at appropriate
times in the process.
The end point method is consistent with the trend in DOE contracting which is towards
performance based and fixed price contracting. Contractor's fee or incentive depends
on achieving objectives at the least cost, consistent with safety. This approach,
especially when fixed price contracts are involved, requires a basis for performance.
End Points can be part of this basis. Micro-management is avoided by having the
contractor take on responsibility for specifying end points which is then concurred
with by the DOE.
End Points Approvals
Several documents will be created in the course of developing a facility's end points
and the activities to achieve the specified conditions. The following table suggests
the points within an organization for preparing and approving the documents as well
as accepting the conditions achieved. (Job titles are typical - the job function
is what is important here.) Each site and/or facility should create a similar table
that addresses its specific contractual and administrative arrangements among its
field office, deactivation contractor, and S&M contractor organizations.
Suggested Approvals
Customer - DOE Field Office
(Deactivation and Post-Deactivation) |
A, F |
A, F |
|
|
|
|
F |
Deactivation Project Manager
(or Facility Director) |
A |
A |
A |
A |
|
A |
A |
|
Engineering Manager |
|
A |
A |
A |
A |
|
|
|
Operations/Maintenance Manager |
|
|
|
A |
A |
A |
A |
|
End Points Coordinator |
P |
P |
P |
P |
|
P |
|
|
Facility Manager after deactivation |
|
A |
A |
|
|
|
|
|
Manager of post-deactivation S&M |
|
|
P* |
A |
|
A |
|
|
System Engineers, Cognizant Engineers |
|
|
|
|
P |
|
A |
|
Craft Foreman, Job Supervisors |
|
|
|
|
|
|
S |
* Primary responsibility. However, deactivation staffs that know the facility are
important to, and should participate in, developing the S&M plan.
Legend:
A = Approves
P = Prepares
S = Signs for conduct of work
F = Final acceptance
Contractor Organization Functions for End Points Implementation
Creating an end points plan and coordinating its execution generally requires very
little dedicated resources. For a complex facility, a three or four person group,
the "Deactivation End Points Team" should be created to augment organization functions
that already exist. This is shown in following figure. For non-complex facilities,
this may require only one or two persons for part of their time.

Organization Interaction for End Points Implementation
Existing Organization Function
The existing facility organization functions and roles are:
- Facility Manager or Project Manager - Overall responsibility for deactivation, including
end point planning, method to be used, and implementation.
- System and Cognizant Engineers - End Point tasks are an extension of normal responsibilities.
Their knowledge of the facility equipment and spaces is essential to establishing
specific end points. These engineers would also create the end point work plans.
- Operations, Maintenance, and Craft - Supervision and labor for accomplishing end
point conditions.
- Budget and Schedule Preparation - End Points will drive the deactivation schedule
and budget and thus there will be significant interaction with the end points team.
Other functions in the existing organization, such as health and safety, quality
assurance, records management, purchasing, etc. will also be involved to the extent
that implementation tasks are part of their normal jobs.
End Points Team
For deactivating a complex facility, an effective end points team, reporting
to the Project Manager, should have the following staffing:
- Leader/Coordinator - a facility knowledgeable engineering manager with good technical,
organizational, and administrative skills. Should report to the deactivation project
manager.
- Facility Expert - an engineer or senior supervisor/technician who is intimately
familiar with the equipment, physical layout, conditions, and materials in the facility.
This person provides advice to the team and interaction with the facility technical
and operating staff.
- End Points Expert - an engineer who will learn the concepts in this handbook and
is assigned to work with system and/or cognizant engineers to specify the detailed
end points. (No special engineering discipline is necessary as the end point approach
is fundamental engineering.)
- Secretary/Text Entry - Clerical support for document creation and data entry.
The end points team should make use of a number of plant personnel in the process.
The best knowledge available on each of the systems/components should be used as
a resource, not necessarily with membership, but with good representation on the
end points team.
The establishment of the end points should be closely associated with the project
schedule and cost baseline planning and the same personnel should be used for both
efforts. There should be a continuation of processes.
End Point Team functions and responsibilities can include:
- Selecting and recommending the end point method to be used.
- Setting up the end point method including objectives, task types, classes, functional
matrices, and criteria, or creating the checklists (See End Points
Specification Methods).
- Obtaining external input that will affect end point specifications, such as relevant
stakeholder commitments, including Federal and State regulators.
- Creating a preliminary Post-Deactivation S&M Plan, including
interaction with the receiving organization.
- Creating the end points document.
- Doing walk downs with system and cognizant engineers to specify detailed end points.
- Establishing End Point Work Plans - Creating the template for the work plans.
- Archiving End Point Work Plans - maintaining and ensuring proper archiving of the
completed end point work plans. (See Deactivation Completion and
Turnover)
Receiving Organization Technical Representatives
When there is a receiving organization identified, its manager should assign technical
representatives to interact with end points planning and for developing the post-deactivation
S&M plan. These representatives should participate directly in these developments,
as opposed to being only reviewers.
Training and Walkdown Guidance for the Facility Engineers
System and cognizant engineers for the facility are instrumental in developing end
point specifications because of their detailed knowledge of the facility. However,
it is unlikely they will be familiar with the end point method and how to proceed.
Therefore, it is necessary for the end points team to familiarize the engineers
with what has to be done. The following approach is suggested:
- Conduct a training session on the end points purpose, methods, and priorities for
all engineers who will prepare end point specifications and work plans.
- Ask the Engineering Manager to have one of the senior engineers participate in creating
the work plan template.
- Using the work plan template as a walkdown guide, walk down his or her areas of
responsibility with each engineer.
- Assist in preparing detailed end points for their areas of responsibility.
- Assist in preparing the work plan for their areas of responsibility.
- Conduct another review session after the first work plan is written.
- Be available for consultation at any time.
In addition, it is recommended that a separate training session for facility managers
and supervisors provide an overview of the end point objectives and process.
|